CN113191732A - Wisdom building site management platform - Google Patents
Wisdom building site management platform Download PDFInfo
- Publication number
- CN113191732A CN113191732A CN202110479771.3A CN202110479771A CN113191732A CN 113191732 A CN113191732 A CN 113191732A CN 202110479771 A CN202110479771 A CN 202110479771A CN 113191732 A CN113191732 A CN 113191732A
- Authority
- CN
- China
- Prior art keywords
- acquisition
- worker
- server
- management
- terminal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 claims abstract description 34
- 238000004458 analytical method Methods 0.000 claims abstract description 20
- 238000012544 monitoring process Methods 0.000 claims abstract description 13
- 230000001133 acceleration Effects 0.000 claims description 13
- 230000008859 change Effects 0.000 claims description 4
- 238000000034 method Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 230000003203 everyday effect Effects 0.000 description 2
- 230000036541 health Effects 0.000 description 2
- 230000008569 process Effects 0.000 description 2
- 238000013473 artificial intelligence Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
- G06Q10/06398—Performance of employee with respect to a job function
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B13/00—Burglar, theft or intruder alarms
- G08B13/22—Electrical actuation
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B7/00—Signalling systems according to more than one of groups G08B3/00 - G08B6/00; Personal calling systems according to more than one of groups G08B3/00 - G08B6/00
- G08B7/06—Signalling systems according to more than one of groups G08B3/00 - G08B6/00; Personal calling systems according to more than one of groups G08B3/00 - G08B6/00 using electric transmission, e.g. involving audible and visible signalling through the use of sound and light sources
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Data Mining & Analysis (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention belongs to the technical field of engineering management, and particularly relates to an intelligent construction site management platform which comprises a management end, a server, a monitoring end and a worker end; a plurality of monitoring ends are respectively arranged on each sub-project; a plurality of worker ends are provided; the management terminal is used for creating and updating an access authority table, and the access authority table comprises specific sub-items which can be accessed by each worker terminal; the server is used for storing the access authority table and also storing an electronic map of each sub item in the construction site; the worker end is used for positioning in real time and sending the positioning to the server; the server is used for analyzing the travel of the worker according to the real-time positioning of the worker end and the electronic map, and sending alarm information to the worker end when the analysis result is that the worker end is about to enter the sub-project which cannot be entered. The potential safety hazard of workers can be reduced while the construction progress is guaranteed.
Description
Technical Field
The invention belongs to the technical field of engineering management, and particularly relates to an intelligent construction site management platform.
Background
An intelligent construction site is a brand-new project full life cycle management concept. Compared with a conventional management system, the intelligent construction site has the advantages that more high-tech technologies such as artificial intelligence, sensing technology, virtual reality and the like are implanted into various objects such as buildings, machinery, personnel wearing facilities, site access gateways and the like, are commonly interconnected to form the Internet of things, and are integrated with the Internet to realize the integration of engineering management major personnel and an engineering construction site.
Key elements of intelligent management include personnel management, equipment management, material management, construction scheme management, production management, environment management and the like. Among them, personnel management directly involves life safety and engineering quality of workers, and plays an important role in numerous management.
However, site management is peculiar in that a large site is divided into a plurality of small sub-projects, and the overall construction period is reasonably shortened by constructing a plurality of sub-projects together. However, a plurality of sub-projects are constructed simultaneously, and generally, construction progress can be different, that is, specific construction contents of the sub-projects can be different at the same time; meanwhile, a plurality of sub-projects are constructed simultaneously, so that more construction personnel are involved, and workers of various types are distributed at various places of a construction site; workers usually only know about the attention of their own work or the attention of related work. When a certain sub-project enters an irrelevant worker, the construction of the sub-project is interfered, and on the other hand, the irrelevant worker may have a safety hazard because the worker does not know about the attention.
Disclosure of Invention
The invention aims to provide an intelligent construction site management platform which can reduce potential safety hazards of workers while ensuring construction progress.
The basic scheme provided by the invention is as follows:
an intelligent construction site management platform comprises a management end, a server, a monitoring end and a worker end;
a plurality of monitoring ends are respectively arranged on each sub-project; a plurality of worker ends are provided; the management terminal is used for creating and updating an access authority table, and the access authority table comprises specific sub-items which can be accessed by each worker terminal; the server is used for storing the access authority table and also storing an electronic map of each sub item in the construction site;
the worker end is used for positioning in real time and sending the positioning to the server; the server is used for analyzing the travel of the worker according to the real-time positioning of the worker end and the electronic map, and sending alarm information to the worker end when the analysis result is that the worker end is about to enter the sub-project which cannot be entered; and the server is also used for controlling the corresponding monitoring terminal to shoot a field image according to the real-time positioning of the worker terminal and sending a processing signal and the field image to the management terminal when the worker terminal still enters the sub-project after sending the alarm information to the worker terminal.
Basic scheme theory of operation and beneficial effect:
the supervisor can create or update the access authority table through the management terminal according to the specific construction condition of each sub-project.
During construction, the worker end can perform real-time positioning and send the real-time positioning to the server, the server can analyze the stroke of a worker according to the real-time positioning and the electronic map after receiving the real-time positioning of the worker end, and if the analysis result is that a certain worker end is about to enter a sub-project which the worker end cannot enter, the situation that the worker is not in a proper moment or does not know the situation is indicated, and the worker end wants to enter the sub-project which the worker cannot enter. Therefore, the server sends the alarm information to the worker end, and if the worker does not know the condition, the worker can leave after receiving the alarm information; entry may continue if the worker is not in compliance.
Therefore, after the server sends the alarm information to the worker end, if the worker end still enters the sub-project, the server can control the corresponding monitoring end to shoot the field image according to the real-time positioning of the worker end, and send the processing signal and the field image to the management end. By processing the signals, the supervision personnel can know the situation and timely process the workers who are not in compliance. Through the field image that the control end was shot, can leave the on-the-spot evidence, also be convenient for simultaneously the supervisor to find this workman fast.
Therefore, unknowing workers can be prevented from entering sub-projects which cannot be entered, and workers who are not on duty can be quickly locked and processed, so that interference on construction is prevented as far as possible, and potential safety hazards are reduced.
In conclusion, this application can reduce workman's potential safety hazard when guaranteeing the construction progress.
Further, the management end is also used for setting temporary access authority of each worker end on the access authority table, and the temporary access authority comprises sub-items which can be accessed and corresponding access time.
Sometimes, when a worker enters a construction sub-project of the worker, the worker needs to pass through another sub-project, and at this time, a supervisor can manage the travel of the worker by setting a temporary access authority (for example, X points can enter a sub-project every day within a certain period of time).
Further, the workman end includes intelligent bracelet, and the workman end receives alarm signal back, controls intelligent bracelet vibrations, shows the alarm characters and sends the alarm sound.
Because the sound of the construction site is noisy, workers are likely to be unnoticeable if only the text reminding or the voice reminding is performed. Through the vibrations of intelligent bracelet, then cooperate the alarm characters and predetermine the alarm sound (if "the place ahead region you are not entitled to the entering, please stop the step" pronunciation and characters), then can guarantee that the workman notices alarm information.
And further, the worker end is also used for collecting the physical sign information of the worker and uploading the physical sign information to the server, the server is also used for carrying out safety analysis according to the received physical sign information, and if the safety analysis indicates that abnormity exists, a rest signal is sent to the corresponding worker end, and a check signal is sent to the management end.
Through such a mode, can let workman oneself in time know the condition when the workman has the health anomaly, take a rest to adjust, also can let supervisory personnel in time know the condition, in time look over the processing.
Further, the server stores contact telephones of all worker ends; the server is also used for sending a processing signal or a checking signal to the management terminal and simultaneously sending a contact telephone corresponding to the worker terminal.
The utility model is convenient for the supervisor to quickly find the workers who need to guide education or need to rest and recuperate.
The system further comprises an acquisition end, a server and a data processing end, wherein the acquisition end is used for acquiring project data of a constructed part and sending the project data to the server; the server is also used for carrying out three-dimensional modeling according to the received project data to obtain a project model; the management side is also used for viewing the project model.
Through the project model, the supervisor can know the specific progress condition of each sub-project in time.
Furthermore, the management end is also used for creating and updating an acquisition schedule, and items of the acquisition schedule comprise acquisition time and acquisition position; the management terminal is also used for sending the latest acquisition schedule to the acquisition terminal when the acquisition schedule is created or updated;
the acquisition end is also used for acquiring the current positioning and acceleration of the acquisition end and sending the current positioning and acceleration to the server; the acquisition end is also used for calling the electronic map to the server when acquiring time in the acquisition schedule and judging whether the electronic map is at the corresponding acquisition position according to the current positioning; if not, the acquisition end is also used for judging whether the distance between the acquisition end and the acquisition position is within a preset range according to the current positioning; if the current positioning and acceleration is within the preset range, the acquisition end is further used for judging whether the current positioning and acceleration moves towards the acquisition position or not, and if not, an acquisition reminding signal is sent out;
the acquisition end is also used for acquiring current weather information and analyzing whether the acquisition is suitable for acquiring construction data or not when the distance between the acquisition end and the acquisition position is judged not to be within a preset range according to the current positioning, and if the analysis result is not suitable, the acquisition end sends an acquisition change signal to the management end; if the analysis result is suitable, the acquisition end sends out an idling warning and sends an idling signal to the management end.
Has the advantages that:
after the acquisition end receives the acquisition schedule, judging whether an acquisition worker is at an acquisition position according to the current positioning when acquiring the acquisition time in the acquisition schedule, and if so, indicating that the acquisition worker is acquiring the construction data according to the schedule; if not, the acquisition end judges whether the distance between the acquisition end and the acquisition position is within a preset range according to the current positioning, if so, the acquisition end indicates that the acquisition personnel can arrive and finish the acquisition work, and therefore, the acquisition end judges whether the acquisition end moves towards the acquisition position according to the current positioning and the acceleration; if the mobile terminal moves towards the collection position, the mobile terminal indicates that the mobile terminal is on the way to the collection position; if not moving towards the collection position, then explain that it can catch up to the collection position but its not know the condition at present, consequently, gather the end and send and gather the reminder signal, let the collection personnel know the condition, be convenient for in time accomplish the collection work.
If the distance between the current positioning judgment and the acquisition position is not within the preset range, the acquisition personnel can not arrive at the acquisition position to complete the acquisition work, and therefore the acquisition end acquires the current weather information and analyzes whether the acquisition is suitable for acquiring construction data. If the analysis result is not suitable (such as rainy and foggy days), the acquisition personnel do not intentionally execute the acquisition work, but the current weather is not suitable, so that the acquisition end sends an acquisition change signal to the management end to inform the management end of changing the corresponding acquisition plan; if the analysis result is proper, it indicates that the acquisition personnel is the subjective reason of the personnel and does not execute the acquisition work, and the acquisition work is an important part of supervision and needs to be aware of the severity of the problem, so the acquisition end sends out an idling warning, and simultaneously the acquisition end sends an idling signal to the management end to enable the supervision personnel to know the situation, and the acquisition personnel can be reasonably punished subsequently, and meanwhile, the supervision personnel can timely modify the corresponding acquisition plan.
Drawings
Fig. 1 is a logic block diagram of a first embodiment of the invention.
Detailed Description
The following is further detailed by the specific embodiments:
example one
As shown in fig. 1, an intelligent worksite management platform includes a management end, a server, a monitoring end and a worker end.
In this embodiment, the management end is for loading the smart mobile phone that corresponds the APP, and the server is cloud ware, and the control end is surveillance camera head, and the workman end includes smart bracelet and loads the smart mobile phone that corresponds the APP.
A plurality of monitoring ends are respectively arranged on each sub-project; a plurality of worker ends are provided; the management terminal is used for creating and updating an access authority table, and the access authority table comprises specific sub-items which can be accessed by each worker terminal; the server is used for storing the access authority table, and an electronic map of each sub-item in the construction site is also stored in the server. The management terminal is further used for setting temporary access authority of each worker terminal on the access authority table, and the temporary access authority comprises sub-items which can be accessed and corresponding access time. Sometimes, when a worker enters a construction sub-project of the worker, the worker needs to pass through another sub-project, and at this time, a supervisor can manage the travel of the worker by setting a temporary access authority (for example, X points can enter a sub-project every day within a certain period of time).
The worker end is used for positioning in real time and sending the positioning to the server; the server is used for analyzing the travel of the worker according to the real-time positioning of the worker end and the electronic map, and sending alarm information to the worker end when the analysis result is that the worker end is about to enter the sub-project which cannot be entered; and after the worker end receives the alarm signal, the intelligent bracelet is controlled to vibrate, alarm characters are displayed and an alarm sound is given out.
And the server is also used for controlling the corresponding monitoring terminal to shoot a field image according to the real-time positioning of the worker terminal and sending a processing signal and the field image to the management terminal when the worker terminal still enters the sub-project after sending the alarm information to the worker terminal.
The worker end is further used for collecting the physical sign information of workers and uploading the physical sign information to the server, the server is further used for conducting safety analysis according to the received physical sign information, if the safety analysis indicates that abnormity exists, a rest signal is sent to the corresponding worker end, and a check signal is sent to the management end. Like this, can let workman oneself in time know the condition when the workman has the health anomaly, have a rest and adjust, also can let supervisory personnel in time know the condition, in time look over the processing. The server stores the contact telephone of each worker end; the server is also used for sending a processing signal or a checking signal to the management terminal and simultaneously sending a contact telephone corresponding to the worker terminal.
By using the technical scheme, the worker end can perform real-time positioning and send the real-time positioning to the server during construction, the server can analyze the stroke of a worker according to the real-time positioning and the electronic map after receiving the real-time positioning of the worker end, and if the analysis result shows that a certain worker end is about to enter a sub-project which the worker end cannot enter, the situation that the worker is not in a proper moment or does not know the situation is indicated, and the worker end wants to enter the sub-project which the worker cannot enter. Therefore, the server sends the alarm information to the worker end, and if the worker does not know the condition, the worker can leave after receiving the alarm information; entry may continue if the worker is not in compliance.
Therefore, after the server sends the alarm information to the worker end, if the worker end still enters the sub-project, the server can control the corresponding monitoring end to shoot the field image according to the real-time positioning of the worker end, and send the processing signal and the field image to the management end. By processing the signals, the supervision personnel can know the situation and timely process the workers who are not in compliance. Through the field image that the control end was shot, can leave the on-the-spot evidence, also be convenient for simultaneously the supervisor to find this workman fast.
Therefore, unknowing workers can be prevented from entering sub-projects which cannot be entered, and workers who are not on duty can be quickly locked and processed, so that interference on construction is prevented as far as possible, and potential safety hazards are reduced.
Example two
Different from the first embodiment, the embodiment further includes an acquisition end, and specifically, the acquisition end in the embodiment includes a three-dimensional scanning device and a smart phone loaded with a corresponding APP.
The acquisition end is used for acquiring project data of the constructed part and sending the project data to the server; the server is also used for carrying out three-dimensional modeling according to the received project data to obtain a project model; the management side is also used for viewing the project model.
The management terminal is also used for creating and updating an acquisition schedule, and items of the acquisition schedule comprise acquisition time and acquisition position; the management terminal is also used for sending the latest acquisition schedule to the acquisition terminal when the acquisition schedule is created or updated;
the acquisition end is also used for acquiring the current positioning and acceleration of the acquisition end and sending the current positioning and acceleration to the server; the acquisition end is also used for calling the electronic map to the server when acquiring time in the acquisition schedule and judging whether the electronic map is at the corresponding acquisition position according to the current positioning; if not, the acquisition end is also used for judging whether the distance between the acquisition end and the acquisition position is within a preset range according to the current positioning; if the current positioning and acceleration is within the preset range, the acquisition end is further used for judging whether the current positioning and acceleration moves towards the acquisition position or not, and if not, an acquisition reminding signal is sent out; the acquisition end is also used for acquiring current weather information and analyzing whether the acquisition is suitable for acquiring construction data or not when the distance between the acquisition end and the acquisition position is judged not to be within a preset range according to the current positioning, and if the analysis result is not suitable, the acquisition end sends an acquisition change signal to the management end; if the analysis result is suitable, the acquisition end sends out an idling warning and sends an idling signal to the management end.
The foregoing is merely an example of the present invention, and common general knowledge in the field of known specific structures and characteristics is not described herein in any greater extent than that known in the art at the filing date or prior to the priority date of the application, so that those skilled in the art can now appreciate that all of the above-described techniques in this field and have the ability to apply routine experimentation before this date can be combined with one or more of the present teachings to complete and implement the present invention, and that certain typical known structures or known methods do not pose any impediments to the implementation of the present invention by those skilled in the art. It should be noted that, for those skilled in the art, without departing from the structure of the present invention, several changes and modifications can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent. The scope of the claims of the present application shall be determined by the contents of the claims, and the description of the embodiments and the like in the specification shall be used to explain the contents of the claims.
Claims (7)
1. The utility model provides an wisdom building site management platform which characterized in that: the system comprises a management end, a server, a monitoring end and a worker end;
a plurality of monitoring ends are respectively arranged on each sub-project; a plurality of worker ends are provided; the management terminal is used for creating and updating an access authority table, and the access authority table comprises specific sub-items which can be accessed by each worker terminal; the server is used for storing the access authority table and also storing an electronic map of each sub item in the construction site;
the worker end is used for positioning in real time and sending the positioning to the server; the server is used for analyzing the travel of the worker according to the real-time positioning of the worker end and the electronic map, and sending alarm information to the worker end when the analysis result is that the worker end is about to enter the sub-project which cannot be entered; and the server is also used for controlling the corresponding monitoring terminal to shoot a field image according to the real-time positioning of the worker terminal and sending a processing signal and the field image to the management terminal when the worker terminal still enters the sub-project after sending the alarm information to the worker terminal.
2. The intelligent worksite management platform of claim 1, wherein: the management terminal is further used for setting temporary access authority of each worker terminal on the access authority table, and the temporary access authority comprises sub-items which can be accessed and corresponding access time.
3. The intelligent worksite management platform of claim 1, wherein: the workman end includes intelligent bracelet, and the workman end receives alarm signal back, control intelligent bracelet vibrations, show alarm characters and send the alarm sound.
4. The intelligent worksite management platform of claim 3, wherein: the worker end is further used for collecting the physical sign information of workers and uploading the physical sign information to the server, the server is further used for conducting safety analysis according to the received physical sign information, if the safety analysis indicates that abnormity exists, a rest signal is sent to the corresponding worker end, and a check signal is sent to the management end.
5. The intelligent worksite management platform of claim 4, wherein: the server stores the contact telephone of each worker end; the server is also used for sending a processing signal or a checking signal to the management terminal and simultaneously sending a contact telephone corresponding to the worker terminal.
6. The intelligent worksite management platform of claim 1, wherein: the system also comprises an acquisition end, a server and a data processing end, wherein the acquisition end is used for acquiring project data of a constructed part and sending the project data to the server; the server is also used for carrying out three-dimensional modeling according to the received project data to obtain a project model; the management side is also used for viewing the project model.
7. The intelligent worksite management platform of claim 6, wherein: the management terminal is also used for creating and updating an acquisition schedule, and items of the acquisition schedule comprise acquisition time and acquisition position; the management terminal is also used for sending the latest acquisition schedule to the acquisition terminal when the acquisition schedule is created or updated;
the acquisition end is also used for acquiring the current positioning and acceleration of the acquisition end and sending the current positioning and acceleration to the server; the acquisition end is also used for calling the electronic map to the server when acquiring time in the acquisition schedule and judging whether the electronic map is at the corresponding acquisition position according to the current positioning; if not, the acquisition end is also used for judging whether the distance between the acquisition end and the acquisition position is within a preset range according to the current positioning; if the current positioning and acceleration is within the preset range, the acquisition end is further used for judging whether the current positioning and acceleration moves towards the acquisition position or not, and if not, an acquisition reminding signal is sent out;
the acquisition end is also used for acquiring current weather information and analyzing whether the acquisition is suitable for acquiring construction data or not when the distance between the acquisition end and the acquisition position is judged not to be within a preset range according to the current positioning, and if the analysis result is not suitable, the acquisition end sends an acquisition change signal to the management end; if the analysis result is suitable, the acquisition end sends out an idling warning and sends an idling signal to the management end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110479771.3A CN113191732A (en) | 2021-04-30 | 2021-04-30 | Wisdom building site management platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110479771.3A CN113191732A (en) | 2021-04-30 | 2021-04-30 | Wisdom building site management platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113191732A true CN113191732A (en) | 2021-07-30 |
Family
ID=76983247
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110479771.3A Pending CN113191732A (en) | 2021-04-30 | 2021-04-30 | Wisdom building site management platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113191732A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107748945A (en) * | 2017-09-01 | 2018-03-02 | 郭亚晋 | A kind of wisdom site staff management system |
CN108446866A (en) * | 2018-04-26 | 2018-08-24 | 中船第九设计研究院工程有限公司 | A kind of wisdom site safety management platform system framework |
CN109670795A (en) * | 2018-12-28 | 2019-04-23 | 广州易宝信息技术有限公司 | Project management system based on big data |
CN110222918A (en) * | 2019-04-18 | 2019-09-10 | 重庆恢恢信息技术有限公司 | Wisdom building site management system, server and storage medium based on cloud platform |
CN111045372A (en) * | 2019-12-30 | 2020-04-21 | 重庆能工科技发展有限公司 | Intelligent construction site management system |
CN111080260A (en) * | 2019-12-19 | 2020-04-28 | 巢湖学院 | Wisdom building site management platform |
CN111898866A (en) * | 2020-07-03 | 2020-11-06 | 浙江华卫智能科技有限公司 | Wisdom building site management platform |
CN112116301A (en) * | 2020-09-25 | 2020-12-22 | 重庆文理学院 | Intelligent construction site management system |
-
2021
- 2021-04-30 CN CN202110479771.3A patent/CN113191732A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107748945A (en) * | 2017-09-01 | 2018-03-02 | 郭亚晋 | A kind of wisdom site staff management system |
CN108446866A (en) * | 2018-04-26 | 2018-08-24 | 中船第九设计研究院工程有限公司 | A kind of wisdom site safety management platform system framework |
CN109670795A (en) * | 2018-12-28 | 2019-04-23 | 广州易宝信息技术有限公司 | Project management system based on big data |
CN110222918A (en) * | 2019-04-18 | 2019-09-10 | 重庆恢恢信息技术有限公司 | Wisdom building site management system, server and storage medium based on cloud platform |
CN111080260A (en) * | 2019-12-19 | 2020-04-28 | 巢湖学院 | Wisdom building site management platform |
CN111045372A (en) * | 2019-12-30 | 2020-04-21 | 重庆能工科技发展有限公司 | Intelligent construction site management system |
CN111898866A (en) * | 2020-07-03 | 2020-11-06 | 浙江华卫智能科技有限公司 | Wisdom building site management platform |
CN112116301A (en) * | 2020-09-25 | 2020-12-22 | 重庆文理学院 | Intelligent construction site management system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US12014304B2 (en) | Identifying and monitoring productivity, health, and safety risks in industrial sites | |
US10896331B2 (en) | Monitoring activities in industrial sites | |
EP3529675B1 (en) | Interior person-tracking-based control of manufacturing in the metalworking industry | |
CN109557934B (en) | Unmanned aerial vehicle cruise control method and device based on fabricated building platform | |
CN109870987A (en) | Platform of internet of things management method and its system suitable for large-sized workshop site operation | |
CN113706355A (en) | Method for building intelligent emergency system of chemical industry park | |
CN113128961B (en) | Wisdom building site management cloud platform system | |
US20210233186A1 (en) | Method for monitoring processes and progress at a construction site | |
CN109618287B (en) | Prisoner management method and device based on UWB positioning | |
CN114140999B (en) | Project supervision system based on communication of Internet of things | |
US10671948B2 (en) | Work cycle management | |
CN113177774A (en) | Building construction supervision method based on BIM | |
CN113869767A (en) | Method, system, electronic equipment and storage medium for supervising site police officer business assessment | |
CN115456595A (en) | Engineering construction project comprehensive control method based on multi-source data fusion | |
CN115860410A (en) | WeChat-based large civil engineering construction potential safety hazard management system | |
CN112367397A (en) | Monitoring and early warning method and system for field work, computer equipment and storage medium | |
US20200219037A1 (en) | System for collecting and analyzing equipment telematic data | |
CN116664343A (en) | System and method based on intelligent building site digital model | |
CN113191732A (en) | Wisdom building site management platform | |
CN117874533A (en) | Intelligent building platform | |
CN110633338A (en) | Intelligent risk prompting system for industrial places | |
CN110880096B (en) | Multi-party collaborative office system for building engineering | |
CN108388873A (en) | A kind of supervisory systems of machine vision, method and client computer, storage medium | |
CN116739299A (en) | Task information processing method and system | |
CN115546723A (en) | Nuclear power construction site management method and system based on real-time personnel live-action positioning |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210730 |
|
RJ01 | Rejection of invention patent application after publication |