CN101625061A - Pipelining emergent repairing method of prestressing steel cylinder concrete pipe - Google Patents
Pipelining emergent repairing method of prestressing steel cylinder concrete pipe Download PDFInfo
- Publication number
- CN101625061A CN101625061A CN200910033929A CN200910033929A CN101625061A CN 101625061 A CN101625061 A CN 101625061A CN 200910033929 A CN200910033929 A CN 200910033929A CN 200910033929 A CN200910033929 A CN 200910033929A CN 101625061 A CN101625061 A CN 101625061A
- Authority
- CN
- China
- Prior art keywords
- cover plate
- hole
- interior lining
- lining panel
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
- Revetment (AREA)
Abstract
The invention relates to a pipelining emergent repairing method of an underground prestressing steel cylinder concrete pipe (hereinafter referred as to PCCP), in particular to an emergent repairing method for PCCP pipeling damaged by external force. According to the technical solution of the invention, a lining plate is arranged in the inner wall of a pipeline which corresponds to a damaged opening; a screw is arranged on the lining plate; a cover plate which covers the damaged opening is arranged on the external surface of the pipeline which corresponds to an exposed steel cylinder at the damaged opening; a rubber ring is arranged between the cover plate and the steel cylinder; the cover plate and the lining plate are mutually connected; a hollow cavity between the cover plate and the lining plate is filled with concrete; a steel plate which is connected with a sample plate is arranged above the cover plate; and the hollow cavities among the steel plate, the cover plate and a top plate are filled with fine stone concrete. The method can solve the problem that the usual repairing method takes much time, has great waste, high cost, etc.
Description
Technical field
The present invention relates to the method for repairing and mending of a kind of underground Prestressed concrete cylinder pipe (hereinafter to be referred as PCCP) pipeline, specifically a kind of PCCP pipeline is subjected to the emergency first-aid repair method of external force breakage.
Background technique
The present invention is mainly used in the PCCP pipeline and is subjected to emergency first-aid repair after the external force breakage is leaked.After the PCCP pipeline is buried underground, beaten because of bottom line pipeline circuit is failed to understand to miss by piling machinery sometimes, cause the pipeline seepage, traditional emergency repair method is that the PCCP pipe of this joint damage is thoroughly smashed, clear, replace the PCCP of this place's vacancy then with steel pipe fittings, such emergency repair method need be the water emptying in the original pipeline, just can carry out operation then, suppose 10 kilometers of impaired lengths of pipeline, 2 meters of pipe bores need more than 30,000 ton of water of emptying, and waste is big, the time of draining may be very long, and the activity duration of replacing impaired PCCP with steel pipe fittings is also very long, and the very long meeting of trunk line water stopping time causes very big loss to life of urban resident and industrial water.
Summary of the invention
The objective of the invention is to design a kind of Prestressed concrete cylinder pipe pipelining emergent repairing technology, big to solve common emergency repair method time length, waste, problems such as expense height.
According to technological scheme provided by the invention, described method comprises the steps:
Before interior lining panel is set, earlier carry out model, and it is standby to cut away a block plate according to the shape at damaged hole and size on model greater than damaged hole by the shape at damaged hole; Outside the pipeline around the damaged hole, cover rubber plate again, on described rubber plate, cut out the shape at damaged hole equally greater than damaged hole; Again model is pressed on the rubber plate, and makes hole and the hole on the model on the rubber plate all aim at damaged hole; Wearing the anchor ear of some strips below pipeline, all fixedlys connected with the lower limb of model in the end of all anchor ears, realizes preliminary pretension.
In step 1, suspension ring are set on interior lining panel earlier, when interior lining panel passes through damaged hole, pass described suspension ring with rope, then described interior lining panel is put into damaged hole, and utilize rope to be hung on the support.Long nut is set on interior lining panel; In step 3, when cover plate and interior lining panel are linked together, utilize bolt to pass hole on the cover plate, be screwed onto with long nut.In step 3, after the outer surface of described steel cylinder is placed rubber ring, coat polysulfide sealant on the outer surface of the steel cylinder outside rubber ring again.In step 3, after cover plate and interior lining panel are linked together, with top board cover board hole is sealed again, and top board and cover plate and screw rod are fixed together.In step 4, after steel plate and model are fixed together, are screwed onto on the screw rod with nut again, and clip the redundance of screw rod.
A kind of Prestressed concrete cylinder pipe pipelining emergent repairing structure, it is characterized in that: the inwall corresponding to damaged hole on pipeline is provided with interior lining panel, on described interior lining panel, screw rod is set, on pipeline, cover the cover plate at damaged hole, between cover plate and steel cylinder, rubber ring is arranged corresponding to the outer surface setting of the exposed steel cylinder in place, damaged hole; Described cover plate and described interior lining panel interconnect, and fill up concrete in the cavity between cover plate and interior lining panel; The steel plate that is connected on the model is being arranged above the cover plate, filling up pea gravel concreten in the cavity between described steel plate and cover plate and top board.
Coat polysulfide sealant on the outer surface of the steel cylinder outside rubber ring; Long nut is set on interior lining panel; Cover plate and interior lining panel utilize bolt to pass hole on the cover plate, are screwed onto with long nut; Cover board hole is on the cover board arranged, on cover plate, be provided for covering the top board of described cover board hole.
Model greater than damaged hole is arranged outside the pipeline corresponding to 1 place, damaged hole, and it is standby to cut away a block plate according to the shape at damaged hole and size on model; Outside the pipeline around the damaged hole, cover rubber plate, on described rubber plate, cut out the shape at damaged hole equally greater than damaged hole; Described model is pressed on the described rubber plate, and makes hole and the hole on the model on the rubber plate all aim at damaged hole; Wearing the anchor ear of some strips below pipeline, all fixedlys connected with the lower limb of model in the end of all anchor ears.
Advantage of the present invention is: general damaged openning is all at the upper half of pipe, this method does not need all water in the emptying pipe, only need reduce to liquid level below damaged mouthful and just can carry out operation, and the repairing time is short, not waste water resource, and expense is also much lower than traditional method.
Description of drawings
Fig. 1 is a damaged hole schematic cross-sectional view on the pipeline.
Fig. 2 is the schematic representation that adds among Fig. 1 behind anchor ear and the rubber plate.
Fig. 3 is the left view of Fig. 2.
Fig. 4 adds partial view behind upper bracket and the interior lining panel among Fig. 3.
Fig. 5 is the schematic representation that adds among Fig. 2 behind interior lining panel, support and cover plate and the top board.
Fig. 6 is the schematic representation behind the fill concrete among Fig. 5.
Fig. 7 is with cover plate and schematic representation after interior lining panel is fixedlyed connected.
Fig. 8 is the longitudinal section schematic representation after top board and cover plate are fixed together among Fig. 7.
Fig. 9 is the schematic representation after on the cover board filling up pea gravel concreten and adding upper steel plate.
Figure 10 is at fastening nut on the screw rod and the schematic representation after clipping unnecessary screw rod.
Figure 11 is whole repairing structural representation.
Embodiment
Described method comprises the steps:
Before interior lining panel 13 is set, earlier carry out model 8, and it is standby to cut away a block plate 27 according to the shape at damaged hole 1 and size on model 8 greater than damaged hole 1 by the shape at damaged hole 1; Outside the pipeline around the damaged hole 1, cover rubber plate 9 again, on described rubber plate 9, cut out the shape at damaged hole 1 equally greater than damaged hole 1; Again model 8 is pressed on the rubber plate 9, and makes hole and the hole on the model 8 on the rubber plate 9 all aim at damaged hole 1; Wearing the anchor ear 11 of some strips below pipeline, all fixedlys connected with the lower limb of model 8 in the end of all anchor ears 11, realizes preliminary pretension.
In step 1, suspension ring 14 are set on interior lining panel 13 earlier, during by damaged hole 1, pass described suspension ring 14 at interior lining panel 13 with rope, then described interior lining panel 13 is put into damaged hole 10, and utilize rope to be hung on the support 12.
In step 3, after the outer surface of described steel cylinder 5 is placed rubber ring 19, on the outer surface of the steel cylinder 5 in rubber ring 19 outsides, coat polysulfide sealant 21 again.
In step 3, after cover plate 18 and interior lining panel 13 are linked together, with top board 17 cover board hole 22 is sealed again, and top board 17 and cover plate 18 and screw rod 16 are fixed together.
7, the method for claim 1 is characterized in that: in step 4, after steel plate 27 and model 8 are fixed together, are screwed onto on the screw rod 16 with nut 28, and clip the redundance of screw rod 16.
The emergency first-aid repair structure of described PCCP pipeline is as shown in figure 11: the inwall corresponding to damaged hole 1 on pipeline is provided with interior lining panel 13, on described interior lining panel 13, screw rod 16 is set, on pipeline, cover the cover plate 18 at damaged hole 1, between cover plate 18 and steel cylinder 5, rubber ring 19 is arranged corresponding to the outer surface setting of the exposed steel cylinder 5 in 1 place, damaged hole; Described cover plate 18 interconnects with described interior lining panel 13, and fills up concrete 23 in the cavity of 13 of cover plate 18 and interior lining panels; The steel plate 27 that is connected on the model 8 is being arranged above the cover plate 18, in the cavity of 17 on described steel plate 27 and cover plate 18 and top board, filling up pea gravel concreten 26.
On the outer surface of the steel cylinder 5 in rubber ring 19 outsides, coat polysulfide sealant 21; Long nut 20 is set on interior lining panel 13; Cover plate 18 and interior lining panel 13 utilize bolt 25 to pass hole on the cover plate 18, are screwed onto with long nut 20; Cover board hole 22 is arranged on cover plate 18, on cover plate 18, be provided for covering the top board 17 of described cover board hole 22.
A kind of emergency repair method of typical PCCP pipeline is as follows:
The first step: interior lining panel is installed, and interior lining panel 13 adopts 20 Plate Steels, is rolled into the radian consistent with the PCCP internal diameter of the pipeline in advance, has cut an interior lining panel 13 by the shape at damaged hole 1, and the narrowest place of interior lining panel 13 is also narrower than interior layer concrete hole the widest position.Above damaged hole 1, adorn the support 12 of a channel-section steel, two hangers 14 of weldering on interior lining panel 13, hitch interior lining panel 13 with rope, interior lining panel 13 the narrowest places are put into pipeline along the maximum direction of the length at damaged hole 1, turn over 90 °, make interior lining panel 13 be close to the inwall of pipeline, seal whole damaged hole 1.
Second step: screw rod 16, rubber ring 19, cover plate 18 etc. are installed.Welding one M32 screw rod 16 in the middle of interior lining panel 13, earlier rubber ring 19 and cover plate 18 and top board 17 are placed on the position shown in Fig. 5,6 before the welding, cover plate 18 is spooled the radian consistent with steel cylinder 5 in advance, the foregoing model unanimity of size fundamental sum, peripheral big about 5 centimeters than damaged hole 1, correct position at cover plate 18 cuts the cover board hole 22 that is used on concrete perfusion, welds M20 in the relevant position of interior lining panel 13 and adds long nut 20.Described interior lining panel 13 utilizes described screw rod 16 to be connected with described support 12.
The 3rd step: repair interior tube core etc.In the pit of 13 of whole pipe and interior lining panels, fill up with concrete 23, (clean out and with blowtorch oven dry back) stamps polysulfide sealant 21 in position shown in Figure 6, cover plate 18 is down compressed, tightens the bolt 25 of 13 of cover plate 18 and interior lining panels, make steel cylinder 5, rubber ring 19, cover plate 18 three's good seals.At last top board 17 and cover plate 18 are welded, top board 17 welds with screw rod 16.
The 5th step: repair outer tube core etc.Remove support 12, fill out pea gravel concreten 26 in the outside of cover plate 13, originally the steel plate 27 that cut off on the saddle is refilled original position, hold groove before the benefit earlier successfully, weld with welding by one side then, tighten the bolt and nut of all M24 on the anchor ear 11, tighten the nut 28 of M32, prescind the redundance on the screw rod 16.
The 6th step: body is reinforced.With one section body bottom concreting of body injury installation saddle, more than 180 °, 180 ° of bodys are also good with concrete protective with the upper part up to body, and earthing was filled and led up after ne-leakage was checked in water flowing again.
Claims (10)
1, a kind of pipelining emergent repairing method of prestressing steel cylinder concrete pipe is characterized in that: described method comprises the steps:
Step 1 is provided with liner and pulls (13): the inwall corresponding to damaged hole (1) on pipeline is placed an interior lining panel (13), and the radian of described interior lining panel (13) and the inwall radian of described pipeline coincide; The size of described interior lining panel (13) should guarantee that interior lining panel (13) can put into pipeline by damaged hole (1), after putting into, can cover described damaged hole (1) fully at inner-walls of duct again, the position corresponding to damaged hole (1) outside described pipeline is provided with support (12);
Step 2 is installed cover plate: cover plate (18) and top board (17) are enclosed within on the screw rod (16), more described screw rod (16) are connected on the interior lining panel (13); Cover board hole (22) is set on described cover plate (18); Described interior lining panel (13) utilizes described screw rod (16) to be connected with described support (12);
Step 3, tube core in repairing: be filled up to concrete (23) in corresponding to the pit of interior lining panel (13) on the pipeline concordant with the steel cylinder (5) of pipeline, clean out and dry the outer surface of exposed steel cylinder (5) then, place rubber ring (19) at the outer surface of described steel cylinder (5) again; Then cover plate (18) is pressed on the rubber ring (19), and cover plate (18) and interior lining panel (13) are linked together;
Step 4, repair outer tube core: the described support (12) of dismantling earlier, fill up pea gravel concreten (26) in the pit of on pipeline, locating corresponding to cover plate (18), again with steel plate (27) with cover the model (8) that damaged hole (1) is located outside pipeline and be fixed together.
2, pipelining emergent repairing method of prestressing steel cylinder concrete pipe as claimed in claim 1, it is characterized in that: interior lining panel (13) is preceding being provided with, earlier carry out model (8), and it is standby to cut away a block plate (27) according to the shape of damaged hole (1) and size on model (8) greater than damaged hole (1) by the shape of damaged hole (1); Outside the pipeline on every side of damaged hole (1), cover rubber plate (9) again, on described rubber plate (9), cut out the shape of damaged hole (1) equally greater than damaged hole (1); Again model (8) is pressed on the rubber plate (9), and makes hole on the rubber plate (9) and the hole on the model (8) all aim at damaged hole (1); Wear the anchor ear (11) of some strips below pipeline, all fixedlying connected with the lower limb of model (8) in the end of all anchor ears (11), realizes preliminary pretension.
3, pipelining emergent repairing method of prestressing steel cylinder concrete pipe as claimed in claim 1, it is characterized in that: in step 1, suspension ring (14) are set on interior lining panel (13) earlier, when interior lining panel (13) passes through damaged hole (1), pass described suspension ring (14) with rope, then described interior lining panel (13) is put into damaged hole (10), and utilize rope to be hung on the support (12).
4, pipelining emergent repairing method of prestressing steel cylinder concrete pipe as claimed in claim 1 is characterized in that: long nut (20) is set on interior lining panel (13); In step 3, with cover plate (18) and interior lining panel (13) when linking together, utilize bolt (25) to pass hole on the cover plate (18), be screwed onto with long nut (20).
5, pipelining emergent repairing method of prestressing steel cylinder concrete pipe as claimed in claim 1, it is characterized in that: in step 3, after the outer surface of described steel cylinder (5) is placed rubber ring (19), coat polysulfide sealant (21) on the outer surface of the steel cylinder (5) outside rubber ring (19) again.
6, pipelining emergent repairing method of prestressing steel cylinder concrete pipe as claimed in claim 1, it is characterized in that: in step 3, after cover plate (18) and interior lining panel (13) are linked together, use top board (17) that cover board hole (22) is sealed again, and top board (17) and cover plate (18) and screw rod (16) are fixed together.
7, pipelining emergent repairing method of prestressing steel cylinder concrete pipe as claimed in claim 1, it is characterized in that: in step 4, after steel plate (27) and model (8) are fixed together, use nut (28) to be screwed onto on the screw rod (16) again, and clip the redundance of screw rod (16).
8, a kind of Prestressed concrete cylinder pipe pipelining emergent repairing structure, it is characterized in that: the inwall corresponding to damaged hole (1) on pipeline is provided with interior lining panel (13), screw rod (16) is set on described interior lining panel (13), the outer surface setting of the steel cylinder of locating to expose corresponding to damaged hole (1) on pipeline (5) covers the cover plate (18) of damaged hole (1), between cover plate (18) and steel cylinder (5) rubber ring (19) is arranged; Described cover plate (18) interconnects with described interior lining panel (13), and fills up concrete (23) in the cavity between cover plate (18) and interior lining panel (13); The steel plate (27) that is connected on the model (8) is arranged in the top of cover plate (18), fill up pea gravel concreten (26) in the cavity between described steel plate (27) and cover plate (18) and top board (17).
9, Prestressed concrete cylinder pipe pipelining emergent repairing structure as claimed in claim 8 is characterized in that: coat polysulfide sealant (21) on the outer surface of the steel cylinder (5) outside rubber ring (19); Long nut (20) is set on interior lining panel (13); Cover plate (18) and interior lining panel (13) utilize bolt (25) to pass hole on the cover plate (18), are screwed onto with long nut (20); Cover board hole (22) is arranged on cover plate (18), on cover plate (18), be provided for covering the top board (17) of described cover board hole (22).
10, Prestressed concrete cylinder pipe pipelining emergent repairing structure as claimed in claim 8, it is characterized in that: the model (8) greater than damaged hole (1) is arranged outside the pipeline of locating corresponding to damaged hole (1), go up at model (8) that to cut away a block plate (27) according to the shape of damaged hole (1) and size standby; Outside the pipeline on every side of damaged hole (1), cover rubber plate (9), on described rubber plate (9), cut out the shape of damaged hole (1) equally greater than damaged hole (1); Described model (8) is pressed on the described rubber plate (9), and makes hole on the rubber plate (9) and the hole on the model (8) all aim at damaged hole (1); Wearing the anchor ear (11) of some strips below pipeline, all fixedlys connected with the lower limb of model (8) in the end of all anchor ears (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100339293A CN101625061B (en) | 2009-05-27 | 2009-05-27 | Pipelining emergent repairing method of prestressing steel cylinder concrete pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009100339293A CN101625061B (en) | 2009-05-27 | 2009-05-27 | Pipelining emergent repairing method of prestressing steel cylinder concrete pipe |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101625061A true CN101625061A (en) | 2010-01-13 |
CN101625061B CN101625061B (en) | 2011-05-18 |
Family
ID=41520999
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009100339293A Active CN101625061B (en) | 2009-05-27 | 2009-05-27 | Pipelining emergent repairing method of prestressing steel cylinder concrete pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101625061B (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101968138A (en) * | 2010-10-29 | 2011-02-09 | 四川国统混凝土制品有限公司 | Holing construction method on PCCP pipeline site |
CN103968186A (en) * | 2014-04-21 | 2014-08-06 | 浙江新中源建设有限公司 | Repair construction method for water supply pre-stressed concrete cylinder pipe |
CN104482352A (en) * | 2014-12-09 | 2015-04-01 | 中国能源建设集团广东省电力设计研究院 | Restoration structure and restoration method of PCCP (prestressed concrete cylinder pipe) |
CN106801768A (en) * | 2017-02-06 | 2017-06-06 | 中国水利水电第十三工程局有限公司 | PCCP pipeline socket rings and steel cylinder weld seam Micro blazed-grating handling process have been installed |
CN108086330A (en) * | 2017-12-06 | 2018-05-29 | 湖北华舟重工应急装备股份有限公司 | A kind of pipeline repairing quick supporting device and application method |
CN110081267A (en) * | 2019-03-27 | 2019-08-02 | 北京京燕水务有限公司 | PCCP pipeline breaking renovation technique |
CN111963813A (en) * | 2020-08-11 | 2020-11-20 | 无锡市正丰建设工程有限公司 | Emergency repair method for non-water-cut prestressed steel cylinder concrete pipe |
CN114409323A (en) * | 2022-03-31 | 2022-04-29 | 中铁十八局集团第四工程有限公司 | High-adhesion repair concrete for PCCP (prestressed concrete cylinder pipe) pipe emergency repair and preparation method thereof |
CN116877827A (en) * | 2023-09-04 | 2023-10-13 | 山西八建集团有限公司 | Repair-free damaged corrugated pipe device and construction method |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201462321U (en) * | 2009-05-27 | 2010-05-12 | 无锡华毅管道有限公司 | Emergency repair structure of pipeline of prestressed concrete cylinder pipe (PCCP) |
-
2009
- 2009-05-27 CN CN2009100339293A patent/CN101625061B/en active Active
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101968138B (en) * | 2010-10-29 | 2012-10-03 | 四川国统混凝土制品有限公司 | Holing construction method on PCCP pipeline site |
CN101968138A (en) * | 2010-10-29 | 2011-02-09 | 四川国统混凝土制品有限公司 | Holing construction method on PCCP pipeline site |
CN103968186A (en) * | 2014-04-21 | 2014-08-06 | 浙江新中源建设有限公司 | Repair construction method for water supply pre-stressed concrete cylinder pipe |
CN104482352A (en) * | 2014-12-09 | 2015-04-01 | 中国能源建设集团广东省电力设计研究院 | Restoration structure and restoration method of PCCP (prestressed concrete cylinder pipe) |
CN104482352B (en) * | 2014-12-09 | 2016-06-29 | 中国能源建设集团广东省电力设计研究院有限公司 | The reparation structure of PCCP pipe and restorative procedure |
CN106801768B (en) * | 2017-02-06 | 2018-10-19 | 中国水利水电第十三工程局有限公司 | PCCP pipeline socket rings and steel cylinder weld seam Micro blazed-grating treatment process have been installed |
CN106801768A (en) * | 2017-02-06 | 2017-06-06 | 中国水利水电第十三工程局有限公司 | PCCP pipeline socket rings and steel cylinder weld seam Micro blazed-grating handling process have been installed |
CN108086330A (en) * | 2017-12-06 | 2018-05-29 | 湖北华舟重工应急装备股份有限公司 | A kind of pipeline repairing quick supporting device and application method |
CN108086330B (en) * | 2017-12-06 | 2020-06-30 | 中国船舶重工集团应急预警与救援装备股份有限公司 | Rapid supporting device for pipeline emergency repair and using method |
CN110081267A (en) * | 2019-03-27 | 2019-08-02 | 北京京燕水务有限公司 | PCCP pipeline breaking renovation technique |
CN110081267B (en) * | 2019-03-27 | 2021-04-09 | 北京京燕水务有限公司 | PCCP pipeline fracture repair process |
CN111963813A (en) * | 2020-08-11 | 2020-11-20 | 无锡市正丰建设工程有限公司 | Emergency repair method for non-water-cut prestressed steel cylinder concrete pipe |
CN114409323A (en) * | 2022-03-31 | 2022-04-29 | 中铁十八局集团第四工程有限公司 | High-adhesion repair concrete for PCCP (prestressed concrete cylinder pipe) pipe emergency repair and preparation method thereof |
CN114409323B (en) * | 2022-03-31 | 2022-06-28 | 中铁十八局集团第四工程有限公司 | High-adhesion repair concrete for first-aid repair of PCCP (prestressed concrete cylinder pipe) and preparation method thereof |
CN116877827A (en) * | 2023-09-04 | 2023-10-13 | 山西八建集团有限公司 | Repair-free damaged corrugated pipe device and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN101625061B (en) | 2011-05-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101625061B (en) | Pipelining emergent repairing method of prestressing steel cylinder concrete pipe | |
CN107489435B (en) | Replaceable inflatable water stop for mine tunnel | |
CN103966956B (en) | A kind of hood type concrete filled steel tube reinforces single-column Bridge Pier Construction device and construction method | |
CN205875736U (en) | Sectional type shear force wall is to drawing sealing screw | |
CN106287001B (en) | Penstock reinforcing bar composite concrete pipe and the pipeline and production method being made from it | |
CN102352630A (en) | Full-thread fiber resin rod body soil nailing wall and construction method thereof | |
CN111536362B (en) | Method for grouting and reinforcing fiber grids of large-diameter concrete pipeline lining | |
CN204803929U (en) | Reinforcement and protection system of water conservancy project foundation pile | |
CN203007824U (en) | Reinforcement device for underwater pier column | |
CN102252147B (en) | Method for repairing crack of pipeline | |
CN104060590B (en) | The reinforcement leakage preventing structure of a kind of pressure diversion tunnel and construction method thereof | |
CN201462321U (en) | Emergency repair structure of pipeline of prestressed concrete cylinder pipe (PCCP) | |
CN203363529U (en) | Concrete pipe repairing device of water supply prestress steel cylinder | |
CN220248104U (en) | Subway maintenance and preservation piece concrete repairing structure | |
CN202899301U (en) | Hold hoop device for jacking steel pipe concrete | |
CN103968186A (en) | Repair construction method for water supply pre-stressed concrete cylinder pipe | |
KR102083378B1 (en) | Reinforcement member and construction method to reinforce concrete box | |
CN204023527U (en) | A kind of reinforcement leakage preventing structure of pressure diversion tunnel | |
CN101581098B (en) | Construction method of solderless self-centring steel inclined strut | |
CN110735403A (en) | Repair structure for bridge pier cracks and reinforcing method thereof | |
CN113790065B (en) | Auxiliary kit for in-situ repair of large-volume defects of tunnel lining by UHPC material and construction method | |
CN113294171B (en) | Corrugated steel plate and UHPC combined assembled tunnel lining structure and construction method thereof | |
CN213596728U (en) | Avoid road and bridge crack reinforced structure of secondary fracture | |
CN212671801U (en) | Structure is restoreed in reinforcement of subway tunnel section of jurisdiction | |
CN211038676U (en) | Composite cavity reinforcing structure adopting prestressed cable |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |