CN111962384A - Seismic bridge pier with built-in energy dissipation device and construction method thereof - Google Patents

Seismic bridge pier with built-in energy dissipation device and construction method thereof Download PDF

Info

Publication number
CN111962384A
CN111962384A CN202010766142.4A CN202010766142A CN111962384A CN 111962384 A CN111962384 A CN 111962384A CN 202010766142 A CN202010766142 A CN 202010766142A CN 111962384 A CN111962384 A CN 111962384A
Authority
CN
China
Prior art keywords
pier
energy dissipation
bridge pier
pipe pile
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010766142.4A
Other languages
Chinese (zh)
Inventor
高玉峰
何乃福
王景全
陈克坚
曾永平
张飞
戴光宇
张煜
舒爽
陈硕
叶至韬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN202010766142.4A priority Critical patent/CN111962384A/en
Publication of CN111962384A publication Critical patent/CN111962384A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/08Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against transmission of vibrations or movements in the foundation soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Bridges Or Land Bridges (AREA)
  • Foundations (AREA)

Abstract

The invention discloses an anti-seismic pier with built-in energy dissipation devices and a construction method thereof, wherein the anti-seismic pier comprises a pier, pipe piles are arranged in the pier, a plurality of rows of shock-absorbing energy dissipation devices are arranged between the pier and the pipe piles, each row of shock-absorbing energy dissipation devices at least comprises a group of symmetrically arranged shock-absorbing energy dissipation devices, each shock-absorbing energy dissipation device comprises energy dissipation components which are distributed in a crossed mode, two ends of each energy dissipation component are respectively fixed on the inner walls of the pier and the pipe piles, each energy dissipation component comprises a group of symmetrically distributed cylinders and piston rods, pistons are arranged at the end parts of the piston rods, and air holes are. The invention has strong applicability; the shock resistance of the pier can be improved, the built-in damping energy dissipation device and the built-in steel pipe foam concrete pile can play a role in energy dissipation and shock absorption, reduce the displacement of the pier under the earthquake load and improve the shock resistance of the pier; when the earthquake is over, the air holes are removed or enter the air cylinder, so that the air pressure inside and outside the air cylinder is balanced, and no additional constant load is applied to the bridge pier.

Description

一种内置耗能装置的抗震桥墩及其施工方法Seismic bridge pier with built-in energy dissipation device and construction method thereof

技术领域technical field

本发明涉及一种抗震桥墩及其施工方法,尤其涉及一种内置耗能装置的抗震桥墩及其施工方法。The invention relates to an anti-seismic bridge pier and a construction method thereof, in particular to an anti-seismic bridge pier with a built-in energy dissipation device and a construction method thereof.

背景技术Background technique

随着我国社会经济快速发展,基础设施建设不断向偏远山区延伸。桥梁工程建设在交通工程中具有举足轻重的作用。桥梁建设成本高,一旦遭到地震破坏,将造成巨大的损失。根据现有地震信息,桥墩震害是桥梁中最为常见的震害形式。桥墩是桥梁受力的关键构件,地震引起的钢筋混凝土桥墩变形将导致桥墩开裂、桥梁掉落、梁间碰撞甚至桥墩垮塌等灾害,严重影响人们的生产生活。With the rapid development of my country's social economy, infrastructure construction continues to extend to remote mountainous areas. Bridge engineering plays an important role in traffic engineering. Bridge construction costs are high, and once damaged by an earthquake, it will cause huge losses. According to the existing seismic information, the seismic damage of bridge piers is the most common form of seismic damage in bridges. Bridge piers are the key components of bridge stress. The deformation of reinforced concrete piers caused by earthquakes will lead to disasters such as pier cracking, bridge falling, collision between beams and even bridge pier collapse, which seriously affects people's production and life.

目前的桥梁设计中,桥梁抗震是重要的设计内容和研究方向,通过增加桥墩的抗剪强度、塑性能力和耗能能力是提高桥梁的抗震性能的关键技术之一。现有抗震设计中,通过在承受弯矩较大处钢筋加密来提高桥墩的抗剪强度,但同时也降低了桥梁的塑性,降低了地震时桥梁的能量耗散,提高了脆性破坏的危险性。In the current bridge design, bridge seismic resistance is an important design content and research direction. Increasing the shear strength, plastic capacity and energy dissipation capacity of bridge piers is one of the key technologies to improve the seismic performance of bridges. In the existing seismic design, the shear strength of the pier is improved by densifying the reinforcement at the place where the bending moment is large, but at the same time, the plasticity of the bridge is reduced, the energy dissipation of the bridge during earthquake is reduced, and the risk of brittle failure is increased. .

发明内容SUMMARY OF THE INVENTION

发明目的:本发明目的是提供一种内置耗能装置的抗震桥墩及其施工方法,在不改变桥梁塑性的情况下,通过外置装置提高桥梁的抗震性能。Purpose of the invention: The purpose of the present invention is to provide a seismic bridge pier with built-in energy dissipation device and a construction method thereof, which can improve the seismic performance of the bridge through external devices without changing the plasticity of the bridge.

技术方案:本发明包括桥墩,所述的桥墩内设有管桩,所述的桥墩和管桩之间设有多排减震耗能装置,每排减震耗能装置至少包括一组对称布置的减震耗能装置,所述的减震耗能装置包括交叉分布的耗能组件,所述耗能组件的两端分别固定在桥墩及管桩内壁上,所述的耗能组件包括一组对称分布的气缸和活塞杆,活塞杆的端部设有活塞,所述的活塞上布设有气孔。Technical solution: The present invention includes a bridge pier, wherein a pipe pile is arranged in the bridge pier, and multiple rows of shock absorption and energy dissipation devices are arranged between the bridge pier and the pipe pile, and each row of shock absorption and energy dissipation devices includes at least one set of symmetrical arrangement. The shock absorption and energy dissipation device includes cross-distributed energy dissipation components, the two ends of the energy dissipation components are respectively fixed on the inner wall of the bridge pier and the pipe pile, and the energy dissipation component includes a set of The cylinder and the piston rod are symmetrically distributed, the end of the piston rod is provided with a piston, and the piston is provided with air holes.

所述桥墩挠曲变形图的斜率最大位置处安装有一排减震耗能装置。A row of shock-absorbing and energy-dissipating devices is installed at the position of the maximum slope of the deflection deformation diagram of the bridge pier.

所述的活塞杆伸出气缸的部分套有弹簧,协助气缸耗散能量,同时防止活塞杆底部与气缸发生碰撞。The part of the piston rod extending out of the cylinder is covered with a spring, which assists the cylinder to dissipate energy and prevents the bottom of the piston rod from colliding with the cylinder.

所述耗能组件的两端设有铰接支座,所述的铰接支座与管桩焊接,与桥墩通过螺栓连接。The two ends of the energy dissipation component are provided with hinged supports, and the hinged supports are welded with the pipe piles and connected with the bridge piers by bolts.

所述的管桩包括钢管桩,所述的钢管桩内浇筑有泡沫混凝土,可以和桥墩的混凝土浇筑同步进行,不会影响施工工期。The pipe piles include steel pipe piles, and foam concrete is poured in the steel pipe piles, which can be performed simultaneously with the concrete pouring of the bridge piers without affecting the construction period.

所述钢管桩的中心与桥墩中心重合。The center of the steel pipe pile coincides with the center of the bridge pier.

所述钢管桩的底部与桥墩基础浇筑或焊接,顶部与桥梁支座之间垫有橡胶垫,可以促使钢管桩随桥梁面板移动,产生能量耗散。The bottom of the steel pipe pile is poured or welded with the bridge pier foundation, and a rubber pad is placed between the top and the bridge support, which can promote the steel pipe pile to move with the bridge deck and generate energy dissipation.

所述钢管桩的直径为桥墩最小内径的1/3~2/3。The diameter of the steel pipe pile is 1/3 to 2/3 of the minimum inner diameter of the bridge pier.

所述的桥墩顶部设有桥梁支座,底部固定在桥墩基础上。The top of the bridge pier is provided with a bridge support, and the bottom is fixed on the bridge pier foundation.

一种内置耗能装置的抗震桥墩的施工方法,包括以下步骤:A construction method for an anti-seismic bridge pier with built-in energy dissipation device, comprising the following steps:

(1)根据工程需要及承载力计算确定桥墩内径最小尺寸D、桥墩各级浇筑高度H和钢管桩直径d,并根据桥墩与钢管桩之间间隙的大小确定减震耗能装置的大小;(1) Determine the minimum size D of the inner diameter of the pier, the pouring height H of the pier at all levels and the diameter d of the steel pipe pile according to the engineering needs and the bearing capacity calculation, and determine the size of the shock absorption and energy dissipation device according to the size of the gap between the pier and the steel pipe pile ;

(2)桥墩基础施工时,将钢管桩插入桥墩基础中并浇筑混凝土,将钢管桩与桥墩基础刚接,安装的钢管桩高度与第一级浇筑的空心墩高度相同;(2) During the construction of the bridge pier foundation, insert the steel pipe pile into the bridge pier foundation and pour concrete, and rigidly connect the steel pipe pile to the bridge pier foundation, and the height of the installed steel pipe pile is the same as that of the hollow pier poured in the first stage;

(3)确定减震耗能装置的安装位置,上下两排减震耗能装置之间的距离不小于(D-d),不大于3(D-d),位于顶部或底部的减震耗能装置分别到桥墩顶部或底部的距离不小于(D-d),不大于3(D-d);(3) Determine the installation position of the shock absorption and energy consumption devices. The distance between the upper and lower rows of shock absorption energy consumption devices is not less than (D-d), not more than 3 (D-d), and the shock absorption energy consumption devices located at the top or bottom are respectively The distance between the top or bottom of the bridge pier is not less than (D-d), not more than 3 (D-d);

(4)桥墩钢筋施工,安装桥墩模板,并将铰接支座通过螺杆安装在模板上,向模板中浇筑混凝土,并将铰接支座浇筑在混凝土中,同时向钢管桩内浇筑泡沫混凝土,在钢管桩的相应位置上焊接另一个铰接支座;(4) Construction of pier reinforcement, installation of pier formwork, and installation of hinged supports on the formwork through screws, pouring concrete into the formwork, pouring the hinged supports in concrete, and pouring foam concrete into the steel pipe pile at the same time. Weld another hinged support on the corresponding position of the steel pipe pile;

(5)该级桥墩拆模后,安装减震耗能装置,使初始位置时,活塞位于气缸的中间位置;(5) After the pier of this level is removed from the formwork, install the shock absorption and energy dissipation device so that the piston is located in the middle position of the cylinder in the initial position;

(6)安装下一级钢管桩,重复步骤(1)~步骤(5),最后一级桥墩安装完成后,在钢管桩顶部安装橡胶垫,最后浇筑桥梁支座。(6) Install the next-level steel pipe pile, and repeat steps (1) to (5). After the installation of the last-level bridge pier is completed, install a rubber pad on the top of the steel pipe pile, and finally pour the bridge support.

有益效果:本发明适用性强,不仅适用于圆柱形空心墩,也适用于其它截面空心桥墩;可提高桥墩的抗震能力,内置减震耗能装置及内置钢管泡沫混凝土桩,可以起到耗能减震的作用,减少桥墩在地震荷载下的位移,提高桥墩的抗震性能;不会给桥墩带来额外的损伤,当地震结束时,气孔排除或进入气缸,使气缸内外气压平衡,不会向桥墩施加额外的恒定荷载。Beneficial effects: the invention has strong applicability, and is not only suitable for cylindrical hollow piers, but also for hollow bridge piers with other cross-sections; it can improve the seismic capacity of the bridge pier, and the built-in shock absorption and energy dissipation device and the built-in steel pipe foam concrete pile can play a role in energy dissipation The effect of shock absorption reduces the displacement of the bridge pier under the earthquake load and improves the seismic performance of the bridge pier; it will not bring additional damage to the bridge pier. Additional constant loads are applied to the piers.

附图说明Description of drawings

图1为本发明的桥墩横断面图;1 is a cross-sectional view of a bridge pier of the present invention;

图2为图1的A-A剖面图;Fig. 2 is the A-A sectional view of Fig. 1;

图3是本发明的减震耗能装置示意图;Fig. 3 is the schematic diagram of the shock absorption and energy dissipation device of the present invention;

图4是本发明的耗能组件示意图。FIG. 4 is a schematic diagram of an energy-consuming component of the present invention.

具体实施方式Detailed ways

下面结合附图对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings.

如图1和图2所示,本发明包括空心桥墩2,空心桥墩2顶部设有桥梁支座1,底部设有桥墩基础12,空心桥墩2承担上部桥梁支座1传递的所有荷载,空心桥墩2内部还浇筑有多个钢筋7。空心桥墩2内设有管桩,管桩由钢管桩3和现浇泡沫混凝土4组合而成,置于空心桥墩2内,不承担上部荷载,其中,钢管桩3的中心与空心桥墩2中心重合。泡沫混凝土4搅拌好后浇筑在钢管桩3内,可以和空心桥墩2的混凝土浇筑同步进行,不会影响施工工期。钢管桩3底部与桥墩基础12固接,可以浇筑,也可以焊接;顶部与桥梁支座1之间垫有橡胶垫6,可以促使钢管桩3随桥梁面板移动,产生能量耗散。钢管桩3的直径为空心桥墩2最小内径的1/3到2/3之间。As shown in Figures 1 and 2, the present invention includes a hollow bridge pier 2, the top of the hollow bridge pier 2 is provided with a bridge support 1, and the bottom is provided with a bridge pier foundation 12, the hollow bridge pier 2 bears all the loads transmitted by the upper bridge support 1, and the hollow bridge pier 2 There are also multiple steel bars 7 poured inside. The hollow pier 2 is provided with a pipe pile. The pipe pile is composed of a steel pipe pile 3 and a cast-in-place foam concrete 4. It is placed in the hollow pier 2 and does not bear the upper load. Centers coincide. After the foam concrete 4 is stirred, it is poured into the steel pipe pile 3, which can be carried out simultaneously with the concrete pouring of the hollow bridge pier 2, and will not affect the construction period. The bottom of the steel pipe pile 3 is fixedly connected with the bridge pier foundation 12, which can be poured or welded; a rubber pad 6 is placed between the top and the bridge support 1, which can promote the steel pipe pile 3 to move with the bridge deck, resulting in energy dissipation. The diameter of the steel pipe pile 3 is between 1/3 and 2/3 of the minimum inner diameter of the hollow pier 2 .

空心桥墩2和管桩之间的空隙中设有多排减震耗能装置,并依据空隙大小确定选用的减震耗能装置5的尺寸。每排减震耗能装置至少包括一组对称布置的减震耗能装置5,如图3所示,减震耗能装置5包括交叉铰接的耗能组件,耗能组件的两端分别固定在桥墩及钢管桩3内壁上,如图4所示,耗能组件包括一组对称分布的气缸8和活塞杆11,活塞杆11的端部设有活塞13,活塞13上布设有气孔。气缸8与铰接支座12铰接连接,活塞杆11置于气缸8中,并能沿气缸8滑动,活塞杆11的长度要和气缸8的深度相宜,不能太长也不能太短。活塞杆11伸出气缸8的部分套有高刚度弹簧9,协助气缸8耗散能量,同时防止活塞杆11底部与气缸8发生碰撞。耗能组件的两端均铰接有铰接支座12,铰接支座12分别固定在钢管桩3和空心桥墩2内壁上,和钢管桩3之间可以焊接,和空心桥墩2之间可以通过对穿螺栓浇筑在混凝土中。Multiple rows of shock absorption and energy dissipation devices are arranged in the gap between the hollow pier 2 and the pipe pile, and the size of the selected shock absorption and energy dissipation device 5 is determined according to the size of the gap. Each row of shock-absorbing and energy-consuming devices includes at least a set of symmetrically arranged shock-absorbing and energy-consuming devices 5. As shown in FIG. 3, the shock-absorbing and energy-consuming devices 5 include cross-hinged energy-consuming components, and both ends of the energy-consuming components are respectively fixed on On the inner wall of the bridge pier and the steel pipe pile 3, as shown in Figure 4, the energy dissipation component includes a set of symmetrically distributed cylinders 8 and piston rods 11. The end of the piston rod 11 is provided with a piston 13, and the piston 13 is provided with air holes. The cylinder 8 is hingedly connected with the hinged support 12. The piston rod 11 is placed in the cylinder 8 and can slide along the cylinder 8. The length of the piston rod 11 should be suitable for the depth of the cylinder 8, neither too long nor too short. The part of the piston rod 11 extending out of the cylinder 8 is covered with a high stiffness spring 9 , which assists the cylinder 8 to dissipate energy and at the same time prevents the bottom of the piston rod 11 from colliding with the cylinder 8 . Both ends of the energy dissipation component are hinged with hinged supports 12, and the hinged supports 12 are respectively fixed on the inner walls of the steel pipe pile 3 and the hollow bridge pier 2, and can be welded with the steel pipe pile 3, and can pass through the hollow bridge pier 2. The studs are cast in concrete.

桥墩挠曲变形图的斜率最大位置处安装有一排减震耗能装置5,其余位置的减震耗能装置5按照上下两排之间的距离不小于(D-d),不大于3(D-d)的间距安装;位于顶部或底部的减震耗能装置5分别到空心桥墩2顶部或底部的距离不小于(D-d),不大于3(D-d)。A row of shock-absorbing and energy-dissipating devices 5 is installed at the position with the maximum slope of the pier deflection deformation diagram, and the distance between the upper and lower rows of the shock-absorbing and energy-dissipating devices 5 is not less than (D-d) and not greater than 3 (D-d) according to the distance between the upper and lower rows. Distance installation; the distance between the shock absorption and energy dissipation device 5 at the top or the bottom and the top or bottom of the hollow pier 2 is not less than (D-d) and not more than 3 (D-d).

活塞13与气缸8之间封闭有一定体积的气体,活塞13上布有少量气孔,气孔要适宜,使得当铰接支座10传递动荷载时,气体来不及排除或进入气缸8,气体被压缩或拉伸,外界对气体做功,耗散能量;当铰接支座10传递较大恒定荷载时,气体可以通过气孔缓慢地排除或进入气缸8,最终气缸8内外气压几乎相同,不会像钢管桩3或空心桥墩2施加额外的荷载。A certain volume of gas is enclosed between the piston 13 and the cylinder 8, and a small amount of air holes are arranged on the piston 13. The air holes should be suitable so that when the hinged support 10 transmits the dynamic load, the air cannot be discharged or entered into the cylinder 8, and the air is compressed or pulled. When the hinged support 10 transmits a large constant load, the gas can be slowly discharged through the air hole or enter the cylinder 8, and finally the air pressure inside and outside the cylinder 8 is almost the same, not like the steel pipe pile 3 or hollow pier 2 to apply additional load.

本发明的抗震工作原理为:当地震作用产生的惯性力作用于桥墩时,空心桥墩2和钢管桩3发生变形。由于钢管桩3和空心桥墩2的质量及顶部施工方式不同,两者之间产生相对位移引起活塞13在气缸8中相对滑动,对气缸8内气体做功,产生能量耗散;当地震结束时,通过气孔排除或进入气缸8,使气缸8内外气压平衡,不会向桥墩施加额外的恒定荷载;此外,钢管桩3发生摆动,使得钢管桩3内的泡沫混凝土4破碎、移动,产生能量耗散。The anti-seismic working principle of the present invention is as follows: when the inertial force generated by the earthquake acts on the bridge pier, the hollow bridge pier 2 and the steel pipe pile 3 are deformed. Due to the different quality and top construction methods of the steel pipe pile 3 and the hollow bridge pier 2, the relative displacement between the two causes the piston 13 to slide relatively in the cylinder 8, doing work on the gas in the cylinder 8, resulting in energy dissipation; when the earthquake ends , Expel or enter the cylinder 8 through the air hole, so that the air pressure inside and outside the cylinder 8 is balanced, and no additional constant load is applied to the bridge pier; energy dissipation.

一种内置耗能装置的抗震桥墩的施工方法,包括以下步骤:A construction method for an anti-seismic bridge pier with built-in energy dissipation device, comprising the following steps:

(1)根据工程需要及承载力计算确定桥墩内径最小尺寸D、桥墩各级浇筑高度H和钢管桩直径d,并根据桥墩与钢管桩之间间隙的大小确定减震耗能装置的大小;(1) Determine the minimum size D of the inner diameter of the pier, the pouring height H of the pier at all levels and the diameter d of the steel pipe pile according to the engineering needs and the bearing capacity calculation, and determine the size of the shock absorption and energy dissipation device according to the size of the gap between the pier and the steel pipe pile ;

(2)桥墩基础施工时,将钢管桩插入桥墩基础中并浇筑混凝土,将钢管桩与桥墩基础刚接,安装的钢管桩高度与第一级浇筑的空心墩高度相同;(2) During the construction of the bridge pier foundation, insert the steel pipe pile into the bridge pier foundation and pour concrete, and rigidly connect the steel pipe pile to the bridge pier foundation, and the height of the installed steel pipe pile is the same as that of the hollow pier poured in the first stage;

(3)确定减震耗能装置的安装位置,上下两排减震耗能装置之间的距离不小于(D-d),不大于3(D-d),位于顶部或底部的减震耗能装置分别到桥墩顶部或底部的距离不小于(D-d),不大于3(D-d);(3) Determine the installation position of the shock absorption and energy consumption devices. The distance between the upper and lower rows of shock absorption energy consumption devices is not less than (D-d), not more than 3 (D-d), and the shock absorption energy consumption devices located at the top or bottom are respectively The distance between the top or bottom of the bridge pier is not less than (D-d), not more than 3 (D-d);

(4)桥墩钢筋施工,安装桥墩模板,并将铰接支座通过螺杆安装在模板上,向模板中浇筑混凝土,并将铰接支座浇筑在混凝土中,同时向钢管桩内浇筑泡沫混凝土,在钢管桩的相应位置上焊接另一个铰接支座;(4) Construction of pier reinforcement, installation of pier formwork, and installation of hinged supports on the formwork through screws, pouring concrete into the formwork, pouring the hinged supports in concrete, and pouring foam concrete into the steel pipe pile at the same time. Weld another hinged support on the corresponding position of the steel pipe pile;

(5)该级桥墩拆模后,安装减震耗能装置,使初始位置时,活塞位于气缸的中间位置;(5) After the pier of this level is removed from the formwork, install the shock absorption and energy dissipation device so that the piston is located in the middle position of the cylinder in the initial position;

(6)安装下一级钢管桩,重复步骤(1)~步骤(5),最后一级桥墩安装完成后,在钢管桩顶部安装橡胶垫,最后浇筑桥梁支座。(6) Install the next-level steel pipe pile, and repeat steps (1) to (5). After the installation of the last-level bridge pier is completed, install a rubber pad on the top of the steel pipe pile, and finally pour the bridge support.

Claims (10)

1.一种内置耗能装置的抗震桥墩,包括桥墩(2),所述的桥墩(2)内设有管桩,其特征在于,所述的桥墩(2)和管桩之间设有多排减震耗能装置,每排减震耗能装置至少包括一组对称布置的减震耗能装置(5),所述的减震耗能装置(5)包括交叉分布的耗能组件,所述耗能组件的两端分别固定在桥墩(2)及管桩内壁上,所述的耗能组件包括一组对称分布的气缸(8)和活塞杆(11),活塞杆(11)的端部设有活塞(13),所述的活塞(13)上布设有气孔。1. An anti-seismic bridge pier with a built-in energy dissipation device, comprising a bridge pier (2), wherein a pipe pile is provided in the described bridge pier (2), and it is characterized in that, there are multiple piers between the described bridge pier (2) and the pipe pile. Row of shock-absorbing and energy-consuming devices, each row of shock-absorbing and energy-consuming devices includes at least a set of symmetrically arranged shock-absorbing and energy-consuming devices (5), and the shock-absorbing energy-consuming devices (5) include cross-distributed energy-consuming components, so The two ends of the energy dissipation assembly are respectively fixed on the bridge pier (2) and the inner wall of the pipe pile, and the energy dissipation assembly includes a set of symmetrically distributed cylinders (8) and piston rods (11). A piston (13) is arranged on the part of the piston (13), and air holes are arranged on the piston (13). 2.根据权利要求1所述的一种内置耗能装置的抗震桥墩,其特征在于,所述桥墩(2)挠曲变形图的斜率最大位置处安装有一排减震耗能装置(5)。2 . The anti-seismic bridge pier with built-in energy dissipation device according to claim 1 , wherein a row of shock absorption and energy dissipation devices ( 5 ) is installed at the position of the maximum slope of the deflection deformation diagram of the bridge pier ( 2 ). 3 . 3.根据权利要求1所述的一种内置耗能装置的抗震桥墩,其特征在于,所述的活塞杆(11)伸出气缸(8)的部分套有弹簧(9)。3 . The anti-seismic bridge pier with built-in energy dissipation device according to claim 1 , wherein the part of the piston rod ( 11 ) extending out of the cylinder ( 8 ) is sleeved with a spring ( 9 ). 4 . 4.根据权利要求1所述的一种内置耗能装置的抗震桥墩,其特征在于,所述耗能组件的两端设有铰接支座(10),所述的铰接支座(10)与管桩焊接,与桥墩(2)通过螺栓连接。4. An anti-seismic bridge pier with built-in energy dissipation device according to claim 1, wherein both ends of the energy dissipation component are provided with hinged supports (10), and the hinged supports (10) are connected with The pipe pile is welded and connected with the pier (2) by bolts. 5.根据权利要求1所述的一种内置耗能装置的抗震桥墩,其特征在于,所述的管桩包括钢管桩(3),所述的钢管桩(3)内浇筑有泡沫混凝土(4)。5. The anti-seismic bridge pier with built-in energy dissipation device according to claim 1, wherein the pipe pile comprises a steel pipe pile (3), and the steel pipe pile (3) is poured with foam concrete (4). 6.根据权利要求5所述的一种内置耗能装置的抗震桥墩,其特征在于,所述钢管桩(3)的中心与桥墩(2)中心重合。6 . The seismic bridge pier with built-in energy dissipation device according to claim 5 , wherein the center of the steel pipe pile ( 3 ) coincides with the center of the bridge pier ( 2 ). 7 . 7.根据权利要求1或5所述的一种内置耗能装置的抗震桥墩,其特征在于,所述钢管桩(3)的底部与桥墩基础(12)浇筑或焊接,顶部与桥梁支座(1)之间垫有橡胶垫(6)。7. An anti-seismic bridge pier with built-in energy dissipation device according to claim 1 or 5, characterized in that the bottom of the steel pipe pile (3) is cast or welded with the pier foundation (12), and the top is connected with the bridge support There is a rubber pad (6) between (1). 8.根据权利要求7所述的一种内置耗能装置的抗震桥墩,其特征在于,所述钢管桩(3)的直径为桥墩(2)最小内径的1/3~2/3。The seismic bridge pier with built-in energy dissipation device according to claim 7, wherein the diameter of the steel pipe pile (3) is 1/3 to 2/3 of the minimum inner diameter of the bridge pier (2). 9.根据权利要求1所述的一种内置耗能装置的抗震桥墩,其特征在于,所述的桥墩(2)顶部设有桥梁支座(1),底部固定在桥墩基础(12)上。9 . The seismic bridge pier with built-in energy dissipation device according to claim 1 , wherein the bridge pier ( 2 ) is provided with a bridge support ( 1 ) at the top, and the bottom is fixed on the bridge pier foundation ( 12 ). 10 . 10.一种内置耗能装置的抗震桥墩的施工方法,其特征在于,包括以下步骤:10. A construction method for an anti-seismic bridge pier with a built-in energy dissipation device, characterized in that it comprises the following steps: (1)根据工程需要及承载力计算确定桥墩内径最小尺寸D、桥墩各级浇筑高度H和钢管桩直径d,并根据桥墩与钢管桩之间间隙的大小确定减震耗能装置的大小;(1) Determine the minimum size D of the inner diameter of the pier, the pouring height H of the pier at all levels and the diameter d of the steel pipe pile according to the engineering needs and the bearing capacity calculation, and determine the size of the shock absorption and energy dissipation device according to the size of the gap between the pier and the steel pipe pile ; (2)桥墩基础施工时,将钢管桩插入桥墩基础中并浇筑混凝土,将钢管桩与桥墩基础刚接,安装的钢管桩高度与第一级浇筑的空心墩高度相同;(2) During the construction of the bridge pier foundation, insert the steel pipe pile into the bridge pier foundation and pour concrete, and rigidly connect the steel pipe pile to the bridge pier foundation, and the height of the installed steel pipe pile is the same as that of the hollow pier poured in the first stage; (3)确定减震耗能装置的安装位置,上下两排减震耗能装置之间的距离不小于(D-d),不大于3(D-d),位于顶部或底部的减震耗能装置分别到桥墩顶部或底部的距离不小于(D-d),不大于3(D-d);(3) Determine the installation position of the shock absorption and energy consumption devices. The distance between the upper and lower rows of shock absorption energy consumption devices is not less than (D-d), not more than 3 (D-d), and the shock absorption energy consumption devices located at the top or bottom are respectively The distance between the top or bottom of the bridge pier is not less than (D-d), not more than 3 (D-d); (4)桥墩钢筋施工,安装桥墩模板,并将铰接支座通过螺杆安装在模板上,向模板中浇筑混凝土,并将铰接支座浇筑在混凝土中,同时向钢管桩内浇筑泡沫混凝土,在钢管桩的相应位置上焊接另一个铰接支座;(4) Construction of pier reinforcement, installation of pier formwork, and installation of hinged supports on the formwork through screws, pouring concrete into the formwork, pouring the hinged supports in concrete, and pouring foam concrete into the steel pipe pile at the same time. Weld another hinged support on the corresponding position of the steel pipe pile; (5)该级桥墩拆模后,安装减震耗能装置,使初始位置时,活塞位于气缸的中间位置;(5) After the pier of this level is removed from the formwork, install the shock absorption and energy dissipation device so that the piston is located in the middle position of the cylinder in the initial position; (6)安装下一级钢管桩,重复步骤(1)~步骤(5),最后一级桥墩安装完成后,在钢管桩顶部安装橡胶垫,最后浇筑桥梁支座。(6) Install the next-level steel pipe pile, and repeat steps (1) to (5). After the installation of the last-level bridge pier is completed, install a rubber pad on the top of the steel pipe pile, and finally pour the bridge support.
CN202010766142.4A 2020-08-03 2020-08-03 Seismic bridge pier with built-in energy dissipation device and construction method thereof Pending CN111962384A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010766142.4A CN111962384A (en) 2020-08-03 2020-08-03 Seismic bridge pier with built-in energy dissipation device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010766142.4A CN111962384A (en) 2020-08-03 2020-08-03 Seismic bridge pier with built-in energy dissipation device and construction method thereof

Publications (1)

Publication Number Publication Date
CN111962384A true CN111962384A (en) 2020-11-20

Family

ID=73363731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010766142.4A Pending CN111962384A (en) 2020-08-03 2020-08-03 Seismic bridge pier with built-in energy dissipation device and construction method thereof

Country Status (1)

Country Link
CN (1) CN111962384A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113699875A (en) * 2021-09-03 2021-11-26 河海大学 Super high shock attenuation pier structure of nearly fault railway
CN114293460A (en) * 2022-02-15 2022-04-08 中南大学 A railway swinging hollow high pier with shock absorption and energy dissipation device
CN114395977A (en) * 2022-02-15 2022-04-26 中南大学 Replaceable shear-resistant energy dissipation device for hollow swing pier of high-speed railway

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000273825A (en) * 1999-03-24 2000-10-03 Sumitomo Heavy Ind Ltd Earthquake-proof structure of bridge pier
JP2009068334A (en) * 2008-12-26 2009-04-02 Mitsui Eng & Shipbuild Co Ltd Steel pier with pressure-resistant core
CN103628402A (en) * 2013-12-20 2014-03-12 中铁二院工程集团有限责任公司 Earthquake energy dissipation structure of multi-pillar pier
CN105839518A (en) * 2016-04-08 2016-08-10 石家庄铁道大学 Energy-dissipation and shock-absorption tie beam for double-limb pier
JP2017096007A (en) * 2015-11-26 2017-06-01 東日本旅客鉄道株式会社 Pedestal structure
CN110344319A (en) * 2019-07-23 2019-10-18 重庆锦森腾建筑工程咨询有限公司 A kind of prefabricated assembled concrete bridge pier
CN110656574A (en) * 2018-06-29 2020-01-07 比亚迪股份有限公司 Method for manufacturing bridge pier

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000273825A (en) * 1999-03-24 2000-10-03 Sumitomo Heavy Ind Ltd Earthquake-proof structure of bridge pier
JP2009068334A (en) * 2008-12-26 2009-04-02 Mitsui Eng & Shipbuild Co Ltd Steel pier with pressure-resistant core
CN103628402A (en) * 2013-12-20 2014-03-12 中铁二院工程集团有限责任公司 Earthquake energy dissipation structure of multi-pillar pier
JP2017096007A (en) * 2015-11-26 2017-06-01 東日本旅客鉄道株式会社 Pedestal structure
CN105839518A (en) * 2016-04-08 2016-08-10 石家庄铁道大学 Energy-dissipation and shock-absorption tie beam for double-limb pier
CN110656574A (en) * 2018-06-29 2020-01-07 比亚迪股份有限公司 Method for manufacturing bridge pier
CN110344319A (en) * 2019-07-23 2019-10-18 重庆锦森腾建筑工程咨询有限公司 A kind of prefabricated assembled concrete bridge pier

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
阎荫槐: "《铸造机械基础》", 31 August 1990, 东北工学院出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113699875A (en) * 2021-09-03 2021-11-26 河海大学 Super high shock attenuation pier structure of nearly fault railway
CN114293460A (en) * 2022-02-15 2022-04-08 中南大学 A railway swinging hollow high pier with shock absorption and energy dissipation device
CN114395977A (en) * 2022-02-15 2022-04-26 中南大学 Replaceable shear-resistant energy dissipation device for hollow swing pier of high-speed railway
CN114293460B (en) * 2022-02-15 2022-09-20 中南大学 Railway swinging hollow high pier with damping and energy-consuming devices

Similar Documents

Publication Publication Date Title
CN111962384A (en) Seismic bridge pier with built-in energy dissipation device and construction method thereof
CN113322794B (en) Anti-roll section assembling swing single-column pier multiple damping system
CN106638946B (en) Connection structure of reinforced concrete rocking column and foundation
CN102121226A (en) Earthquake-resistant bridge abutment with flexible walls
CN111287071B (en) A multi-directional buffering, limiting, energy-dissipating, resettable bridge seismic stopper structure
CN110904825B (en) Integral bridge multistage abutment flexible main bridge abutment with replaceable damper and application thereof
CN218291565U (en) Assembled abutment structure of antidetonation power consumption
CN111074756B (en) A shock-absorbing and energy-consuming assembled swing bridge pier component and construction method thereof
CN110847010B (en) Construction and construction method suitable for large-span abutment rigid frame bridge
CN215253455U (en) An assembled multi-directional swing self-resetting cylinder structure system
CN221000584U (en) No cushion cap steel pipe concrete BRB shock attenuation frame pier
CN112112198A (en) Rigid-flexible combined novel damper device and construction method thereof
CN109898540B (en) Wet joint structure among bridge pier, bearing platform and pile foundation and construction process thereof
CN116335017B (en) Full-assembled bridge structure system of separated type swing bearing platform
CN109083001B (en) Improved structure of stop block for slowly reducing earthquake action and construction method thereof
CN113638361B (en) Connection structure of port and pier PHC tubular pile and superstructure
CN219637905U (en) A New Base Isolation and Damping System
CN111236287A (en) Integral foundation bearing platform for rapid construction
CN114016415B (en) Large cantilever bent cap mounting structure based on UHPC permanent template
CN216615473U (en) Take energy consumption damping device's assembled hollow concrete pier
CN107859196A (en) A kind of replaceable assembled energy-eliminating shock-absorbing node with runback bit function
CN210482044U (en) Self-anchored suspension bridge tower shock absorption structure
CN111945550A (en) An energy-consuming and shock-absorbing bridge pier structure and its construction method and application
CN112663663B (en) Prefabricated type foundation bearing platform
CN115573325B (en) Precast pile damping connection device and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201120

RJ01 Rejection of invention patent application after publication