CN113073557A - Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge - Google Patents

Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge Download PDF

Info

Publication number
CN113073557A
CN113073557A CN202110298376.5A CN202110298376A CN113073557A CN 113073557 A CN113073557 A CN 113073557A CN 202110298376 A CN202110298376 A CN 202110298376A CN 113073557 A CN113073557 A CN 113073557A
Authority
CN
China
Prior art keywords
steel
concrete
bridge deck
bridge
tensioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110298376.5A
Other languages
Chinese (zh)
Other versions
CN113073557B (en
Inventor
夏学军
李智勇
牛伟峰
韩胜利
马涛
王海彬
张锐鹏
杨庆
解晓涛
杨登辉
饶培红
董建兵
梁燕军
王帅帅
魏宁
路灵伟
王红然
孙强强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
1st Engineering Co Ltd of MBEC
Original Assignee
1st Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 1st Engineering Co Ltd of MBEC filed Critical 1st Engineering Co Ltd of MBEC
Priority to CN202110298376.5A priority Critical patent/CN113073557B/en
Publication of CN113073557A publication Critical patent/CN113073557A/en
Application granted granted Critical
Publication of CN113073557B publication Critical patent/CN113073557B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

The invention discloses a method for installing a concrete bridge deck of a steel-concrete combined continuous steel truss bridge, and relates to the technical field of bridge engineering construction. After the continuous steel truss girder is erected beyond one hole, the prefabricated bridge deck slab is synchronously installed; after continuous steel trusses are closed, pier top steel trusses are jacked at intervals in batches, longitudinal and transverse wet joint pouring of a bridge deck, transverse post-tensioning prestressed steel beam tensioning, shear nail groove pouring, pier top steel trusses falling beams, longitudinal post-tensioning prestressed steel beam tensioning and the like are performed. The concrete bridge deck is installed and the steel truss girder is erected synchronously, so that the construction period can be effectively saved; pouring a bridge deck wet joint after the steel trussed beams span and jack up, and then dropping the beams to enable the bridge deck in the hogging moment area of the steel trussed beams to be squeezed and pressed, so that partial tensile stress generated by the concrete bridge deck in the bridge operation state is counteracted; and pouring a shear nail groove after transversely tensioning the prestressed steel beam to ensure that the transverse tensioning force is completely acted on the highway bridge deck, so as to prevent the initial stress generated by the transverse stress of the steel beam.

Description

Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge
Technical Field
The invention relates to the technical field of bridge engineering construction, in particular to a method for installing a prestressed concrete bridge deck of a steel-concrete combined continuous steel truss bridge.
Background
The steel concrete combined bridge can give full play to the respective advantages of two materials of steel and concrete, can realize factory manufacturing to the greatest extent, and reduces field operation. The concrete bridge deck can be hoisted after being prefabricated, and the construction is flexible and convenient.
The advantages of the steel concrete combined bridge are as follows: compared with a steel bridge, the corrosion of the steel beam can be greatly reduced, and the service life of the bridge is prolonged.
In the traditional construction method of the structure, the pre-pressing effect of the concrete bridge deck is achieved and the cracking of the concrete bridge deck is avoided only by increasing the prestressed steel bundles, and the construction method easily causes great waste of the prestressed steel bundles.
Disclosure of Invention
The invention aims to overcome the defects in the prior art, and provides a method for installing a concrete bridge deck of a steel-concrete combined continuous steel truss bridge, which can economically and efficiently offset partial tensile stress generated by the concrete bridge deck in a bridge operation state.
The invention provides a method for installing a concrete bridge deck of a steel-concrete combined continuous steel truss girder bridge, which comprises the following steps of:
s1, prefabricating a concrete bridge deck;
s2, installing a concrete bridge deck: after the steel truss girder is erected over one hole, synchronously hoisting the concrete bridge deck;
s3, jacking a first wheel with even-numbered main pier top steel beams, pouring a wet joint of a bridge deck in a pier top negative bending moment area, tensioning the transverse backward-tensioned prestressed steel bundles after the design strength is reached, then, dropping the even-numbered main pier top steel beams, and constructing the longitudinal backward-tensioned prestressed steel bundles in the pier top negative bending moment area;
s4, jacking odd-numbered main pier top steel beams by the second wheel, pouring a wet joint of a bridge deck in a pier top hogging moment area, tensioning the transversely post-tensioned prestressed steel bundles after the design strength is reached, and then dropping the odd-numbered main pier top steel beams; constructing a longitudinal post-tensioned prestressed steel strand in a hogging moment area of the pier top;
s5, longitudinal and transverse wet joints of the bridge deck in the side span and span positive bending moment area are poured, the transverse post-tensioning prestressed steel bundles are tensioned after the designed strength is achieved, and then the longitudinal post-tensioning prestressed steel bundles are tensioned.
The method preferably includes the step of performing a pre-tensioning process and a post-tensioning process on the concrete deck slab in the step S1.
The technical scheme for improving the method is that the concrete bridge deck slab in the step S2 always lags behind the erection of the continuous steel trussed beams by not less than 1 pier position before the steel trussed beams are closed, and the installation of the rest bridge deck slabs is completed after the steel trussed beams are closed.
In a further improved technical solution, in the steps S3 and S4, the wet joints of the bridge deck in the hogging moment area at the top of the pier comprise transverse wet joints and longitudinal wet joints.
The technical scheme of further improvement is that the steps S3 and S4 include a pouring shear nail groove, and the operation of the pouring shear nail groove is completed after the transverse post-tensioning prestressed steel beam is tensioned and before the pier-top steel beam falls down.
In a further improved technical solution, in the steps S3 and S4, a plurality of pier tops can be simultaneously operated when the top beam and the beam falling operation are performed.
The still further improved technical scheme is that the step S5 includes a pouring shear nail groove, and the operation of the pouring shear nail groove is completed before the longitudinal post-tensioned prestressed steel bundles in the side span and mid-span positive bending moment area are tensioned after the transverse post-tensioned prestressed steel bundles are tensioned.
A more preferable technical solution is that, in step S1, the boards are temporarily stored in the board storage area in the pre-yard.
The present invention also provides a precast concrete deck slab, comprising: the concrete bridge deck slab comprises a concrete bridge deck slab body, wherein transverse backward-tensioned prestressed steel bundles and longitudinal backward-tensioned prestressed steel bundles are arranged in the concrete bridge deck slab body.
The invention has the beneficial effects that:
1. according to the invention, the bridge deck wet joint is poured after the steel trussed beams are separated to span and jack up, and then the beams are dropped to enable the bridge deck in the hogging moment area of the steel trussed beams to be squeezed and pressed, so that partial tensile stress generated by the concrete bridge deck in the bridge operation state is counteracted.
2. According to the installation method of the concrete bridge deck of the steel-concrete combined continuous steel truss girder bridge, the installation of the concrete bridge deck and the erection of the steel truss girder are carried out synchronously, and the construction period can be effectively shortened.
3. According to the invention, the shear nail groove is poured after the transverse tension prestressed steel beam, so that the transverse tension force is completely acted on the highway bridge deck, and the steel beam is prevented from generating initial stress due to transverse stress.
Drawings
Fig. 1 is a flow chart of an installation method in an embodiment of the present invention.
FIG. 2 is a schematic diagram illustrating a bridge deck erecting process according to an embodiment of the present invention.
Fig. 3 is a schematic structural view of the bridge deck after erection in the embodiment of the present invention.
Fig. 4 is a layout drawing of 1/2 single-span longitudinal post-tensioned prestressed steel strands in the embodiment of the invention.
Fig. 5 is a schematic view of the structure in the direction of a-a in the structure shown in fig. 4.
Fig. 6 is a layout view of a bridge deck slab transverse prestress steel beam in the embodiment of the invention.
FIG. 7 is a schematic diagram of the structure of FIG. 6 showing the direction A '-A'.
Fig. 8 is a cross-sectional view of the structure after the installation of the embodiment of the invention.
The concrete bridge comprises 1-concrete bridge deck, 2-shear nail grooves, 3-positive bending moment area longitudinal post-tensioned prestressed steel bundles, 4-middle girders, 5-negative bending moment area longitudinal post-tensioned prestressed steel bundles, 6-positive bending moment area, 7-negative bending moment area, 8-side girders, 9-longitudinal post-tensioned prestressed steel bundles, 10-bridge center line, 11-transverse wet joint, 12-longitudinal wet joint, 13-pier center line (excluding side piers), 14-single span center line or side pier center line, 15-tensioning grooves and 16-transverse post-tensioned prestressed steel bundles.
Detailed Description
To further illustrate the technical means and effects of the present invention adopted to achieve the predetermined objects, the following detailed description will be given of the specific implementation and operation principle of the installation method of the concrete bridge deck of the steel-concrete combined continuous steel truss bridge according to the present invention with reference to the accompanying drawings and preferred embodiments.
As shown in fig. 1, the installation method of the concrete bridge deck of the steel-concrete combined continuous steel truss bridge provided by the embodiment of the invention comprises the following steps:
firstly, prefabricating a concrete bridge deck 1; preferably, the prefabrication method of the concrete deck slab 1 includes a pre-tensioning method and a post-tensioning method. After the prefabrication of the concrete bridge deck slab 1 in the prefabrication field is finished, the concrete bridge deck slab is temporarily stored in a slab storage area in the prefabrication field.
Secondly, installing a concrete bridge deck 1: after the steel truss girder is erected beyond one hole, synchronously hoisting the prefabricated bridge deck slab 1; before the steel trussed beams are closed, the concrete bridge deck 1 is always installed at not less than 1 pier position behind the erection of the continuous steel trussed beams, as shown in figure 2, the installation of the rest bridge deck 1 is completed after the steel trussed beams are closed, and the structure of the bridge deck 1 after the erection is completed in the embodiment of the invention is shown in figure 3.
Thirdly, jacking even-numbered main pier top steel beams by the first wheel, and pouring longitudinal and transverse wet joints of the bridge deck in the pier top hogging moment area to achieve the design strength and post-tensioning transverse post-tensioning prestressed steel bundles; pouring a shear nail groove; and after the shear nail groove concrete reaches the design strength, the pier top steel beams of the even-numbered main piers fall to the beam, and the longitudinal post-tensioned prestressed steel bundles in the hogging moment area of the construction pier top.
Fourthly, jacking the odd-numbered main pier top steel beams by the second wheel, pouring a bridge deck wet joint in a pier top hogging moment area, post-tensioning the transverse post-tensioning prestressed steel bundles to reach the designed strength, and pouring a shear nail groove; after the shear nail groove concrete reaches the design strength, the odd-numbered main pier top steel beams fall off; and (5) constructing a longitudinal post-tensioned prestressed steel strand in the hogging moment area of the pier top.
Fifthly, longitudinal and transverse wet joints of the bridge deck in the side span and mid-span positive bending moment area are poured, and the post-tensioning transverse post-tensioning prestressed steel bundles with the designed strength are achieved; pouring a shear nail groove; and after the concrete reaches the designed strength, tensioning the longitudinal post-tensioned prestressed steel bundles.
The cross section of the structure after the installation of the embodiment of the invention is shown in fig. 8.
The prefabricated concrete deck slab 1 employed in the embodiment of the present invention includes: the longitudinal and transverse post-tensioned prestressed steel bundles.
Finally, it should be noted that the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, and although the present invention has been described in detail with reference to examples, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made on the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, which should be covered by the claims of the present invention.

Claims (8)

1. A method for installing a concrete bridge deck of a steel-concrete combined continuous steel truss bridge is characterized by comprising the following steps of:
s1, prefabricating a concrete bridge deck;
s2, installing a concrete bridge deck: after the steel truss girder is erected over one hole, synchronously hoisting the concrete bridge deck;
s3, jacking a first wheel with even-numbered main pier top steel beams, pouring a wet joint of a bridge deck in a pier top negative bending moment area, tensioning the transverse backward-tensioned prestressed steel bundles after the design strength is reached, then, dropping the even-numbered main pier top steel beams, and constructing the longitudinal backward-tensioned prestressed steel bundles in the pier top negative bending moment area;
s4, jacking odd-numbered main pier top steel beams by the second wheel, pouring a wet joint of a bridge deck in a pier top hogging moment area, tensioning the transversely post-tensioned prestressed steel bundles after the design strength is reached, and then dropping the odd-numbered main pier top steel beams; constructing a longitudinal post-tensioned prestressed steel strand in a hogging moment area of the pier top;
s5, longitudinal and transverse wet joints of the bridge deck in the side span and span positive bending moment area are poured, the transverse post-tensioning prestressed steel bundles are tensioned after the designed strength is achieved, and then the longitudinal post-tensioning prestressed steel bundles are tensioned.
2. The method for installing a concrete deck slab for a steel-concrete-combined continuous steel girder bridge according to claim 1, wherein the method for prefabricating the concrete deck slab in the step S1 includes a pre-tensioning method and a post-tensioning method.
3. The method for installing the concrete bridge deck slab of the steel-concrete combined continuous steel truss bridge according to claim 1 or 2, wherein the concrete bridge deck slab in the step S2 is installed before the steel trusses are closed, the installation always lags behind the erection of the continuous steel trusses by not less than 1 pier, and the installation of the rest bridge deck slabs is completed after the steel trusses are closed.
4. The method for installing a concrete bridge deck slab comprising a steel and concrete combined continuous steel truss bridge as claimed in claim 3, wherein the wet joints of the deck slab in the hogging moment region of the pier top include a transverse wet joint and a longitudinal wet joint in the steps S3 and S4.
5. The method for installing a concrete deck slab of a steel-concrete combined continuous steel truss bridge as claimed in claim 4, wherein the steps S3 and S4 include casting the shear pin groove, and the casting of the shear pin groove is completed after the transverse post-tensioned prestressed steel beam is tensioned and before the pier-top steel beam falls down.
6. The method for installing a concrete deck slab for a steel-concrete-combined continuous steel girder bridge according to claim 5, wherein a plurality of pier tops are simultaneously operated while the girder cutting and falling operations are performed in the steps S3 and S4.
7. The method as claimed in claim 6, wherein the step S5 includes casting the shear pin groove after the transverse post-tensioned prestressed steel beam is tensioned and before the longitudinal post-tensioned prestressed steel beam in the side span and mid-span positive bending moment region is tensioned.
8. The method for installing a concrete deck slab for a steel-concrete-combined continuous steel girder bridge according to claim 7, wherein the slab storage area is temporarily stored in a precast yard in step S1.
CN202110298376.5A 2021-03-19 2021-03-19 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge Active CN113073557B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110298376.5A CN113073557B (en) 2021-03-19 2021-03-19 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110298376.5A CN113073557B (en) 2021-03-19 2021-03-19 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge

Publications (2)

Publication Number Publication Date
CN113073557A true CN113073557A (en) 2021-07-06
CN113073557B CN113073557B (en) 2022-08-30

Family

ID=76612831

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110298376.5A Active CN113073557B (en) 2021-03-19 2021-03-19 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge

Country Status (1)

Country Link
CN (1) CN113073557B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114775424A (en) * 2022-04-20 2022-07-22 中交一公局集团有限公司 Prefabricated installation construction method for assembled steel-mixed beam panel

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0350139A2 (en) * 1983-11-07 1990-01-10 Harumoto Iron Works Co., Ltd. A method for forming a composite structural member
JP2002004219A (en) * 2000-06-16 2002-01-09 Komai Tekko Kk Continuous composition girder using chemical prestress and its manufacturing method
JP2002302909A (en) * 2001-04-10 2002-10-18 Yokogawa Koji Kk Floor slab installation method in continuous beam bridge
CN1587531A (en) * 2004-06-30 2005-03-02 清华大学 Method for anti-cracking in hogging moment area of steel-concrete combined beam
CN101424073A (en) * 2008-12-04 2009-05-06 中铁大桥局股份有限公司 Bridge deck and steel girder second combination method for whole arch precasted steel-concrete composite continuous box girder
CN105002816A (en) * 2015-07-29 2015-10-28 广西交通科学研究院 Prefabricated-assembling fish-bellied I-shaped prestress steel-concrete combination continuous beam bridge and construction method
CN106894346A (en) * 2017-04-28 2017-06-27 山西省交通科学研究院 A kind of the continuous beam bridge construction method
CN108914778A (en) * 2018-07-24 2018-11-30 福州大学 The method that the concrete slab of a kind of pair of combination beam top flange applies precompression
CN208201610U (en) * 2018-03-16 2018-12-07 广州市市政工程设计研究总院 A kind of steel-concrete part bondbeam
CN110230268A (en) * 2019-07-30 2019-09-13 郑州铁路职业技术学院 The steel truss composite beam bridge construction method of freely-supported after first continuous
CN110700113A (en) * 2019-11-05 2020-01-17 中建交通建设集团有限公司 Prestress applying device of non-prestressed beam bridge and construction method thereof
CN111206487A (en) * 2020-02-28 2020-05-29 甘肃省交通规划勘察设计院股份有限公司 Variable-height corrugated web steel box-concrete continuous beam bridge and construction method
CN111455806A (en) * 2020-04-17 2020-07-28 浙江省交通规划设计研究院有限公司 Prestressed concrete beam hogging moment area bridge structure and construction method thereof

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0350139A2 (en) * 1983-11-07 1990-01-10 Harumoto Iron Works Co., Ltd. A method for forming a composite structural member
JP2002004219A (en) * 2000-06-16 2002-01-09 Komai Tekko Kk Continuous composition girder using chemical prestress and its manufacturing method
JP2002302909A (en) * 2001-04-10 2002-10-18 Yokogawa Koji Kk Floor slab installation method in continuous beam bridge
CN1587531A (en) * 2004-06-30 2005-03-02 清华大学 Method for anti-cracking in hogging moment area of steel-concrete combined beam
CN101424073A (en) * 2008-12-04 2009-05-06 中铁大桥局股份有限公司 Bridge deck and steel girder second combination method for whole arch precasted steel-concrete composite continuous box girder
CN105002816A (en) * 2015-07-29 2015-10-28 广西交通科学研究院 Prefabricated-assembling fish-bellied I-shaped prestress steel-concrete combination continuous beam bridge and construction method
CN106894346A (en) * 2017-04-28 2017-06-27 山西省交通科学研究院 A kind of the continuous beam bridge construction method
CN208201610U (en) * 2018-03-16 2018-12-07 广州市市政工程设计研究总院 A kind of steel-concrete part bondbeam
CN108914778A (en) * 2018-07-24 2018-11-30 福州大学 The method that the concrete slab of a kind of pair of combination beam top flange applies precompression
CN110230268A (en) * 2019-07-30 2019-09-13 郑州铁路职业技术学院 The steel truss composite beam bridge construction method of freely-supported after first continuous
CN110700113A (en) * 2019-11-05 2020-01-17 中建交通建设集团有限公司 Prestress applying device of non-prestressed beam bridge and construction method thereof
CN111206487A (en) * 2020-02-28 2020-05-29 甘肃省交通规划勘察设计院股份有限公司 Variable-height corrugated web steel box-concrete continuous beam bridge and construction method
CN111455806A (en) * 2020-04-17 2020-07-28 浙江省交通规划设计研究院有限公司 Prestressed concrete beam hogging moment area bridge structure and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘漫杰: "基于先简支后连续桥梁施工要点研究", 《科技与企业》 *
焦亚萌等: "大跨度连续钢桁结合梁设计研究", 《铁道勘察》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114775424A (en) * 2022-04-20 2022-07-22 中交一公局集团有限公司 Prefabricated installation construction method for assembled steel-mixed beam panel

Also Published As

Publication number Publication date
CN113073557B (en) 2022-08-30

Similar Documents

Publication Publication Date Title
CN109610314B (en) Prefabricated bridge deck wet joint structure and assembling method
CN113481826B (en) Prefabricated assembled corrugated steel web plate combined box girder
CN108914778B (en) Method for applying pre-pressing force to concrete slab of upper flange of composite beam
CN109958049B (en) Modular steel-concrete combined small box girder simply-supported continuous bridge and construction method thereof
CN110846996A (en) Construction method of continuous composite beam bridge and continuous composite beam bridge
CN113073557B (en) Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge
CN111469267B (en) Wood-UHPC combined box girder and preparation method thereof
CN112982139A (en) Wide-width large-span hybrid beam and short-tower cable-stayed bridge system and construction method thereof
CN215714553U (en) Box girder steel bundle beam-end tensioning post-cast strip structure
CN215758473U (en) Steel-concrete combined simply-supported T-beam bridge
CN211665537U (en) Prestressed inverted-T-shaped combined cross-section beam bridge
CN212404773U (en) UHPC-NC mixed box girder and large-span rigid frame bridge
CN211665536U (en) Prestressed U-shaped combined cross-section beam bridge
CN214737317U (en) Steel-concrete combined rigid frame bridge connected through slots
CN114657887A (en) Construction method of precast slab anti-cracking structure in hogging moment area of combined beam bridge
CN113774811A (en) Method for building upper structure of composite beam cable-stayed bridge
CN112832116A (en) Plate-truss combined main beam suitable for large-span cable-stayed bridge in mountainous area
CN112030717A (en) Steel-concrete composite pin combination beam
CN214613536U (en) Plate-truss combined main beam suitable for large-span cable-stayed bridge in mountainous area
CN209836768U (en) Separating steel box combined bridge
CN114263121B (en) Prestressed steel beam tensioning structure in concrete box girder structure system transformation and construction method
CN210288076U (en) Prefabricated assembled steel truss combined beam bridge
CN219825595U (en) Large-span prestress prefabricated integral casting beam structure
CN113529569B (en) Double-deck slab structure and construction method thereof
CN217869975U (en) Pretensioned prestressing UHPC-superposed bridge deck composite beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant