CN112983503A - Waterproof board structure - Google Patents
Waterproof board structure Download PDFInfo
- Publication number
- CN112983503A CN112983503A CN202110421152.9A CN202110421152A CN112983503A CN 112983503 A CN112983503 A CN 112983503A CN 202110421152 A CN202110421152 A CN 202110421152A CN 112983503 A CN112983503 A CN 112983503A
- Authority
- CN
- China
- Prior art keywords
- waterproof
- waterproof board
- tunnel
- length direction
- foundation pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 11
- 238000011144 upstream manufacturing Methods 0.000 abstract description 3
- 230000002265 prevention Effects 0.000 description 3
- 239000004568 cement Substances 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
- E02D31/025—Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F16/00—Drainage
- E21F16/02—Drainage of tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses a waterproof board structure, which comprises a plurality of waterproof boards paved on the primary supporting surface of a tunnel or the surface of a foundation pit, wherein the plurality of waterproof boards are arranged in parallel, one end of any one waterproof board in the length direction is lapped and fixed on the upper end surface of one end of the adjacent waterproof board in the length direction at one side to form a stepped structure, and the other end of the waterproof board in the length direction is lapped and fixed on the lower end surface of one end of the adjacent waterproof board in the length direction at the other side to form a stepped structure; the long edge of the waterproof board is laid in the tunnel direction of the tunnel primary support surface or the horizontal direction of the surface of the foundation pit, and the short edge of the waterproof board is laid in the vertical direction of the tunnel primary support surface or the vertical direction of the surface of the foundation pit. Compared with the prior art, the waterproof plate structure can enable the upstream surface to be in a step shape, solves the water leakage situation at the splicing position of the waterproof plate, and can well guide water above the tunnel out.
Description
Technical Field
The invention relates to the technical field of water prevention and drainage, in particular to a waterproof board structure.
Background
Along with the economic development in recent years, the urban construction of China also develops abnormally and rapidly. From high-rise and super high-rise buildings to urban rail transit construction, related underground engineering is increasing, and a large number of deep foundation pit engineering and tunnel engineering in water-rich areas are developed. The water prevention and drainage of foundation pits, tunnels and the like become the important difficulty of water prevention and drainage nowadays, and the laying of waterproof boards is one of the important steps.
The waterproof and tunnel-waterproof part of the foundation pit is paved with a waterproof board, the surface of the waterproof board is polished and filled, and the long edge of the waterproof board is along the vertical direction of the surface of the tunnel primary support or the vertical direction of the foundation pit. The splicing parts of the waterproof boards are connected in a welding mode.
However, a large number of engineering examples show that the laying of the waterproof boards does not lead water above the tunnel out well, and the water cannot be led out well at the splicing position of the waterproof boards, so that materials are wasted, and excessive time is spent.
Disclosure of Invention
The invention aims to solve the problems in the prior art and provides a waterproof board structure.
In order to achieve the purpose, the invention is implemented according to the following technical scheme:
a waterproof board structure comprises a plurality of waterproof boards paved on the primary supporting surface of a tunnel or the surface of a foundation pit, wherein the plurality of waterproof boards are arranged in parallel, one end of any one waterproof board in the length direction is lapped and fixed on the upper end face of one end of the waterproof board adjacent to one side in the length direction to form a step-shaped structure, and the other end of the waterproof board in the length direction is lapped and fixed on the lower end face of one end of the waterproof board adjacent to the other side in the length direction to form a step-shaped structure; the long edge of the waterproof board is laid in the tunnel direction of the tunnel primary support surface or the horizontal direction of the surface of the foundation pit, and the short edge of the waterproof board is laid in the vertical direction of the tunnel primary support surface or the vertical direction of the surface of the foundation pit.
Preferably, the length of the faying surface between adjacent flashing is 80 mm.
Preferably, the adjacent waterproof boards are fixedly connected through the shooting nails.
Compared with the prior art, the waterproof plate structure can enable the upstream surface to be in a step shape, solves the water leakage situation at the splicing position of the waterproof plate, and can well guide water above the tunnel out.
Drawings
FIG. 1 is a perspective view of a flashing in a horizontal direction;
fig. 2 is a perspective view of the waterproof board in a vertical direction.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. The specific embodiments described herein are merely illustrative of the invention and do not limit the invention.
The embodiment provides a waterproof board structure, and the waterproof board structure is specifically described in detail by taking the waterproof board structure laid on the surface of a foundation pit as an example. As shown in fig. 1 and 2, the waterproof board structure comprises a plurality of waterproof boards adhered on cement waterproof mortar 1 on the surface of a foundation pit, the waterproof boards are arranged in parallel, wherein one end of any one waterproof board in the length direction is lapped and fixed on the upper end surface of one end of the adjacent waterproof board in the length direction at one side to form a step-shaped structure, the other end of the waterproof board in the length direction is lapped and fixed on the lower end surface of one end of the adjacent waterproof board in the length direction at the other side to form a step-shaped structure, the length of the lapping surface is generally 80mm, in order to explain the embodiment more easily, fig. 1 only schematically shows the connection relationship between the first layer of waterproof board 2 and the second layer of waterproof board 3, the right end of the first layer of waterproof board 2 in the length direction is fixed to the lower end face of one end of the second layer of waterproof board 3 in the length direction in a lap joint manner to form a stepped structure, and the lower end faces of the first layer of waterproof board 2 and the second layer of waterproof board 3 are both adhered to the cement waterproof mortar 1 on the surface of the foundation pit; the overlapping surfaces of the first layer of waterproof board 2 and the second layer of waterproof board 3 are fixedly connected through a shooting nail 4; the long sides of the first layer of waterproof board 2 and the second layer of waterproof board 3 are laid along the horizontal direction of the surface of the foundation pit, and the short sides of the first layer of waterproof board 2 and the second layer of waterproof board 3 are laid along the vertical direction of the surface of the foundation pit.
The waterproof principle of the waterproof plate structure of the invention is as follows: the waterproof board structure can make the upstream face be cascaded, solves the condition of leaking of waterproof board concatenation department, and the water drainage with the tunnel top that moreover can be fine flows out.
The technical solution of the present invention is not limited to the limitations of the above specific embodiments, and all technical modifications made according to the technical solution of the present invention fall within the protection scope of the present invention.
Claims (3)
1. The utility model provides a waterproof board structure, is including laying a plurality of waterproof boards on tunnel preliminary bracing surface or foundation ditch surface, its characterized in that: the waterproof boards are arranged in parallel, one end of any one waterproof board in the length direction is lapped and fixed on the upper end face of one end of the waterproof board adjacent to one side in the length direction to form a stepped structure, and the other end of the waterproof board in the length direction is lapped and fixed on the lower end face of one end of the waterproof board adjacent to the other side in the length direction to form a stepped structure; the long edge of the waterproof board is laid in the tunnel direction of the tunnel primary support surface or the horizontal direction of the surface of the foundation pit, and the short edge of the waterproof board is laid in the vertical direction of the tunnel primary support surface or the vertical direction of the surface of the foundation pit.
2. The flashing structure of claim 1, wherein: the length of the overlapping surface between adjacent waterproof boards is 80 mm.
3. The flashing structure of claim 1, wherein: the adjacent waterproof boards are fixedly connected through the shooting nails.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110421152.9A CN112983503A (en) | 2021-04-19 | 2021-04-19 | Waterproof board structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110421152.9A CN112983503A (en) | 2021-04-19 | 2021-04-19 | Waterproof board structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112983503A true CN112983503A (en) | 2021-06-18 |
Family
ID=76341177
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110421152.9A Pending CN112983503A (en) | 2021-04-19 | 2021-04-19 | Waterproof board structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112983503A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203742624U (en) * | 2014-03-26 | 2014-07-30 | 福州市规划设计研究院 | Splicing laying structure of tunnel water proof board |
CN104018857A (en) * | 2014-03-26 | 2014-09-03 | 福州市规划设计研究院 | Splicing paving method of waterproof plates in tunnel and splicing paving structure of waterproof plates in tunnel |
CN206957745U (en) * | 2017-05-23 | 2018-02-02 | 中铁十二局集团有限公司 | A kind of mounted waterproof layer of tunnel magic |
CN212744026U (en) * | 2020-08-25 | 2021-03-19 | 北京立高立德工程技术有限公司 | Tunnel waterproof board |
CN212837862U (en) * | 2020-07-29 | 2021-03-30 | 建国伟业防水科技望都有限公司 | Novel tunnel waterproof construction |
-
2021
- 2021-04-19 CN CN202110421152.9A patent/CN112983503A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203742624U (en) * | 2014-03-26 | 2014-07-30 | 福州市规划设计研究院 | Splicing laying structure of tunnel water proof board |
CN104018857A (en) * | 2014-03-26 | 2014-09-03 | 福州市规划设计研究院 | Splicing paving method of waterproof plates in tunnel and splicing paving structure of waterproof plates in tunnel |
CN206957745U (en) * | 2017-05-23 | 2018-02-02 | 中铁十二局集团有限公司 | A kind of mounted waterproof layer of tunnel magic |
CN212837862U (en) * | 2020-07-29 | 2021-03-30 | 建国伟业防水科技望都有限公司 | Novel tunnel waterproof construction |
CN212744026U (en) * | 2020-08-25 | 2021-03-19 | 北京立高立德工程技术有限公司 | Tunnel waterproof board |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207597428U (en) | Prefabricated piping lane is connected waterproof construction with cast-in-place piping lane | |
CN103410175A (en) | Water seepage control construction method for karst water-rich geological underground structure waterproof construction | |
CN109763424B (en) | Fully-precast concrete anti-collision guardrail and construction method | |
CN110644538A (en) | Basement side wall extra front and back pouring belt periphery protection structure | |
CN208604416U (en) | A kind of continuous supporting track structure of assemblyization | |
CN214499095U (en) | Tunnel preliminary bracing surface or foundation ditch surface waterproof board structure | |
CN207277667U (en) | Insulation blocks | |
CN112983503A (en) | Waterproof board structure | |
CN210975898U (en) | Prefabricated template system of basement outer wall post-cast strip | |
CN106499187A (en) | A kind of arm support and concrete spraying machine | |
CN106939586B (en) | A kind of panel construction of concrete face rockfill dam | |
CN109881661A (en) | Assembled underground continuous wall transverse connection structure | |
CN205917862U (en) | Connected node on basis | |
CN210975900U (en) | Basement side wall extra front and back pouring belt periphery protection structure | |
CN213572061U (en) | Waterproof overlap joint structure of new and old underground works bottom plate | |
CN212223970U (en) | Prefabricated apron post-cast strip stagnant water temporary enclosed construction | |
CN111350524B (en) | Hydraulic shield tunnel composite lining structure and construction method thereof | |
CN211714041U (en) | Prefabricated piping lane joint sealing waterproof construction of assembling | |
CN209798764U (en) | Foundation pit structure | |
CN211850791U (en) | Leak protection thick liquid structure of plastics turnover membrane shell piece | |
CN212078858U (en) | Assembled reinforced concrete pond | |
CN210797663U (en) | Post-cast strip structure for bottom plate of underground chamber | |
CN207048079U (en) | Built-in steel mixed connection fitting water proof structure | |
CN218148526U (en) | Waterproof structure for underground engineering structure deformation joint water leakage | |
CN210917476U (en) | Waterproof structure of concrete post-cast strip |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |