CN113123218A - Multistage lateral limiting device suitable for bent and inclined bridge - Google Patents

Multistage lateral limiting device suitable for bent and inclined bridge Download PDF

Info

Publication number
CN113123218A
CN113123218A CN202110489330.1A CN202110489330A CN113123218A CN 113123218 A CN113123218 A CN 113123218A CN 202110489330 A CN202110489330 A CN 202110489330A CN 113123218 A CN113123218 A CN 113123218A
Authority
CN
China
Prior art keywords
steel
plate
limit
baffle
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110489330.1A
Other languages
Chinese (zh)
Other versions
CN113123218B (en
Inventor
孙宏涛
李东
刘聪
段守辉
欧阳嵩
高莉莉
李国峰
高超
胡鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority to CN202110489330.1A priority Critical patent/CN113123218B/en
Publication of CN113123218A publication Critical patent/CN113123218A/en
Application granted granted Critical
Publication of CN113123218B publication Critical patent/CN113123218B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A multi-stage lateral limiting device suitable for a curved bridge and an inclined bridge is characterized in that a limiting steel box is connected to the bottom of a beam body of a main beam, and a concrete stop block and a guide steel plate are connected to a cap beam or a bridge pier of a bridge abutment; a steel support piece and a steel baffle plate are arranged between the concrete stop block and the limiting steel box, and the tetrafluoroethylene sliding plate is fixed in front of the steel baffle plate and is in contact with the limiting steel box; the steel support piece is connected with the back of the steel baffle plate and is in piston type sliding connection with the steel shell, and the rear end of the steel shell is connected with the concrete stop block; a first limiting spring and a second limiting spring are arranged between the steel supporting piece and the front wall and the rear wall in the cavity of the steel shell; the steel sliding bottom plate is connected to the steel baffle bottom, and the steel sliding bottom plate is placed and is connected with pre-buried bottom plate through fixing bolt in the spout of direction steel sheet, and the direction steel sheet extends to the concrete dog, the steel baffle with connect the stiffening plate between the steel sliding bottom plate. The invention realizes displacement control of the bent bridge and the inclined bridge through multi-stage limiting measures, and can limit the displacement of the bridge under normal use condition and earthquake action in a grading way.

Description

一种适用于弯、斜桥的多级侧向限位装置A multi-stage lateral limit device suitable for curved and inclined bridges

技术领域technical field

本发明涉及土木工程技术领域,适用于桥梁限位尤其适用于弯、斜桥,具体是提供一种适用于弯、斜桥的多级侧向限位装置The invention relates to the technical field of civil engineering, is suitable for bridge limit, especially suitable for curved and inclined bridges, and specifically provides a multi-stage lateral limit device suitable for curved and inclined bridges

背景技术Background technique

在市政道路桥梁设计中,常常由于道路的线形要求及道路线形走向的原因导致桥梁为弯桥和斜桥。弯、斜桥由于其特殊的结构形式,在温度力、汽车制动力等纵桥向水平力作用下会产生绕桥墩(桥台)的转动以及横桥向的位移,若侧向不加以限制,随着时间的发展桥梁梁体出现侧向的偏位,也就是“爬移”现象,影响桥梁的使用以及整体结构的安全。In the design of municipal roads and bridges, the bridges are often curved bridges and inclined bridges due to the alignment requirements of the roads and the alignment of the roads. Due to their special structural forms, curved and inclined bridges will rotate around the piers (abutments) and displacements in the transverse bridge direction under the action of temperature force, vehicle braking force and other longitudinal bridge direction horizontal forces. If the lateral direction is not restricted, With the development of time, the lateral deviation of the bridge beam body, that is, the phenomenon of "climbing", affects the use of the bridge and the safety of the overall structure.

目前,弯、斜桥的设计中多采用刚性的混凝土挡块完全限制桥梁的横向位移,以保证桥梁线形的稳定。但在地震荷载作用下,刚性挡块会将梁体地震力完全传递给桥墩或桥台,因此对于桥墩和桩基等下部结构的抗震要求也更为严格,尤其在E2地震作用下,下部结构设计带来很大困难。At present, rigid concrete blocks are often used in the design of curved and inclined bridges to completely limit the lateral displacement of the bridge to ensure the stability of the bridge alignment. However, under the action of seismic load, the rigid block will completely transmit the seismic force of the beam body to the pier or abutment, so the seismic requirements for the substructure such as the pier and the pile foundation are also stricter, especially under the action of E2 earthquake, the substructure Design brings great difficulties.

弯、斜桥梁在温度和制动力作用下的具有横向位移和转动趋势,如果产生梁体变位将影响桥梁的正常使用,必须加以限制。通过分析,梁体本身及下部能够承受刚性限位带来的局部荷载。但对于偶然发生的地震作用尤其是E2作用,刚性限位措施导致结构受力较大,严重时甚至会造成梁体局部破坏,下部结构也因巨大的水平力而带来破坏。因此,本发明旨在通过多级弹性限位措施,既能够限制弯、斜桥梁体在温度力和制动力及E1地震作用下的侧向位移,保证桥梁在一般情况下正常使用,在罕遇强震E2地震作用下,又可以通过措施将侧向支撑调整为相对较弱的限位作用进而耗散地震作用,贯彻抗震多道设防的理念,达到保护梁体及下部结构的作用。Curved and inclined bridges have lateral displacement and rotation trends under the action of temperature and braking force. If the beam body is displaced, it will affect the normal use of the bridge and must be limited. Through analysis, the beam itself and the lower part can bear the local load brought by the rigid limit. However, for the occasional earthquake action, especially the E2 action, the rigid limit measures will cause the structure to be greatly stressed, and even cause local damage to the beam body in severe cases, and the substructure is also damaged due to the huge horizontal force. Therefore, the present invention aims to limit the lateral displacement of curved and inclined bridge bodies under the action of temperature force, braking force and E1 earthquake through multi-level elastic limiting measures, so as to ensure the normal use of bridges under normal circumstances, and in rare cases Under the action of the strong earthquake E2, the lateral support can be adjusted to a relatively weak limit effect through measures to dissipate the seismic action, and the concept of multi-channel fortification against earthquakes can be implemented to protect the beam body and the substructure.

发明内容SUMMARY OF THE INVENTION

本发明提供了一种适用于弯、斜桥的多级侧向限位装置,安装于桥台帽梁(或中墩)之上的多级限位装置,通过多道不同的限位分等级的进行弯、斜桥侧向位移的限制,其目的在于既能够满足桥梁在正常使用情况下对于温度、制动力顺桥向的自由伸缩,同时对侧向位移进行限制,也能够在罕遇强震E2地震作用下,通过抗震设施抗剪牺牲构件的剪断,从而对梁体能够产生相对较弱的限位作用进而耗散地震作用,达到保护梁体及下部结构的作用;既要解决限制弯、斜桥梁体在温度力和制动力及E1地震作用下的侧向位移的支撑问题,又要解决在罕遇强震E2地震作用下该支撑不破坏桥墩和桩基等下部结构的技术问题。The invention provides a multi-level lateral limiting device suitable for curved and inclined bridges. The multi-level limiting device installed on the bridge abutment cap beam (or middle pier) can be classified into grades through multiple different limiting channels. The purpose is to not only satisfy the free expansion and contraction of the bridge along the bridge direction for temperature and braking force under normal use conditions, but also to limit the lateral displacement, and also to be able to meet the requirements of rare and strong Under the action of earthquake E2, the shearing of the anti-shearing sacrificial members of the anti-seismic facilities can produce a relatively weak limiting effect on the beam body and then dissipate the seismic action, so as to protect the beam body and the substructure; it is necessary to solve the problem of limiting bending , The support of the inclined bridge body under the action of temperature force and braking force and the lateral displacement of the E1 earthquake, and the technical problem that the support will not damage the substructure such as the pier and the pile foundation under the action of the rare strong earthquake E2 earthquake.

本发明的技术方案如下:The technical scheme of the present invention is as follows:

一种适用于弯、斜桥的多级侧向限位装置,包括限位钢盒、钢挡板、钢支撑件、混凝土挡块;A multi-level lateral limiting device suitable for curved and inclined bridges, comprising a limiting steel box, a steel baffle, a steel support, and a concrete stop;

在主梁的梁体底部固定连接所述限位钢盒,并在桥台的帽梁或桥墩上固定连接混凝土挡块、导向钢板;The limit steel box is fixedly connected at the bottom of the girder body of the main beam, and the concrete block and the guide steel plate are fixedly connected to the cap beam or the bridge pier of the bridge abutment;

所述的混凝土挡块与所述限位钢盒之间设置钢支撑件、钢挡板,竖向设置的所述钢挡板与所述限位钢盒之间通过四氟乙烯滑板相接触;所述四氟乙烯滑板固定于钢挡板前面上,与限位钢盒仅保持接触;所述钢支撑件为在一水平设置的杆体两端分别固定连接竖向设置的支撑板、活塞板构成,所述活塞板放置于水平设置的钢外壳的腔体内并与其呈活塞式滑动连接,所述钢支撑件的支撑板在所述钢外壳的腔体外并与所述钢挡板后面固定连接;所述钢外壳后端顶靠在所述凝土挡块上并与其固定连接;所述钢支撑件的活塞板后端与所述钢外壳的腔体内的后壁之间设置限位弹簧一涨紧,所述活塞板前端与所述钢外壳的腔体内的前壁之间设置限位弹簧二涨紧,所述限位弹簧二套置在所述钢支撑件的杆体上滑动连接;所述钢支撑件与所述限位弹簧一、限位弹簧二呈水平设置;A steel support and a steel baffle are arranged between the concrete block and the limit steel box, and the vertically arranged steel baffle and the limit steel box are in contact with each other through a tetrafluoroethylene sliding plate; The tetrafluoroethylene sliding plate is fixed on the front of the steel baffle, and only keeps contact with the limit steel box; the steel support is composed of a horizontally arranged rod body that is fixedly connected to a vertically arranged support plate and a piston plate. , the piston plate is placed in the cavity of the horizontally arranged steel casing and is connected with it in a piston-type sliding manner, and the support plate of the steel support is outside the cavity of the steel casing and is fixedly connected behind the steel baffle; The rear end of the steel shell abuts on the concrete block and is fixedly connected with it; a limit spring is set between the rear end of the piston plate of the steel support and the rear wall in the cavity of the steel shell to expand A second limit spring is set between the front end of the piston plate and the front wall in the cavity of the steel shell to tighten, and the second limit spring is sleeved on the rod body of the steel support and is slidably connected; the The steel support is arranged horizontally with the first limit spring and the second limit spring;

钢底板包括滑动底板、预埋底板;所述预埋底板预埋在所述桥台的帽梁或桥墩表面,所述的导向钢板直立着焊接在所述预埋底板两侧并延伸到所述混凝土挡块与其接触;所述预埋底板表面与所述导向钢板内的帽梁顶面齐平共同构成滑槽内底面,所述导向钢板与所述预埋底板表面及所述导向钢板内的帽梁顶面共同组成所述滑槽;The steel bottom plate includes a sliding bottom plate and a pre-embedded bottom plate; the pre-embedded bottom plate is pre-buried on the surface of the cap beam or the pier of the bridge abutment, and the guide steel plate is welded upright on both sides of the pre-embedded bottom plate and extends to the The concrete block is in contact with it; the surface of the embedded bottom plate is flush with the top surface of the cap beam in the guide steel plate to form the inner bottom surface of the chute, the guide steel plate is in contact with the surface of the embedded bottom plate and the inner bottom surface of the guide steel plate. The top surface of the hat beam together forms the chute;

所述钢挡板底部固定连接水平设置的钢滑动底板,并在所述钢挡板与所述钢滑动底板之间固定连接所述加劲板,所述钢滑动底板放置于所述滑槽内的所述预埋底板上并通过固定螺栓与所述预埋底板固定连接,所述钢滑动底板与所述导向钢板之间呈可滑动接触,所述滑槽内的滑动方向与所述钢支撑件的移动方向一致。The bottom of the steel baffle is fixedly connected to a horizontally arranged steel sliding bottom plate, and the stiffening plate is fixedly connected between the steel baffle and the steel sliding bottom plate, and the steel sliding bottom plate is placed in the chute. The pre-embedded bottom plate is fixedly connected to the pre-embedded bottom plate through fixing bolts, the steel sliding bottom plate and the guide steel plate are in slidable contact, and the sliding direction in the chute is in contact with the steel support. move in the same direction.

在所述钢挡板与所述限位钢盒之间,所述钢挡板前面固定连接悬臂式的水平设置的竖向限位钢板。Between the steel baffle and the limit steel box, a cantilevered horizontally arranged vertical limit steel plate is fixedly connected in front of the steel baffle.

所述限位钢盒的顶部设置梁底连接钢板与主梁的梁体底部固定连接,其底部设置钢盒限位钢板,在所述梁底连接钢板与所述钢盒限位钢板之间连接竖向的钢盒侧向钢板构成长方体框架;所述梁底连接钢板与所述钢盒限位钢板悬出钢盒侧向钢板之外;所述钢挡板与所述限位钢盒后面的钢盒侧向钢板之间通过夹持的所述四氟乙烯滑板相接触;所述钢盒限位钢板悬出端位于所述竖向限位钢板(7)下方相互交错。The top of the limit steel box is provided with a beam bottom connecting steel plate and the bottom of the beam body of the main beam is fixedly connected, and the bottom of the limit steel box is provided with a steel box limit steel plate, which is connected between the beam bottom connecting steel plate and the steel box limit steel plate The vertical steel box side steel plate forms a cuboid frame; the beam bottom connecting steel plate and the steel box limit steel plate hang out of the steel box side steel plate; the steel baffle and the steel box behind the limit steel box; The side steel plates of the steel box are in contact with the clamped tetrafluoroethylene sliding plates; the overhanging ends of the limit steel plates of the steel box are located under the vertical limit steel plates (7) and staggered with each other.

所述导向钢板位于所述钢外壳下方,且所述导向钢板后端抵靠混凝土挡块。The guide steel plate is located under the steel shell, and the rear end of the guide steel plate abuts against the concrete block.

所述滑槽设置在所述钢支撑件的下方,所述滑槽的中轴线与所述钢支撑件的杆体中轴线在一个立面内。The chute is arranged below the steel support, and the central axis of the chute and the central axis of the rod body of the steel support are in a vertical plane.

所述的限位弹簧一的弹力不小于所述的限位弹簧二的弹力。The elastic force of the first limit spring is not less than the elastic force of the second limit spring.

在E1地震作用下,固定螺栓不发生剪断;在E2地震作用下,固定螺栓才会发生剪断。Under the action of the E1 earthquake, the fixing bolts will not be sheared; under the action of the E2 earthquake, the fixing bolts will be sheared.

所述的混凝土挡块随帽梁的施工同步浇筑制成。The concrete block is made by pouring synchronously with the construction of the cap beam.

预埋锚栓上端焊接连接所述预埋底板的底部、下端锚固在所述帽梁内,随所述帽梁的施工同步浇筑制成。The upper end of the pre-embedded anchor bolt is welded and connected to the bottom of the pre-embedded bottom plate, and the lower end is anchored in the cap beam, and is made by pouring synchronously with the construction of the cap beam.

所述加劲板沿所述滑槽方向直立。The stiffening plate stands upright along the direction of the chute.

本发明的技术效果如下:The technical effect of the present invention is as follows:

本发明通过多级限位措施实现了弯、斜桥的位移控制,能够分等级的限制桥梁在正常使用情况下和地震作用下的位移;并可以通过限位弹簧为桥梁提供一定的自恢复能力。本发明能够很好的满足弯、斜桥多级限位的要求,保证桥梁在正常使用和地震作用下的安全性,并且不会引起桥梁下部结构过大的荷载响应。The invention realizes the displacement control of curved and inclined bridges through multi-level limiting measures, and can limit the displacement of the bridge under normal use and earthquake action by levels; and can provide the bridge with a certain self-recovery ability through the limiting spring. . The invention can well meet the multi-level limit requirements of curved and inclined bridges, ensure the safety of the bridge under normal use and earthquake action, and will not cause excessive load response of the lower structure of the bridge.

附图说明:Description of drawings:

图1是本发明的整体结构示意图,Fig. 1 is the overall structure schematic diagram of the present invention,

图2是本发明的局部放大示意图,Fig. 2 is the partial enlarged schematic diagram of the present invention,

图3是本发明的局部俯视图,Figure 3 is a partial top view of the present invention,

附图编号说明:Description of drawing numbers:

主梁1、帽梁2、限位钢盒3、钢挡板4、预埋锚栓5、四氟乙烯滑板6、竖向限位钢板7、钢底板8、滑动底板81、预埋底板82、钢支撑件9、支撑板91、活塞板92(请见红色编号标注在图中)、杆体93、钢外壳11、混凝土挡块12、导向钢板13、滑槽131、固定螺栓14、加劲板15、钢盒侧向钢板16、梁底连接钢板17、钢盒限位钢板18、限位弹簧一19、限位弹簧二20Main beam 1, hat beam 2, limit steel box 3, steel baffle 4, embedded anchor bolt 5, tetrafluoroethylene slide plate 6, vertical limit steel plate 7, steel base plate 8, sliding base plate 81, embedded base plate 82 , steel support 9, support plate 91, piston plate 92 (please see the red number marked in the figure), rod body 93, steel shell 11, concrete block 12, guide steel plate 13, chute 131, fixing bolt 14, stiffening plate 15. Steel box side steel plate 16, beam bottom connecting steel plate 17, steel box limit steel plate 18, limit spring one 19, limit spring two 20

E1地震是指:工程场地重现期较短的地震作用,在第一阶段抗震设计中采用;E1 earthquake refers to the earthquake action with a short return period of the engineering site, which is adopted in the first-stage seismic design;

E2地震是指:工程场地重现期较长的地震作用,在第二阶段抗震设计中采用;详见《公路桥梁抗震设计规范》(JTG/T 2231-01-2020)。E2 earthquake refers to the earthquake action with a long return period of the engineering site, which is used in the second stage seismic design; see "Code for Seismic Design of Highway Bridges" (JTG/T 2231-01-2020).

具体实施方式Detailed ways

下面结合附图详细说明本发明的具体实施方式:The specific embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings:

参见图1、2、3所示,本发明的一种适用于弯、斜桥的多级侧向限位装置,包括限位钢盒3、钢挡板4、钢支撑件9、混凝土挡块12;Referring to Figures 1, 2, and 3, a multi-stage lateral limiting device suitable for curved and inclined bridges of the present invention includes a limiting steel box 3, a steel baffle 4, a steel support 9, and a concrete stopper 12;

在主梁1的梁体底部固定连接所述限位钢盒3,并在桥台的帽梁2或桥墩上固定连接混凝土挡块12、导向钢板13;The limit steel box 3 is fixedly connected to the bottom of the beam body of the main beam 1, and the concrete block 12 and the guide steel plate 13 are fixedly connected to the cap beam 2 or the pier of the bridge abutment;

所述的混凝土挡块12与所述限位钢盒3之间设置钢支撑件9、钢挡板4,竖向设置的所述钢挡板4与所述限位钢盒3之间通过四氟乙烯滑板6相接触;所述四氟乙烯滑板6固定于钢挡板4前面上,与限位钢盒3仅保持接触;所述钢支撑件9为在一水平设置的杆体93两端分别固定连接竖向设置的支撑板91、活塞板92构成,所述活塞板放置于水平设置的钢外壳11的腔体内并与其呈活塞式滑动连接,所述钢支撑件9的支撑板91在所述钢外壳11的腔体外并与所述钢挡板4后面固定连接;所述钢外壳11后端靠在所述凝土挡块12上并与其固定连接;所述钢支撑件9的活塞板后端与所述钢外壳1的腔体内的后壁之间设置限位弹簧一19涨紧,所述活塞板前端与所述钢外壳1的腔体内的前壁之间设置限位弹簧二20涨紧,所述限位弹簧二20套置在所述钢支撑件的杆体93上滑动连接;所述钢支撑件9与所述限位弹簧一、限位弹簧二呈水平设置;A steel support 9 and a steel baffle 4 are arranged between the concrete block 12 and the limit steel box 3 , and the vertically arranged steel baffle 4 and the limit steel box 3 pass through four corners. The fluoroethylene sliding plate 6 is in contact; the tetrafluoroethylene sliding plate 6 is fixed on the front of the steel baffle 4, and only keeps contact with the limit steel box 3; the steel support 9 is a horizontally arranged rod body 93 at both ends respectively The vertical support plate 91 and the piston plate 92 are fixedly connected, and the piston plate is placed in the cavity of the horizontally arranged steel casing 11 and is connected with it in a piston-type sliding manner. The support plate 91 of the steel support 9 is in the The steel casing 11 is outside the cavity and is fixedly connected to the back of the steel baffle 4; the rear end of the steel casing 11 is against the concrete block 12 and is fixedly connected to it; the piston plate of the steel support 9 A limit spring 19 is set between the rear end and the rear wall of the cavity of the steel shell 1 to tighten, and a limit spring 20 is set between the front end of the piston plate and the front wall of the cavity of the steel shell 1 When tensioned, the second limit spring 20 is sleeved on the rod body 93 of the steel support and is slidably connected; the steel support 9 is arranged horizontally with the first limit spring and the second limit spring;

钢底板8包括滑动底板81、预埋底板82;所述预埋底板82预埋在所述桥台的帽梁2或桥墩表面,所述的导向钢板13直立着焊接在所述预埋底板两侧并延伸到所述混凝土挡块12与其接触;所述预埋底板82表面与所述导向钢板13内的帽梁2顶面齐平共同构成滑槽131内底面,所述导向钢板13与所述预埋底板82表面及所述导向钢板13内的帽梁2顶面共同组成所述滑槽131;The steel bottom plate 8 includes a sliding bottom plate 81 and a pre-embedded bottom plate 82; the pre-embedded bottom plate 82 is pre-buried on the surface of the cap beam 2 or the pier of the bridge abutment, and the guide steel plate 13 is welded upright on the two sides of the pre-embedded bottom plate. The surface of the embedded bottom plate 82 is flush with the top surface of the cap beam 2 in the guide steel plate 13 to form the inner bottom surface of the chute 131, and the guide steel plate 13 and the The surface of the embedded bottom plate 82 and the top surface of the cap beam 2 in the guide steel plate 13 together form the chute 131;

所述钢挡板4底部固定连接水平设置的钢滑动底板81,并在所述钢挡板4与所述钢滑动底板81之间固定连接所述加劲板15,所述钢滑动底板81放置于所述滑槽131内的所述预埋底板82上并通过固定螺栓14与所述预埋底板82固定连接,所述钢滑动底板81与所述导向钢板13之间呈可滑动接触,所述滑槽内的滑动方向与所述钢支撑件9的移动方向一致。The bottom of the steel baffle 4 is fixedly connected to a horizontally arranged steel sliding bottom plate 81 , and the stiffening plate 15 is fixedly connected between the steel baffle 4 and the steel sliding bottom plate 81 , and the steel sliding bottom plate 81 is placed on the The pre-embedded bottom plate 82 in the chute 131 is fixedly connected to the pre-embedded bottom plate 82 through the fixing bolts 14 , and the steel sliding bottom plate 81 is in slidable contact with the guide steel plate 13 . The sliding direction in the chute corresponds to the moving direction of the steel support 9 .

在所述钢挡板4与所述限位钢盒3之间,所述钢挡板4前面固定连接悬臂式的水平设置的竖向限位钢板7。Between the steel baffle 4 and the limit steel box 3 , a cantilevered horizontally arranged vertical limit steel plate 7 is fixedly connected in front of the steel baffle 4 .

所述限位钢盒3的顶部设置梁底连接钢板17与主梁1的梁体底部固定连接,其底部设置钢盒限位钢板18,在所述梁底连接钢板17与所述钢盒限位钢板18之间连接竖向的钢盒侧向钢板16构成长方体框架;所述梁底连接钢板17与所述钢盒限位钢板18悬出钢盒侧向钢板16之外;所述钢挡板4与所述限位钢盒3后面的钢盒侧向钢板16之间通过夹持的所述四氟乙烯滑板6相接触;所述钢盒限位钢板18悬出端位于所述竖向限位钢板7下方相互交错。The top of the limit steel box 3 is provided with a beam bottom connecting steel plate 17 to be fixedly connected to the bottom of the beam body of the main beam 1, and a steel box limit steel plate 18 is arranged at the bottom, and the connecting steel plate 17 at the bottom of the beam is connected to the steel box limit. The vertical steel box side steel plates 16 are connected between the position steel plates 18 to form a cuboid frame; the beam bottom connecting steel plate 17 and the steel box limit steel plate 18 hang out of the steel box side steel plate 16; the steel block The plate 4 is in contact with the steel box lateral steel plate 16 behind the limit steel box 3 through the clamped tetrafluoroethylene sliding plate 6; the overhanging end of the steel box limit steel plate 18 is located in the vertical direction. The bottoms of the limiting steel plates 7 are staggered with each other.

所述导向钢板13位于所述钢外壳11下方,且所述导向钢板13后端抵靠混凝土挡块12。The guide steel plate 13 is located under the steel casing 11 , and the rear end of the guide steel plate 13 abuts against the concrete block 12 .

所述滑槽设置在所述钢支撑件的下方,所述滑槽的中轴线与所述钢支撑件的杆体中轴线在一个立面内。The chute is arranged below the steel support, and the central axis of the chute and the central axis of the rod body of the steel support are in a vertical plane.

所述的限位弹簧一19的弹力不小于所述的限位弹簧二20的弹力。The elastic force of the first limit spring 19 is not less than the elastic force of the second limit spring 20 .

在E1地震作用下,固定螺栓14不发生剪断;在E2地震作用下,固定螺栓14才会发生剪断。Under the action of the E1 earthquake, the fixing bolt 14 will not be sheared; under the action of the E2 earthquake, the fixing bolt 14 will be sheared.

所述的混凝土挡块12随帽梁2的施工同步浇筑制成。The concrete block 12 is cast synchronously with the construction of the cap beam 2 .

预埋锚栓5上端焊接连接所述预埋底板82的底部、下端锚固在所述帽梁2内,随所述帽梁2的施工同步浇筑制成。The upper end of the pre-embedded anchor bolt 5 is welded and connected to the bottom of the pre-embedded bottom plate 82 , and the lower end is anchored in the cap beam 2 , and is made by pouring synchronously with the construction of the cap beam 2 .

所述加劲板15沿所述滑槽方向直立。The stiffening plate 15 is erected along the direction of the chute.

四氟乙烯滑板6固定于钢挡板4上,与限位钢盒3仅保持接触;这样,四氟乙烯滑板6既可以为限位钢盒3与钢挡板4的碰撞提供缓冲作用,又不会限制主梁1在正常使用下的顺桥向位移,本发明不限于使用四氟乙烯滑板,还可以使用具有同等功能作用的其它材料的滑板。The tetrafluoroethylene sliding plate 6 is fixed on the steel baffle 4 and only keeps contact with the limit steel box 3; in this way, the tetrafluoroethylene sliding plate 6 can not only provide a buffer for the collision between the limit steel box 3 and the steel baffle 4, but also The displacement along the bridge direction of the main girder 1 under normal use will not be restricted, and the present invention is not limited to the use of tetrafluoroethylene sliding plates, and sliding plates of other materials with equivalent functions can also be used.

竖向限位钢板7与其底部的交错设置的钢盒限位钢板18的悬出段共同形成了桥梁的竖向限位。The vertical limit steel plate 7 and the overhanging section of the steel box limit steel plate 18 arranged staggeredly at the bottom together form the vertical limit of the bridge.

所述四氟乙烯板6在横桥向提供了钢盒与钢挡板之间的碰撞缓冲;由于四氟乙烯板6不与限位钢盒3连接,还保证了桥梁沿纵桥向的位移能力。当梁体发生横向位移时,首先利用所述钢挡板4与所述加劲板15自身的刚度,为梁体提供第一级的横向限位。The tetrafluoroethylene plate 6 provides a collision buffer between the steel box and the steel baffle in the transverse bridge direction; since the tetrafluoroethylene plate 6 is not connected with the limit steel box 3, the displacement of the bridge along the longitudinal bridge direction is also guaranteed. ability. When the beam body is displaced laterally, firstly, the rigidity of the steel baffle 4 and the stiffening plate 15 is used to provide the first-level lateral limit for the beam body.

所述钢支撑件9与所述限位弹簧一19构成第二级限位,随着梁体位移的增大,限位弹簧一提供的侧向限制力逐渐增大,实现了桥梁横向位移的分级控制。The steel support 9 and the limit spring 1 19 constitute a second-level limit. As the displacement of the beam body increases, the lateral limit force provided by the limit spring 1 gradually increases, and the lateral displacement of the bridge is realized. Grading control.

桥台的最外侧依旧采用传统的刚性混凝土挡块12作为最高级别的限位措施,以保证桥梁完全不发生落梁危害。The outermost side of the bridge abutment still uses the traditional rigid concrete block 12 as the highest level limit measure to ensure that the bridge does not suffer from falling beams at all.

本发明可以按现有设计方法依据不同的弯、斜桥角度以及相应的地震动分类进行限位设施具体刚度的设计;主要包括固定螺栓14的最大抗剪承载力、限位弹簧的具体刚度,限位弹簧的刚度主要考虑保证主梁在E2地震作用下的位移满足规范要求和帽梁尺寸要求,并应保证主梁发生横向地震位移时不出现绕梁中心转动的现象,以及最外侧刚性混凝土挡块的结构尺寸和配筋等。According to the existing design method, the present invention can design the specific stiffness of the limit facility according to different bending and inclined bridge angles and the corresponding ground motion classification; it mainly includes the maximum shear bearing capacity of the fixing bolt 14, the specific stiffness of the limit spring, The stiffness of the limit spring is mainly considered to ensure that the displacement of the main beam under the action of the E2 earthquake meets the requirements of the code and the size of the cap beam, and it should ensure that the main beam does not rotate around the center of the beam when the lateral seismic displacement occurs, and the outermost rigid concrete Structural dimensions and reinforcement of the stopper.

本发明的安装步骤:The installation steps of the present invention:

(1)混凝土挡块12随帽梁2的施工同步浇筑完成;钢底板8中的预埋底板82和预埋锚栓5随帽梁2的施工同步进行,应确保预埋底板82和预埋锚栓5在帽梁2中安装牢固。(1) The concrete block 12 is poured synchronously with the construction of the cap beam 2; the pre-embedded base plate 82 and the pre-embedded anchor bolts 5 in the steel base plate 8 are carried out synchronously with the construction of the cap beam 2, and it should be ensured that the pre-embedded base plate 82 and the embedded The anchor bolts 5 are firmly installed in the hat beam 2 .

(2)而后将滑动底板81通过固定螺栓14固定于预埋钢板82上,并在预埋钢板上焊接导向钢板13。(2) Then, the sliding bottom plate 81 is fixed on the embedded steel plate 82 by the fixing bolts 14, and the guide steel plate 13 is welded on the embedded steel plate.

(3)将钢盒侧向钢板16、钢盒限位钢板18焊接组成限位钢盒3,并通过梁底连接钢板17固定于主梁1底部。(3) The steel box lateral steel plate 16 and the steel box limit steel plate 18 are welded to form the limit steel box 3, and are fixed to the bottom of the main beam 1 through the beam bottom connecting steel plate 17.

(4)完成主梁安装工作,在帽梁2顶面可设置临时橡胶板,用作限位钢盒3和主梁1的临时支撑。主梁安装过程中,应当确保限位钢盒3与钢底板8的相对位置准确,减少后期的调整工作。(4) The installation of the main beam is completed, and a temporary rubber plate can be arranged on the top surface of the hat beam 2 to serve as a temporary support for the limit steel box 3 and the main beam 1. During the installation of the main beam, it should be ensured that the relative position of the limit steel box 3 and the steel base plate 8 is accurate, so as to reduce the adjustment work in the later stage.

(5)在滑动底板81上焊接钢挡板4以及加劲板15,竖向限位钢板7和四氟乙烯滑板6也一并焊接于钢挡板4上。若在安装过程中出现限位钢盒3与钢挡板4的相对位置偏差,可以通过调整四氟乙烯滑板6的厚度进行调整。(5) Weld the steel baffle plate 4 and the stiffening plate 15 on the sliding bottom plate 81 , and the vertical limit steel plate 7 and the tetrafluoroethylene sliding plate 6 are also welded to the steel baffle plate 4 together. If the relative positional deviation of the limiting steel box 3 and the steel baffle 4 occurs during the installation process, it can be adjusted by adjusting the thickness of the tetrafluoroethylene sliding plate 6 .

(6)将钢支撑件9与限位弹簧一19、限位弹簧二20以及钢外壳11组装完毕后安装于钢挡板4和混凝土挡块12之间;其中,支撑板91与钢挡板4固定连接,钢外壳11后壁与混凝土挡块12固定连接。(6) After the steel support 9 is assembled with the limit spring one 19, the limit spring two 20 and the steel shell 11, it is installed between the steel baffle 4 and the concrete block 12; wherein, the support plate 91 and the steel baffle 4. Fixed connection, the rear wall of the steel shell 11 is fixedly connected with the concrete block 12.

(7)完成上述安装步骤、确定各构件相对位置准确且连接牢固后,撤除临时橡胶板,本发明安装完毕。(7) After completing the above installation steps and confirming that the relative positions of the components are accurate and the connection is firm, the temporary rubber plate is removed, and the installation of the present invention is completed.

本发明的工作原理:The working principle of the present invention:

本发明依据不同弯、斜桥的具体结构形式,可以按现有设计方法,分析温度力和汽车制动力的组合作用下可能产生的水平力,并与E1地震作用下产生的横向水平力相比较,选择两者的较大值对固定螺栓14进行设计,保证在E1地震作用以及正常温度力和汽车制动力组合作用下,固定螺栓14不发生剪断。According to the specific structural forms of different curved and inclined bridges, the present invention can analyze the horizontal force that may be generated under the combined action of temperature force and vehicle braking force according to the existing design method, and compare it with the lateral horizontal force generated under the action of the E1 earthquake. , select the larger value of the two to design the fixing bolt 14 to ensure that the fixing bolt 14 will not be sheared under the combined action of the E1 earthquake and the combined action of the normal temperature force and the vehicle braking force.

当弯、斜桥在温度力和汽车制动力、以及E1地震力作用下产生转动或者横桥向位移时,安装于梁底的限位钢盒3就会与四氟乙烯板6以及钢挡板4发生碰撞,此时通过钢挡板4、加劲板15以及锚固螺栓14对梁体位移进行限制,并保证锚固螺栓5不发生剪坏。When the curved or inclined bridge rotates or the transverse bridge is displaced under the action of temperature force, automobile braking force, and E1 seismic force, the limit steel box 3 installed at the bottom of the beam will be connected with the tetrafluoroethylene plate 6 and the steel baffle. 4 collides, at this time, the beam body displacement is limited by the steel baffle 4, the stiffening plate 15 and the anchor bolt 14, and the anchor bolt 5 is not damaged by shearing.

在E2地震作用下,锚固螺栓14发生剪坏,导致钢挡板4、滑动底板81以及加劲板15在导向钢板13的限制下发生侧向移动,引起钢支撑件9的位移,并使限位弹簧一一侧受压、限位弹簧二一侧受拉,而限位弹簧一和二也会产生相应的反向作用力,以实现桥梁限位功能。基于E2地震产生的水平力以及规范规定的主梁位移限值和帽梁2的尺寸要求,可以计算得到限位弹簧一和限位弹簧二的最小刚度值,以保证E2地震作用下主梁位移在可控范围内。同时,由于限位弹簧在此过程中发生了形变,当地震结束后,还可以为梁体提供一个自复位的恢复力恢复,保证桥梁整体线型的稳定。Under the action of the E2 earthquake, the anchor bolts 14 are sheared, resulting in the lateral movement of the steel baffle 4, the sliding bottom plate 81 and the stiffening plate 15 under the restriction of the guide steel plate 13, causing the displacement of the steel support 9 and making the limit One side of the spring is compressed and the second side of the limit spring is pulled, and the first and second limit springs will also generate corresponding reverse forces to realize the bridge limit function. Based on the horizontal force generated by the E2 earthquake, the displacement limit of the main beam and the size requirements of the cap beam 2 specified in the code, the minimum stiffness values of the limit spring 1 and the limit spring 2 can be calculated to ensure the displacement of the main beam under the E2 earthquake. within the controllable range. At the same time, due to the deformation of the limit spring in the process, when the earthquake is over, it can also provide a self-resetting restoring force for the beam body to ensure the stability of the overall line shape of the bridge.

在极高烈度地震作用下,锚固螺栓14发生剪坏,并且限位弹簧一和钢支撑件9由于极大的水平地震力作用而失效,此时梁体的横桥向地震位移完全由混凝土挡块12限制;混凝土挡块12的尺寸和配筋应能够满足防止发生落梁的要求。Under the action of extremely high-intensity earthquake, the anchor bolts 14 are sheared, and the limit spring 1 and the steel support 9 fail due to the extremely large horizontal seismic force. At this time, the transverse seismic displacement of the beam body is completely blocked by concrete. The block 12 is limited; the size and reinforcement of the concrete block 12 should be able to meet the requirements of preventing the occurrence of falling beams.

Claims (10)

1.一种适用于弯、斜桥的多级侧向限位装置,其特征在于,包括限位钢盒(3)、钢挡板(4)、钢支撑件(9)、混凝土挡块(12);1. A multi-stage lateral limiting device suitable for curved and inclined bridges, characterized in that it comprises a limiting steel box (3), a steel baffle (4), a steel support (9), a concrete stop (3). 12); 在主梁(1)的梁体底部固定连接所述限位钢盒(3),并在桥台的帽梁(2)或桥墩上固定连接混凝土挡块(12)、导向钢板(13);The limiting steel box (3) is fixedly connected to the bottom of the beam body of the main beam (1), and the concrete block (12) and the guide steel plate (13) are fixedly connected to the cap beam (2) or the pier of the bridge abutment; 所述的混凝土挡块(12)与所述限位钢盒(3)之间设置钢支撑件(9)、钢挡板(4),竖向设置的所述钢挡板(4)与所述限位钢盒(3)之间通过四氟乙烯滑板(6)相接触;所述四氟乙烯滑板(6)固定于钢挡板(4)前面上,与限位钢盒(3)仅保持接触;所述钢支撑件(9)为在一水平设置的杆体(93)两端分别固定连接竖向设置的支撑板(91)、活塞板(92)构成,所述活塞板放置于水平设置的钢外壳(11)的腔体内并与其呈活塞式滑动连接,所述钢支撑件(9)的支撑板(91)在所述钢外壳(11)的腔体外并与所述钢挡板(4)后面固定连接;所述钢外壳(11)后端靠在所述凝土挡块(12)上并与其固定连接;所述钢支撑件(9)的活塞板后端与所述钢外壳(1)的腔体内的后壁之间设置限位弹簧一(19)涨紧,所述活塞板前端与所述钢外壳(1)的腔体内的前壁之间设置限位弹簧二(20)涨紧,所述限位弹簧二(20)套置在所述钢支撑件的杆体(93)上滑动连接;所述钢支撑件(9)与所述限位弹簧一、限位弹簧二呈水平设置;A steel support member (9) and a steel baffle (4) are arranged between the concrete block (12) and the limit steel box (3), and the vertically arranged steel baffle (4) is connected to the steel baffle (4). The limit steel boxes (3) are in contact with each other through a tetrafluoroethylene sliding plate (6); the tetrafluoroethylene sliding plate (6) is fixed on the front of the steel baffle plate (4), and only has keep in contact; the steel support (9) is composed of a horizontally arranged rod body (93) both ends fixedly connected to a vertically arranged support plate (91) and a piston plate (92), the piston plate is placed on a horizontal The steel casing (11) is arranged in the cavity and is connected in a piston-type sliding manner, and the support plate (91) of the steel support (9) is outside the cavity of the steel casing (11) and is connected with the steel baffle. (4) The rear is fixedly connected; the rear end of the steel shell (11) rests on the concrete block (12) and is fixedly connected with it; the rear end of the piston plate of the steel support (9) is connected to the steel A limit spring 1 (19) is arranged between the rear walls in the cavity of the casing (1) to tighten, and a limit spring 2 (19) is arranged between the front end of the piston plate and the front wall in the cavity of the steel casing (1). 20) Tighten, the second limit spring (20) is sleeved on the rod body (93) of the steel support and is slidably connected; the steel support (9) is connected with the first limit spring, the limit spring Two are set horizontally; 钢底板(8)包括滑动底板(81)、预埋底板(82);所述预埋底板(82)预埋在所述桥台的帽梁(2)或桥墩表面,所述的导向钢板(13)直立着焊接在所述预埋底板两侧并延伸到所述混凝土挡块(12)与其接触;所述预埋底板(82)表面与所述导向钢板(13)内的帽梁(2)顶面齐平共同构成滑槽(131)内底面,所述导向钢板(13)与所述预埋底板(82)表面及所述导向钢板(13)内的帽梁(2)顶面共同组成所述滑槽(131);The steel bottom plate (8) includes a sliding bottom plate (81) and a pre-embedded bottom plate (82); the pre-embedded bottom plate (82) is pre-embedded on the surface of the cap beam (2) or the pier of the bridge abutment, and the guide steel plate ( 13) Weld upright on both sides of the pre-embedded bottom plate and extend to the concrete block (12) in contact with it; the surface of the pre-embedded bottom plate (82) and the cap beam (2) in the guide steel plate (13) ) flush with the top surface together to form the inner bottom surface of the chute (131), the guide steel plate (13) and the surface of the pre-embedded bottom plate (82) and the top surface of the cap beam (2) in the guide steel plate (13) are common forming the chute (131); 所述钢挡板(4)底部固定连接水平设置的钢滑动底板(81),并在所述钢挡板(4)与所述钢滑动底板(81)之间固定连接所述加劲板(15),所述钢滑动底板(81)放置于所述滑槽(131)内的所述预埋底板(82)上并通过固定螺栓(14)与所述预埋底板(82)固定连接,所述钢滑动底板(81)与所述导向钢板(13)之间呈可滑动接触,所述滑槽内的滑动方向与所述钢支撑件(9)的移动方向一致。The bottom of the steel baffle plate (4) is fixedly connected to a horizontally arranged steel sliding bottom plate (81), and the stiffening plate (15) is fixedly connected between the steel baffle plate (4) and the steel sliding bottom plate (81). ), the steel sliding bottom plate (81) is placed on the pre-embedded bottom plate (82) in the chute (131) and is fixedly connected to the pre-embedded bottom plate (82) through the fixing bolts (14), so The steel sliding bottom plate (81) and the guide steel plate (13) are in slidable contact, and the sliding direction in the chute is consistent with the moving direction of the steel support (9). 2.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,在所述钢挡板(4)与所述限位钢盒(3)之间,所述钢挡板(4)前面固定连接悬臂式的水平设置的竖向限位钢板(7)。2. A multi-stage lateral limiting device suitable for curved and inclined bridges according to claim 1, characterized in that, between the steel baffle (4) and the limiting steel box (3) In between, a cantilevered horizontally arranged vertical limit steel plate (7) is fixedly connected in front of the steel baffle plate (4). 3.如权利要求2所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,所述限位钢盒(3)的顶部设置梁底连接钢板(17)与主梁(1)的梁体底部固定连接,其底部设置钢盒限位钢板(18),在所述梁底连接钢板(17)与所述钢盒限位钢板(18)之间连接竖向的钢盒侧向钢板(16)构成长方体框架;所述梁底连接钢板(17)与所述钢盒限位钢板(18)悬出钢盒侧向钢板(16)之外;所述钢挡板(4)与所述限位钢盒(3)后面的钢盒侧向钢板(16)之间通过夹持的所述四氟乙烯滑板(6)相接触;所述钢盒限位钢板(18)悬出端位于所述竖向限位钢板(7)下方相互交错。3. A multi-stage lateral limiting device suitable for curved and inclined bridges as claimed in claim 2, wherein the top of the limiting steel box (3) is provided with a beam bottom connecting steel plate (17) and The bottom of the beam body of the main beam (1) is fixedly connected, the bottom of which is provided with a steel box limit steel plate (18), and the vertical connection between the beam bottom connecting steel plate (17) and the steel box limit steel plate (18) The steel box lateral steel plate (16) constitutes a cuboid frame; the beam bottom connecting steel plate (17) and the steel box limit steel plate (18) hang out of the steel box lateral steel plate (16); the steel block The plate (4) is in contact with the steel box lateral steel plate (16) behind the limit steel box (3) through the clamped tetrafluoroethylene sliding plate (6); the steel box limit steel plate ( 18) The overhanging ends are located under the vertical limiting steel plate (7) and staggered with each other. 4.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,所述导向钢板(13)位于所述钢外壳(11)下方,且所述导向钢板(13)后端抵靠混凝土挡块(12)。4. A multi-stage lateral limiting device suitable for curved and inclined bridges according to claim 1, characterized in that the guide steel plate (13) is located under the steel casing (11), and the The rear end of the guide steel plate (13) abuts against the concrete block (12). 5.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,所述滑槽设置在所述钢支撑件的下方,所述滑槽的中轴线与所述钢支撑件的杆体中轴线在一个立面内。5 . The multi-stage lateral limiting device suitable for curved and inclined bridges according to claim 1 , wherein the chute is arranged below the steel support, and the middle of the chute is arranged. 6 . The axis is in one elevation with the central axis of the rod body of the steel support. 6.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,所述的限位弹簧一(19)的弹力不小于所述的限位弹簧二(20)的弹力。6. A multi-stage lateral limiting device suitable for curved and inclined bridges as claimed in claim 1, characterized in that the elastic force of the first limiting spring (19) is not less than that of the limiting spring Two (20) stretches. 7.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,在E1地震作用下,固定螺栓(14)不发生剪断;在E2地震作用下,固定螺栓(14)才会发生剪断。7. A kind of multi-stage lateral limiting device suitable for curved and inclined bridges as claimed in claim 1, characterized in that, under the action of the E1 earthquake, the fixing bolts (14) do not shear; under the action of the E2 earthquake , the fixing bolt (14) will be sheared. 8.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,所述的混凝土挡块(12)随帽梁(2)的施工同步浇筑制成。8. A multi-stage lateral limiting device suitable for curved and inclined bridges as claimed in claim 1, characterized in that, the concrete block (12) is cast synchronously with the construction of the cap beam (2). to make. 9.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,预埋锚栓(5)上端焊接连接所述预埋底板(82)的底部、下端锚固在所述帽梁(2)内,随所述帽梁(2)的施工同步浇筑制成。9. A multi-stage lateral limiting device suitable for curved and inclined bridges according to claim 1, characterized in that the upper end of the embedded anchor bolt (5) is welded to the bottom of the embedded bottom plate (82) and the lower end is anchored in the hat beam (2), and is made by pouring synchronously with the construction of the hat beam (2). 10.如权利要求1所述的一种适用于弯、斜桥的多级侧向限位装置,其特征在于,所述加劲板(15)沿所述滑槽方向直立。10 . The multi-stage lateral limiting device suitable for curved and inclined bridges according to claim 1 , wherein the stiffening plate ( 15 ) is erected along the direction of the chute. 11 .
CN202110489330.1A 2021-05-06 2021-05-06 A multi-stage lateral limit device suitable for curved and inclined bridges Active CN113123218B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110489330.1A CN113123218B (en) 2021-05-06 2021-05-06 A multi-stage lateral limit device suitable for curved and inclined bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110489330.1A CN113123218B (en) 2021-05-06 2021-05-06 A multi-stage lateral limit device suitable for curved and inclined bridges

Publications (2)

Publication Number Publication Date
CN113123218A true CN113123218A (en) 2021-07-16
CN113123218B CN113123218B (en) 2024-12-13

Family

ID=76781497

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110489330.1A Active CN113123218B (en) 2021-05-06 2021-05-06 A multi-stage lateral limit device suitable for curved and inclined bridges

Country Status (1)

Country Link
CN (1) CN113123218B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541244A (en) * 2022-01-25 2022-05-27 河南大学 A self-resetting anti-vibration block

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104963278A (en) * 2015-07-15 2015-10-07 浙江省交通规划设计研究院 Pier top displacement spring limiter for high-pier bridge
JP2017014749A (en) * 2015-06-29 2017-01-19 首都高速道路株式会社 Sliding mechanism of bridge seismic resistance device
CN206467556U (en) * 2017-02-16 2017-09-05 西南交通大学 A kind of spring-rubber damping device with multistage function of seismic resistance
KR101830863B1 (en) * 2017-04-05 2018-02-21 용일토건 주식회사 Hydraulic stopper for seismic control of bridge, and construction method for the same
CN111501514A (en) * 2020-04-30 2020-08-07 陈贞全 Assembled bridge capable of effectively absorbing shock
CN215252257U (en) * 2021-05-06 2021-12-21 北京市市政工程设计研究总院有限公司 Multistage lateral limiting device suitable for bent and inclined bridge

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017014749A (en) * 2015-06-29 2017-01-19 首都高速道路株式会社 Sliding mechanism of bridge seismic resistance device
CN104963278A (en) * 2015-07-15 2015-10-07 浙江省交通规划设计研究院 Pier top displacement spring limiter for high-pier bridge
CN206467556U (en) * 2017-02-16 2017-09-05 西南交通大学 A kind of spring-rubber damping device with multistage function of seismic resistance
KR101830863B1 (en) * 2017-04-05 2018-02-21 용일토건 주식회사 Hydraulic stopper for seismic control of bridge, and construction method for the same
CN111501514A (en) * 2020-04-30 2020-08-07 陈贞全 Assembled bridge capable of effectively absorbing shock
CN215252257U (en) * 2021-05-06 2021-12-21 北京市市政工程设计研究总院有限公司 Multistage lateral limiting device suitable for bent and inclined bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541244A (en) * 2022-01-25 2022-05-27 河南大学 A self-resetting anti-vibration block

Also Published As

Publication number Publication date
CN113123218B (en) 2024-12-13

Similar Documents

Publication Publication Date Title
JP6173553B1 (en) Seismic control device for bridge
CN204000587U (en) New city viaduct Horizontal Seismic system
Filiatrault et al. Development of self-centering earthquake resisting systems
CN113123218A (en) Multistage lateral limiting device suitable for bent and inclined bridge
CN111254818B (en) A bridge integral reinforcement device with shock-absorbing support
Tong et al. Experimental investigation of a single-yielding precast concrete beam–column connection with replaceable energy-dissipation connector
CN111962384A (en) Seismic bridge pier with built-in energy dissipation device and construction method thereof
Proske et al. Debris flow impacts on masonry arch bridges
Wang et al. Mechanical performance of steel ring restrainers with corrosion damage
CN215252257U (en) Multistage lateral limiting device suitable for bent and inclined bridge
Ates et al. Example of application of response history analysis for seismically isolated curved bridges on drilled shaft with springs representing soil
CN208309365U (en) It is a kind of to lead to the device of bridge vertical displacement suitable for limiting multiple spot earthquake
Jowza Safety Investigation and Guidance for Retrofitting Existing Approach Guardrail Transitions
CN115323943B (en) Fracture-resistant device of reverse fault bridge crossing based on hydraulic system
CN215857164U (en) Cushion block device capable of adjusting displacement
Yan et al. Shake table experimental study of cable-stayed bridges with two different design strategies of H-shaped towers
CN211079890U (en) A seismically replaceable railway bridge anti-seismic block after earthquake
Pètursson et al. Composite bridges with integral abutments minimizing lifetime cost
CN110485272A (en) Formula bridge shock-proof check block device is raised in a kind of rolling
CN112813852A (en) Repairing and reinforcing method for bridge deck subsidence of in-service bridge
Mohebi et al. Retrofitting damaged buildings under seismic mainshock-aftershock sequence
CN216615458U (en) Cushion block device capable of adjusting displacement and inclination angle
Miyachi et al. Ultimate strength and collapse process of cable-stayed arch bridges
CN218090473U (en) Shock-absorbing and energy-consuming anti-drop beam device for bridges
Markogiannaki et al. A proposal for improving regularity of brigdes with the rocking response of precast piers

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant