CN106894346A - A kind of the continuous beam bridge construction method - Google Patents

A kind of the continuous beam bridge construction method Download PDF

Info

Publication number
CN106894346A
CN106894346A CN201710290347.8A CN201710290347A CN106894346A CN 106894346 A CN106894346 A CN 106894346A CN 201710290347 A CN201710290347 A CN 201710290347A CN 106894346 A CN106894346 A CN 106894346A
Authority
CN
China
Prior art keywords
jack
continuous
precast beam
temporary support
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710290347.8A
Other languages
Chinese (zh)
Other versions
CN106894346B (en
Inventor
王磊
韩之江
吴佳佳
刘志华
赵雷
汪永强
郭文龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Province Transport Science Research Institute
Original Assignee
Shanxi Province Transport Science Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Province Transport Science Research Institute filed Critical Shanxi Province Transport Science Research Institute
Priority to CN201710290347.8A priority Critical patent/CN106894346B/en
Publication of CN106894346A publication Critical patent/CN106894346A/en
Application granted granted Critical
Publication of CN106894346B publication Critical patent/CN106894346B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a kind of the continuous beam bridge construction method, comprise the following steps:A precast beams are hole-specifically installed and are placed on temporary support;B sets Temporary Piers in prefabricated beam end, installs jack on Temporary Piers, and with the upper and lower levelling of steel plate;C uniformly exerts a force to each jack simultaneously, beam-ends top lifting height is met calculating and requires;D is poured after continuous joint concrete reaches design requirement intensity, tensioning hogging moment area prestressed strand;E removes temporary support, completes system transform;Removal, respectively across jack load, makes girder fall after rise to jack-up front position to F successively, and the final internal force status of structural system reach and once fall frame bridge completion state.Whole process of the present invention is simple to operate, and construction is quick;In addition, in work progress, system stress is clear and definite, structure is safe and reliable, can greatly improve final Internal force of bridge under completion stage state.

Description

A kind of the continuous beam bridge construction method
Technical field
The invention belongs to technical field of bridge construction, more particularly, to a kind of the continuous beam bridge construction method.
Background technology
At present, the construction method of Mid and minor spans continuous bridge mainly has two classes, after full framing built a bridge at once and first freely-supported Continuous system is changed.Full framing continuous bridge good integrity, into pontic architecture reasonable stress, span centre under a phase dead load Bending moment level is relatively low, but work progress is complicated, and the construction period is long, and cost is higher;Simply supported-to-continuous system bridge is by prefabricated Assembly, easy construction is quick, but under a phase dead load, span centre maximal bending moment is almost equal with the simply supported beam of same across footpath, passes through System transform also fails to improve into the internal force status of structural system after bridge, simply in structure " bridge floor is continuous ", for weight Traffic loading is carried, " bridge floor is continuous " in structure is also difficult to ensure that structural system has enough safety stocks.
The content of the invention
The technical problems to be solved by the invention are to solve Simply supported non-uniform system beam bridge to be stored up safely in operation phase inner structure Standby low problem.
In order to solve the above-mentioned technical problem, the technical solution adopted in the present invention provides a kind of the continuous beam bridge construction side Method, comprises the following steps:
A, precast beam set temporary support on pier cap beam and install permanent bearing, in advance after the completion of Liang Chang constructions Beam processed is hole-specifically installed and is placed on temporary support;
B, prefabricated beam end set Temporary Piers, jack is installed on Temporary Piers, each jack is upper and lower to use steel plate levelling;
C, while uniformly exerted a force to each jack, displacement meter monitored over time beam-ends jacking process, jacking to computed altitude;
After D, jack jacking to computed altitude, the continuous joint concrete of precast beam is poured, rear pouring concrete reaches design After desired strength, tensioning hogging moment area prestressed strand;
E, the continuous joint temporary support of precast beam is removed, complete Program for structural Transformation;
F, successively removal are each across jack load, girder is fallen after rise to jack-up front position, final structure system internal force status Reach and once fall frame bridge completion state.
In such scheme, in the step C, the computed altitude by etc. formula (I) be calculated:
Wherein, q is that precast beam is conducted oneself with dignity per linear meter(lin.m.);L is calculating across footpath;E is concrete elastic modelling quantity;I is prefabricated beam section bending resistance The moment of inertia.
The present invention, jack-up construction is carried out using jack in prefabricated beam end, and finally falls after rise girder, whole process behaviour Make simple, construction is quick;In addition, in work progress, system stress is clear and definite, structure is safe and reliable, can greatly improve final Cheng Qiao Internal force status.
Brief description of the drawings
Fig. 1 is precast beam scheme of installation.
Fig. 2 is the prefabricated beam end jacking apparatus schematic diagram of jack.
Fig. 3 is jack jacking precast beam construction schematic diagram.
Fig. 4 is precast beam Simply supported non-uniform construction schematic diagram.
Fig. 5 is Program for structural Transformation schematic diagram.
Fig. 6 is that main back rises falling schematic diagram.
Fig. 7 is structural system end-state schematic diagram.
Fig. 8 is precast beam simply-supported state internal force diagram.
Fig. 9 is jack jacking precast beam mechanical model schematic diagram.
Figure 10 is that precast beam falls mechanical model schematic diagram after rise.
Figure 11 is that precast beam falls internal force diagram after rise.
Figure 12 is the final Internal force of bridge under completion stage figure of structural system.
Description of reference numerals:
Pier cap beam -1, precast beam -2, temporary support -3, permanent bearing -4, sagging moment area prestressing tendon -5, Temporary Piers - 6th, jack -7, steel plate -8, displacement meter -9, continuous joint -10, hogging moment area prestressing tendon -11.
Specific embodiment
Below by specific embodiment, the present invention will be described, but the invention is not limited in this.
Embodiment 1
As shown in Fig. 1~Figure 12, the present invention provides a kind of the continuous beam bridge construction method, comprises the following steps:
A precast beams 2 set interim branch after the completion of beam tensioning sagging moment area prestressing tendon 5 is constructed on pier cap beam 1 Seat 3 simultaneously installs permanent bearing 4, and precast beam 2 is hole-specifically installed and is placed on temporary support 3;
The freely-supported of precast beam 2 is installed and is placed on temporary support 3, and internal force status are shown in Fig. 8, respectively across span centre maximum sagging moment:
Beam-ends corner:
In formula:Q is that precast beam is conducted oneself with dignity per linear meter(lin.m.);L is calculating across footpath;E is concrete elastic modelling quantity;I is prefabricated beam section bending resistance The moment of inertia.
B sets Temporary Piers 6 in the end of precast beam 2, and jack 7, the upper and lower use steel plate 8 of each jack 7 are installed on Temporary Piers 6 Levelling;
C uniformly exerts a force to each jack 7 simultaneously, and the monitored over time beam-ends jacking process of displacement meter 9 makes top lifting height meet meter Calculate and require.
Jack 7 in the work progress of jacking precast beam 2, the corner that prefabricated beam-ends is produced:
By ∑ θc'=0, ∑ θc=0 can obtain:
Jack 7 calculates top lifting height Δ in the work progress of jacking precast beam 2, sees Fig. 9:
After the jacking of D jack 7 to computed altitude, the continuous joint concrete 10 of precast beam is poured, rear pouring concrete 10 reaches After design requirement intensity, hogging moment area prestressing tendon 11 carries out tensioning;
E removes temporary support 3 at the continuous joint 10 of precast beam 2, completes Program for structural Transformation;
Removal is each across the load of jack 7 successively for F, girder 2 is fallen after rise to jack-up front position, final structure system internal force status Reach and once fall frame bridge completion state.
The load of removal B ends jack 7, make the beam-ends of girder 2 fall after rise height Δ, see Figure 10, cause in structural system in Power.
In formula:
After B ends are fallen after rise, removal A ends jack load, the accumulative internal force caused in structural system is shown in Figure 11:
Internal force diagram shown in Figure 11 is overlapped with the internal force diagram shown in Fig. 8, obtains final structure system internal force status, that is, reach To the frame bridge completion state that once falls, shown in Figure 12.
It is understood that above is example in order to illustrate principle of the invention and exploitativeness, the present invention not office It is limited to this.For those skilled in the art, without departing from the spirit and substance in the present invention, can be with All variations and modifications are made, these variations and modifications are also considered as protection scope of the present invention.

Claims (2)

1. a kind of the continuous beam bridge construction method, it is characterised in that comprise the following steps:
A, precast beam set temporary support on pier cap beam and install permanent bearing, precast beam after the completion of Liang Chang constructions Hole-specifically install and be placed on temporary support;
B, prefabricated beam end set Temporary Piers, jack is installed on Temporary Piers, each jack is upper and lower to use steel plate levelling;
C, while uniformly exerted a force to each jack, displacement meter monitored over time beam-ends jacking process, jacking to computed altitude;
After D, jack jacking to computed altitude, the continuous joint concrete of precast beam is poured, rear pouring concrete reaches design requirement After intensity, tensioning hogging moment area prestressed strand;
E, the continuous joint temporary support of precast beam is removed, complete Program for structural Transformation;
F, successively removal are each to make girder fall after rise to jack-up front position across jack load, and final structure system internal force status reach Once fall frame bridge completion state.
2. the continuous beam bridge construction method according to claim 1, it is characterised in that in the step C, the computed altitude By etc. formula (I) be calculated:
Δ = ql 4 24 E I - - - ( I )
Wherein, q is that precast beam is conducted oneself with dignity per linear meter(lin.m.);L is calculating across footpath;E is concrete elastic modelling quantity;I is prefabricated beam section bending resistance inertia Square.
CN201710290347.8A 2017-04-28 2017-04-28 A kind of the continuous beam bridge construction method Active CN106894346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710290347.8A CN106894346B (en) 2017-04-28 2017-04-28 A kind of the continuous beam bridge construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710290347.8A CN106894346B (en) 2017-04-28 2017-04-28 A kind of the continuous beam bridge construction method

Publications (2)

Publication Number Publication Date
CN106894346A true CN106894346A (en) 2017-06-27
CN106894346B CN106894346B (en) 2019-10-11

Family

ID=59196603

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710290347.8A Active CN106894346B (en) 2017-04-28 2017-04-28 A kind of the continuous beam bridge construction method

Country Status (1)

Country Link
CN (1) CN106894346B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107245954A (en) * 2017-07-28 2017-10-13 山西省交通科学研究院 A kind of Mid and minor spans steel box girder bridge construction method
CN108060636A (en) * 2017-12-11 2018-05-22 重庆交通大学 The construction method of overall assembled composite beam bridge
CN110512795A (en) * 2018-05-21 2019-11-29 深圳市建筑设计研究总院有限公司 A kind of fixing means and fixed device of flexural member
CN110512726A (en) * 2018-05-21 2019-11-29 深圳市建筑设计研究总院有限公司 A kind of fixing means and fixed device of concrete flexural member
CN113073557A (en) * 2021-03-19 2021-07-06 中铁大桥局集团第一工程有限公司 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003313824A (en) * 2002-04-25 2003-11-06 Kajima Corp Construction method of overhead crossing, overhead crossing and moving frame
JP2003313813A (en) * 2002-04-25 2003-11-06 Kajima Corp Construction method of overhead crossing, overhead crossing and bridge pier structure
CN103774554A (en) * 2013-10-30 2014-05-07 北京工业大学 Main tower traction erecting method of self-anchored suspension bridge box girder
CN103981808A (en) * 2014-05-15 2014-08-13 宝鸡中铁宝桥天元实业发展有限公司 Large steel tank beam depth bed position assembly walking-type pushing construction method and walking-type pushing equipment
CN104032681A (en) * 2014-06-30 2014-09-10 北京交通大学 Linear adjustment method of track girder bridges of straddle-type monorail transportation simple-support-first rigid-framework-second system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003313824A (en) * 2002-04-25 2003-11-06 Kajima Corp Construction method of overhead crossing, overhead crossing and moving frame
JP2003313813A (en) * 2002-04-25 2003-11-06 Kajima Corp Construction method of overhead crossing, overhead crossing and bridge pier structure
CN103774554A (en) * 2013-10-30 2014-05-07 北京工业大学 Main tower traction erecting method of self-anchored suspension bridge box girder
CN103981808A (en) * 2014-05-15 2014-08-13 宝鸡中铁宝桥天元实业发展有限公司 Large steel tank beam depth bed position assembly walking-type pushing construction method and walking-type pushing equipment
CN104032681A (en) * 2014-06-30 2014-09-10 北京交通大学 Linear adjustment method of track girder bridges of straddle-type monorail transportation simple-support-first rigid-framework-second system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李睿林: ""西宁西过境高速公路预应力连续梁体系转换施工技术"", 《青海交通科技》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107245954A (en) * 2017-07-28 2017-10-13 山西省交通科学研究院 A kind of Mid and minor spans steel box girder bridge construction method
CN107245954B (en) * 2017-07-28 2019-03-01 山西省交通科学研究院 A kind of Mid and minor spans steel box girder bridge construction method
CN108060636A (en) * 2017-12-11 2018-05-22 重庆交通大学 The construction method of overall assembled composite beam bridge
CN108060636B (en) * 2017-12-11 2019-09-17 重庆交通大学 The construction method of overall assembled composite beam bridge
CN110512795A (en) * 2018-05-21 2019-11-29 深圳市建筑设计研究总院有限公司 A kind of fixing means and fixed device of flexural member
CN110512726A (en) * 2018-05-21 2019-11-29 深圳市建筑设计研究总院有限公司 A kind of fixing means and fixed device of concrete flexural member
CN110512726B (en) * 2018-05-21 2021-11-09 深圳市建筑设计研究总院有限公司 Method and device for fixing concrete flexural member
CN110512795B (en) * 2018-05-21 2021-12-21 深圳市建筑设计研究总院有限公司 Method and device for fixing flexural member
CN113073557A (en) * 2021-03-19 2021-07-06 中铁大桥局集团第一工程有限公司 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge
CN113073557B (en) * 2021-03-19 2022-08-30 中铁大桥局集团第一工程有限公司 Method for mounting concrete bridge deck of steel-concrete combined continuous steel truss bridge

Also Published As

Publication number Publication date
CN106894346B (en) 2019-10-11

Similar Documents

Publication Publication Date Title
CN106894346A (en) A kind of the continuous beam bridge construction method
CN101824800B (en) Method for construction of bridge cast-in-situ pre-stressed concrete continuous beam
CN207143733U (en) A kind of simple-supported thencontinuous bridge system converting system
CN110965474A (en) Construction method of cable tower cross beam
CN104831639A (en) Consolidation and release construction method for 0# blocks of ultra-wide non-uniform continuous beam
CN107988924B (en) Steel-concrete composite girder bridge system conversion system and conversion method based on old bridge reconstruction
CN113550235A (en) Cast-in-place bent cap support and construction method thereof
CN106320192B (en) A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge
CN210684430U (en) Main bridge jacking system of large-span tied arch bridge
CN202809494U (en) Bracket for pouring 0# block to rigid continuous girder bridge
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN111749133A (en) Beam-arch combined rigid frame bridge and construction method of bridge pier thereof
CN203729211U (en) Suspension type curved bridge panel cast-in-situ formwork
CN211772868U (en) Pier temporary consolidation device in large-span continuous beam
CN209873553U (en) Prefabricated assembled cylindricality pier
CN210194449U (en) Tower beam temporary consolidation structure for construction of main beam of semi-floating body system cable-stayed bridge
CN112482193A (en) Method for applying compressive stress to concrete slab in hogging moment area of combination beam, main beam and cable-stayed bridge
CN211596369U (en) Bracket for high pier capping beam of bridge
CN105839541B (en) Construction method and structure of No. 0 section non-welding bracket of rigid frame bridge
CN213233165U (en) Bridge auxiliary pier support installation device
CN210458950U (en) Formwork support for inclined vertical column construction
KR200230089Y1 (en) Shifting up and down system of continuous preflex composite girder on temporary support
CN215714684U (en) Cast-in-situ bent cap support
CN110424244B (en) Large-span steel pipe concrete tied arch bridge jacking construction method
CN210975551U (en) Formwork support for pier stud tie beam construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wang Lei

Inventor after: Guo Wenlong

Inventor after: Wu Jiajia

Inventor after: Liu Zhihua

Inventor after: Han Zhijiang

Inventor after: Wang Yongqiang

Inventor after: Zhao Lei

Inventor before: Wang Lei

Inventor before: Han Zhijiang

Inventor before: Wu Jiajia

Inventor before: Liu Zhihua

Inventor before: Zhao Lei

Inventor before: Wang Yongqiang

Inventor before: Guo Wenlong

GR01 Patent grant
GR01 Patent grant