CN113202077A - Automatic monitoring equipment installation process suitable for ballast track railway roadbed - Google Patents

Automatic monitoring equipment installation process suitable for ballast track railway roadbed Download PDF

Info

Publication number
CN113202077A
CN113202077A CN202010185941.2A CN202010185941A CN113202077A CN 113202077 A CN113202077 A CN 113202077A CN 202010185941 A CN202010185941 A CN 202010185941A CN 113202077 A CN113202077 A CN 113202077A
Authority
CN
China
Prior art keywords
ballast
aluminum wire
railway
monitoring system
line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010185941.2A
Other languages
Chinese (zh)
Inventor
苏伟
杨学林
刘洪占
禚一
孟繁增
邸昊
王旭
魏剑峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN202010185941.2A priority Critical patent/CN113202077A/en
Publication of CN113202077A publication Critical patent/CN113202077A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ

Abstract

The invention provides an installation process of automatic monitoring equipment suitable for a ballast track railway roadbed, and relates to the field of installation processes of static leveling equipment. The method comprises the following steps: carrying out online survey, lofting the basic position and carrying out geophysical prospecting on the positions of the ballast feet; adjusting the basic position according to the geophysical prospecting condition; assembling a static leveling system offline; excavating the top surface of the roadbed at the foundation position to form a pit, implanting reinforcing steel bars into the pit, and pouring a concrete embedded flange; pulling back the railway ballast and maintaining the basic concrete; pulling away the railway ballast at the line position of the static leveling system and placing an aluminum wire slot; the monitoring system pipeline and the heat insulation cotton are arranged in the aluminum wire groove and then connected with the aluminum wire groove; the system comprises a fixed collection box, a solar cell panel, a measuring point and pipeline equipment; pulling back a railway ballast covering monitoring system; and (4) debugging the on-line static level system, and after the debugging is finished, completing the installation and operation of the monitoring system. By adopting the invention, the time for installing the monitoring system on line is saved, the stability of the monitoring system is more reliable after installation, and the monitoring data is closer to the true value of the track deformation.

Description

Automatic monitoring equipment installation process suitable for ballast track railway roadbed
Technical Field
The invention relates to the technical field of static leveling equipment mounting processes, in particular to a novel static leveling equipment mounting process flow related to a ballast track subgrade of a high-speed railway.
Background
At present, the national foundation is built and developed, the technology is advanced, and the Chinese high-speed railway becomes a name card manufactured in China and is a business card handed out at present. The total length of the mileage of the high-speed railway in China which is put into operation at present exceeds 3 kilometers, the high-speed railway has high speed and strict requirements on the smoothness of the track, and a plurality of newly built, reconstructed and expanded projects are crossed with the high-speed railway which is operated at present, so that the environment of the projects around the high-speed railway which is operated at present is worsened and the smoothness of the projects is adversely affected, and therefore how to grasp the smoothness of the track in real time is a key factor for ensuring the operation safety of the high-speed railway.
Under the technical background, the high-speed railway uses a closed operation management mode, the skylight maintenance time is only 2-3 hours every day, and according to the railway operation characteristics and the development of the automatic monitoring technology of the high-speed railway in recent years, a set of safe, stable, quick and reliable silicon piezoresistive static leveling system installation process is not formed in the field of ballast track subgrade monitoring of the high-speed railway.
Disclosure of Invention
The invention aims to provide an installation process of automatic monitoring equipment suitable for a ballast track railway subgrade, namely an automatic silicon piezoresistive static level monitoring system is formed, wherein the silicon piezoresistive static level monitoring system accurately calculates the settlement change condition at the position of a measuring point according to the size change of pressure values of different measuring points by utilizing the principle of a communicating vessel; the process flow is reasonable in design, the time for installing the monitoring system on line is saved, the stability of the monitoring system after installation is more reliable, and the monitoring data is closer to the true value of track deformation.
The invention provides an installation process of automatic monitoring equipment suitable for a ballast track railway subgrade, which comprises the following steps:
step A, entering a closed railway range, directly contacting a steel rail, investigating and lofting a foundation position, and performing geophysical prospecting on a position of a ballast foot;
adjusting the basic position of a part according to the geophysical prospecting condition;
b, assembling a static leveling system in an environment outside the influence range of the line according to the final basic position;
c, pulling off the ballast at the foundation position, excavating the top surface of the roadbed at the foundation position to form a pit, implanting reinforcing steel bars into the pit, and pouring a concrete embedded flange;
d, pulling back the railway ballast and maintaining the basic concrete;
e, pulling off the ballast at the line position of the static leveling system and placing an aluminum wire slot;
the monitoring system pipeline and the heat insulation cotton are arranged in the aluminum wire groove and then connected with the aluminum wire groove;
the system comprises a fixed collection box, a solar cell panel, a measuring point and pipeline equipment; pulling back a railway ballast covering monitoring system;
step F, debugging an on-line static level system; and after debugging is finished, the monitoring system is installed and operated.
Further, in the step B, the static level monitoring system sequentially comprises a silicon piezoresistive sensor, a liquid storage barrel, a solar cell panel, a solar cell, a solar controller, a liquid through pipe, a vent pipe, heat preservation cotton and a four-core cable.
And furthermore, the aluminum wire grooves in the step E are segmented, finally, the aluminum wire grooves distributed in multiple segments are connected into a whole in a lap joint mode through bolts, are arranged on the line beside the ballast in a straight line mode, and are connected.
And step E, after the aluminum wire grooves distributed in multiple sections are connected, the heat preservation cotton, the liquid through pipe and the vent pipe which are well assembled at positions outside the influence range of the circuit are arranged in the aluminum wire grooves, and then the aluminum wire grooves are packaged.
The invention has the following beneficial effects:
by adopting the automatic monitoring equipment installation process suitable for the ballast track railway subgrade, the top surface of a railway basic body needs to be excavated before the concrete cast-in-place mode is adopted, reinforcing steel bars are implanted into the excavated foundation pit, and the excavation position is the position of a ballast foot of a ballast track of a high-speed railway subgrade; and assembling the static leveling system according to the final foundation position and the environment outside the influence range of the line, burying each part of the static leveling system at the position of a foundation pit beside the steel rail at intervals, and simultaneously timely pulling away the railway ballast according to the requirement. By adopting the rapid installation process, the requirement of high-speed rail safe operation management can be met, technical examination of an operation management unit can be smoothly passed, the time for installing the monitoring system on line is saved, the stability of the installed monitoring system is more reliable, the monitoring data is closer to the true value of rail deformation, and the operation safety of a railway is guaranteed.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.
Fig. 1 is a schematic plan view of a subgrade according to the invention;
fig. 21-1 is a schematic view of a roadbed cross section instrumentation arrangement of the present invention;
fig. 32-2 is a schematic view of a roadbed cross section apparatus arrangement of the present invention;
fig. 43-3 is a schematic view of a roadbed cross section apparatus arrangement of the present invention;
FIG. 5 is a process flow diagram of the present invention.
Reference numerals:
1-ballast;
2-a track;
3-a collection box;
4-measuring points;
5-a solar panel;
6-aluminum wire grooves;
7-ballast feet;
8-heat preservation cotton;
9-a pipeline apparatus;
10-a flange;
11-reinforcing steel bars;
12-liquid storage barrel.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the accompanying drawings, and it should be understood that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The technical scheme of the installation process of the automatic monitoring equipment suitable for the ballast track railway subgrade of the embodiment is described in detail below with reference to fig. 1 to 5.
Examples
The rapid installation process of the automatic monitoring equipment for the ballast track 2 subgrade of the high-speed railway provided by the embodiment has the following specific implementation modes:
the method comprises the following steps:
step A, entering a closed railway range, directly contacting a steel rail, investigating and lofting a foundation position, and performing geophysical prospecting on a position of a ballast foot 7;
adjusting part of foundation positions according to geophysical prospecting conditions, wherein the foundation positions are required to be arranged at intervals with steel rails of a railway and are not in direct contact with each other;
b, assembling a static leveling system in an environment outside the influence range of the line according to the final basic position;
it should be noted that, in this step, the process of assembling the static level system may be performed before the adjustment of the base position in step a, or may be performed after the adjustment of the base position in step a.
C, pulling off the ballast 1 at the foundation position, excavating the top surface of the roadbed at the foundation position to form a pit, implanting reinforcing steel bars 11 into the pit, and pouring a concrete embedded flange 10;
the step C is to adopt a concrete cast-in-place mode, and the excavation position of the top surface of the roadbed at the base position is the position of a ballast foot 7 of a ballast track 2 of the high-speed railway roadbed; the embedded flange 10 is a relevant part for installing a static leveling system.
D, pulling back the railway ballast 1 and maintaining the basic concrete;
it should be noted here that the ballast 1 can play a role in maintaining concrete, and is also a mandatory requirement of a high-speed rail operation management unit, and the time period of the on-line railway (generally, the time period of 00: 30 to 3: 30 at night) can change the state of the original roadbed part, but the changed state of the roadbed part must be recovered before the off-line railway is completed.
Step E, pulling off the railway ballast 1 at the line position of the static leveling system and placing an aluminum wire slot 6:
the monitoring system pipeline and the heat insulation cotton 8 are arranged in the aluminum wire groove 6 and then connected with the aluminum wire groove 6;
it should be noted that, in step E, the aluminum wire troughs 6 are arranged along the plurality of foundation positions of step a, spaced apart from the railway rails, and not in contact with the railway rails.
The device comprises a fixed collection box 3, a solar cell panel 5, a measuring point 4 and pipeline equipment 9; pulling back a track ballast 1 covering monitoring system;
it is to be noted here that the fixed collection box 3, the solar panel 5, the measuring point 4 and the pipeline device 9 in step E are all arranged in succession at different base positions.
Step F, debugging an on-line static level system; and after debugging is finished, the monitoring system is installed and operated.
In the specific scheme of this embodiment, in step B, static level monitoring system includes silicon piezoresistive sensor, liquid storage bucket 12, solar cell panel 5, solar cell, solar controller, logical liquid pipe, breather pipe, heat preservation cotton 8 and four-core cable in proper order.
In the concrete scheme of this embodiment, aluminium wire casing 6 is the segmentation in step E, and finally the aluminium wire casing 6 that the multistage distributes connects into a whole through bolt overlap joint, and the line is gone up and is opened in a word next to railway ballast 1, then connects, just can connect after contacting the rail promptly to avoid contacting the rail in-process electric shock accident to appear.
In the specific scheme of this embodiment, in step E, after connecting between the aluminum wire casing 6 that the multistage distributes, pack the heat preservation cotton 8, the liquid pipe that leads to and the breather pipe that will assemble in the position outside the influence range of circuit into aluminum wire casing 6 back encapsulation aluminum wire casing 6.
By adopting the rapid installation process of the automatic monitoring equipment for the ballast track 2 subgrade of the high-speed railway, the top surface of a roadbed base body needs to be excavated before the concrete cast-in-place mode is adopted, reinforcing steel bars 11 are implanted into an excavated foundation pit, and the excavation position is the position of a ballast foot 7 of the ballast track 2 of the high-speed railway subgrade; and assembling the static leveling system according to the final foundation position and the environment outside the influence range of the line, burying each part of the static leveling system at the position of a foundation pit beside a steel rail at intervals, and simultaneously timely pulling out the railway ballast 1 according to the requirement. By adopting the rapid installation process, the requirement of safe operation management of the high-speed rail can be met, technical examination of an operation management unit can be smoothly passed, the time for installing the monitoring system on line is saved, the stability of the installed monitoring system is more reliable, the monitoring data is closer to the true value of deformation of the track 2, and the operation safety of the railway is guaranteed.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; and the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (4)

1. The automatic monitoring equipment installation process suitable for the ballast track railway subgrade is characterized by comprising the following steps of:
step A, entering a closed railway range, directly contacting a steel rail, investigating and lofting a foundation position, and performing geophysical prospecting on a position of a ballast foot;
adjusting the basic position of a part according to the geophysical prospecting condition;
b, assembling a static leveling system in an environment outside the influence range of the line according to the final basic position;
c, pulling off the ballast at the foundation position, excavating the top surface of the roadbed at the foundation position to form a pit, implanting reinforcing steel bars into the pit, and pouring a concrete embedded flange;
d, pulling back the railway ballast and maintaining the basic concrete;
e, pulling off the ballast at the line position of the static leveling system and placing an aluminum wire slot;
the monitoring system pipeline and the heat insulation cotton are arranged in the aluminum wire groove and then connected with the aluminum wire groove;
the system comprises a fixed collection box, a solar cell panel, a measuring point and pipeline equipment; pulling back a railway ballast covering monitoring system;
step F, debugging an on-line static level system; and after debugging is finished, the monitoring system is installed and operated.
2. The mounting process of the automatic monitoring equipment suitable for the ballast track railway subgrade according to the claim 1, wherein in the step B, the static level monitoring system sequentially comprises a silicon piezoresistive sensor, a liquid storage barrel, a solar cell panel, a solar cell, a solar controller, a liquid through pipe, a vent pipe, heat insulation cotton and a four-core cable.
3. The mounting process of the automatic monitoring equipment suitable for the ballast track railway subgrade according to the claim 1 is characterized in that the aluminum wire grooves in the step E are segmented, finally, the aluminum wire grooves distributed in multiple segments are connected into a whole through bolt lap joint, are arranged in a line beside the ballast and then are connected.
4. The mounting process of the automatic monitoring equipment suitable for the ballast track railway subgrade according to the claim 1 is characterized in that in the step E, after the aluminum wire grooves distributed in multiple sections are connected, the heat insulation cotton, the liquid through pipe and the air through pipe which are assembled at positions outside the influence range of the circuit are arranged in the aluminum wire grooves, and then the aluminum wire grooves are packaged.
CN202010185941.2A 2020-07-27 2020-07-27 Automatic monitoring equipment installation process suitable for ballast track railway roadbed Pending CN113202077A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010185941.2A CN113202077A (en) 2020-07-27 2020-07-27 Automatic monitoring equipment installation process suitable for ballast track railway roadbed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010185941.2A CN113202077A (en) 2020-07-27 2020-07-27 Automatic monitoring equipment installation process suitable for ballast track railway roadbed

Publications (1)

Publication Number Publication Date
CN113202077A true CN113202077A (en) 2021-08-03

Family

ID=77024906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010185941.2A Pending CN113202077A (en) 2020-07-27 2020-07-27 Automatic monitoring equipment installation process suitable for ballast track railway roadbed

Country Status (1)

Country Link
CN (1) CN113202077A (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005326372A (en) * 2004-05-17 2005-11-24 Elmes Keisoku Kogyo Kk Settlement measuring device and measuring method of railway track
CN103017827A (en) * 2012-12-11 2013-04-03 武汉理工大学 Multi-sensor real-time monitoring system for construction protection of bridges and culverts of business lines of railways
WO2015127740A1 (en) * 2014-02-28 2015-09-03 中铁第四勘察设计院集团有限公司 Correction method and correction structure for ballastless track subgrade of high-speed railway in soft soil region
CN204630570U (en) * 2015-04-22 2015-09-09 昆明地铁运营有限公司 A kind of track traffic Foundation Settlement Monitor device
CN206488771U (en) * 2017-02-17 2017-09-12 中国铁路设计集团有限公司 One kind operation ballastless track of high-speed railway subgrade settlement deformation automatic monitoring system
CN109029349A (en) * 2018-07-27 2018-12-18 厦门大学嘉庚学院 Settlement monitoring device and monitoring method based on GPS positioning
CN110081854A (en) * 2019-04-26 2019-08-02 太原理工大学 The sedimentation monitoring system and method for a kind of pair of Ballast track railway ballast
CN110158367A (en) * 2019-04-12 2019-08-23 同济大学 A kind of structure and deformation control method for helping the existing high-speed railway subgrade of width
CN209459638U (en) * 2019-01-14 2019-10-01 武汉地震科学仪器研究院有限公司 Engineering level settlement gauge
CN209459639U (en) * 2019-01-14 2019-10-01 武汉地震科学仪器研究院有限公司 Engineering level settlement measurement system
CN110702068A (en) * 2019-09-04 2020-01-17 朔黄铁路发展有限责任公司 Existing railway settlement monitoring system and monitoring method
CN210198368U (en) * 2019-08-12 2020-03-27 中国电建集团国际工程有限公司 Hydraulic static leveling device
CN211085196U (en) * 2019-10-15 2020-07-24 北京大成国测科技有限公司 High-speed railway structure deformation layered monitoring system

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005326372A (en) * 2004-05-17 2005-11-24 Elmes Keisoku Kogyo Kk Settlement measuring device and measuring method of railway track
CN103017827A (en) * 2012-12-11 2013-04-03 武汉理工大学 Multi-sensor real-time monitoring system for construction protection of bridges and culverts of business lines of railways
WO2015127740A1 (en) * 2014-02-28 2015-09-03 中铁第四勘察设计院集团有限公司 Correction method and correction structure for ballastless track subgrade of high-speed railway in soft soil region
CN204630570U (en) * 2015-04-22 2015-09-09 昆明地铁运营有限公司 A kind of track traffic Foundation Settlement Monitor device
CN206488771U (en) * 2017-02-17 2017-09-12 中国铁路设计集团有限公司 One kind operation ballastless track of high-speed railway subgrade settlement deformation automatic monitoring system
CN109029349A (en) * 2018-07-27 2018-12-18 厦门大学嘉庚学院 Settlement monitoring device and monitoring method based on GPS positioning
CN209459639U (en) * 2019-01-14 2019-10-01 武汉地震科学仪器研究院有限公司 Engineering level settlement measurement system
CN209459638U (en) * 2019-01-14 2019-10-01 武汉地震科学仪器研究院有限公司 Engineering level settlement gauge
CN110158367A (en) * 2019-04-12 2019-08-23 同济大学 A kind of structure and deformation control method for helping the existing high-speed railway subgrade of width
CN110081854A (en) * 2019-04-26 2019-08-02 太原理工大学 The sedimentation monitoring system and method for a kind of pair of Ballast track railway ballast
CN210198368U (en) * 2019-08-12 2020-03-27 中国电建集团国际工程有限公司 Hydraulic static leveling device
CN110702068A (en) * 2019-09-04 2020-01-17 朔黄铁路发展有限责任公司 Existing railway settlement monitoring system and monitoring method
CN211085196U (en) * 2019-10-15 2020-07-24 北京大成国测科技有限公司 High-speed railway structure deformation layered monitoring system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴良: "《城市轨道交通车站施工》", 31 January 2013, 中国铁道出版社 *

Similar Documents

Publication Publication Date Title
CN104111091B (en) A kind of mud-rock flow mechanics parameter monitoring method and debris flow early-warning method
CN104831762A (en) Dynamic monitoring system and monitoring method of deep foundation pit confined water drawdown
CN108280969A (en) A kind of high slope surface deformation monitoring and warning system and its method for early warning
CN104655101A (en) High-precision lead type whole-section slope stability monitoring pre-alarming system and monitoring method thereof
CN102494658A (en) Online wind deviation angle monitoring device for power transmission line
CN111609808A (en) Deformation monitoring system for oil-gas pipeline of water-sealed tunnel
CN103401183A (en) Assembled-type stringing method
CN110454231A (en) A kind of tunnel safety early warning robot device
CN103591982B (en) A kind of monitoring method of electric power tunnel structure problem
CN112556903A (en) Tower material all-state monitoring and analyzing method
CN112033355A (en) Method for monitoring settlement of pier stud in underpinning of bridge pile foundation
CN105318859B (en) Directly measurement monitoring underground utilities and building structure sedimentation and deformation method and device thereof
CN110307825A (en) A kind of overhead transmission line arc sag on-line monitoring system
CN113202077A (en) Automatic monitoring equipment installation process suitable for ballast track railway roadbed
CN111970382A (en) Iron tower safety monitoring and early warning system
CN208172969U (en) A kind of high slope surface deformation monitoring and warning system
CN115853030A (en) Integrated intelligent monitoring system and method for operating subway adjacent to deep foundation pit project
CN112541455B (en) Machine vision-based prediction method for reverse breaking accidents of distribution network concrete electric pole
CN205317245U (en) Monitoring system is mixed to long distance water delivery tunnel safety
CN213028117U (en) Iron tower safety monitoring and early warning system
CN204529984U (en) A kind of buried long-distance oil & gas pipeline corrosion on-line testing stake
CN113936433B (en) High-precision intelligent monitoring station for early warning of hydropower engineering and geological disasters
Yang Technical Code for Monitoring of Building Structures
CN210664437U (en) Overhead transmission line sag on-line monitoring system
CN218973534U (en) Electric power iron tower safety monitoring system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210803

RJ01 Rejection of invention patent application after publication