CN113373985A - Basement waterproof construction method - Google Patents

Basement waterproof construction method Download PDF

Info

Publication number
CN113373985A
CN113373985A CN202110650082.4A CN202110650082A CN113373985A CN 113373985 A CN113373985 A CN 113373985A CN 202110650082 A CN202110650082 A CN 202110650082A CN 113373985 A CN113373985 A CN 113373985A
Authority
CN
China
Prior art keywords
pipe
water guide
guide pipe
water
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110650082.4A
Other languages
Chinese (zh)
Other versions
CN113373985B (en
Inventor
沈国林
杜佳青
程孝锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Pengsheng Construction Group Co ltd
Original Assignee
Zhejiang Pengsheng Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Pengsheng Construction Group Co ltd filed Critical Zhejiang Pengsheng Construction Group Co ltd
Priority to CN202110650082.4A priority Critical patent/CN113373985B/en
Publication of CN113373985A publication Critical patent/CN113373985A/en
Application granted granted Critical
Publication of CN113373985B publication Critical patent/CN113373985B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Electromagnetism (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The application relates to a basement waterproof construction method, which belongs to the technical field of waterproof construction of underground structures of buildings and comprises the following steps: s1, preparing a water pipe with two open ends and marking as a water guide pipe; drilling holes on the outer wall of the water guide pipe to form a plurality of water inlet holes along the axis of the water guide pipe; preparing an inner pipe which can be inserted into the water conduit; preparing a template, and cutting the template to enable the water guide pipe to pass through the template; s2, supporting a template inside the foundation pit to form a pouring cavity, and taking a water guide pipe to penetrate through the template to enable two ends of the water guide pipe to be located outside the pouring cavity; inserting the inner pipe into the water guide pipe; and S3, pouring concrete in the pouring cavity, after the concrete is solidified, drawing out the inner pipe, and removing the template to form an outer wall. This application has the waterproof effect of realization basement initiative.

Description

Basement waterproof construction method
Technical Field
The application relates to the technical field of waterproof construction of underground structures of buildings, in particular to a basement waterproof construction method.
Background
In order to improve the utilization rate of underground space, a basement is usually arranged at the bottom of a building, and the basement is usually located in a space below the ground. Due to the existence of underground water, the waterproof of the wall surface of the basement is a problem which needs to be solved in the construction process of the basement.
The construction steps of the basement are as follows: s1, supporting a template at the bottom of the foundation pit; s2, pouring concrete in the area surrounded by the templates, and forming an outer wall after the concrete is solidified; and S3, backfilling soil between the outer wall of the outer wall and the inner wall of the foundation pit, and tamping the soil.
The existing basement waterproofing method is generally to treat after water seepage occurs, and the nature of the water seepage is that cracks penetrating through the interior and the exterior of a basement appear on the wall surface of the basement, and underground water seeps into the interior of the basement through the cracks. The waterproof treatment method is to fill up the crack position, and the treatment mode is very passive.
Aiming at the related technologies, the application provides a basement waterproofing construction method which can realize active waterproofing.
Disclosure of Invention
In order to realize active waterproofing, the application provides a basement waterproofing construction method.
The above object of the present application is achieved by the following technical solutions:
a basement waterproof construction method comprises the following steps:
s1, preparing a water pipe with two open ends and marking as a water guide pipe; drilling holes on the outer wall of the water guide pipe to form a plurality of water inlet holes along the axis of the water guide pipe; preparing an inner pipe which can be inserted into the water conduit; preparing a template, and cutting the template to enable the water guide pipe to pass through the template;
s2, supporting a template inside the foundation pit to form a pouring cavity, and taking a water guide pipe to penetrate through the template to enable two ends of the water guide pipe to be located outside the pouring cavity; inserting the inner pipe into the water guide pipe;
and S3, pouring concrete in the pouring cavity, after the concrete is solidified, drawing out the inner pipe, and removing the template to form an outer wall.
Through adopting above-mentioned technical scheme, set up the aqueduct of intercommunication basement inside and outside the wall body, when the height of groundwater surpassed the aqueduct, groundwater can carry out the drainage through the aqueduct. The underground water which has penetrated into the outer wall can enter the water guide pipe through the water inlet hole and then is discharged from the water guide pipe, so that the dredging replaces the repairing, and the waterproof effect is greatly improved. The underground water can be led out quickly and efficiently by the water guide pipe, so that the probability of cracks generated in the outer wall is reduced.
In the actual construction process, a plurality of water guide pipes are arranged along the width direction of the outer wall, and the specific arrangement positions are determined according to the design requirements. And the setting height of the water guide pipe on the outer wall is determined according to the underground water conditions of different areas, so that the aim of draining water is better fulfilled.
Optionally, in S1, a water pipe with openings at both ends is prepared and marked as a drain pipe; drilling holes on the outer wall of the drain pipe to form a plurality of drain holes along the axis of the drain pipe; and S4 is additionally arranged after S3 is finished, the drain pipe is arranged at one section of the water guide pipe facing the inner wall of the foundation pit, and the drain hole faces upwards.
Through adopting above-mentioned technical scheme, water that enters into in the drain pipe through the wash port dredges along the diapire of drain pipe and discharges in leading the water pipe, improves the outside water guide efficiency of outer wall to water-proof effects has been improved.
Alternatively, in S4, after the drain pipe is installed, the drain pipe is disposed obliquely upward from the end of the drain pipe in a direction away from the drain pipe.
Through adopting above-mentioned technical scheme, get into the groundwater in the drain pipe and enter into the water guide pipe inside along the drain pipe faster under the action of gravity to improve water-proof effects.
Alternatively, in S4, before installing the drain pipe, the outer wall is covered with a waterproof roll through which the water introduction pipe passes.
Through adopting above-mentioned technical scheme, waterproofing membrane can improve the water-proof effects in the outer wall outside for groundwater's discharge only can go on through the aqueduct, thereby has reduced groundwater and has deepened the inside probability of outer wall.
Alternatively, in S4, a swivel is fixed to the drain pipe and then the swivel is fixed to the end of the water pipe.
Through adopting above-mentioned technical scheme, rotary joint's setting can be better in the position of the in-process adjustment drain pipe of installation to make the position and the angle that set up of drain pipe accord with the design requirement. In addition, the rotary joint is fixed in a threaded connection mode, so that the installation and the disassembly between the drain pipe and the water guide pipe can be facilitated.
Optionally, in S4, a rubber pad is sleeved outside the water conduit, and then the rotary joint is sleeved outside the water conduit for fixation, and an end face of the rotary joint abuts against the rubber pad.
Through adopting above-mentioned technical scheme, the setting of rubber pad can improve the water-proof effects of aqueduct and outer wall hookup location to reduce the probability of groundwater from outer wall and aqueduct hookup location infiltration. Simultaneously, the setting of rubber pad can also improve rotary joint's joint strength, because rotary joint supports tightly on rubber pad to the restriction that goes on rotary joint's position better reduces the probability that rotary joint breaks away from because rotating in the later stage use.
Optionally, in S2, after the water conduit is inserted into the formwork, the two ends of the water conduit are limited on the corresponding formwork.
Through adopting above-mentioned technical scheme, with the both ends of aqueduct spacing in the template, the both ends that utilize the aqueduct in other words have carried on spacingly to the template to make the aqueduct possess the fixed effect to drawing the screw rod, improved the stability and the pouring quality of concrete placement in-process.
Alternatively, in S2, the inner pipe is inserted outside the water guide pipe after the release agent is sprayed on the outer wall of the inner pipe.
Through adopting above-mentioned technical scheme, at the in-process of concreting, partial concrete can be through the outer wall of the contact inner tube in the inlet hole, and the spraying of release agent can be convenient for later stage inner tube to take out from.
Optionally, in S1, the length of the inner tube is greater than that of the water conduit, and a limiting plate is fixed on the outer wall of the inner tube; the outer diameter of the inner pipe is consistent with the inner diameter of the water guide pipe, and when the inner pipe is inserted into the water guide pipe and the limiting plate is tightly abutted to the end part of the water guide pipe, the inner pipe can cover all water inlet holes in the water guide pipe.
Through adopting above-mentioned technical scheme, the external diameter of inner tube and the internal diameter of aqueduct are unanimous to make the inner tube insert the inside back of aqueduct, and the outer wall of inner tube and the inner wall of aqueduct are in and support tight state to the probability in clearance between concrete entering aqueduct inner wall and the inner tube outer wall through the income water hole has been reduced to the concrete in-process of building. And the setting of spacing board on the inner tube can be convenient for fix a position the position of inner tube in the work progress to make the inner tube construction cover the income water hole on the aqueduct, can be convenient for the later stage simultaneously and extract the inner tube.
In summary, the invention includes at least one of the following beneficial technical effects:
1. the water guide pipe is pre-buried in the construction process of the outer wall, and the water inlet hole is formed in the water guide pipe, so that underground water outside the outer wall and underground water penetrating into the inner part of the outer wall can be discharged through the water guide pipe, dredging replaces repairing, and the waterproof effect of the outer wall is improved;
2. the drainage effect can be improved through the arrangement of the drainage pipe;
3. the water guide pipe is used as the counter-pulling screw rod, so that the cost of materials in the construction process is reduced, the construction quality can be improved, and two purposes are achieved.
Drawings
FIG. 1 is a schematic view showing an overall structure of a water introduction duct and an inner pipe when they are installed;
FIG. 2 is an enlarged view of a portion of the structure of FIG. 1;
FIG. 3 is a schematic view of the overall structure of the drain pipe when installed;
FIG. 4 is an enlarged view of a portion of the structure of FIG. 3;
fig. 5 is a sectional view taken along line a-a of fig. 3.
In the figure, 1, a side die; 11. pouring a cavity; 111. an outer wall; 2. a rotary joint; 3. waterproof coiled materials; 4. a rubber pad; 5. a water conduit; 51. a water inlet hole; 52. a flange plate; 6. an inner tube; 61. a limiting plate; 7. a drain pipe; 71. a drain hole; 8. and (6) foundation pit.
Detailed Description
The present application is described in further detail below with reference to figures 1-5.
The embodiment of the application discloses a basement waterproof construction method. Referring to fig. 1-2, the basement waterproofing construction method includes the following steps:
s1, preparing materials;
preparing a plurality of templates, a plurality of metal water pipes with different pipe diameters, a metal plate made of the same material as the metal water pipes, a plurality of rotary joints 2, a flange plate 52, a waterproof coiled material 3 (shown in figure 4) and a rubber pad 4 (shown in figure 4).
One of the metal water pipes with one specification is selected as the water guide pipe 5 according to design requirements, two ends of the water guide pipe 5 are opened, and the outer walls of the two ends are provided with threads. Holes 51 are drilled in the outer wall of the water guide pipe 5, and the holes 51 are uniformly arranged along the axis of the water guide pipe 5.
The flange 52 and the rubber pad 4 (see fig. 4) can be sleeved outside the water conduit 5, and the flange 52 can be connected with the threads at the two ends of the water conduit 5.
The water guide pipe 5 can be passed through the hole which is set out at the position 1/3 in the height direction of the formwork and drilled.
According to design requirements, a metal water pipe with one specification is selected as an inner pipe 6, and the length of the inner pipe 6 is larger than that of the water guide pipe 5. The inner pipe 6 can be inserted into the water guide pipe 5, and after the inner pipe 6 is inserted into the water guide pipe 5, the outer wall of the inner pipe 6 is abutted against the inner wall of the water guide pipe 5. Cutting the metal plate to form an annular limiting plate 61, sleeving the annular limiting plate 61 outside the inner tube 6 so that the annular limiting plate 61 is perpendicular to the axis of the inner tube 6, and welding the annular limiting plate 61 and the inner tube 6.
Two metal water pipes are selected as the drain pipe 7 according to design requirements (see fig. 5), and both ends of the drain pipe 7 are opened. One end of each of the two drain pipes 7 is cut to form a chamfer, and the chamfered ends of the two drain pipes 7 are welded, so that the two drain pipes 7 are connected into a whole, and an obtuse angle is formed between the two drain pipes 7. The round hole is formed by cutting at the position where the two water drainage pipes 7 are connected, the fixed end of the rotary joint 2 is inserted into the round hole and welded, so that the rotary structure is communicated with the two water drainage pipes 7, and meanwhile, the rotary structure can be connected with the threads at the end part of the water guide pipe 5. A plurality of drain holes 71 (see fig. 5) are drilled on the side of the two drain pipes 7 facing the included angle, and the drain holes 71 are uniformly arranged along the axis of the corresponding drain pipe 7.
S2, supporting the template;
and supporting the template at the bottom of the foundation pit 8, so that the hole in the template is close to the bottom of the foundation pit 8. Two templates are vertically arranged to form the side mould 1. The two side moulds 1 are parallel to each other, and a casting cavity 11 is formed between the side moulds 1.
And spraying a release agent on the outer part of the inner pipe 6, and inserting the inner pipe 6 into the water guide pipe 5 until the annular limiting plate 61 abuts against the outer wall of the water guide pipe 5. The water inlet hole 51 faces upwards, the water guide pipe 5 is inserted into the hole of the side mold 1, the water guide pipe 5 sequentially penetrates through the holes of the two parallel side molds 1, and meanwhile the annular limiting plate 61 deviates from the inner wall of the foundation pit 8. And the flange plates 52 are sleeved at the two ends of the water guide pipe 5, and the flange plates 52 are rotated until the flange plates 52 are tightly pressed on the two side dies 1.
S3, pouring the outer wall 111;
with reference to fig. 2 and 3, concrete is poured into the pouring cavity 11, and after the concrete is solidified, an outer wall 111 is formed. Turning the inner tube 6 loosens the inner tube 6 and pulls the inner tube 6 away from the conduit 5, turning the flange 52 away from the conduit 5 and removing the side mould 1.
S4, installing a drain pipe 7;
referring to fig. 4 and 5, the waterproofing membrane 3 is selected and cut at a position corresponding to the water conduit 5 to form a through hole, the waterproofing membrane 3 is covered and adhered to the outer side of the outer wall 111, and the water conduit 5 passes through the through hole. The rubber pad 4 is sleeved outside the aqueduct 5, so that the rubber pad 4 is abutted against the waterproof coiled material 3.
The rotary joint 2 is sleeved on one side, facing the inner wall of the foundation pit 8, of the water guide pipe 5, the rotary joint 2 is rotated to enable the rotary structure and the water guide pipe 5 to be fixed, and meanwhile the end face of the rotary joint 2 abuts against the rubber pad 4 tightly. The drain pipes 7 are rotated to enable the drain holes 71 to face upwards, meanwhile, the angle flat wind lines of the two drain pipes 7 are vertical, and then structural glue is injected into the rotating position of the rotating joint 2 to lock the positions of the drain pipes 7.
S5, backfilling soil;
and backfilling soil between the waterproof coiled material 3 and the inner wall of the foundation pit 8, and tamping the soil.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (9)

1. A basement waterproof construction method is characterized in that: the method comprises the following steps:
s1, preparing a water pipe with two open ends, and marking as a water guide pipe (5); drilling holes on the outer wall of the water guide pipe (5) to form a plurality of water inlet holes (51) along the axis of the water guide pipe (5); preparing an inner pipe (6), wherein the inner pipe (6) can be inserted into the water guide pipe (5); preparing a template, cutting the template so that the water guide pipe (5) can pass through the template;
s2, supporting a template inside the foundation pit (8) to form a pouring cavity (11), and enabling the water guide pipe (5) to penetrate through the template, so that two ends of the water guide pipe (5) are located outside the pouring cavity (11); inserting the inner pipe (6) into the water conduit (5);
and S3, pouring concrete in the pouring cavity (11), after the concrete is solidified, drawing out the inner pipe (6), and removing the template to form the outer wall (111).
2. The basement waterproofing construction method according to claim 1, wherein: in S1, a water pipe with two open ends is prepared and marked as a drain pipe (7); a plurality of drain holes (71) along the axis of the drain pipe (7) are drilled on the outer wall of the drain pipe (7); and S4 is additionally arranged after S3 is finished, the drain pipe (7) is arranged at one section of the inner wall of the foundation pit (8) facing the water guide pipe (5), and the drain hole (71) faces upwards.
3. The basement waterproofing construction method according to claim 2, wherein: in S4, after the drain pipe (7) is mounted, the drain pipe (7) is disposed obliquely upward from the end of the water guide pipe (5) in a direction away from the water guide pipe (5).
4. The basement waterproofing construction method according to claim 2, wherein: in S4, before installing the drain pipe (7), the waterproof roll (3) is covered on the outer wall (111), and the water guide pipe (5) is passed through the waterproof roll (3).
5. The basement waterproofing construction method according to claim 2, wherein: in S4, the rotary joint (2) is fixed to the drain pipe (7), and the rotary joint (2) is further fixed to the end of the water conduit (5).
6. The basement waterproofing construction method according to claim 5, wherein: in S4, a rubber pad (4) is sleeved outside the water guide pipe (5), then the rotary joint (2) is sleeved outside the water guide pipe (5) to be fixed, and the end face of the rotary joint (2) is abutted against the rubber pad (4).
7. The basement waterproofing construction method according to claim 1, wherein: in S2, the water guide pipe (5) is inserted into the formwork, and then both ends of the water guide pipe (5) are positioned on the corresponding formwork.
8. The basement waterproofing construction method according to claim 1, wherein: in S2, the release agent is sprayed on the outer wall of the inner pipe (6), and then the inner pipe (6) is inserted outside the water conduit (5).
9. The basement waterproofing construction method according to claim 1, wherein: in S1, the length of the inner pipe (6) is larger than that of the water guide pipe (5), and a limit plate (61) is fixed on the outer wall of the inner pipe (6); the outer diameter of the inner pipe (6) is consistent with the inner diameter of the water guide pipe (5), and when the inner pipe (6) is inserted into the water guide pipe (5) and the limiting plate (61) abuts against the end part of the water guide pipe (5), the inner pipe (6) can cover all the water inlet holes (51) in the water guide pipe (5).
CN202110650082.4A 2021-06-10 2021-06-10 Basement waterproof construction method Active CN113373985B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110650082.4A CN113373985B (en) 2021-06-10 2021-06-10 Basement waterproof construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110650082.4A CN113373985B (en) 2021-06-10 2021-06-10 Basement waterproof construction method

Publications (2)

Publication Number Publication Date
CN113373985A true CN113373985A (en) 2021-09-10
CN113373985B CN113373985B (en) 2022-12-09

Family

ID=77573819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110650082.4A Active CN113373985B (en) 2021-06-10 2021-06-10 Basement waterproof construction method

Country Status (1)

Country Link
CN (1) CN113373985B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115075305A (en) * 2022-08-05 2022-09-20 中国十七冶集团有限公司 Basement waterproof structure and construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120102851A1 (en) * 2010-10-29 2012-05-03 United Waterproofing Corp Apparatus and Method for Waterproofing a Basement
CN105544622A (en) * 2015-06-05 2016-05-04 龚展宇 Floating resisting device, and seepage insulation device and drainage path checking device thereof for underground building
CN206754608U (en) * 2017-03-30 2017-12-15 深圳市沃特玛电池有限公司 A kind of adjustable rotary joint
CN206844172U (en) * 2017-05-03 2018-01-05 深圳艺洲建筑工程设计有限公司 A kind of basement bottom board catchments drain structure
CN207245184U (en) * 2017-09-01 2018-04-17 重庆钢铁集团建设工程有限公司 A kind of new cooling sealing up screw
CN108316354A (en) * 2018-03-29 2018-07-24 沈阳建筑大学 With waterproof, the underground pipe gallery structure of drain function and its construction method
CN108442699A (en) * 2018-04-28 2018-08-24 山东建筑大学 A kind of split bolt for pouring miniature underground pipe gallery
CN210263097U (en) * 2019-05-10 2020-04-07 浙江东欣建设集团有限公司 Basement outer wall waterproof construction
CN212801559U (en) * 2020-07-13 2021-03-26 中电建十一局工程有限公司 Soil nail wall drainage device
CN112879050A (en) * 2021-02-10 2021-06-01 中国电建集团成都勘测设计研究院有限公司 Waterproof structure of drainage type tunnel primary support system and construction method thereof

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120102851A1 (en) * 2010-10-29 2012-05-03 United Waterproofing Corp Apparatus and Method for Waterproofing a Basement
CN105544622A (en) * 2015-06-05 2016-05-04 龚展宇 Floating resisting device, and seepage insulation device and drainage path checking device thereof for underground building
CN206754608U (en) * 2017-03-30 2017-12-15 深圳市沃特玛电池有限公司 A kind of adjustable rotary joint
CN206844172U (en) * 2017-05-03 2018-01-05 深圳艺洲建筑工程设计有限公司 A kind of basement bottom board catchments drain structure
CN207245184U (en) * 2017-09-01 2018-04-17 重庆钢铁集团建设工程有限公司 A kind of new cooling sealing up screw
CN108316354A (en) * 2018-03-29 2018-07-24 沈阳建筑大学 With waterproof, the underground pipe gallery structure of drain function and its construction method
CN108442699A (en) * 2018-04-28 2018-08-24 山东建筑大学 A kind of split bolt for pouring miniature underground pipe gallery
CN210263097U (en) * 2019-05-10 2020-04-07 浙江东欣建设集团有限公司 Basement outer wall waterproof construction
CN212801559U (en) * 2020-07-13 2021-03-26 中电建十一局工程有限公司 Soil nail wall drainage device
CN112879050A (en) * 2021-02-10 2021-06-01 中国电建集团成都勘测设计研究院有限公司 Waterproof structure of drainage type tunnel primary support system and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115075305A (en) * 2022-08-05 2022-09-20 中国十七冶集团有限公司 Basement waterproof structure and construction method
CN115075305B (en) * 2022-08-05 2023-09-08 中国十七冶集团有限公司 Basement waterproof structure and construction method

Also Published As

Publication number Publication date
CN113373985B (en) 2022-12-09

Similar Documents

Publication Publication Date Title
CN107326918B (en) Hidden type plugging impervious water collecting well penetrating through raft plates and construction process thereof
CN111365032B (en) Anti-seepage treatment method for ring beam of tunnel door of subway station
CN106320353B (en) A kind of construction method of basement construction Yield rainfall relation device
CN207177063U (en) Pre-buried air conditioner comdenstion water drain pipe sheathed tube prefabricated building block
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN113323440A (en) Concrete gap repairing and anti-seepage treatment method
CN216841801U (en) Shaft drainage system
CN212837843U (en) IV-class and V-class surrounding rock tunnel concrete lining anti-cracking structure
CN113373985B (en) Basement waterproof construction method
CN114150749A (en) Construction method for non-stop connection of new and old sewage wells
CN111321749A (en) Recyclable rapid dredging device for water leakage of foundation pit enclosure and construction method thereof
CN109723055B (en) Underground diaphragm wall bottom reinforcing structure and construction method thereof
CN220318582U (en) Well wall construction template of municipal administration tube well
CN114109442A (en) Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method
CN112761158B (en) Green construction method of integral three-wall-in-one outer wall of reverse engineering steel concrete key pin meshed row pile
CN106013168A (en) Slag trough structure and construction method for same
CN216475060U (en) Occlusive pile structure with reinforcing function
CN107460873B (en) Manual digging pile construction method
CN216130157U (en) Deep basal pit spring eye gushes water drainage structures
CN113445488A (en) Method for treating underground pipeline or karst cave
CN112610022B (en) Old building translation construction method near deep foundation pit
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN113957903A (en) Secant pile structure with reinforcing function and construction method thereof
CN107059944A (en) Basement seepage point gradually leak stopping structure and construction method
CN106051316A (en) Construction method for penetrating pool by pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant