CN113107155A CN202110369613.2A CN202110369613A CN113107155A CN 113107155 A CN113107155 A CN 113107155A CN 202110369613 A CN202110369613 A CN 202110369613A CN 113107155 A CN113107155 A CN 113107155A
Authority
CN
China
Prior art keywords
hanging
piece
keel
connecting piece
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110369613.2A
Other languages
Chinese (zh)
Other versions
CN113107155B (en
Inventor
胡俊华
李宽良
万奕非
吴荣荣
姜龙
俞志龙
徐剑峰
马云
吴淳
周鑫
张明武
龚春松
刘丽平
俞升东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Merud Building Decoration Co Ltd
Original Assignee
Suzhou Merud Building Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Merud Building Decoration Co Ltd filed Critical Suzhou Merud Building Decoration Co Ltd
Priority to CN202110369613.2A priority Critical patent/CN113107155B/en
Publication of CN113107155A publication Critical patent/CN113107155A/en
Application granted granted Critical
Publication of CN113107155B publication Critical patent/CN113107155B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a concrete plate dry-hanging type design and installation structure with balanced stress, which comprises: keel frame basic unit and a plurality of clear water concrete board, keel frame basic unit is including erecting fossil fragments and horizontal fossil fragments, and the clear water concrete board back is provided with first articulate piece and two second and articulates the piece, and first articulate piece fixed mounting is in clear water concrete board bottom, and first articulate piece articulates on horizontal fossil fragments, is provided with the connecting piece that the position corresponds the second articulate piece in keel frame basic unit, and the second articulates on the connecting piece, and the second articulates the contact surface of piece and connecting piece for the inclined plane. According to the dry hanging type design and installation structure of the concrete plate with balanced stress, the gravity of the large-area fair-faced concrete plate is uniformly transmitted to the steel skeleton, the flatness of the surface of the large-area fair-faced concrete plate is ensured, and the deformation and warping of the whole surface layer caused by the deformation of the plate and the keel frame base layer are avoided.

Description

Balanced concrete board dry-hanging design mounting structure of atress
Technical Field
The invention belongs to the field of bare concrete plate installation, and particularly relates to a dry-hanging type designed installation structure for a concrete plate with balanced stress.
Background
In the design process of architectural decoration, industrial styles and concrete color designs are gradually accepted by more people and are applied to wall decoration in various places in a large amount, such as: commercial buildings, sports buildings, traffic buildings, large exhibition halls, large bookstores, and the like. A large indoor space is generally present in such a place, and the space is decorated by using original-color concrete for decoration effect, so that a large amount of fair-faced concrete plates are used.
However, the fair-faced concrete board has the problems of low density and strength, is easy to damage, has a complex construction process, and is low in popularity, and the surface of a building using the wire-drawing fair-faced concrete board is easy to break and deform when bearing certain bending moment and tensile force due to the low tensile strength of the concrete.
Most materials of the fair-faced concrete plate are composed of cement and fibers, the plate is thinned by directly slotting on the fair-faced concrete plate, the bearing capacity is greatly weakened, the long-term stability of the plate is influenced, and therefore dry-hanging type installation is needed. The weight and the brittleness of the clear water concrete plate are large, and when the clear water concrete plate is hung on a base layer framework, if the stress is unbalanced, the plate and the base layer are easy to deform, and then the deformation and the warping of the whole surface layer are caused.
Disclosure of Invention
The invention aims to: the utility model provides a balanced concrete panel of atress is hanging formula design mounting structure futilely, when dry hanging of fair-faced concrete panel connects in keel frame base layer, makes the even transmission of gravity of whole large tracts of land fair-faced concrete panel to the steel skeleton through a plurality of stress points, guarantees the roughness on large tracts of land fair-faced concrete panel surface, avoids the deformation warpage that panel self and keel frame base layer lead to whole surface course.
In order to achieve the purpose, the invention adopts the following technical scheme: a concrete slab dry-hanging design installation structure with balanced stress comprises: keel frame basic unit and a plurality of clear water concrete board, keel frame basic unit is including erecting fossil fragments and horizontal fossil fragments, erect fossil fragments fixed mounting on building basic unit, horizontal fossil fragments fixed mounting is on erecting fossil fragments, the clear water concrete board back is provided with first articulate piece and two second and articulates the piece, first articulate piece fixed mounting is in clear water concrete board bottom, first articulate on horizontal fossil fragments, two second articulate piece symmetrical arrangement are in clear water concrete board both sides, be provided with the connecting piece that the position corresponds the second and articulates the piece in keel frame basic unit, connecting piece fixed mounting is on erecting fossil fragments, the second articulates the piece and articulates on the connecting piece, the contact surface of second articulate piece and connecting piece is the inclined plane.
As a further description of the above technical solution:
the first hanging piece comprises a first hanging portion and a first end plate, the first hanging portion is fixedly installed on the fair-faced concrete plate through a first connecting plate, the first hanging portion is placed on the transverse keel, the thickness of the first hanging portion is equal to that of the transverse keel, the first end plate is fixedly installed at the end portion of the first hanging portion, and the first end plate is perpendicular to the first hanging portion.
As a further description of the above technical solution:
the cross-section of the first hanging part is in a trapezoidal structure with a narrow top and a wide bottom.
As a further description of the above technical solution:
the second hanging and connecting piece comprises a base part, a second hanging and connecting part and a second end plate which are sequentially arranged along a straight line, the base part is fixedly installed on the fair-faced concrete plate, a first inclined plane is arranged on the second hanging and connecting part, and the first inclined plane is abutted to the connecting piece.
As a further description of the above technical solution:
the thickness of base portion equals the thickness of horizontal fossil fragments, and base portion passes through countersunk head bolt fixed mounting at the clear water concrete panel back.
As a further description of the above technical solution:
the connecting piece includes second connecting plate and third hitching part, and second connecting plate fixed mounting is provided with the second inclined plane on the third hitching part on the vertical keel, and the second inclined plane matches first inclined plane.
As a further description of the above technical solution:
first reinforcing rods are arranged between the first hanging and connecting pieces and the second hanging and connecting pieces, second reinforcing rods are arranged between the two second hanging and connecting pieces, and the two first reinforcing rods are symmetrically arranged on two sides of the first hanging and connecting pieces.
As a further description of the above technical solution:
the fair-faced concrete board is a high-density board with water absorption rate less than 20%.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
1. in the invention, the keel frame base layer is fixedly arranged on the building base layer, and then the bare concrete plate is hung on the keel frame base layer. The first hanging and connecting piece on the back surface of the fair-faced concrete plate is hung and connected on the transverse keel, and the two second hanging and connecting pieces are hung and connected on the vertical keels on the two sides of the first hanging and connecting piece. The height difference of first hitching and connecting piece and second, two second hitching and connecting pieces and first hitching and connecting piece according to clockwise line in proper order can form isosceles triangle structure, and the gravity of whole large tracts of land clear water concrete panel is through the dry pendant structure of arranging like this, and even transmission is for on the keel frame basic unit, guarantees the roughness on large tracts of land clear water concrete panel surface, avoids the deformation of panel self. Because the first portion cross-section of hitching of first articulate is "narrow-end-up wide down" trapezoidal, increase and cross keel's area of contact reduces cross keel's deformation risk. Meanwhile, the contact surface of the second hanging piece and the connecting piece is an inclined surface, the gravity of the large-area fair-faced concrete plate is dispersed into the force in the horizontal direction, the vertical keel helps the transverse keel to bear part of the weight, the deformation risk of the transverse keel and the deformation risk of the whole keel frame base layer are further reduced, and the surface layer formed by hanging the fair-faced concrete plate is prevented from deforming and warping.
2. According to the dry-hanging structure, the first hanging piece and the second hanging piece are connected through the first reinforcing rod, and the two second hanging pieces are connected through the second reinforcing rod, so that the integrity of the dry-hanging structure arranged on the back surface of the fair-faced concrete plate is improved, the hanging effect is ensured, the supporting effect on the large-area fair-faced concrete plate is achieved, and the deformation of the fair-faced concrete plate is avoided.
3. According to the invention, the fair-faced concrete board is a high-density board with the water absorption rate of less than 20%, has strong moisture resistance, and further avoids surface layer deformation.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
Fig. 1 is a schematic view of a main viewing angle structure of a concrete plate dry-hanging type design installation structure with balanced stress.
FIG. 2 is a schematic view of the hanging of bare concrete panels in a concrete panel dry-hanging design installation structure with balanced stress.
FIG. 3 is a schematic structural view of a bare concrete panel in a dry-hanging type design installation structure of a concrete panel with balanced stress.
Fig. 4 is a schematic structural diagram of a keel frame base layer in a concrete plate dry-hanging type design installation structure with balanced stress.
Fig. 5 is a schematic structural view of a first hanging member in a concrete plate dry-hanging type design installation structure with balanced stress.
FIG. 6 is a schematic structural diagram of a second hanging member and a connecting member in a concrete plate dry-hanging type design installation structure with balanced stress.
Illustration of the drawings:
1. a keel frame base layer; 11. a vertical keel; 12. a transverse keel; 2. bare concrete plates; 3. a first hanging piece; 31. a first hanging part; 32. a first end plate; 311. a first connecting plate; 4. a second hanging piece; 41. a base part; 42. a second hanging part; 421. a first inclined plane; 43. a second end plate; 5. a connecting member; 51. a second connecting plate; 52. a third hanging part; 521. a second inclined plane; 6. a first reinforcing bar; 7. a second reinforcing bar.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present invention, presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures.
In the description of the embodiments of the present invention, it should be noted that the terms "upper", "inner", and the like refer to orientations or positional relationships based on the orientations or positional relationships shown in the drawings or orientations or positional relationships that are conventionally arranged when the products of the present invention are used, and are used only for convenience in describing the present invention and simplifying the description, but do not indicate or imply that the devices or elements referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-6, the present invention provides a technical solution: a concrete slab dry-hanging design installation structure with balanced stress comprises: keel frame basic unit 1 and a plurality of clear water concrete board 2, keel frame basic unit 1 includes vertical keel 11 and horizontal keel 12, vertical keel 11 fixed mounting is on building basic unit, horizontal keel 12 fixed mounting is on vertical keel 11, 2 backs of clear water concrete board are provided with first articulate piece 3 and two second articulate piece 4, first articulate piece 3 fixed mounting is in 2 bottoms of clear water concrete board, first articulate piece 3 articulates on horizontal keel 12, two second articulate piece 4 symmetrical arrangement are in 2 both sides of clear water concrete board, be provided with the connecting piece 5 that the position corresponds second articulate piece 4 on keel frame basic unit 1, connecting piece 5 fixed mounting is on vertical keel 11, second articulate piece 4 articulates on connecting piece 5, the contact surface of second articulate piece 4 and connecting piece 5 is the inclined plane.
First hanging piece 3 includes first hanging portion 31 and first endplate 32, and first hanging portion 31 is through first connecting plate 311 fixed mounting on clear water concrete plate 2, and first hanging portion 31 is placed on horizontal keel 12, and the thickness of first hanging portion 31 equals the thickness of horizontal keel 12, and first endplate 32 fixed mounting is at the tip of first hanging portion 31, the first hanging portion 31 of first endplate 32 perpendicular to. First end plate 32 catches on cross keel 12, prevents that first articulate piece 3 from breaking away from keel frame basic unit 1 along the direction of perpendicular to clear water concrete board 2, and the detachable design of first end plate 32 is convenient for change to and set up according to the thickness flexibility of cross keel.
The cross-section of first portion 31 of hanging is the trapezium structure of "narrow-end-up width down", and the increase reduces the deformation risk of cross keel with the area of contact of cross keel.
The second hanging part 4 comprises a base part 41, a second hanging part 42 and a second end plate 43 which are sequentially arranged along a straight line, the base part 41 is fixedly installed on the fair-faced concrete plate 2, the second hanging part 42 is provided with a first inclined surface 421, and the first inclined surface 421 is abutted to the connecting part 5.
The thickness of base portion 41 equals the thickness of horizontal keel 12, and base portion 41 passes through countersunk head bolt fixed mounting at the clear water concrete plate 2 back, and base portion 41 fills the vacancy between clear water concrete plate 2 and the vertical keel 11, guarantees that clear water concrete plate 2 installs firmly.
The connecting piece 5 comprises a second connecting plate 51 and a third hanging part 52, the second connecting plate 51 is fixedly installed on the vertical keel 11, a second inclined plane 521 is arranged on the third hanging part 52, the second inclined plane 521 is matched with the first inclined plane 421, and the second end plate 43 of the second hanging piece 4 can hang the side edge of the second inclined plane 521 to limit the clear water concrete plate 2 to be separated from the keel frame base layer 1.
Be provided with first strengthening rod 6 between first articulate piece 3 and the second articulate piece 4, be provided with second strengthening rod 7 between two second articulate piece 4, two first strengthening rod 6 symmetrical arrangement improve the wholeness in first articulate 3 both sides of piece, avoid clear water concrete panel 2 to warp.
The fair-faced concrete board 2 is a high-density board with the water absorption rate of less than 20%, has strong moisture-proof capability, and further avoids the deformation of a surface layer.
The working principle is as follows: firstly, the keel frame base layer is fixedly installed on the building base layer, and then the bare concrete plate is hung on the keel frame base layer. The first hanging and connecting piece on the back surface of the fair-faced concrete plate is hung and connected on the transverse keel, and the two second hanging and connecting pieces are hung and connected on the vertical keels on the two sides of the first hanging and connecting piece. The height difference of first hitching and connecting piece and second, two second hitching and connecting pieces and first hitching and connecting piece according to clockwise line in proper order can form isosceles triangle structure, and the gravity of whole large tracts of land clear water concrete panel is through the dry pendant structure of arranging like this, and even transmission is for on the keel frame basic unit, guarantees the roughness on large tracts of land clear water concrete panel surface, avoids the deformation of panel self. Because the first portion cross-section of hitching of first articulate is "narrow-end-up wide down" trapezoidal, increase and cross keel's area of contact reduces cross keel's deformation risk. Meanwhile, the contact surface of the second hanging piece and the connecting piece is an inclined surface, the gravity of the large-area fair-faced concrete plate is dispersed into the force in the horizontal direction, the vertical keel helps the transverse keel to bear part of the weight, the deformation risk of the transverse keel and the deformation risk of the whole keel frame base layer are further reduced, and the surface layer formed by hanging the fair-faced concrete plate is prevented from deforming and warping. Connect through first anchor strut between first hitching member and the second hitching member, connect through the second anchor strut between two second hitching members, improve the wholeness of hanging the structure futilely that the clear water concrete panel back set up, guarantee to articulate the effect to play the supporting role to large tracts of land clear water concrete panel, avoid clear water concrete panel to warp.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (8)

1. The utility model provides a balanced concrete slab dry-hanging design mounting structure of atress which characterized in that includes: the novel building exposed concrete slab comprises a keel frame base layer (1) and a plurality of exposed concrete slabs (2), wherein the keel frame base layer (1) comprises a vertical keel (11) and a horizontal keel (12), the vertical keel (11) is fixedly arranged on the building base layer, the horizontal keel (12) is fixedly arranged on the vertical keel (11), a first hanging piece (3) and two second hanging pieces (4) are arranged on the back surface of the exposed concrete slabs (2), the first hanging piece (3) is fixedly arranged at the bottom of the exposed concrete slabs (2), the first hanging piece (3) is hung on the horizontal keel (12), the two second hanging pieces (4) are symmetrically arranged on two sides of the exposed concrete slabs (2), a connecting piece (5) corresponding to the second hanging piece (4) in position is arranged on the keel frame base layer (1), the connecting piece (5) is fixedly arranged on the vertical keel (11), the second hanging piece (4) is hung on the connecting piece (5), and the contact surface of the second hanging piece (4) and the connecting piece (5) is an inclined plane.
2. The concrete slab dry-hanging type design and installation structure with balanced stress according to claim 1, wherein the first hanging piece (3) comprises a first hanging part (31) and a first end plate (32), the first hanging part (31) is fixedly installed on the fair-faced concrete slab (2) through a first connecting plate (311), the first hanging part (31) is placed on the cross keel (12), the thickness of the first hanging part (31) is equal to that of the cross keel (12), the first end plate (32) is fixedly installed at the end part of the first hanging part (31), and the first end plate (32) is perpendicular to the first hanging part (31).
3. The concrete slab dry-hanging type design and installation structure with balanced stress according to claim 2, wherein the cross section of the first hanging part (31) is in a trapezoidal structure with a narrow top and a wide bottom.
4. The concrete slab dry-hanging design installation structure with balanced stress according to claim 1, wherein the second hanging piece (4) comprises a base part (41), a second hanging part (42) and a second end plate (43) which are sequentially arranged along a straight line, the base part (41) is fixedly installed on the fair-faced concrete slab (2), the second hanging part (42) is provided with a first inclined surface (421), and the first inclined surface (421) is abutted to the connecting piece (5).
5. A force balanced concrete slab hanging design mounting structure as claimed in claim 4 characterized in that the thickness of the base part (41) is equal to the thickness of the cross keel (12), the base part (41) is fixed on the back of the fair-faced concrete slab (2) by countersunk head bolts.
6. The concrete slab dry-hanging type design and installation structure with balanced stress according to claim 4, wherein the connecting piece (5) comprises a second connecting plate (51) and a third hanging part (52), the second connecting plate (51) is fixedly installed on the vertical keel (11), a second inclined surface (521) is arranged on the third hanging part (52), and the second inclined surface (521) is matched with the first inclined surface (421).
7. The concrete slab dry-hanging type design and installation structure with balanced stress according to claim 1, characterized in that a first reinforcing rod (6) is arranged between the first hanging and connecting piece (3) and the second hanging and connecting piece (4), a second reinforcing rod (7) is arranged between the two second hanging and connecting pieces (4), and the two first reinforcing rods (6) are symmetrically arranged at two sides of the first hanging and connecting piece (3).
8. The dry-hanging design installation structure of concrete board with balanced stress according to claim 1, characterized in that the bare concrete board (2) is a high-density board with water absorption less than 20%.
CN202110369613.2A 2021-04-06 2021-04-06 Balanced concrete board dry-hanging design mounting structure of atress Active CN113107155B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110369613.2A CN113107155B (en) 2021-04-06 2021-04-06 Balanced concrete board dry-hanging design mounting structure of atress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110369613.2A CN113107155B (en) 2021-04-06 2021-04-06 Balanced concrete board dry-hanging design mounting structure of atress

Publications (2)

Publication Number Publication Date
CN113107155A true CN113107155A (en) 2021-07-13
CN113107155B CN113107155B (en) 2022-04-19

Family

ID=76714364

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110369613.2A Active CN113107155B (en) 2021-04-06 2021-04-06 Balanced concrete board dry-hanging design mounting structure of atress

Country Status (1)

Country Link
CN (1) CN113107155B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB160226A (en) * 1919-12-04 1921-03-04 Walter Francis Ballinger Improvements relating to combined wood and reinforced concrete walls for buildings
CN203174841U (en) * 2013-04-24 2013-09-04 瑞高(浙江)建筑系统有限公司 Ceramic plate curtain wall mounting structure
CN104453152A (en) * 2014-12-01 2015-03-25 中建一局集团装饰工程有限公司 Detachable timber panel and hanging piece system and installation method of detachable timber panel and hanging piece system
CN105952095A (en) * 2016-05-10 2016-09-21 广东英特沃新型建材实业有限公司 Dry-hanging decoration sheet material mounting structure
CN107327111A (en) * 2017-08-31 2017-11-07 苏州金螳螂建筑装饰股份有限公司 A kind of dried hanging hang structure and finishing systems
CN206707083U (en) * 2017-05-23 2017-12-05 德才装饰股份有限公司 A kind of stone curtain wall with connector
CN108277915A (en) * 2017-01-05 2018-07-13 辽东学院 Super large super thick diamond shape stone material plate installs hanging structure
CN209568648U (en) * 2019-02-27 2019-11-01 深圳市建筑装饰(集团)有限公司 A kind of detachable decoration component of device of shifting block type installation

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB160226A (en) * 1919-12-04 1921-03-04 Walter Francis Ballinger Improvements relating to combined wood and reinforced concrete walls for buildings
CN203174841U (en) * 2013-04-24 2013-09-04 瑞高(浙江)建筑系统有限公司 Ceramic plate curtain wall mounting structure
CN104453152A (en) * 2014-12-01 2015-03-25 中建一局集团装饰工程有限公司 Detachable timber panel and hanging piece system and installation method of detachable timber panel and hanging piece system
CN105952095A (en) * 2016-05-10 2016-09-21 广东英特沃新型建材实业有限公司 Dry-hanging decoration sheet material mounting structure
CN108277915A (en) * 2017-01-05 2018-07-13 辽东学院 Super large super thick diamond shape stone material plate installs hanging structure
CN206707083U (en) * 2017-05-23 2017-12-05 德才装饰股份有限公司 A kind of stone curtain wall with connector
CN107327111A (en) * 2017-08-31 2017-11-07 苏州金螳螂建筑装饰股份有限公司 A kind of dried hanging hang structure and finishing systems
CN209568648U (en) * 2019-02-27 2019-11-01 深圳市建筑装饰(集团)有限公司 A kind of detachable decoration component of device of shifting block type installation

Also Published As

Publication number Publication date
CN113107155B (en) 2022-04-19

Similar Documents

Publication Publication Date Title
CN102493622B (en) Wallboard installing component
CN107327111A (en) A kind of dried hanging hang structure and finishing systems
CN113107155B (en) Balanced concrete board dry-hanging design mounting structure of atress
CN207376884U (en) Splicing partition wall body with sash
CN207122081U (en) A kind of dried hanging hang structure and finishing systems
US4982537A (en) Device for joining two building units
CN215254199U (en) Wall aluminum plate's mounting structure and aluminum plate wall
CN215483979U (en) Light gauge steel furred ceiling corner draws structure of preventing ftractureing to one side
CN203546908U (en) Assembly type building wall beam stable connection structure
CN112663828A (en) Hidden caulking design structure of steel skeleton concrete partition wall and mounting method thereof
CN216007638U (en) Light bracket grid for installing heat-insulation decorative plate and light curtain wall
CN216042355U (en) Assembled wall surface mounting structure with local reinforcement design
CN219710679U (en) Back-bolt type dry-hanging stone corner connection structure
CN220162441U (en) Assembled rack structure of wall panel
CN218861851U (en) Corner stone column system of multi-angle and cambered surface concatenation combination
CN217924306U (en) Stone curtain wall hanging installation structure
CN221255873U (en) Assembly type node structure of auxiliary dragon bone layer and wall body
CN216893293U (en) Outer wall face brick connecting hanging piece
CN103498512A (en) Stable connecting structure of prefabricated building wall beam
CN221095548U (en) Hanging framework and stone curtain wall mounting system
CN214246621U (en) Novel aluminum-wood connecting structure
CN217949478U (en) Curtain wall mounting structure
CN219411321U (en) Building construction external wall insulation board concatenation frame
CN215290783U (en) Building glass brick wall facade wall body structure beneficial to disassembly and assembly
CN210797971U (en) Easily change cavity composite construction exterior wall cladding

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant