CN113393140A - Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM - Google Patents

Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM Download PDF

Info

Publication number
CN113393140A
CN113393140A CN202110699930.0A CN202110699930A CN113393140A CN 113393140 A CN113393140 A CN 113393140A CN 202110699930 A CN202110699930 A CN 202110699930A CN 113393140 A CN113393140 A CN 113393140A
Authority
CN
China
Prior art keywords
construction
information
bim
constructors
constructor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110699930.0A
Other languages
Chinese (zh)
Inventor
葛俊健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Detai Construction Engineering Co ltd
Original Assignee
Shenzhen Detai Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Detai Construction Engineering Co ltd filed Critical Shenzhen Detai Construction Engineering Co ltd
Priority to CN202110699930.0A priority Critical patent/CN113393140A/en
Publication of CN113393140A publication Critical patent/CN113393140A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses building monitoring method and system, equipment and storage medium based on BIM, wherein the method comprises the following steps: acquiring building process information regularly; judging whether the building process is out of date; when the process is out of date, acquiring constructor information and construction material information; based on constructor information and construction materials information, generate the record of expiry and save, this application the scheme can be regularly to the construction process analysis, judges the reason of expiry, conveniently carries out the analysis of expiry, in time revises, guarantees the construction process.

Description

Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM
Technical Field
The application relates to the field of building construction, in particular to a building monitoring method and system based on BIM, equipment and a storage medium.
Background
BIM (Building Information Modeling) is another important computer application technology appearing in the engineering construction industry after CAD (computer aided design) technology, and is a Building full life cycle Information management technology. The method has the five characteristics of visualization, coordination, simulation, optimization and diagraph.
BIM is a brand-new building design, construction and management method, and based on three-dimensional digital information technology, data information of planning, design, construction, operation and other stages is completely contained in a 3D model, so that workers in any stage in the whole life cycle of a building can make effective and correct decisions according to accurate and complete data when using the model.
Based on BIM, in the existing building system, a model for temporarily not completing the analysis of project overdue is not provided, when the project is overdue, the reason of the overdue cannot be known in time, and the subsequent project is possible to continue to be overdue, or the project construction cost is increased, so that the temporary solution and the permanent solution are not achieved, and therefore, the prior art is still to be improved.
Disclosure of Invention
The method aims to realize the reason analysis of the project overdue in the building project.
The technical purpose of the application is realized by the following technical scheme:
a BIM-based building monitoring method, comprising the steps of:
acquiring building process information regularly;
judging whether the building process is out of date;
when the process is out of date, acquiring constructor information and construction material information;
and generating and storing an overdue record based on the information of the constructors and the information of the construction materials.
According to the scheme, the construction process is acquired regularly, whether the construction process is overdue or not is judged, when the construction process is overdue, constructor information and construction material information are acquired, the factor of the process overdue is acquired, the overdue record is generated and stored, the process overdue reason is analyzed conveniently, and the process is rectified and corrected timely, so that the follow-up construction process is guaranteed to be delivered on time.
Optionally, the building monitoring method based on BIM further includes the steps of:
different time periods, corresponding building construction processes, the number of required personnel and construction material information are preset.
According to the scheme, through presetting different time periods, the corresponding building process and the required constructors and the construction material information are convenient to judge whether the constructors and the material information are factors causing the construction process to be out of date, and the problems are conveniently found and rectified in time.
Optionally, the building monitoring method based on the BIM includes the following steps that, based on the information of the constructors and the information of the construction materials, an overdue record is generated and stored:
comparing the constructor information and the construction material information with preset information;
when the number of constructors is less than the preset number of constructors required by construction, generating an overdue record of personnel shortage;
and when the construction material is less than the preset material required by construction, generating an overdue record of insufficient construction material.
According to the scheme, when the process is out of date, through comparing constructor information and construction material information with preset information, when the constructor is not enough, the out-of-date record that the generation personnel are not enough can in time increase constructor, guarantees the construction progress, when the construction material is not enough, the out-of-date record that the generation construction material is not enough can in time increase required construction material, guarantees the construction progress.
Optionally, the building monitoring method based on the BIM, wherein the method for generating and storing the overdue record based on the information of the constructors and the information of the construction materials further includes:
when the number of constructors is equal to or greater than the preset number of constructors required for construction, and the construction materials are equal to or greater than the preset materials required for construction, the working hours of each constructor are obtained;
and when the working hours of the constructors are less than the preset time, outputting the attendance record of the constructors.
According to the scheme, when constructors and construction are saturated, the construction period is still prolonged, the constructors are acquired in time, whether the constructors are absent from duty is judged, constructors are generated, absent from duty records are timely rectified, the working time of the constructors is guaranteed, and the construction progress is ensured.
On the other hand, this application still discloses a building monitored control system based on BIM, wherein, includes:
the construction process acquisition module is used for periodically acquiring the building process information;
the excess time judging module is used for judging whether the building process is excess time;
the construction information acquisition module is used for acquiring constructor information and construction material information when the process is out of date;
and the construction overdue recording module is used for generating and storing an overdue record based on the information of the constructors and the information of the construction materials.
According to the scheme, the construction process is acquired regularly, whether the construction process is overdue or not is judged, when the construction process is overdue, constructor information and construction material information are acquired, the factor of the process overdue is acquired, the overdue record is generated and stored, the process overdue reason is analyzed conveniently, and the process is rectified and corrected timely, so that the follow-up construction process is guaranteed to be delivered on time.
Optionally, the building monitoring system based on BIM, wherein the system further includes:
and the presetting module is used for presetting different time periods, corresponding building construction processes, the number of required personnel and construction material information.
According to the scheme, through presetting different time periods, the corresponding building process and the required constructors and the construction material information are convenient to judge whether the constructors and the material information are factors causing the construction process to be out of date, and the problems are conveniently found and rectified in time.
Optionally, the building monitoring system based on BIM, wherein the construction overdue recording module includes:
the comparison unit is used for comparing the constructor information and the construction material information with preset information;
the insufficient personnel recording unit is used for generating an overdue record of insufficient personnel when the number of constructors is less than the preset number of the constructors required by construction;
and the material shortage recording unit is used for generating an overdue record of the construction material shortage when the construction material is less than the preset construction required material.
According to the scheme, when the process is out of date, through comparing constructor information and construction material information with preset information, when the constructor is not enough, the out-of-date record that the generation personnel are not enough can in time increase constructor, guarantees the construction progress, when the construction material is not enough, the out-of-date record that the generation construction material is not enough can in time increase required construction material, guarantees the construction progress.
Optionally, the building monitoring system based on BIM, wherein the construction overdue recording module further includes:
the construction personnel working hour obtaining unit is used for obtaining the working hour of each construction personnel when the number of the construction personnel is equal to or larger than the preset number of the personnel required for construction and the construction materials are equal to or larger than the preset materials required for construction;
and the constructor attendance record unit is used for outputting the constructor attendance record when the constructor is lower than the preset time in working hours.
According to the scheme, when constructors and construction are saturated, the construction period is still prolonged, the constructors are acquired in time, whether the constructors are absent from duty is judged, constructors are generated, absent from duty records are timely rectified, the working time of the constructors is guaranteed, and the construction progress is ensured.
On the other hand, the application also discloses a building monitoring device based on the BIM, wherein the building monitoring device comprises a memory and a processor, and the memory stores a computer program which can be loaded by the processor and executes the building monitoring method based on the BIM.
In another aspect, the present application further discloses a storage medium storing a computer program that can be loaded by a processor and execute the BIM-based building monitoring method as described above.
In summary, the present application discloses a building monitoring method and system, a device, and a storage medium based on BIM, wherein the method includes the steps of: acquiring building process information regularly; judging whether the building process is out of date; when the process is out of date, acquiring constructor information and construction material information; based on constructor information and construction materials information, generate the record of expiry and save, this application the scheme can be regularly to the construction process analysis, judges the reason of expiry, conveniently carries out the analysis of expiry, in time revises, guarantees the construction process.
Drawings
FIG. 1 is a flow chart of the steps of a BIM-based building monitoring method described herein.
FIG. 2 is a block diagram of a BIM-based building monitoring system according to the present application.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
The scheme is provided based on the condition that engineering is easy to exceed the period in the building engineering, and mainly aims to realize reason analysis of the period, specifically, the application discloses a building monitoring method based on BIM (building information modeling), referring to FIG. 1, which is a step flow chart of the method, wherein the method comprises the following steps:
s1, regularly acquiring building process information;
s2, judging whether the building process is out of date;
s3, acquiring constructor information and construction material information when the process is out of date;
and S4, generating an overdue record and storing the overdue record based on the information of the constructors and the information of the construction materials.
In the embodiment of the application, during specific implementation, a construction project necessarily has a very long construction period, and analysis of the construction process needs to be performed regularly, for example, a total period of the project is expected to be three months, then, during a half-month or one-month period, the construction process in the period needs to be analyzed, how much the project is completed and whether an overdue risk exists are checked within the half-month or one-month period, if the project is seriously delayed within the half-month or one-month period, reasons should be checked in time, and timely adjustment is found in time to ensure that the whole construction period can be completed normally, based on the above problems, in the embodiment of the application, by acquiring the construction process information regularly, whether the construction process in the period is overdue is judged, if the construction period is not overdue, the construction is indicated to be operated normally, and when the construction process is overdue, the reason for the construction process exceeding is required to be acquired, and timely correction is found, so that the constructor information and the construction material information are acquired, and an exceeding record is generated and stored based on the constructor information and the construction material information, the construction exceeding factor generally means that the constructor is not enough, or the construction material is not enough, and the time consumed by the construction material is waited, so that the reason for the construction process exceeding is convenient to know timely through acquisition of the parameters, the correction is convenient to timely, and the normal operation of the subsequent construction process is ensured.
In the foregoing solution, when the construction process is out of date, the construction reason needs to be analyzed, the constructor and the construction material information need to be analyzed, and a certain reference standard needs to be provided, so that based on the above problem, in the embodiment of the present application, further, the building monitoring method based on the BIM further includes the following steps:
s0., different time periods are preset, and corresponding construction progress and corresponding required personnel number and construction material information are preset.
In the embodiment of the application, different time periods are preset, corresponding construction processes and corresponding personnel and construction material information are obtained, for example, in half a month, the construction progress needs to reach what standard, the standard is reached, different constructors need to be how much, different construction materials need to be how much, the data are input in a preset mode, and when the processes of the periods are analyzed, judgment basis is provided, rational data are provided, whether the construction processes are overdue or not is conveniently and accurately analyzed, and reason analysis in the overdue process is achieved.
In the foregoing solution, when the construction is out of date, the reason for the out of date needs to be analyzed, which mainly lies in analyzing information of constructors and construction materials, and therefore, based on the above problems, in this embodiment of the present application, further, the building monitoring method based on BIM, wherein the method for generating and storing the out of date record based on the information of the constructors and the information of the construction materials includes:
comparing the constructor information and the construction material information with preset information;
when the number of constructors is less than the preset number of constructors required by construction, generating an overdue record of personnel shortage;
and when the construction material is less than the preset material required by construction, generating an overdue record of insufficient construction material.
In the embodiment of the application, in the concrete implementation, when the construction progress in the period is over, it is described that the construction progress is dragged, on one hand, the construction progress may be caused by insufficient personnel, on the other hand, the construction material may be caused by insufficient construction material, and certainly, the construction cannot be performed due to extreme weather, which is generally rare, therefore, based on special cases, the analysis can be performed according to a case, based on common problems such as personnel and material problems, the construction personnel information and the construction material information are compared with the preset information mentioned in the foregoing scheme, for example, within half a month, the number of people required for completing the progress is 10, the specific personnel distribution can be refined again, the general difference is not too large, for example, the required material is 3 tons of lime and 5 tons of gravel, within half a month, the progress falls behind, at this moment, with constructor information and construction materials information and the contrast of above-mentioned data, be less than 10 when constructor quantity, lime and gravel are normal when, then it leads to the overdue to show that constructor is not enough, generate the overdue record that personnel are not enough this moment, and be 10 or more when constructor's quantity, and lime is 2 tons, the grit is 6 tons, or the grit is 4 tons, as long as the material has not enough, the construction process can certainly be lagged behind, therefore, generate the overdue record that the construction materials are not enough this moment, through the aforesaid analysis, can in time know the reason of overdue, when personnel are not enough, in time increase personnel, when the construction materials are not enough, in time increase the construction materials, ensure the normal clear of subsequent construction process.
In the foregoing solution, when the constructor and the construction material are analyzed, the constructor is insufficient or the construction material is insufficient, which results in an overdue construction process, but in the case that the constructor is sufficient and the construction material is sufficient, an overdue condition may also occur, and then based on this condition, in this embodiment of the present application, further, the building monitoring method based on BIM, wherein, based on the constructor information and the construction material information, the method for generating the overdue record and storing further includes:
when the number of constructors is equal to or greater than the preset number of constructors required for construction, and the construction materials are equal to or greater than the preset materials required for construction, the working hours of each constructor are obtained;
and when the working hours of the constructors are less than the preset time, outputting the attendance record of the constructors.
In the embodiment of the application, when the constructors and the construction materials are sufficient, the process may also be over-term, at this time, in order to further analyze the reason of over-term, the man-hours of the constructors are analyzed, when the man-hours of the constructors are lower than the preset time, the absence record of the constructors is output, which indicates that the construction over-term is caused by the absence of the constructors, and the subsequent strict attendance is required, so as to avoid the absence of the constructors, for example, 10 constructors are required, when the constructors acquire the information, 12 constructors are provided at the acquired time node, but 5 constructors are added into the construction team after the construction begins one week, at this time, the judgment of the man-hours should be judged according to the total man-hours of all the employees, for example, the construction time of 10 hours a day, 10 employees, and the total man-hours within a half month, 10 × 15, in total, 1500 man-hours, as mentioned above, 12 constructors, and 5 constructors have a normal working time of 8 days, so the total man-hour is 7 × 10 × 15+5 × 10 × 8=1450 man-hours, and therefore, less than 1500 total man-hours, it is still insufficient to explain, and therefore, in order to ensure the construction process, in the subsequent construction, strict attendance is required, and it is ensured that the total man-hour meets the construction requirement.
Based on the above method, the present application also discloses a building monitoring system based on BIM, refer to fig. 2, which is a structural block diagram of the system, wherein, including:
a construction process acquisition module 100, configured to periodically acquire building process information;
the excess time judging module 200 is used for judging whether the building process is excess time;
the construction information acquisition module 300 is used for acquiring constructor information and construction material information when the process is over-term;
and the construction overdue recording module 400 is used for generating and storing an overdue record based on the information of the constructors and the information of the construction materials.
The specific implementation of each module described above has been described in the method steps, for example, the construction process obtaining module corresponds to the method step of implementing S1, so the specific implementation of each module described above is not described again.
Further, the building monitoring system based on BIM, wherein the system further includes:
the presetting module 500 is used for presetting different time periods, corresponding building construction processes, corresponding required personnel number and construction material information.
The implementation of the preset module is already described in the method, and therefore is not described herein.
Further, the building monitoring system based on BIM, wherein the construction overdue recording module 400 includes:
the comparison unit is used for comparing the constructor information and the construction material information with preset information;
the insufficient personnel recording unit is used for generating an overdue record of insufficient personnel when the number of constructors is less than the preset number of the constructors required by construction;
and the material shortage recording unit is used for generating an overdue record of the construction material shortage when the construction material is less than the preset construction required material.
The specific implementation of each unit in the present application has been described in detail in the method steps, and thus, the detailed description is omitted.
Further, the building monitoring system based on BIM, wherein the construction overdue recording module 400 further includes:
the construction personnel working hour obtaining unit is used for obtaining the working hour of each construction personnel when the number of the construction personnel is equal to or larger than the preset number of the personnel required for construction and the construction materials are equal to or larger than the preset materials required for construction;
and the constructor attendance record unit is used for outputting the constructor attendance record when the constructor is lower than the preset time in working hours.
In the embodiment of the present application, the specific implementation of each module is described in detail in the method steps, and therefore is not described herein again.
Further, the present application also discloses a building monitoring device based on BIM, which includes a memory and a processor, wherein the memory stores a computer program that can be loaded by the processor and execute the building monitoring method based on BIM as described above.
Further, the present application also discloses a storage medium storing a computer program that can be loaded by a processor and execute the BIM-based building monitoring method as described above.
The embodiments of the present invention are preferred embodiments of the present application, and the scope of protection of the present application is not limited by the embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. A building monitoring method based on BIM is characterized by comprising the following steps:
acquiring building process information regularly;
judging whether the building process is out of date;
when the process is out of date, acquiring constructor information and construction material information;
and generating and storing an overdue record based on the information of the constructors and the information of the construction materials.
2. The BIM-based building monitoring method of claim 1, further comprising the steps of:
different time periods, corresponding building construction processes, the number of required personnel and construction material information are preset.
3. The BIM-based building monitoring method of claim 2, wherein the method for generating and storing the overdue records based on the constructor information and the construction material information comprises:
comparing the constructor information and the construction material information with preset information;
when the number of constructors is less than the preset number of constructors required by construction, generating an overdue record of personnel shortage;
and when the construction material is less than the preset material required by construction, generating an overdue record of insufficient construction material.
4. The BIM-based building monitoring method of claim 3, wherein the method of generating and storing an overdue record based on the constructor information and the construction material information further comprises:
when the number of constructors is equal to or greater than the preset number of constructors required for construction, and the construction materials are equal to or greater than the preset materials required for construction, the working hours of each constructor are obtained;
and when the working hours of the constructors are less than the preset time, outputting the attendance record of the constructors.
5. A building monitoring system based on BIM, comprising:
the construction process acquisition module is used for periodically acquiring the building process information;
the excess time judging module is used for judging whether the building process is excess time;
the construction information acquisition module is used for acquiring constructor information and construction material information when the process is out of date;
and the construction overdue recording module is used for generating and storing an overdue record based on the information of the constructors and the information of the construction materials.
6. The BIM-based building monitoring system of claim 5, further comprising:
and the presetting module is used for presetting different time periods, corresponding building construction processes, the number of required personnel and construction material information.
7. The BIM-based building monitoring system of claim 6, wherein the construction timeout recording module comprises:
the comparison unit is used for comparing the constructor information and the construction material information with preset information;
the insufficient personnel recording unit is used for generating an overdue record of insufficient personnel when the number of constructors is less than the preset number of the constructors required by construction;
and the material shortage recording unit is used for generating an overdue record of the construction material shortage when the construction material is less than the preset construction required material.
8. The BIM-based building monitoring system of claim 7, wherein the construction timeout recording module further comprises:
the construction personnel working hour obtaining unit is used for obtaining the working hour of each construction personnel when the number of the construction personnel is equal to or larger than the preset number of the personnel required for construction and the construction materials are equal to or larger than the preset materials required for construction;
and the constructor attendance record unit is used for outputting the constructor attendance record when the constructor is lower than the preset time in working hours.
9. BIM-based building monitoring device, comprising a memory and a processor, the memory storing a computer program that can be loaded by the processor and that executes the BIM-based building monitoring method according to claims 1-4.
10. A storage medium storing a computer program that can be loaded by a processor and that executes the BIM-based building monitoring method according to claims 1-4.
CN202110699930.0A 2021-06-23 2021-06-23 Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM Pending CN113393140A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110699930.0A CN113393140A (en) 2021-06-23 2021-06-23 Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110699930.0A CN113393140A (en) 2021-06-23 2021-06-23 Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM

Publications (1)

Publication Number Publication Date
CN113393140A true CN113393140A (en) 2021-09-14

Family

ID=77623632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110699930.0A Pending CN113393140A (en) 2021-06-23 2021-06-23 Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM

Country Status (1)

Country Link
CN (1) CN113393140A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114693158A (en) * 2022-04-19 2022-07-01 深圳市深安企业有限公司 Intelligent construction site management method and system based on BIM technology and storage medium

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108009758A (en) * 2018-01-09 2018-05-08 中建七局安装工程有限公司 A kind of site operation material intelligent management based on BIM
CN109492875A (en) * 2018-10-15 2019-03-19 筑梦高科建筑有限公司 Construction site role's management-control method based on BIM
CN110298629A (en) * 2019-06-20 2019-10-01 四川省劲腾环保建材有限公司 A kind of BIM implementation integration method
CN112132543A (en) * 2020-09-25 2020-12-25 广西路桥工程集团有限公司 Engineering project progress management system
US20210035383A1 (en) * 2019-06-25 2021-02-04 Scientia Potentia Est, LLC. System for management of verification of project commencement and completion
CN112633717A (en) * 2020-12-28 2021-04-09 青岛亿联建设集团股份有限公司 BIM-based management system for building construction
CN112988662A (en) * 2021-02-19 2021-06-18 惠州市建设集团工程建设监理有限公司 BIM-based project supervision information processing method, system, equipment and storage medium

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108009758A (en) * 2018-01-09 2018-05-08 中建七局安装工程有限公司 A kind of site operation material intelligent management based on BIM
CN109492875A (en) * 2018-10-15 2019-03-19 筑梦高科建筑有限公司 Construction site role's management-control method based on BIM
CN110298629A (en) * 2019-06-20 2019-10-01 四川省劲腾环保建材有限公司 A kind of BIM implementation integration method
US20210035383A1 (en) * 2019-06-25 2021-02-04 Scientia Potentia Est, LLC. System for management of verification of project commencement and completion
CN112132543A (en) * 2020-09-25 2020-12-25 广西路桥工程集团有限公司 Engineering project progress management system
CN112633717A (en) * 2020-12-28 2021-04-09 青岛亿联建设集团股份有限公司 BIM-based management system for building construction
CN112988662A (en) * 2021-02-19 2021-06-18 惠州市建设集团工程建设监理有限公司 BIM-based project supervision information processing method, system, equipment and storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋盈莹;: "BIM系统在城市超高层建筑中的应用研究", 环渤海经济望, no. 03 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114693158A (en) * 2022-04-19 2022-07-01 深圳市深安企业有限公司 Intelligent construction site management method and system based on BIM technology and storage medium

Similar Documents

Publication Publication Date Title
Tausworthe The work breakdown structure in software project management
US20220027744A1 (en) Resource data modeling, forecasting and simulation
de Soto et al. Using a Tabu-search algorithm and 4D models to improve construction project schedules
CN111191879B (en) Comprehensive evaluation method and system
CN112052506A (en) Project construction progress and safety management method and system based on BIM
CN111291994A (en) Multi-project management system and method suitable for agile development mode in big data environment
CN111476550A (en) Engineering cost auditing system
CN113393140A (en) Building monitoring method, building monitoring system, building monitoring equipment and storage medium based on BIM
CN113537945A (en) Automatic analysis method and device for capital construction material excess saving
CN115187039A (en) Construction progress management method and system based on BIM
CN113793126B (en) Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost
CN116167582A (en) Intelligent construction progress monitoring system based on BIM technology
CN111190817B (en) Method and device for processing software defects
CN112116322A (en) Three-dimensional design-based method and system for quickly and accurately compiling construction cost of power transformation project
JP2000039904A (en) Project management system
CN112507416A (en) BIM-based highway construction real-time supervision system and working method thereof
CN111027803A (en) Construction management method and construction management system
CN115965207A (en) Resource allocation method, system and storage medium
JP4683284B2 (en) PLANT PLANNING SYSTEM AND PLANNING METHOD
CN115760493A (en) Investment project land monitoring system
CN115185825A (en) Interface test scheduling method and device
CN112269826A (en) Visual processing system and method based on big data
US20150356518A1 (en) Aggregate task system
CN117313960B (en) Construction log display method based on visualization
Abdelmageed et al. A hybrid simulation model for modules installation in modular integrated construction projects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination