CN210238573U - A waterproof construction that is used for open cut station main part and attached junction - Google Patents
A waterproof construction that is used for open cut station main part and attached junction Download PDFInfo
- Publication number
- CN210238573U CN210238573U CN201920906620.XU CN201920906620U CN210238573U CN 210238573 U CN210238573 U CN 210238573U CN 201920906620 U CN201920906620 U CN 201920906620U CN 210238573 U CN210238573 U CN 210238573U
- Authority
- CN
- China
- Prior art keywords
- waterproof
- auxiliary
- side wall
- main body
- station
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model relates to a waterproof construction for open cut station main part and additional connection department, the additional structure inserts from the major structure side wall of station main part, and the major structure side wall all is provided with the horizontally steel sheet waterstop that crosses both sides with the three types of seam crossing of major structure roof, major structure medium plate and additional structure bottom plate and major structure side wall and additional structure side wall. The utility model discloses be the tongue-and-groove with the structural side wall design, reserve out the steel sheet waterstop and set up the space, add the steel sheet waterstop on the basis of optimizing the structure, form the waterproof measure of the waterproof + steel sheet waterstop of outsourcing + slip casting pipe + waterstop, can play waterproof and leaking stoppage's dual efficiency, effectively prevent the groundwater seepage to reduce later stage leaking stoppage expense and operation risk.
Description
Technical Field
The utility model belongs to the technical field of subway engineering's structure, concretely relates to a waterproof construction that is used for open cut station main part and attached junction.
Background
Subway engineering is mostly located underground, receives groundwater influence very big, and waterproof requirement is high, and the construction degree of difficulty is big, and the influence factor is many, and waterproof construction is difficult to control, and subway seepage, water leakage phenomenon are comparatively general. The subway leakage water has great influence on the subway construction and operation, and on one hand, the subway leakage water needs to be repaired by spending a large amount of manpower and material resources, so that the subway construction cost is increased; on the other hand, the service life of the subway is influenced by the leakage water of the subway, the riding environment is influenced, and the quality hidden danger is brought to the station; leakage water during the operation period of opening the subway generates huge maintenance cost, and increases the operation cost of the subway. Subway waterproof control becomes the central importance of subway quality control. At present, the waterproof concept of the subway is that the structure is mainly self-waterproof, and the outer waterproof is assisted, namely, the waterproof concrete of the main structure is taken as a main waterproof means, the full outer waterproof of coiled materials, coating materials and the like is taken as an auxiliary means, and a waterproof reinforcing means is adopted at the weak points (structure seams, reserved parts, structure transformation positions and the like) of the structure.
The construction joint is used as a weak point of a structure and is easy to leak water, a 'serious disaster area' of the water leakage is arranged at the joint of a main body structure and an auxiliary structure of a survey station, the position has the problem of overlapping of new and old concrete due to different construction time sequences and is influenced by a fender post, and the general waterproof method mainly adopts water swelling and sealing glue and a pre-buried grouting pipe as waterproof measures. However, the water-swelling waterproof glue is an amorphous waterproof material, and the waterproof effect of the joint is affected by the problems of extrusion, uneven thickness, unclean base surface cleaning, early swelling in case of water and the like in site construction; reserve the slip casting pipe and also often appear buried depth not in place, the slip casting pipe scheduling problem that is obstructed, and additional structure foundation bearing capacity is inhomogeneous etc. all can reduce deformation joint department waterproof ability, finally leads to the structure to appear the percolating water. Therefore, the traditional waterproof method for the joint of the main structure and the auxiliary structure of the station has a plurality of disadvantages.
Disclosure of Invention
The utility model aims at providing a waterproof construction for open cut station main part and attached junction adds through optimizing the interface structure way and establishes the steel sheet waterstop, thereby strengthens the seepage that waterproof measure effectively prevented groundwater.
The utility model discloses the technical scheme who adopts does:
the utility model provides a waterproof construction that is used for open cut station main part and attached junction, its characterized in that:
the auxiliary structure is accessed from the main structure side wall of the station main body, and horizontal steel plate water stops transversely penetrating through two sides are arranged at the three types of seams of the main structure side wall and the auxiliary structure top plate, the main structure middle plate and the auxiliary structure bottom plate and the main structure side wall and the auxiliary structure side wall.
And grouting guide pipes are arranged at the joints of the three types, one end of each grouting guide pipe is positioned in the station main body, and the other end of each grouting guide pipe is positioned in the auxiliary structure and is connected into the grouting pipe at the joint.
The outer wall of the joint of the auxiliary structure connected to the station main body is paved with waterproof coiled materials.
The waterproofing membrane of station main part side and the waterproofing membrane of accessory structure side are laid separately to overlap joint each other.
The end faces of the three types of joints are coated with cement-based permeable crystalline materials.
And water stop strips are arranged on the side of the auxiliary structure at the joint of the three types.
The utility model has the advantages of it is following:
1. the utility model discloses be the tongue-and-groove with the design of structure side wall, reserve out the steel sheet waterstop and set up the space.
2. The utility model discloses add the steel sheet waterstop on the basis of optimizing the structure, form the waterproof measure of outsourcing waterproof + steel sheet waterstop + slip casting pipe + sealing strip, can play waterproof and leaking stoppage's dual efficiency, effectively prevent the groundwater seepage to reduce later stage leaking stoppage expense and operation risk.
Drawings
FIG. 1 is a cross-sectional view of the structure of the present invention;
FIG. 2 is a water-proof structure of the joint of the station side wall and the auxiliary side wall of the utility model;
FIG. 3 is a waterproof structure of the joint between the middle plate and the auxiliary bottom plate of the station of the present invention;
FIG. 4 is a waterproof structure of the joint of the station roof and the attached roof of the present invention;
in the figure, 1-main structure middle plate, 2-main structure side wall, 3-main structure top plate, 4-waterproof coiled material, 5-steel plate water stop belt, 6-grouting guide pipe, 7-grouting pipe, 8-water stop strip, 9-auxiliary structure top plate, 10-auxiliary structure bottom plate, 11-auxiliary structure side wall, 12-cement-based permeable crystallization type material, 13-station main body and 14-auxiliary structure (channel).
Detailed Description
The present invention will be described in detail with reference to the following embodiments.
The utility model relates to a waterproof construction for open cut station main part and attached junction, attached structure 14 inserts from the major structure side wall 2 of station main part 13, adopts the mode of the structure way of reserving of side wall. Horizontal steel plate water stops 5 which transversely penetrate through the two sides are arranged at the three types of seams of the main structure side wall 2 and the accessory structure top plate 9, the main structure middle plate 1 and the accessory structure bottom plate 10 and the main structure side wall 2 and the accessory structure side wall 11.
Grouting pipes 6 are arranged at the joints of the three types, one end of each grouting pipe 6 is positioned in the station main body 13, and the other end of each grouting pipe 6 is positioned in the auxiliary structure 14 and is connected into the grouting pipe 7 at the joint.
Waterproof coiled materials 4 are laid on the outer wall of the joint of the auxiliary structure 14, which is connected with the station main body 13. The waterproofing membrane 4 on the station main body 13 side and the waterproofing membrane 4 on the attachment structure 14 side are laid separately and overlapped with each other.
The end faces of the three types of joints are coated with cement-based permeable crystalline materials 12. And water stopping strips 8 are arranged on the side of the auxiliary structure 14 at the joints of the three types.
The specific implementation process is as follows:
firstly, constructing a main body fender post, excavating a foundation pit, erecting a support, excavating to the bottom of the foundation pit, constructing a bottom plate, a side wall, a middle plate and a top plate of a main body structure, and constructing a waterproof coiled material 4; and (3) pre-burying a steel plate water stop 5, a grouting guide pipe 6 and a grouting pipe 7 while constructing the side wall 2 of the main body structure, recovering the road surface above the main body structure after the steps are completed, and completing the construction of the main body structure.
And then, constructing an auxiliary structure, constructing auxiliary fender piles, excavating a foundation pit, excavating a side support to the bottom of the pit, breaking the fender piles at the position of the joint, coating a cement-based permeable crystalline material 12 at the construction joint of the joint, embedding a water stop strip 8, constructing a bottom plate, a side wall and a top plate of the auxiliary structure, simultaneously completing the construction of a waterproof coiled material 4 of the auxiliary structure and the lap joint of the waterproof coiled material 4 of the reserved part of the main structure, finally restoring the road surface, and completing the construction of the whole subway station structure.
The content of the present invention is not limited to the examples, and any equivalent transformation adopted by the technical solution of the present invention is covered by the claims of the present invention by those skilled in the art through reading the present invention.
Claims (6)
1. The utility model provides a waterproof construction that is used for open cut station main part and attached junction, its characterized in that:
the auxiliary structure (14) is connected into the main structure side wall (2) of the station main body (13), and horizontal steel plate water stops (5) transversely penetrating through two sides are arranged at three types of seams of the main structure side wall (2) and the auxiliary structure top plate (9), the main structure middle plate (1) and the auxiliary structure bottom plate (10) and the main structure side wall (2) and the auxiliary structure side wall (11).
2. The waterproof structure for the main body and the auxiliary junction of the open cut station as claimed in claim 1, wherein:
grouting guide pipes (6) are arranged at the joints of the three types, one ends of the grouting guide pipes (6) are positioned in the station main body (13), and the other ends of the grouting guide pipes are positioned in the auxiliary structures (14) and are connected into the grouting pipes (7) at the positions.
3. The waterproof structure for the main body and the auxiliary junction of the open cut station as claimed in claim 2, wherein:
waterproof coiled materials (4) are laid on the outer wall of the joint of the auxiliary structure (14) connected to the station main body (13).
4. The waterproof structure for the main body and the auxiliary junction of the open cut station as claimed in claim 3, wherein:
the waterproof roll (4) on the side of the station main body (13) and the waterproof roll (4) on the side of the accessory structure (14) are laid separately and are overlapped with each other.
5. The waterproof structure for the main body and the auxiliary junction of the open cut station as claimed in claim 4, wherein:
the end faces of the three types of joints are coated with cement-based permeable crystalline materials (12).
6. The waterproof structure for the main body and the auxiliary junction of the open cut station as claimed in claim 5, wherein:
and water stop strips (8) are arranged on the side of the auxiliary structure (14) at the three types of seams.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920906620.XU CN210238573U (en) | 2019-06-17 | 2019-06-17 | A waterproof construction that is used for open cut station main part and attached junction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920906620.XU CN210238573U (en) | 2019-06-17 | 2019-06-17 | A waterproof construction that is used for open cut station main part and attached junction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210238573U true CN210238573U (en) | 2020-04-03 |
Family
ID=69986010
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920906620.XU Active CN210238573U (en) | 2019-06-17 | 2019-06-17 | A waterproof construction that is used for open cut station main part and attached junction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210238573U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111706350A (en) * | 2020-05-07 | 2020-09-25 | 中铁十八局集团有限公司 | Plugging side wall breaking method for communication of newly-built transfer hall and existing tunnel |
-
2019
- 2019-06-17 CN CN201920906620.XU patent/CN210238573U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111706350A (en) * | 2020-05-07 | 2020-09-25 | 中铁十八局集团有限公司 | Plugging side wall breaking method for communication of newly-built transfer hall and existing tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111734457B (en) | Construction method of tunnel water-drainage-preventing system | |
CN110878700B (en) | Tunnel waterproof structure and construction method thereof | |
CN111828056B (en) | Shallow-buried underground excavation tunnel waterproof construction method | |
CN109026064A (en) | A kind of construction method that large span multiple-arch tunnel is hazy | |
CN103256052A (en) | Construction method for integral straight middle wall type double-arch tunnel | |
CN107327308A (en) | A kind of Railway Tunnel waterproof method | |
CN105019919A (en) | Tunnel for transmitting fluid and construction method thereof | |
CN109440951A (en) | New-old concrete works intersection stitches waterproof construction and construction technology | |
CN106988440A (en) | A kind of waterproof construction and its construction method at subway station main body and accessory interface | |
CN210238573U (en) | A waterproof construction that is used for open cut station main part and attached junction | |
CN203161256U (en) | Large-span swelling rock tunnel system in severe cold area | |
CN206616711U (en) | A kind of waterproof construction at subway station main body and accessory interface | |
CN113529982A (en) | Deformation joint waterproof construction method | |
CN209397743U (en) | New-old concrete works intersection stitches waterproof construction | |
CN111636483A (en) | Waterproof device for reverse construction concrete structure gap and construction method | |
CN103628506B (en) | Construction method for waterproof positions of foundation platform and pile head | |
CN204827469U (en) | A tunnel for transmission fluid | |
CN205954632U (en) | Pipeline crosses supporting construction of foundation ditch department in rich water sand layer | |
CN216077128U (en) | Subway double-layer full-section freezing underground excavation transfer station structure | |
CN206635786U (en) | Prefabricated assembled transformer substation foundation structure | |
CN212827208U (en) | PVC pre-paved anti-sticking inner-reinforced waterproof roll | |
CN114319454A (en) | Waterproof construction of lid excavation reverse construction method side wall horizontal construction seam | |
CN211714041U (en) | Prefabricated piping lane joint sealing waterproof construction of assembling | |
CN111779503A (en) | Triple baffling type partition waterproof structure of underground excavation tunnel | |
CN114263215B (en) | Construction method for building waterproof structure at storey-added connection part of subway station by combined excavation and excavation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |