CN113309539A - Tunnel supporting structure with shock attenuation and stress early warning effect - Google Patents

Tunnel supporting structure with shock attenuation and stress early warning effect Download PDF

Info

Publication number
CN113309539A
CN113309539A CN202110787154.XA CN202110787154A CN113309539A CN 113309539 A CN113309539 A CN 113309539A CN 202110787154 A CN202110787154 A CN 202110787154A CN 113309539 A CN113309539 A CN 113309539A
Authority
CN
China
Prior art keywords
foam concrete
layer
concrete pouring
spring
pouring layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110787154.XA
Other languages
Chinese (zh)
Inventor
路沙沙
徐红
聂伟
尹航
张亚楠
王中胜
冯若若
赵东旭
靳才
罗祖良
王兴隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Technical University
Original Assignee
Liaoning Technical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Technical University filed Critical Liaoning Technical University
Priority to CN202110787154.XA priority Critical patent/CN113309539A/en
Publication of CN113309539A publication Critical patent/CN113309539A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/155Laggings made of strips, slats, slabs or sheet piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • E21F17/185Rock-pressure control devices with or without alarm devices; Alarm devices in case of roof subsidence

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a tunnel supporting construction with shock attenuation and stress early warning effect, includes interior outer foam concrete placement layer, seals the backup pad of U-shaped, foam concrete is for the novel foam concrete material of doping tip area crotch shaped steel fibre, concrete placement layer is pour inside two-layer foam concrete, the U-shaped backup pad passes through the spring and is connected with foam concrete, the inside pressure sensor that is equipped with of spring, pressure sensor with pilot lamp and power in the U-shaped backup pad link to each other, the U-shaped backup pad is for sealing mouthful shape to the bottom welding has the conical body, can effectively prevent that the backup pad from sinking and the phenomenon of side shifting. The supporting plate is connected with the foam concrete through the spring, so that the influence caused by vibration can be effectively reduced, the phenomenon of stress concentration is avoided, the damage degree of the top stress of the concrete pouring layer is prolonged, and the phenomenon of damage caused by exceeding the stress can be timely warned.

Description

Tunnel supporting structure with shock attenuation and stress early warning effect
Technical Field
The invention belongs to the technical field of tunnel construction, and particularly relates to a tunnel supporting structure with shock absorption and stress early warning functions.
Background
In recent years, the progress of the construction of modern cities in China is faster and faster, and the construction of underground rail transit, urban subway industry and mine roadway chambers is continuously developed. At present, the most widely applied structures of tunnel supporting are metal supports, U-shaped steel supports, anchor-shotcrete supporting, anchor-net-shotcrete supporting and the like, and in the using process, due to the fact that the strength of the supports is low, the contractibility is small, a plurality of problems are caused due to vibration and the fact that the problems cannot be found in time, the situation is frequent, and loss is caused.
Therefore, before the supporting structure is applied to actual engineering, an indoor model test is needed to measure the bearing capacity and deformation condition of the supporting structure and find weak parts of the supporting structure in time so as to adjust the supporting structure in the actual engineering.
At present, with the development of construction in China, the phenomenon that supports are damaged due to vibration exists, and serious influence cannot be found in time, so that a tunnel support structure with the functions of shock absorption and stress early warning is needed.
Disclosure of Invention
Based on the analysis and in combination with the defects in the prior art, the invention solves the problem of providing the tunnel supporting structure with the functions of shock absorption and stress early warning, which can effectively reduce the influence of shock on the tunnel, avoid the damage of the supporting structure caused by the shock, avoid the economic influence caused by the untimely discovery, prolong the service life of the supporting structure and play a role of effective early warning.
In order to solve the technical problems, the invention is realized by the following technical scheme:
the invention provides a tunnel supporting structure with shock absorption and stress early warning functions.
Novel foam concrete materials with hook-shaped steel fibers at the end parts are poured in the outer layer foam concrete pouring layer and the inner layer foam concrete pouring layer;
the outer layer foam concrete pouring layer and the inner layer foam concrete pouring layer are poured inside the tunnel.
The concrete pouring layer is poured between the outer layer foam concrete pouring layer and the inner layer foam concrete pouring layer.
The sealing U-shaped supporting plate is connected with the inner-layer foam concrete pouring layer through a spring, the bottom of the sealing U-shaped supporting plate is embedded in the bottom surface of the inside of the tunnel, and a plurality of conical bodies are fixedly welded at the bottom of the sealing U-shaped supporting plate;
the upper surface of sealing the U-shaped backup pad is equipped with a plurality of first spring grooves, first spring inslot portion is placed the spring, the upper portion of spring is connected inlayer foam concrete placement layer, the lower surface on inlayer foam concrete placement layer is equipped with second spring groove, the upper portion of spring is located in the second spring inslot, just first spring groove sets up with second spring groove one-to-one.
And an anti-corrosion silica gel sleeve is arranged inside the spring.
And a pressure sensor is arranged inside the anti-corrosion silica gel sleeve.
And opening square grooves are arranged below all the first spring grooves in the sealing U-shaped supporting plate.
And an indicator light and a power supply are fixed inside the square groove of the opening.
The pressure sensor is connected with the indicator light and the power supply.
The technical scheme of the tunnel supporting structure with the shock absorption and stress early warning functions comprises the following steps:
preferably, the upper surface of the U-shaped supporting plate is provided with a plurality of first spring grooves, the springs are placed in the first spring grooves, the upper portions of the springs are connected with the inner-layer foam concrete pouring layer, the lower surface of the inner-layer foam concrete pouring layer is provided with second spring grooves, the upper portions of the springs are located in the second spring grooves, and the first spring grooves and the second spring grooves are arranged in a one-to-one correspondence mode.
Preferably, 2-5% by volume of steel fibers with hooks at the end parts are added into the outer foam concrete pouring layer, foam concrete is pumped in the metal formwork and the inner wall space of the tunnel from bottom to top through a concrete filling pump, and the mold is disassembled after the concrete reaches the designed strength.
Further, the concrete pouring layer pumps the foam concrete from bottom to top in the metal template and the lower surface space of the outer layer foam concrete pouring layer through a concrete filling pump, and the mould is disassembled after the concrete reaches the designed strength.
Furthermore, 2-5% by volume of steel fibers with hooks at the end parts are added into the inner-layer foam concrete pouring layer, foam concrete is pumped from bottom to top in the metal template and the space on the lower surface of the concrete pouring layer through a concrete filling pump, and the mold is disassembled after the concrete reaches the designed strength.
Further, seal U-shaped backup pad bottom fixed welding and have the conical body, seal U-shaped backup pad with the conical body is pre-buried in the inside bottom surface in tunnel.
By above, add the steel fibre of tip area crotch type and can increase the intensity on foam concrete pouring layer, can reach the effect of fixed tunnel supporting construction steadily simultaneously, prevent that supporting construction from taking place to remove, increase the contact surface with the tunnel bottom, prevent to sink with the side displacement.
Preferably, the U-shaped supporting plate for sealing is connected with the inner layer foam concrete pouring layer through a spring.
Furthermore, the spring is stainless steel, the lower part of the spring is welded in a first spring groove formed in the upper surface of the sealed U-shaped supporting plate, and the upper part of the spring is placed in a second spring groove formed in the lower surface of the inner foam concrete pouring layer.
Therefore, the tunnel supporting structure can be effectively protected by arranging the springs and the foam concrete layer, so that the tunnel supporting structure is prevented from being damaged by impact and vibration resistance, and the service life of the supporting structure is prolonged; and the supporting device is convenient to construct, and the construction steps are simple, so that the manufacturing cost is reduced.
Preferably, the pressure sensor is a sensor with high precision and is fully in contact with the sealing U-shaped supporting plate and the inner layer foam concrete pouring layer.
Furthermore, the indicator light is an indicator light with low power consumption and high brightness, the change of the indicator light can be better reflected, the power supply equipment with large storage capacity is selected for the power supply, and the pressure sensor, the indicator light and the power supply are connected through wires with good conductivity.
Therefore, the invention can timely warn whether the supporting structure reaches the damage limit or not by arranging the pressure sensor, the indicator light and the power supply, and can effectively prevent and reduce the serious influence caused by an emergency.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings of the embodiments will be briefly described below.
FIG. 1 is a schematic view of a tunnel supporting structure with shock absorption and stress early warning functions according to the present invention;
FIG. 2 is a partial schematic view of the closed U-shaped support plate of the present invention connected to an inner foam concrete pour layer;
FIG. 3 is a schematic cross-sectional view of the U-shaped support plate of the closure of the present invention attached to the inner foam concrete pour layer.
In the figure: 1-outer foam concrete pouring layer; 2-concrete pouring layer; 3-inner layer foam concrete pouring layer; 4-sealing the U-shaped supporting plate; 5-a spring; 6-a cone; 7-a first spring groove; 8-a second spring groove; 9-anti-corrosion silica gel sleeve; 10-a pressure sensor; 11-open square groove; 12-an indicator light; 13-power supply.
Detailed Description
Other aspects, features and advantages of the present invention will become apparent from the following detailed description, taken in conjunction with the accompanying drawings, which form a part of this specification, and which illustrate, by way of example, the principles of the invention. In the referenced drawings, the same or similar components in different drawings are denoted by the same reference numerals.
Furthermore, the terms "upper portion", "space", "inner bottom surface", "upper surface", "lower surface", "provided with", "welded", "connected", etc., are to be understood broadly, such as "connected", which may be a fixed connection, a detachable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
As shown in fig. 1 to 3, the present invention provides a tunnel supporting structure with shock absorption and stress warning functions, which can effectively prevent a supporting plate from sinking and laterally moving after being stressed in some aspects, and can effectively resist a shock sensation in other aspects, so as to avoid damage to the supporting structure due to shock, avoid deformation and damage of the supporting structure due to extrusion or strong shock sensation, and further prolong the service life of the supporting structure; and prevent that supporting construction from taking place to destroy suddenly, cause the injury to inside equipment of tunnel and personnel. The tunnel sealing structure comprises an outer layer foam concrete pouring layer 1, a concrete pouring layer 2, an inner layer foam concrete pouring layer 3 and a sealing U-shaped support plate 4, wherein the outer layer foam concrete pouring layer 1 is poured inside a tunnel, the concrete pouring layer 2 is poured between the outer layer foam concrete pouring layer 1 and the inner layer foam concrete pouring layer 3, and the sealing U-shaped support plate 4 is connected with the inner layer foam concrete pouring layer 3 through a spring 5. Seal U-shaped backup pad 4 pre-buried in the inside bottom surface in tunnel, seal the fixed welding in U-shaped backup pad 4 bottom and have a plurality of coniform bodies 6.
According to the outer-layer foam concrete pouring layer 1, 2-5% by volume of steel fibers with hooks at the end parts are added, foam concrete is pumped in a metal template and a tunnel inner wall space from bottom to top through a concrete filling pump, and a mold is disassembled after the concrete reaches the designed strength. And the concrete pouring layer 2 pumps concrete in the lower surface spaces of the metal template and the outer layer foam concrete pouring layer 1 from bottom to top through a concrete filling pump, and the mould is disassembled after the concrete reaches the designed strength. And 2-5% by volume of steel fibers with hook-shaped ends are added into the inner-layer foam concrete pouring layer 3, foam concrete is pumped from bottom to top in the metal template and the lower surface space of the concrete pouring layer 2 through a concrete filling pump, and the mold is disassembled after the concrete reaches the designed strength.
The U-shaped supporting plate 4 for sealing is a stainless steel supporting plate, and the spring 5 is a stainless steel spring. The sealing U-shaped support plate 4 and the spring 5 can be prevented from rusting, and the service life of the sealing U-shaped support plate and the spring is prolonged.
According to the invention, 2-5% by volume of steel fiber with a hook at the end is added into the outer layer foam concrete pouring layer 1 and the inner layer foam concrete pouring layer 3, so that the strength of a supporting structure can be effectively increased, and the influence caused by vibration can be effectively reduced.
The indicating lamp 12 is an indicating lamp with various color changes, when the pressure sensor 10 bears different pressures, the displayed colors are different, early warning can be effectively carried out, and the condition that equipment and personnel in a tunnel are injured due to sudden damage of a supporting structure is avoided.
The anti-corrosion silica gel sleeve 9 has high strength, corrosion resistance and good contractibility, and the problem that the pressure sensor 10 is inaccurate in acquisition due to the influence of the anti-corrosion silica gel sleeve is avoided.
The power supply 13 of the invention is a concentrated power supply with high-strength storage effect, can be repeatedly used by one-time charging, avoids manual loss caused by repeated replacement and repeated charging, or can be connected with a circuit in a tunnel for power utilization.
The working principle of the tunnel supporting structure with shock absorption and stress warning function according to the present invention is briefly described with reference to fig. 1 to 3 in conjunction with the above description of the structural features:
through setting up and sealing U-shaped backup pad 4 and conical body 6, can play the supporting role to supporting construction better, prevent that the backup pad from taking place to sink and the phenomenon appearance that the side moved. Because the influence that vibrations brought supporting construction through the reduction that sets up spring 5 can be better, prevent that strutting arrangement from taking place to warp and damaging and prevent that the backup pad from bringing direct extrusion influence to inlayer foam concrete placement layer 3, through setting up outer foam concrete placement layer 1 and inlayer foam concrete placement layer 3, can effectual support concrete placement layer 2, avoid appearing stress concentration's phenomenon, and because the influence that the characteristic of foam concrete can effectual reduction vibrations bring concrete placement layer 2, can effectually avoid the destruction that vibrations brought whole supporting construction, and the support intensity of its own is strengthened simultaneously to extension supporting construction's life, prop up fine supporting effect to whole tunnel.
According to the invention, the pressure sensor 10, the indicator light 12 and the power supply 13 are arranged, the pressure sensor 10 can be used for receiving the pressure 4 between the inner concrete pouring layer 3 and the sealed U-shaped support plate, and further the stress condition of the whole supporting device is determined, and the pressure sensor 10 is arranged in multiple directions, and information is transmitted through the indicator light 12 in the open square groove 11, so that the stress and the stability condition of the whole supporting structure can be comprehensively reflected, and the loss caused by sudden damage is effectively reduced.
While the foregoing is directed to the preferred embodiment of the present invention, other and further embodiments of the invention may be devised without departing from the basic scope thereof, and the scope thereof is determined by the claims that follow.

Claims (5)

1. The tunnel supporting structure with the shock absorption and stress early warning functions is characterized by comprising an outer-layer foam concrete pouring layer, a concrete pouring layer, an inner-layer foam concrete pouring layer and a sealing U-shaped supporting plate, wherein the foam concrete pouring layer is poured inside a tunnel, the concrete pouring layer is poured between the outer-layer foam concrete pouring layer and the inner-layer foam concrete pouring layer, and the sealing U-shaped supporting plate is connected with the inner-layer foam concrete pouring layer through a spring. Seal U-shaped backup pad pre-buried in the inside bottom surface in tunnel, seal U-shaped backup pad bottom fixed welding and have a plurality of coniform bodies.
2. A tunnel supporting structure with shock absorption and stress warning functions as claimed in claim 1, wherein a plurality of first spring grooves are formed in the upper surface of the U-shaped supporting plate, the springs are placed in the first spring grooves, the upper portions of the springs are connected with the inner foam concrete pouring layer, second spring grooves are formed in the lower surface of the inner foam concrete pouring layer, the upper portions of the springs are located in the second spring grooves, and the first spring grooves and the second spring grooves are arranged in a one-to-one correspondence manner.
3. A tunnel supporting structure with shock absorption and stress early warning functions as claimed in claim 1, wherein an anti-corrosion silica gel sleeve is arranged inside the spring, and a pressure sensor is arranged inside the anti-corrosion silica gel sleeve.
4. The tunnel supporting structure with the functions of shock absorption and stress early warning as claimed in claim 1, wherein an open square groove is arranged below all the first spring grooves in the U-shaped supporting plate, and an indicator light and a power supply are fixed inside the open square groove.
5. A tunnel supporting structure with shock-absorbing and stress-warning functions as claimed in claim 3, wherein said pressure sensor is connected with an indicator light and a power supply.
CN202110787154.XA 2021-07-13 2021-07-13 Tunnel supporting structure with shock attenuation and stress early warning effect Pending CN113309539A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110787154.XA CN113309539A (en) 2021-07-13 2021-07-13 Tunnel supporting structure with shock attenuation and stress early warning effect

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110787154.XA CN113309539A (en) 2021-07-13 2021-07-13 Tunnel supporting structure with shock attenuation and stress early warning effect

Publications (1)

Publication Number Publication Date
CN113309539A true CN113309539A (en) 2021-08-27

Family

ID=77382141

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110787154.XA Pending CN113309539A (en) 2021-07-13 2021-07-13 Tunnel supporting structure with shock attenuation and stress early warning effect

Country Status (1)

Country Link
CN (1) CN113309539A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914901A (en) * 2021-11-11 2022-01-11 中国铁建大桥工程局集团有限公司 Tunnel supporting structure

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003129800A (en) * 2001-10-24 2003-05-08 Hazama Gumi Ltd Concrete placing method and its apparatus for tunnel
CN102562091A (en) * 2012-01-30 2012-07-11 中铁七局集团有限公司 Foam concrete shock absorbing structure of tunnel and construction method of foam concrete shock absorbing structure
CN202360107U (en) * 2012-01-30 2012-08-01 中铁七局集团武汉工程有限公司 Tunnel foam concrete shock-absorbing structure
CN203515598U (en) * 2013-10-18 2014-04-02 四川省交通运输厅公路规划勘察设计研究院 Tunnel supporting structure bridged active fault
JP2016069823A (en) * 2014-09-26 2016-05-09 鹿島建設株式会社 Method for constructing lining concrete and lining arch center
CN107120125A (en) * 2017-06-29 2017-09-01 西南交通大学 A kind of tunnel antidetonation support system suitable for the regional Cross-fault leveling of highlight lines
CN207776879U (en) * 2017-11-30 2018-08-28 兰州铁道设计院有限公司 A kind of deformation buffer structure applied in the larger tunnel of pressure from surrounding rock
CN209163872U (en) * 2018-11-12 2019-07-26 陕西铁路工程职业技术学院 A kind of tunnel protection tunnel deformation detection prior-warning device
CN110159314A (en) * 2019-05-07 2019-08-23 山东大学 A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt
CN110985079A (en) * 2019-11-25 2020-04-10 辽宁工程技术大学 Energy-absorbing impact-resistant roadway support method
CN111911205A (en) * 2020-09-18 2020-11-10 辽宁工程技术大学 Coal mining roadway supporting device with damping and buffering effects
CN212927865U (en) * 2020-06-13 2021-04-09 石家庄铁道大学 Tunnel supporting structure

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003129800A (en) * 2001-10-24 2003-05-08 Hazama Gumi Ltd Concrete placing method and its apparatus for tunnel
CN102562091A (en) * 2012-01-30 2012-07-11 中铁七局集团有限公司 Foam concrete shock absorbing structure of tunnel and construction method of foam concrete shock absorbing structure
CN202360107U (en) * 2012-01-30 2012-08-01 中铁七局集团武汉工程有限公司 Tunnel foam concrete shock-absorbing structure
CN203515598U (en) * 2013-10-18 2014-04-02 四川省交通运输厅公路规划勘察设计研究院 Tunnel supporting structure bridged active fault
JP2016069823A (en) * 2014-09-26 2016-05-09 鹿島建設株式会社 Method for constructing lining concrete and lining arch center
CN107120125A (en) * 2017-06-29 2017-09-01 西南交通大学 A kind of tunnel antidetonation support system suitable for the regional Cross-fault leveling of highlight lines
CN207776879U (en) * 2017-11-30 2018-08-28 兰州铁道设计院有限公司 A kind of deformation buffer structure applied in the larger tunnel of pressure from surrounding rock
CN209163872U (en) * 2018-11-12 2019-07-26 陕西铁路工程职业技术学院 A kind of tunnel protection tunnel deformation detection prior-warning device
CN110159314A (en) * 2019-05-07 2019-08-23 山东大学 A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt
CN110985079A (en) * 2019-11-25 2020-04-10 辽宁工程技术大学 Energy-absorbing impact-resistant roadway support method
CN212927865U (en) * 2020-06-13 2021-04-09 石家庄铁道大学 Tunnel supporting structure
CN111911205A (en) * 2020-09-18 2020-11-10 辽宁工程技术大学 Coal mining roadway supporting device with damping and buffering effects

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113914901A (en) * 2021-11-11 2022-01-11 中国铁建大桥工程局集团有限公司 Tunnel supporting structure
CN113914901B (en) * 2021-11-11 2024-04-09 中国铁建大桥工程局集团有限公司 Tunnel supporting structure

Similar Documents

Publication Publication Date Title
CN113309539A (en) Tunnel supporting structure with shock attenuation and stress early warning effect
CN115452256B (en) Sealing wall performance testing device and method for utilizing compressed air energy storage in abandoned roadway space
CN219641716U (en) Tunnel vault lining concrete pouring anti-void monitoring equipment
CN101319502A (en) Method for reducing concrete thickness of steel cofferdam back cover
CN101625061A (en) Pipelining emergent repairing method of prestressing steel cylinder concrete pipe
CN201883380U (en) Steel sand cylinder temporary support
CN208937244U (en) A kind of piston type slurries fluctuation pressure monitoring device
CN209129607U (en) A kind of adaptive protective device of Deep Vertical Well pit shaft based on constant resistance and large deformation structure
CN203248175U (en) Automatic coupling supporting device of mineshaft deep roadway
CN207878428U (en) A kind of hydraulic bolt formula jack-up unit wedge bracket guide frame
CN201614601U (en) Well lid structure
CN213743452U (en) A prevent drain bar for reducing cold district tunnel frozen swelling power
CN204000611U (en) A kind of vertical amount of decrease based on fail safety design is from early warning type boom system
CN210976604U (en) Dysmorphism pier stud template reinforced structure
CN211263479U (en) Novel laboratory is with dismantling grouting material calculus rate survey device
CN100473783C (en) Liquid bearing pier structure
CN202947890U (en) Water tank type test weight for bridge type crane static test
CN106049866A (en) Method for blocking holes of hollow cement bricks and product
CN207331429U (en) A kind of bridge with detachable Antivibration block
CN202580561U (en) Steel wire rope lubricator
CN204510293U (en) A kind of large diameter pile self-reaction force checkout gear being convenient to pouring concrete
CN205713866U (en) A kind of building water fender
CN201462321U (en) Emergency repair structure of pipeline of prestressed concrete cylinder pipe (PCCP)
CN209837691U (en) Shear wall template hole rubber plug rod piece
CN206320108U (en) A kind of ultra-thin two-way cylinder of big stroke with ball-type saddle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20210827