CN113202325A - Deep hole epoxy resin chemical grouting construction method - Google Patents

Deep hole epoxy resin chemical grouting construction method Download PDF

Info

Publication number
CN113202325A
CN113202325A CN202110457421.7A CN202110457421A CN113202325A CN 113202325 A CN113202325 A CN 113202325A CN 202110457421 A CN202110457421 A CN 202110457421A CN 113202325 A CN113202325 A CN 113202325A
Authority
CN
China
Prior art keywords
grouting
epoxy resin
construction method
deep hole
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110457421.7A
Other languages
Chinese (zh)
Inventor
田庞军
董党
刘钊
苏丹
李晓峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN202110457421.7A priority Critical patent/CN113202325A/en
Publication of CN113202325A publication Critical patent/CN113202325A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention provides a deep hole epoxy resin chemical grouting construction method, which sequentially comprises the following steps; (1) drilling to a target depth at one time, blowing accumulated water by pressure air until no water mist is generated, and continuing for 5-15 min; (2) preparing epoxy resin grouting liquid, and then performing segmented pure-pressure grouting from bottom to top, wherein the injection rate of the grouting section under the maximum design pressure is not more than 0.02 L.min‑1·m‑1And then continuously pouring for 20-40min or reaching the gelling time, and stopping grouting. The construction can be completed by using the traditional drilling grouting equipment without other special equipment, and the problems of difficult construction of medium-length hole chemical grouting, high construction cost and the like in the prior art are effectively solved.

Description

Deep hole epoxy resin chemical grouting construction method
Technical Field
The invention belongs to the technical field of grouting construction, and particularly relates to a deep hole epoxy resin chemical grouting construction method.
Background
Chemical grouting is an engineering technology which combines chemistry and engineering, applies chemical science and chemical grout materials to solve defects of foundations and concrete (reinforcement, seepage prevention and leakage stoppage), and ensures smooth progress of engineering or improves engineering quality. With the development and progress of chemical grouting technology, the technology has become an advanced technology which is very distinctive and indispensable in modern engineering. The chemical grouting is applied from the application after the construction of the project to the design before the construction of the project, and is applied to projects such as dam foundation seepage prevention, consolidation reinforcement, poor foundation treatment and the like in quantity, and a series of grouting forms such as chemical curtain grouting, chemical consolidation grouting, cement chemical composite grouting and the like are formed in sequence. However, most of the chemical grouting applications at the present stage are defect treatment, seepage prevention, leakage stoppage and the like of concrete and poor stratum surface layers, the difficult problem of deep hole chemical grouting construction is not solved, some special equipment is required to be used in construction, and the construction cost is high.
Disclosure of Invention
Aiming at the problems in the prior art, the invention provides a deep hole epoxy resin chemical grouting construction method, which can finish construction by using traditional drilling grouting equipment without other special equipment, and effectively solves the problems of difficult deep hole chemical grouting construction and high construction cost in the prior art.
In order to achieve the purpose, the technical scheme adopted by the invention for solving the technical problems is as follows: the deep hole epoxy resin chemical grouting construction method comprises the following steps in sequence;
(1) drilling to a target depth at one time, blowing accumulated water by pressure air until no water mist is generated, and continuing for 5-15 min;
(2) preparing epoxy resin grouting liquid, and then performing segmented pure-pressure grouting from bottom to top, wherein the injection rate of the grouting section under the maximum design pressure is not more than 0.02 L.min-1·m-1And then continuously pouring for 20-40min or reaching the gelling time, and stopping grouting.
Further, in the step (1), the pressure of the blowing hole is 0.1-0.4 MPa.
Further, in the step (2), the epoxy resin grouting liquid is prepared by the following method: NE-IV type epoxy grouting material produced by Zhengzhou scientific research design limited company of eleven Bureau of hydropower of China is adopted, the mixing proportion of A, B components is determined through field test, and the epoxy resin grouting liquid is obtained after mixing and stirring for 5-10 min.
Further, in the step (2), grouting is performed in at least three steps.
Further, in the step (2), a 3SNS slurry pump is adopted for grouting, the length of a grouting section is 4-5m, and the grouting pressure is 1-1.5 MPa.
In summary, the invention has the following advantages:
1. the construction can be completed by using the traditional drilling grouting equipment without other special equipment, the construction cost is reduced, and the problems of difficult construction of medium-length hole chemical grouting, high construction cost and the like in the prior art are effectively solved.
2. The epoxy resin grouting liquid product is a bi-component, is convenient to operate, and can be used for grouting concrete fine cracks, rock cracks, broken zones and the like to achieve the purposes of seepage prevention, reinforcement and reinforcement; the concrete grouting material has small viscosity, groutability and strong permeability, can be poured into a fine seam with the thickness of less than 0.2mm, has high bonding strength with concrete, and is generally greater than the tensile strength of a concrete body; the slurry can be normally cured under dry, humid and even water conditions, and a cured product has high compressive strength and tensile strength, good flexibility, no shrinkage and good reinforcing effect; the slurry has hydrophilicity and excellent bonding strength to a wet base surface; the operable time can be adjusted according to the situation, and the adjustment range is between 1 and 12 h.
3. By adopting the curtain grouting construction process of drilling to the designed hole depth once and blocking pure-pressure type self-descending and segmented grouting in the hole, the construction problem of epoxy resin chemical grouting with the depth of 40m is solved; the epoxy resin grouting liquid is used, the construction equipment adopts curtain or consolidation grouting equipment, other special equipment is not needed, and equipment investment is saved; provides a reference example for the chemical grouting construction with similar or larger hole depth, and has good reference utilization value.
Detailed Description
Example 1
A deep hole epoxy resin chemical grouting construction method sequentially comprises the following steps;
(1) drilling to a target depth at one time, blowing accumulated water by pressure air until no water mist is generated, and blowing the holes at the pressure of 0.2Mpa for 10 min;
(2) preparing epoxy resin grouting liquid, and then performing segmented pure-pressure grouting from bottom to top, wherein the injection rate of the grouting section under the maximum design pressure is not more than 0.02 L.min-1·m-1And then continuously pouring for 20-40min or reaching the gelling time, and stopping grouting. The epoxy resin grouting liquid is prepared by the following method: NE-IV type epoxy grouting material produced by Zhengzhou scientific research design limited company of eleven Bureau of hydropower of China is adopted, and the mixing proportion of A, B components is determined to be 4 through field tests: 1, mixing and stirring for 8min to obtain the epoxy resin grouting liquid with the operable time of 10 h. And grouting by using a 3SNS slurry pump, wherein the length of a grouting section is 5m, and the grouting pressure is 1.5 MPa.
Example 2
The Giller braker hydropower station in Xinjiang is positioned on a Harba river in Harba river county in Alterna region in Xinjiang, the dam site is positioned near a Giller braker ditch, the dam-shaped structure is a concrete panel rock-fill dam, the dam top elevation is 756.30m, the dam top width is 8.0m, the dam length is 473.5m, and the maximum dam height is 146.3 m.
The pyrite enrichment areas of the Xinjiang Gilles Brack hydropower station are respectively positioned in the ranges of 0+ 238.000-0 +298.000 of the left shore toe and 0+ 356.082-0 +447.092 of the right shore toe, the rock mass structure of the part is not compact due to the oxidation corrosion of the pyrite, the hammer is generally empty and mute, and sulfate ions of underground water (S04)2-) The content is as high as 614.78-1346.7 mg/L. The sulfate ions are subjected to chemical reaction in the contact process with the dam foundation concrete and the cement stones, and generate an acid etching effect, so that the dam foundation concrete and the cement stone structures are damaged, the strength of the dam foundation concrete and the cement stones is reduced, and hidden dangers are brought to the safety of the dam. Considering the problem of corrosion of sulfate in a pyrite enrichment zone, when the excavated foundation is subjected to antiseptic treatment, a row of chemical grouting is additionally arranged between front and rear rows of high-sulfate-resistance cement curtain grouting, and the chemical grouting also serves as the dense grouting after the cement grouting. The chemical grouting material is made of epoxy resin, the distance between single-row holes is 1m, the maximum depth is 38m, construction is carried out in three steps, and the qualified standard after grouting is that the water permeability q of a hole pressure water test is not more than 1 Lu. The total chemical grouting is finished at 4010m, the quality inspection effect after grouting is good, the expected purpose is achieved, and the design requirement is met.
Example 3
Since the reservoir starts to store water in the Golang hydropower station in 2008, the water discharge amount of the drain holes of the dam foundation of the No. 3-No. 8 dam section of the left bank is relatively large, 11-No. 4 main drain holes of the No. 6 dam section with relatively concentrated water discharge amount are generally discharged in a full pipe, and the maximum water discharge amount of a single hole exceeds 0.4L/s. In order to reduce the drainage of a dam foundation and facilitate long-term permeation and stability of the dam foundation, a design determines to perform reinforcing, leaking stoppage and grouting on a No. 6 dam section curtain of the left bank of a large dam of a Golang beach hydropower station.
The reinforcing, plugging and grouting is mainly made of epoxy resin chemical materials and assisted by superfine cement, and main and auxiliary double-row reinforcing and grouting holes are arranged in the 6# dam section, wherein the row spacing is 0.7m, and the reinforcing and plugging grouting holes are arranged in a quincunx manner. The main reinforcing grouting holes are inclined holes with the angle of 6 degrees upstream, the auxiliary reinforcing grouting holes are vertical holes, the average depth of the grouting holes is 42m, and construction is carried out in three sequences. A lifting hole with the depth of 50m is arranged at the position 1m upstream of the No. 6 dam section No. 8 drain hole to monitor the lifting of the dam body in the grouting process and ensure the construction safety. After grouting, arranging 1 inspection hole for pressurized water test inspection, wherein the water permeability after grouting is 1.76Lu, and the design requirement is met; meanwhile, by comparing the water discharge before and after grouting, the total monitored water discharge amount before grouting is 2.23L/s and the total monitored water discharge amount after grouting is 0.83L/s under the same water level condition, so that the water discharge amount is obviously reduced, the grouting effect is obvious, and the expected purpose is achieved. The problem that the water yield of the dam foundation drain hole is relatively large is solved satisfactorily, the seepage stability of the dam foundation is enhanced, and a foundation is tamped for the safe operation of the dam.
While the invention has been described in detail in connection with specific embodiments thereof, it is not intended to limit the scope of the invention. Various modifications and changes may be made by those skilled in the art without inventive step within the scope of the appended claims.

Claims (5)

1. A deep hole epoxy resin chemical grouting construction method is characterized by sequentially comprising the following steps;
(1) drilling to a target depth at one time, blowing accumulated water by pressure air until no water mist is generated, and continuing for 5-15 min;
(2) preparing epoxy resin grouting liquid, and then performing segmented pure-pressure grouting from bottom to top, wherein the injection rate of the grouting section under the maximum design pressure is not more than 0.02 L.min-1·m-1Then continuously perfusing for 20-40min or reaching the gelling time, and stopping grouting.
2. The deep hole epoxy resin chemical grouting construction method according to claim 1, wherein in the step (1), the hole blowing pressure is 0.1-0.4 MPa.
3. The deep hole epoxy resin chemical grouting construction method according to claim 1, wherein in the step (2), the epoxy resin grouting liquid is prepared by the following method: NE-IV type epoxy grouting material produced by Zhengzhou scientific research design limited company of eleven Bureau of hydropower of China is adopted, the mixing proportion of A, B components is determined through field test, and the epoxy resin grouting liquid is obtained after mixing and stirring for 5-10 min.
4. The deep hole epoxy resin chemical grouting construction method according to claim 1, wherein in the step (2), grouting is performed in at least three steps.
5. The deep hole epoxy resin chemical grouting construction method according to claim 1, wherein in the step (2), a 3SNS slurry pump is adopted for grouting, the length of a grouting section is 4-5m, and the grouting pressure is 1-1.5 MPa.
CN202110457421.7A 2021-04-27 2021-04-27 Deep hole epoxy resin chemical grouting construction method Pending CN113202325A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110457421.7A CN113202325A (en) 2021-04-27 2021-04-27 Deep hole epoxy resin chemical grouting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110457421.7A CN113202325A (en) 2021-04-27 2021-04-27 Deep hole epoxy resin chemical grouting construction method

Publications (1)

Publication Number Publication Date
CN113202325A true CN113202325A (en) 2021-08-03

Family

ID=77028812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110457421.7A Pending CN113202325A (en) 2021-04-27 2021-04-27 Deep hole epoxy resin chemical grouting construction method

Country Status (1)

Country Link
CN (1) CN113202325A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114685124A (en) * 2022-05-31 2022-07-01 中建六局(天津)绿色建筑科技有限公司 Prefabricated rail top air duct assembling gap sealing filler and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10154201A1 (en) * 2001-11-07 2003-05-22 Frank Otto Underground foundation procedure mixes suspension of fiber aggregates and binder for injection into ground already worked out by cutting fluid jets.
CN102808427A (en) * 2012-08-21 2012-12-05 中国水利水电第七工程局成都水电建设工程有限公司 Composite grouting reinforcement anti-seepage treatment technology
CN103132528A (en) * 2013-03-18 2013-06-05 中国水利水电第七工程局成都水电建设工程有限公司 Chemical grouting technology
CN107130583A (en) * 2016-11-11 2017-09-05 新疆北方建设集团有限公司 Inclined hole cement grout construction method
US20190024460A1 (en) * 2015-08-18 2019-01-24 Shandong University Anti-collapse jet grouting drill bit with bi-directional rib wings, grouting consolidation system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10154201A1 (en) * 2001-11-07 2003-05-22 Frank Otto Underground foundation procedure mixes suspension of fiber aggregates and binder for injection into ground already worked out by cutting fluid jets.
CN102808427A (en) * 2012-08-21 2012-12-05 中国水利水电第七工程局成都水电建设工程有限公司 Composite grouting reinforcement anti-seepage treatment technology
CN103132528A (en) * 2013-03-18 2013-06-05 中国水利水电第七工程局成都水电建设工程有限公司 Chemical grouting technology
US20190024460A1 (en) * 2015-08-18 2019-01-24 Shandong University Anti-collapse jet grouting drill bit with bi-directional rib wings, grouting consolidation system and method
CN107130583A (en) * 2016-11-11 2017-09-05 新疆北方建设集团有限公司 Inclined hole cement grout construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
严恺: "《水利辞典》", 31 October 1991, 上海辞书出版社 *
王立民主编: "《水工建筑物检测与维修》", 30 June 1993 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114685124A (en) * 2022-05-31 2022-07-01 中建六局(天津)绿色建筑科技有限公司 Prefabricated rail top air duct assembling gap sealing filler and construction method thereof
CN114685124B (en) * 2022-05-31 2022-09-02 中建六局(天津)绿色建筑科技有限公司 Prefabricated rail top air duct assembling gap sealing filler and construction method thereof

Similar Documents

Publication Publication Date Title
CN100572686C (en) The construction technology of hole support system in the hole
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN110359467A (en) A kind of construction method that base pit engineering high-pressure rotary jet grouting pile is reinforced
CN111042146A (en) Construction method of deep foundation pit supporting anti-seepage system of coastal karst stratum
CN108119143A (en) A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain
CN112281927A (en) Construction method for treating leakage of independent foundation of frame column
CN113338361A (en) Deviation rectifying method for settlement of overlying building caused by subway construction in soft soil stratum
CN112459010A (en) Hydraulic engineering concrete dam leakage-repairing reinforcing grouting method
CN113202325A (en) Deep hole epoxy resin chemical grouting construction method
CN111809670A (en) Leaking stoppage grouting and reinforcing construction method for basement exterior wall construction joint
CN110777775A (en) Foundation pit structure and construction method thereof
CN104790425A (en) Corrosion-resistant pole tower foundation for power transmission tower
CN103061351B (en) Prevent the device that basement bottom board swells, seeps water
CN114541408B (en) Front upper part wind-containing well structure of underground station end well and underpass construction method thereof
CN114411640B (en) Construction method for reinforcing and repairing rock-fill core wall dam
CN113233864B (en) Foundation pit leaking stoppage construction method and leaking stoppage material
CN109837811A (en) A kind of counterforce structure and preparation method thereof laterally rectified a deviation for roadbed section non-fragment orbit
CN112299796B (en) Wall pile inter-pile grouting material for building envelope and construction method thereof
CN116104530A (en) Poor geological disaster construction method for diversion tunnel
CN112065416B (en) Construction method for vertical deviation correction of shield tunneling
CN107780424A (en) A kind of mud riverbed earth rock cofferdam and its construction method
CN108049424A (en) Sunk type basement structure
CN1461857A (en) Construction method and its use
CN111809669A (en) Basement post-cast strip leaking stoppage grouting and reinforcing construction method
CN110453659B (en) Construction method for rock plug reservation construction key technology of diversion tunnel of weak surrounding rock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210803

RJ01 Rejection of invention patent application after publication