CN112982427A - 一种软土区基坑险情的加固施工方法 - Google Patents
一种软土区基坑险情的加固施工方法 Download PDFInfo
- Publication number
- CN112982427A CN112982427A CN202110303912.6A CN202110303912A CN112982427A CN 112982427 A CN112982427 A CN 112982427A CN 202110303912 A CN202110303912 A CN 202110303912A CN 112982427 A CN112982427 A CN 112982427A
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- raft
- pouring
- cushion layer
- soft soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Abstract
本发明公开一种软土区基坑险情的加固施工方法,通过取消常规基坑险情下增加的预应力锚索,将底板垫层浇筑至厚度不小于20cm,并将桩顶和垫层浇筑为一体并延伸浇筑至支护桩边缘;同时在底板垫层浇筑后浇筑筏板,筏板浇筑至支护桩边,将筏板肥槽用素混凝土回填形成支撑;能保证施工质量及基坑稳定性,避免基坑事故,同时缩短工期,适合软土区基坑险情参考使用。
Description
技术领域
本发明涉及地基基础工程技术领域,具体的涉及一种软土区基坑险情的加固施工方法。
背景技术
软土区的深基坑开挖一直是危险性较大的分部工程,虽然近几年在支护设计上不断加大了安全系数,但是基坑开挖是一个复杂且较漫长的施工过程,不可控因素多,故仍不时出现险情。
钢筋混凝土灌注桩+预应力锚索支护结构、地下连续墙+预应力锚索支护结构在软土、砂层地区深基坑支护结构中有着广泛的应用,现有技术中,钢筋混凝土灌注桩+预应力锚索支护结构造价比较经济,由于在软土、砂层地区预应力锚索成孔易出现塌孔、堵孔、清孔不干净、注浆不到位等情况发生,造成预应力锚索抗拔力小,不满足设计要求,轻着造成工程造价增加及工期拖延,重者造成工程安全事故,因锚索抗拔力达不到设计要求造成基坑位移增加,发生险情的项目比比皆是。
因此,申请人旨在提出一种软土区基坑险情的加固施工方法,解决现有技术存在的上述技术问题。
发明内容
针对现有技术存在的上述问题,本发明提供了一种软土区基坑险情的加固施工方法,保证施工质量及基坑稳定性,避免基坑事故,同时缩短工期,适合软土区基坑险情参考使用。
为实现上述技术目的,达到上述技术效果,本发明是通过以下技术方案实现:
一种软土区基坑险情的加固施工方法,通过取消常规基坑险情下增加的预应力锚索,将底板垫层浇筑至厚度不小于20cm,并将桩顶和垫层浇筑为一体并延伸浇筑至支护桩边缘;
同时在底板垫层浇筑后浇筑筏板,筏板混凝土浇筑至支护桩边缘,将肥槽用素混凝土回填形成支撑。
进一步的,所述底板垫层在基坑开挖完成后24小时内完成浇筑。
进一步的,所述筏板混凝土浇筑的时间在底板垫层浇筑后2-3天内完成。
进一步的,所述底板垫层、筏板基础分段开挖、分段施工,沿基坑边分段长度不超过20m,筏板混凝土浇筑48小时后才能开挖相邻土方。
进一步的,所述筏板基础前后段间留设竖直施工缝,预留筏板主筋套筒机械连接,清楚施工缝处松散混凝土,用清水冲洗干净后才能浇筑后段筏板混凝土。
本发明的有益效果:
本发明的软土区基坑险情的加固施工方法,通过取消常规基坑险情下增加的预应力锚索,将底板垫层浇筑至厚度不小于20cm,并将桩顶和垫层浇筑为一体并延伸浇筑至支护桩边缘;同时在底板垫层浇筑后浇筑筏板,筏板混凝土浇筑至支护桩边,将筏板肥槽用素混凝土回填形成支撑;能保证施工质量及基坑稳定性,避免基坑事故,同时缩短工期,适合软土区基坑险情参考使用。
当然,实施本发明的任一产品并不一定需要同时达到以上所述的所有优点。
具体实施方式
下面将结合本发明实施例对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。
实施例
一种软土区基坑险情的加固施工方法,通过取消常规基坑险情下增加的预应力锚索,将底板垫层浇筑至厚度不小于20cm,并将桩顶和垫层浇筑为一体并延伸浇筑至支护桩边缘;
同时在底板垫层浇筑后浇筑筏板,筏板混凝土浇筑至支护桩边缘,将肥槽用素混凝土回填形成支撑。
所述底板垫层在基坑开挖完成后24小时内完成浇筑。
所述筏板混凝土浇筑的时间在底板垫层浇筑后2-3天内完成。
所述底板垫层、筏板基础分段开挖、分段施工,沿基坑边分段长度不超过20m,筏板混凝土浇筑48小时后才能开挖相邻土方。
所述筏板基础前后段间留设竖直施工缝,预留筏板主筋套筒机械连接,清楚施工缝处松散混凝土,用清水冲洗干净后才能浇筑后段筏板混凝土。
本发明的软土区基坑险情的加固施工方法,垫层浇筑至支护桩边缘,垫层和桩顶相连,混凝土凝固后对支护桩形成一定的支撑力,可以减小、限制基坑变形;基础筏板和支护桩间同时回填素混凝土,混凝土凝固后对整个筏板基础及支护桩提供了一个水平支撑力,和上部锚索共同作用,控制住了基坑变形,为后续施工创造了条件;
筏板基础分段开挖、分段施工,减少开挖长度即减少了空间效应,可以减小基坑变形;同时利用时间效应原理,将土方挖至筏板混凝土浇筑完成时间控制在3-4天内,减少基坑裸露时间,可以大大的减小基坑变形。
以上公开的本发明优选实施例只是用于帮助阐述本发明。优选实施例并没有详尽叙述所有的细节,也不限制该发明仅为所述的具体实施方式。显然,根据本说明书的内容,可作很多的修改和变化。本说明书选取并具体描述这些实施例,是为了更好地解释本发明的原理和实际应用,从而使所属技术领域技术人员能很好地理解和利用本发明。本发明仅受权利要求书及其全部范围和等效物的限制。
Claims (5)
1.一种软土区基坑险情的加固施工方法,其特征在于:通过取消常规基坑险情下增加的预应力锚索,将底板垫层浇筑至厚度不小于20cm,并将桩顶和垫层浇筑为一体并延伸浇筑至支护桩边缘;
同时在底板垫层浇筑后浇筑筏板,筏板浇筑至支护桩边缘,将肥槽用素混凝土回填形成支撑。
2.如权利要求1所述的软土区基坑险情的加固施工方法,其特征在于:所述底板垫层在基坑开挖完成后24小时内完成浇筑。
3.如权利要求1所述的软土区基坑险情的加固施工方法,其特征在于:所述筏板混凝土浇筑的时间在底板垫层浇筑后2-3天内完成。
4.如权利要求1所述的软土区基坑险情的加固施工方法,其特征在于:所述底板垫层、筏板基础分段开挖、分段施工,沿基坑边分段长度不超过20m,筏板混凝土浇筑48小时后才能开挖相邻土方。
5.如权利要求1所述的软土区基坑险情的加固施工方法,其特征在于:所述筏板基础前后段间留设竖直施工缝,预留筏板主筋套筒机械连接,清楚施工缝处松散混凝土,用清水冲洗干净后才能浇筑后段筏板混凝土。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110303912.6A CN112982427A (zh) | 2021-03-22 | 2021-03-22 | 一种软土区基坑险情的加固施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110303912.6A CN112982427A (zh) | 2021-03-22 | 2021-03-22 | 一种软土区基坑险情的加固施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112982427A true CN112982427A (zh) | 2021-06-18 |
Family
ID=76334323
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110303912.6A Pending CN112982427A (zh) | 2021-03-22 | 2021-03-22 | 一种软土区基坑险情的加固施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112982427A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113684832A (zh) * | 2021-08-26 | 2021-11-23 | 中天建设集团有限公司 | 一种深浅基坑施工结构及施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103306301A (zh) * | 2013-07-04 | 2013-09-18 | 天津市天友建筑设计股份有限公司 | 基于围护桩与地下室底板的桩基基础结构及其施工方法 |
CN104164895A (zh) * | 2013-05-15 | 2014-11-26 | 陈开向 | 一种不产生水浮力的地下室 |
CN104695492A (zh) * | 2015-02-13 | 2015-06-10 | 上海建工集团股份有限公司 | 一种软土地区水泥土重力式围护墙险情处理方法 |
CN105178327A (zh) * | 2015-07-17 | 2015-12-23 | 上海建工七建集团有限公司 | 一种基坑工程的复合围护结构及其施工方法 |
CN108570979A (zh) * | 2018-04-17 | 2018-09-25 | 中国水利水电第九工程局有限公司 | 一种在白云岩层上修筑防渗复合地基的施工方法 |
CN109371982A (zh) * | 2018-12-07 | 2019-02-22 | 武汉丰达地质工程有限公司 | 一种地下室底板换撑的施工方法 |
CN112359848A (zh) * | 2020-10-30 | 2021-02-12 | 北京住总第六开发建设有限公司 | 一种使用固化土进行肥槽回填的施工方法 |
-
2021
- 2021-03-22 CN CN202110303912.6A patent/CN112982427A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104164895A (zh) * | 2013-05-15 | 2014-11-26 | 陈开向 | 一种不产生水浮力的地下室 |
CN103306301A (zh) * | 2013-07-04 | 2013-09-18 | 天津市天友建筑设计股份有限公司 | 基于围护桩与地下室底板的桩基基础结构及其施工方法 |
CN104695492A (zh) * | 2015-02-13 | 2015-06-10 | 上海建工集团股份有限公司 | 一种软土地区水泥土重力式围护墙险情处理方法 |
CN105178327A (zh) * | 2015-07-17 | 2015-12-23 | 上海建工七建集团有限公司 | 一种基坑工程的复合围护结构及其施工方法 |
CN108570979A (zh) * | 2018-04-17 | 2018-09-25 | 中国水利水电第九工程局有限公司 | 一种在白云岩层上修筑防渗复合地基的施工方法 |
CN109371982A (zh) * | 2018-12-07 | 2019-02-22 | 武汉丰达地质工程有限公司 | 一种地下室底板换撑的施工方法 |
CN112359848A (zh) * | 2020-10-30 | 2021-02-12 | 北京住总第六开发建设有限公司 | 一种使用固化土进行肥槽回填的施工方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113684832A (zh) * | 2021-08-26 | 2021-11-23 | 中天建设集团有限公司 | 一种深浅基坑施工结构及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101914925A (zh) | 利用优化复合预制拱墙作外墙的地下室 | |
CN105178327A (zh) | 一种基坑工程的复合围护结构及其施工方法 | |
CN100510281C (zh) | 超大直径、超埋深度调蓄池的半逆作施工方法 | |
CN105756091A (zh) | 一种控制邻近建筑物变形的地铁车站基坑施工方法 | |
CN110700280A (zh) | 一种狭小地带基坑支护施工导流装置及施工方法 | |
CN110952567A (zh) | 一种前墙后桩复合双排基坑支护结构及其施工方法 | |
CN206752667U (zh) | 一种地下室挡墙结构 | |
CN112982427A (zh) | 一种软土区基坑险情的加固施工方法 | |
CN106758890A (zh) | 排桩箱涵结构及其施工方法 | |
CN110117959B (zh) | 一种临近江河基坑支护施工方法 | |
CN210737572U (zh) | 一种基坑止水帷幕结构 | |
CN104005370B (zh) | 空心砌块生态护面的加筋土轻质驳岸挡墙及其建造方法 | |
CN211340808U (zh) | 一种前墙后桩基坑支护结构 | |
CN110080234B (zh) | 一种在软土地基深基坑二次中心岛开挖的方法 | |
CN115198790B (zh) | 一种既有路堤直立挡墙加固支护方法 | |
CN207727603U (zh) | 大承台深基坑模板支护装置 | |
CN218027730U (zh) | 钻孔灌注桩组合基坑围护结构 | |
CN112982296B (zh) | 用于边坡防护的桩箱式挡墙的施工方法 | |
CN102296620A (zh) | 帷幕止水护坡墙及其施工方法 | |
CN212956576U (zh) | 受限空间高填方路基边坡泡沫混凝土的加固结构 | |
CN113136854A (zh) | 双排桩支护与扶壁侧墙结合的分离式闸室系统 | |
CN107119716A (zh) | 海涂涌潮区公路隧道修建结构及其方法 | |
CN208748686U (zh) | 一种上字型挡土墙结构 | |
CN111894009A (zh) | 一种逆作法拼装钢板桩支护结构及施工方法 | |
CN110284511A (zh) | 超长湖底隧道多仓滚动式的围堰明挖施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |