CN113323424B - Intelligent construction method of fabricated building - Google Patents

Intelligent construction method of fabricated building Download PDF

Info

Publication number
CN113323424B
CN113323424B CN202110788599.XA CN202110788599A CN113323424B CN 113323424 B CN113323424 B CN 113323424B CN 202110788599 A CN202110788599 A CN 202110788599A CN 113323424 B CN113323424 B CN 113323424B
Authority
CN
China
Prior art keywords
wall body
arm
bracing piece
fixed
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110788599.XA
Other languages
Chinese (zh)
Other versions
CN113323424A (en
Inventor
管亮亮
沈家玲
方学娣
金双琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Chenhan Construction Group Co ltd
Original Assignee
Anhui Chenhan Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Chenhan Construction Group Co ltd filed Critical Anhui Chenhan Construction Group Co ltd
Priority to CN202110788599.XA priority Critical patent/CN113323424B/en
Publication of CN113323424A publication Critical patent/CN113323424A/en
Application granted granted Critical
Publication of CN113323424B publication Critical patent/CN113323424B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/142Means in or on the elements for connecting same to handling apparatus
    • E04G21/147Means in or on the elements for connecting same to handling apparatus specific for prefabricated masonry wall elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09FDISPLAYING; ADVERTISING; SIGNS; LABELS OR NAME-PLATES; SEALS
    • G09F13/00Illuminated signs; Luminous advertising
    • G09F13/16Signs formed of or incorporating reflecting elements or surfaces, e.g. warning signs having triangular or other geometrical shape

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses an intelligent construction method of an assembly type building, which comprises a ground, a wall body, a support rod, a steel bar and a connecting device, wherein the wall body is arranged at one end of the ground, the support rod is arranged between the wall body and the ground, the steel bar is arranged in the wall body and protrudes out of the wall body, the connecting device is arranged on the surface of the support rod and comprises a bottom plate, one end of the bottom plate and the support rod are fixedly installed, a sliding groove is formed in one end, far away from the support rod, of the bottom plate, two sliding rods are connected in the sliding groove in a sliding mode, one end, far away from the sliding groove, of each sliding rod is fixedly connected with a movable clamping plate, threaded holes are formed in the surfaces of the sliding rods, and screws are connected in the bottom plate in a threaded mode. Through setting up connecting device, can be in the same place a plurality of bracing pieces are fixed, and then when avoiding carrying a plurality of bracing pieces, a plurality of bracing pieces can't be fixed each other, lead to the condition emergence of unable disposable transport.

Description

Intelligent construction method of prefabricated building
Technical Field
The invention belongs to the technical field of assembly type buildings, and particularly relates to an intelligent construction method of an assembly type building.
Background
The prefabricated building refers to that a large amount of field operation work in the traditional construction mode is transferred to a factory, and building components and accessories such as: floor, wall board, stairs, balcony, etc. are transported to the construction site, and assembled and installed in site in reliable connection mode to form the building, which can greatly shorten the building construction time.
When an existing fabricated building is installed, a poured wall body is usually supported and fixed, most of the wall bodies are supported by support rods, a large number of support rods can be adopted during building, the support rods need to be carried before and after use, each support rod is independent and is not connected with each other, great inconvenience can be caused when the support rods are carried, protruding reinforcing steel bars can be arranged on the side wall of the poured wall body, workers need to hold aside to install the support rods when the supporting rods are installed, the protruding reinforcing steel bars do not have any protective measures, workers are easy to scratch when the supporting rods are installed, and the support rods which are fixed on the ground are easy to trip when construction site patrollers patrol at night.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide an intelligent construction method of an assembly type building, which solves the problems that a plurality of supporting rods are difficult to fix with each other and are carried at one time.
In order to achieve the purpose, the invention provides the following technical scheme: an intelligent construction method of an assembly type building comprises the following steps:
A. production: and pouring and molding the wall body in a factory, finishing the processing of the wall body, checking whether the poured wall body is qualified, performing quality inspection on the wall body, and waiting for delivery after the quality inspection is finished.
B. And (3) transportation: and loading the wall body after the quality inspection is finished, transporting the wall body to a construction site through a vehicle, placing the wall body, and waiting for hoisting.
C. Hoisting: the wall body is lifted through the tower crane, and after the wall body is lifted to a proper position, the wall body is butted through the ground workers, so that the wall body and other assembly bodies are butted and assembled, and the wall body is supported and fixed through the support rods.
Preferably, including ground, wall body, bracing piece, reinforcing bar and connecting device, the one end on ground is equipped with the wall body, be equipped with the bracing piece between wall body and the ground, the inside of wall body is equipped with the reinforcing bar, and the outstanding wall body of reinforcing bar, the surface of bracing piece is equipped with connecting device, connecting device includes the bottom plate, the one end and the bracing piece fixed mounting of bottom plate, the bottom plate is kept away from the one end of bracing piece and is seted up the spout, the inside sliding connection of spout has two slide bars, the slide bar is kept away from the one end fixedly connected with movable clamp plate of spout, the screw hole has been seted up on the surface of slide bar, the inside threaded connection of bottom plate has the screw.
Preferably, two first springs are fixedly mounted inside the sliding groove, and one end, far away from the sliding groove, of each first spring is fixedly connected with the sliding rod.
Preferably, two move the one end fixedly connected with connecting block that splint kept away from each other, the connecting block is "U" font, the one end fixed mounting that the bracing piece was kept away from to the bottom plate has the convex arm, the inside sliding connection of convex arm has the picture peg.
Preferably, the surface of reinforcing bar is equipped with protector, protector includes the lag, the inside of lag is hollow, the inside sliding connection of lag has two slip posts, two the one end fixed mounting that the slip post is close to each other has the arm lock, the one end fixedly connected with arm-tie that the arm lock was kept away from to the slip post, the one end fixed mounting of arm-tie has two shell fragments, the shell fragment is "V" font, the one end and the lag fixed connection of arm-tie are kept away from to the shell fragment, and the center pin symmetric distribution of two shell fragments with the arm-tie.
Preferably, the clamping arm is C-shaped, and the size of the clamping arm is matched with that of the steel bar.
Preferably, a rectangular groove is formed in the surface of the protecting sleeve, a fixing rod is connected to the inside of the rectangular groove in a sliding mode, and a fixing ring is welded to one end, far away from the elastic sheet, of the pulling plate.
Preferably, the surface of bracing piece is equipped with warning device, warning device includes the lasso, the inner wall and the bracing piece fixed connection of lasso, the standing groove has been seted up on the surface of lasso, the inside of standing groove is equipped with reflection of light strip, the inside sliding connection of standing groove has the clamp plate, the one end fixedly connected with handle of clamp plate, the fixed surface of lasso installs the welding piece, the inside sliding connection of welding piece has the gag lever post, the clamp plate is close to the one end of handle and has seted up spacing hole.
Compared with the prior art, the invention has the beneficial effects that:
1. through setting up connecting device, when the bracing piece is no longer used, with bracing piece and ground, after the wall body is demolishd, screw out from the threaded hole of slide bar, make slide bar and movable clamp plate no longer fixed, slide two slide bars to the direction of keeping away from each other this moment, make two slide bars take two movable clamp plates to move together, can take first spring to move together when the slide bar removes, let the slide bar, first spring, movable clamp plate and connecting block slide to the convex arm direction together, slide the picture peg to the direction of keeping away from the convex arm this moment, and then let the connecting block move to under the picture peg, after putting the connecting block, slide the picture peg back to the normal position, make the picture peg get into chucking between movable clamp plate and the connecting block, the picture peg passes through the connecting block and will move movable clamp plate fixed, and then avoid movable clamp plate and slide bar to receive the elastic force influence of first spring and reset, put another bracing piece between two movable clamp plates this moment, make the surface and the bottom plate swing joint of bracing piece connect, after putting the picture peg out from the connecting block, make movable clamp plate fixed by the first spring in the slide bar, thereby can's screw thread hole can's not take place the fixed clamp plate and the fixed screw hole together, thereby can's fixed two fixed support bars, thereby can's the fixed screw hole can's the fixed screw together, the fixed screw can's not take place, and the fixed screw hole can's the fixed condition.
2. Through setting up protector, through pulling two arm-stays, let two arm-stays take two arm-stays to the direction slip of keeping away from each other through the slip post, the arm-stay can take solid fixed ring and shell fragment to move together when moving, when solid fixed ring remove with the dead lever when collinear and stop, the dead lever in the slip rectangular channel, it is internal fixed to slide the dead lever into the fixed ring, the dead lever passes through solid fixed ring with the arm-stay, the slip post, arm-stay and shell fragment are fixed, at this moment with the surface of lag cover at the reinforcing bar port, after the lag cover is good, take out the dead lever from the fixed ring, make solid fixed ring no longer fixed, the shell fragment on lag surface resumes elasticity this moment, the shell fragment takes solid fixed ring through the arm-stay, slip post and arm-stay reset, make two "C" font arm-stays to clip the reinforcing bar, and let lag and reinforcing bar fixed, through setting up protector, can fix the port department of lag and reinforcing bar, and then avoid the staff when hoisting the wall body, because the wall body can make a round trip to rock, the condition that leads to outstanding turning fish tail staff on the wall body takes place.
3. Through setting up warning device, through the pulling handle, let the handle take the clamp plate to the direction slip of keeping away from the standing groove, thereby space grow between standing groove and the clamp plate, thereby conveniently put into the standing groove with reflection of light strip, make reflection of light strip be in between standing groove and the clamp plate, surround ferrule winding a week with reflection of light strip, and reflection of light strip's initiating terminal and terminal coincidence, all be located the clamp plate under, after putting reflection of light strip, with the clamp plate slip home position, press reflection of light strip with the clamp plate, slide the gag lever post on the welded block this moment, let the gag lever post get into the spacing downthehole of clamp plate and fix, make the gag lever post fixed the clamp plate, the clamp plate is fixed reflection of light strip in the ferrule, through setting up warning device, can fix reflection of light strip in the standing groove of ferrule, when staff tours night, light can shine on reflection of light strip, and then avoid the staff to be stumbled the condition emergence of taking place by the bracing piece.
Drawings
FIG. 1 is a schematic structural view of a wall according to the present invention;
FIG. 2 is a schematic structural view of a support rod according to the present invention;
FIG. 3 is a schematic view of the connecting device of the present invention;
FIG. 4 is a schematic structural diagram of a slide bar according to the present invention;
FIG. 5 is a schematic view of the structure of the protection device of the present invention;
FIG. 6 is a schematic view of the structure of FIG. 5 at A in accordance with the present invention;
fig. 7 is a schematic structural diagram of the warning device of the present invention.
In the figure: 1. a ground surface; 2. a wall body; 3. a support bar; 4. a connecting device; 41. a base plate; 42. a chute; 43. a slide bar; 44. a movable clamping plate; 45. a first spring; 46. a screw; 47. connecting blocks; 48. a convex arm; 49. inserting plates; 5. reinforcing steel bars; 6. a guard; 61. a protective sleeve; 62. a sliding post; 63. clamping arms; 64. pulling a plate; 65. a spring plate; 66. a rectangular groove; 67. fixing the rod; 68. a fixing ring; 7. a warning device; 71. a ferrule; 72. a placement groove; 73. pressing a plate; 74. a handle; 75. welding the blocks; 76. a limiting hole; 77. a limiting rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
The first embodiment is as follows:
referring to fig. 1-7, the present invention provides a technical solution: an intelligent construction method of an assembly type building comprises the following steps: and pouring and molding the wall body 2 in a factory, finishing processing the wall body 2, checking whether the poured wall body 2 is qualified, performing quality inspection on the wall body, and waiting for delivery after the quality inspection is finished.
B. And (3) transportation: and (3) loading the wall body 2 after the quality inspection is finished, transporting the wall body 2 to a construction site through a vehicle for placing, and waiting for hoisting.
C. Hoisting: hang wall body 2 through the tower crane, after hanging wall body 2 to suitable position again, the staff through subaerial 1 docks wall body 2, make wall body 2 and other assembly bodies dock the assembly, reuse bracing piece 3 supports fixedly wall body 2, including ground 1, wall body 2, bracing piece 3, reinforcing bar 5 and connecting device 4, the one end of ground 1 is equipped with wall body 2, be equipped with bracing piece 3 between wall body 2 and the ground 1, the inside of wall body 2 is equipped with reinforcing bar 5, and reinforcing bar 5 extrudes wall body 2, the surface of bracing piece 3 is equipped with connecting device 4, connecting device 4 includes bottom plate 41, the one end and the bracing piece 3 fixed mounting of bottom plate 41, bottom plate 41 keeps away from the one end of bracing piece 3 and has seted up spout 42, the inside sliding connection of spout 42 has two slide bars 43, the one end fixedly connected with movable clamp plate 44 that spout 42 was kept away from to slide bar 43, the screw hole has been seted up on the surface of slide bar 43, the inside threaded connection of bottom plate 41 has screw 46, the inside fixed mounting of spout 42 has two first spring 45, the one end and the slide bar 43 fixed connection that spout 42 were kept away from to first spring 45.
In this embodiment, through pouring wall body 2 in the mill after carrying out quality control, get into the building site and assemble after quality control is accomplished, wall body 2 after the assembly is accomplished need support fixedly through bracing piece 3, after bracing piece 3 used up, bracing piece 3 need be collected, drive two movable clamp plate 44 and first spring 45 through two slide bars 43 and slide to the direction of keeping away from each other, and then let the space between two movable clamp plate 44 grow, conveniently put into bracing piece 3 between two movable clamp plate 44 this moment, loose movable clamp plate 44 after putting bracing piece 3 and let first spring 45 resume elasticity, first spring 45 drives movable clamp plate 44 through slide bar 43 and resets, make two movable clamp plate 44 clip bracing piece 3, reuse screw 46 and the screw hole on slide bar 43 surface fixed, make screw 46 fixed slide bar 43, slide bar 43 fixes bracing piece 3 through movable clamp plate 44.
The second embodiment:
as shown in fig. 1 to 7, on the basis of the first embodiment, the present invention provides a technical solution: one end of each movable clamping plate 44, which is far away from each other, is fixedly connected with a connecting block 47, the connecting block 47 is in a U shape, one end of the bottom plate 41, which is far away from the supporting rod 3, is fixedly provided with a convex arm 48, and the inner part of the convex arm 48 is slidably connected with an inserting plate 49.
In this embodiment, after the two movable clamping plates 44 move away from each other, the connecting block 47 on the movable clamping plate 44 is located right below the inserting plate 49, the inserting plate 49 is used to fix the connecting block 47, so that the inserting plate 49 fixes the movable clamping plate 44 through the connecting block 47, and the support rod 3 is further conveniently installed between the two movable clamping plates 44.
Example three:
as shown in fig. 1 to 7, on the basis of the first embodiment and the second embodiment, the present invention provides a technical solution: the surface of reinforcing bar 5 is equipped with protector 6, protector 6 includes lag 61, the inside of lag 61 is hollow, the inside sliding connection of lag 61 has two slip posts 62, the one end fixed mounting that two slip posts 62 are close to each other has arm lock 63, the one end fixedly connected with arm lock 64 that arm lock 63 was kept away from to slip post 62, the one end fixed mounting of arm lock 64 has two shell fragments 65, shell fragment 65 is "V" font, the one end and the lag 61 fixed connection of arm lock 64 are kept away from to shell fragment 65, and the center pin symmetric distribution of two shell fragments 65 with arm lock 64, arm lock 63 is "C" font, the size of arm lock 63 and the big or small looks adaptation of reinforcing bar 5, rectangular channel 66 has been seted up on the surface of lag 61, the inside sliding connection of rectangular channel 66 has the dead lever 67, the one end welding that arm lock 65 was kept away from to arm lock 64 has solid fixed ring 68.
In this embodiment, cover lag 61 on reinforcing bar 5 surface, slide two slip post 62 and arm lock 63 to the direction of keeping away from each other, reuse dead lever 67 through solid fixed ring 68 with slip post 62 and arm lock 63 fixed, cover lag 61 this moment on reinforcing bar 5, after having covered lag 61, reset slip post 62 and arm lock 63, clip with two arm lock 63 and reinforcing bar 5, let two arm lock 63 take lag 61 and reinforcing bar 5 fixed, and then play the effect of protection.
Example four:
as shown in fig. 1 to 7, on the basis of the first embodiment, the second embodiment and the third embodiment, the present invention provides a technical solution: the surface of bracing piece 3 is equipped with warning device 7, warning device 7 includes lasso 71, the inner wall and the bracing piece 3 fixed connection of lasso 71, standing groove 72 has been seted up on the surface of lasso 71, the inside of standing groove 72 is equipped with reflective strip, the inside sliding connection of standing groove 72 has clamp plate 73, the one end fixedly connected with handle 74 of clamp plate 73, the fixed surface of lasso 71 installs welding block 75, the inside sliding connection of welding block 75 has gag lever post 77, spacing hole 76 has been seted up to the one end that clamp plate 73 is close to handle 74.
In this embodiment, through putting reflection of light strip in standing groove 72, reuse clamp plate 73 is pressing reflection of light strip for reflection of light strip is in the standing groove 72 of lasso 71, and gag lever post 77 in the welding piece 75 that slides again makes gag lever post 77 fixed with clamp plate 73, makes clamp plate 73 fixed with reflection of light strip, thereby avoids the staff to see not clearly bracing piece 3 when patrolling night, leads to being taken place by the condition that bracing piece 3 stumbled.
The working principle and the using process of the invention are as follows: by arranging the connecting device 4, when the supporting rod 3 is not used any more, after the supporting rod 3, the ground 1 and the wall 2 are dismantled, the screw 46 is screwed out of the threaded hole of the sliding rod 43, so that the sliding rod 43 and the movable clamping plate 44 are not fixed any more, at the moment, the two sliding rods 43 slide towards the direction away from each other, so that the two sliding rods 43 drive the two movable clamping plates 44 to move together, the sliding rod 43 drives the first spring 45 to move together, the sliding rod 43, the first spring 45, the movable clamping plate 44 and the connecting block 47 slide towards the convex arm 48 together, at the moment, the inserting plate 49 slides towards the direction away from the convex arm 48, further the connecting block 47 moves to the right below the inserting plate 49, after the connecting block 47 is placed, the inserting plate 49 slides back to the original position, so that the inserting plate 49 enters between the movable clamping plate 44 and the connecting block 47 to clamp the inserting plate 49, and the movable clamping plate 44 is fixed by the connecting block 47, further avoiding the movable clamping plate 44 and the sliding rod 43 from being reset under the influence of the elastic force of the first spring 45, at this time, another supporting rod 3 is placed between the two movable clamping plates 44, so that the surface of the supporting rod 3 is movably connected with the bottom plate 41, after the supporting rod 3 is protected, the inserting plate 49 is taken out of the connecting block 47, so that the movable clamping plate 44 is not fixed any more, at this time, the first spring 45 in the sliding groove 42 recovers the elastic force, the first spring 45 drives the sliding rod 43, the movable clamping plate 44 and the connecting block 47 to reset, so that the two movable clamping plates 44 clamp the supporting rod 3, the threaded holes and the screws 46 on the surface of the sliding rod 43 are in the same straight line, the screwing screws 46 enter the threaded holes of the sliding rod 43 to be fixed, the screws 46 fix the sliding rod 43 and the movable clamping plate 44, the two movable clamping plates 44 fix the supporting rod 3, through the arrangement of the connecting device 4, the plurality of supporting rods 3 can be fixed together, further avoiding the carrying of the plurality of the supporting rods 3, the plurality of support rods 3 cannot be fixed to each other, so that the support rods cannot be carried at one time.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. An intelligent construction method of an assembly type building is characterized in that: the method comprises the following steps:
A. production: pouring and molding the wall body (2) in a factory, finishing processing the wall body (2), checking whether the poured wall body (2) is qualified, performing quality inspection on the wall body, and waiting for delivery after the quality inspection is finished;
B. and (3) transportation: loading the wall body (2) after the quality inspection is finished, transporting the wall body (2) to a construction site through a vehicle for placing, and waiting for hoisting;
C. hoisting: the wall body (2) is lifted by the tower crane, the wall body (2) is lifted to a proper position, the wall body (2) is butted by workers on the ground (1), the wall body (2) and other assembly bodies are butted and assembled, and the wall body (2) is supported and fixed by the support rods (3);
the one end of ground (1) is equipped with wall body (2), be equipped with bracing piece (3) between wall body (2) and ground (1), the inside of wall body (2) is equipped with reinforcing bar (5), and reinforcing bar (5) outstanding wall body (2), the surface of bracing piece (3) is equipped with connecting device (4), connecting device (4) are including bottom plate (41), the one end and bracing piece (3) fixed mounting of bottom plate (41), the one end that bracing piece (3) were kept away from in bottom plate (41) has seted up spout (42), the inside sliding connection of spout (42) has two slide bars (43), the one end fixedly connected with who keeps away from spout (42) of slide bar (43) moves splint (44), the screw hole has been seted up on the surface of slide bar (43), the inside threaded connection of bottom plate (41) has screw (46).
2. The intelligent construction method of an assembly type building according to claim 1, wherein: two first springs (45) are fixedly mounted inside the sliding groove (42), and one end, far away from the sliding groove (42), of each first spring (45) is fixedly connected with the sliding rod (43).
3. The intelligent construction method of an assembly type building according to claim 1, wherein: two move splint (44) one end fixedly connected with connecting block (47) of keeping away from each other, connecting block (47) are "U" font, the one end fixed mounting that bracing piece (3) were kept away from in bottom plate (41) has protruding arm (48), the inside sliding connection of protruding arm (48) has picture peg (49).
4. The intelligent construction method of an assembly type building according to claim 1, wherein: the surface of reinforcing bar (5) is equipped with protector (6), protector (6) include lag (61), the inside of lag (61) is hollow, the inside sliding connection of lag (61) has two slip posts (62), two the one end fixed mounting that slip post (62) are close to each other has arm lock (63), the one end fixedly connected with arm-tie (64) of arm lock (63) are kept away from in slip post (62), the one end fixed mounting of arm-tie (64) has two shell fragments (65), shell fragment (65) are "V" font, the one end and lag (61) fixed connection of arm-tie (64) are kept away from in shell fragment (65), and the center pin symmetric distribution of two shell fragments (65) with arm-tie (64).
5. The intelligent construction method of the fabricated building according to claim 4, wherein: the clamping arm (63) is C-shaped, and the size of the clamping arm (63) is matched with that of the steel bar (5).
6. The intelligent construction method of the fabricated building according to claim 4, wherein: rectangular channel (66) have been seted up on the surface of lag (61), the inside sliding connection of rectangular channel (66) has dead lever (67), the one end welding that shell fragment (65) were kept away from in arm-tie (64) has solid fixed ring (68).
7. The intelligent construction method of an assembly type building according to claim 1, wherein: the surface of bracing piece (3) is equipped with warning device (7), warning device (7) are including lasso (71), the inner wall and bracing piece (3) fixed connection of lasso (71), standing groove (72) have been seted up on the surface of lasso (71), the inside of standing groove (72) is equipped with anti-light strip, the inside sliding connection of standing groove (72) has clamp plate (73), the one end fixedly connected with handle (74) of clamp plate (73), the fixed surface of lasso (71) installs welding block (75), the inside sliding connection of welding block (75) has gag lever post (77), spacing hole (76) have been seted up to the one end that clamp plate (73) are close to handle (74).
CN202110788599.XA 2021-07-13 2021-07-13 Intelligent construction method of fabricated building Active CN113323424B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110788599.XA CN113323424B (en) 2021-07-13 2021-07-13 Intelligent construction method of fabricated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110788599.XA CN113323424B (en) 2021-07-13 2021-07-13 Intelligent construction method of fabricated building

Publications (2)

Publication Number Publication Date
CN113323424A CN113323424A (en) 2021-08-31
CN113323424B true CN113323424B (en) 2022-10-28

Family

ID=77426133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110788599.XA Active CN113323424B (en) 2021-07-13 2021-07-13 Intelligent construction method of fabricated building

Country Status (1)

Country Link
CN (1) CN113323424B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114263414B (en) * 2021-11-12 2024-06-25 广州花都广建工程建设有限公司 Building window and city intelligent building

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951998A (en) * 2016-06-30 2016-09-21 三新房屋制造股份有限公司 Integrated assembly type residential system and construction method thereof

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7040059B2 (en) * 2003-09-20 2006-05-09 Hodsdon Edwin R Method and adjustable apparatus for anchor-free masonry wall bracing
CN101818539B (en) * 2010-06-04 2012-02-08 北京万科企业有限公司 Assembled integral building and construction method thereof
CN102127934A (en) * 2011-01-30 2011-07-20 上海建工集团股份有限公司 Prefabricated outer wall external thermal insulation structure and construction method thereof
CN210396195U (en) * 2019-07-12 2020-04-24 苏州嘉盛建设工程有限公司 Prefabricated outer heat preservation PCF wallboard strutting arrangement of assembled

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951998A (en) * 2016-06-30 2016-09-21 三新房屋制造股份有限公司 Integrated assembly type residential system and construction method thereof

Also Published As

Publication number Publication date
CN113323424A (en) 2021-08-31

Similar Documents

Publication Publication Date Title
CN113323424B (en) Intelligent construction method of fabricated building
CN204571259U (en) A kind of annular inspection platform being applicable to blower fan tower barrel maintenance
CN217975496U (en) Construction elevator well protective structure is built to building room
CN215971961U (en) Railing that marine security performance is high
CN215331524U (en) Reverse-installation type gear rack demolding device
CN214495373U (en) Protection device for glass installation and construction
CN108729673A (en) A kind of tool-typed formwork hoisting die construction method at plate face difference of height
CN213199849U (en) Finished product conveyor of light environmental protection concrete building block brick
CN211949708U (en) Railing is prevented to building engineering instrument formula stair
CN210369868U (en) Bracing structure of disc type scaffold
CN112428913A (en) Platform trailer for transferring concrete segments
CN112072581A (en) Pipeline erecting device for assembled wall
CN218990858U (en) Portable hanging flower basket device
CN221168693U (en) Be used for box structure bottom surface clear water concrete construction template
CN216476272U (en) Scaffold net rack connecting device
CN217653622U (en) Toughened glass curtain wall spontaneous explosion risk detection device
CN209922760U (en) Tower crane safety protection cat ladder
CN220336428U (en) Novel embedded type turnover outer frame wall connecting piece
CN219889180U (en) Fire control monitoring device convenient to installation
CN218715127U (en) Be used for concrete building one-time to pour fashioned aluminium template mounting structure
CN216690382U (en) Building concrete construction plank sheathing anchor clamps
CN215166902U (en) Combined unit type curtain wall nondestructive connecting structure
CN213140539U (en) A holder for slab
CN212687396U (en) Bridge crane frame beam convenient to installation
CN208858175U (en) A kind of wallboard cleaning bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 241000 No.6 Fuyuan Road, Jiujiang Economic Development Zone, Wuhu City, Anhui Province

Applicant after: Anhui Chenhan Construction Group Co.,Ltd.

Address before: 241000 No.6 Fuyuan Road, Jiujiang Economic Development Zone, Wuhu City, Anhui Province

Applicant before: Anhui Chenhan Construction Engineering Co.,Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: An Intelligent Construction Method for Prefabricated Buildings

Granted publication date: 20221028

Pledgee: Wuhu Yan'an Road Sub branch of Huishang Bank Co.,Ltd.

Pledgor: Anhui Chenhan Construction Group Co.,Ltd.

Registration number: Y2024980014364

PE01 Entry into force of the registration of the contract for pledge of patent right