CN112942420B - Prefabricated buttress structure for pipeline in pipeline and construction method - Google Patents
Prefabricated buttress structure for pipeline in pipeline and construction method Download PDFInfo
- Publication number
- CN112942420B CN112942420B CN202110111697.XA CN202110111697A CN112942420B CN 112942420 B CN112942420 B CN 112942420B CN 202110111697 A CN202110111697 A CN 202110111697A CN 112942420 B CN112942420 B CN 112942420B
- Authority
- CN
- China
- Prior art keywords
- channel
- buttress
- prefabricated
- pipeline
- prefabricated block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a prefabricated buttress structure for pipelines in a pipe gallery and a construction method, wherein the structure comprises a main structure at the top of the pipe gallery, and a buttress prefabricated block and a channel which are arranged above the main structure; wherein: the bottom of the buttress precast block is provided with four pulleys; two channels are arranged below each buttress prefabricated block; the bottom of the channel is provided with a plurality of bottom supporting mechanisms, and the bottom supporting mechanisms of the channel are arranged at the top of the main structure; the channel top includes long recess and two short recesses, and long recess is the recess of rectangle, and two short recesses set up respectively in one side and the middle part of channel, pour and only need push the channel position with the buttress prefabricated section after accomplishing, and the pulley is fixed in channel turn position department. The invention reduces the number of pier construction operations in the pipe gallery, facilitates the construction, overcomes the material feeding difficulty and the influence of weather factors in the pier construction, greatly shortens the construction period and effectively reduces the construction cost.
Description
Technical Field
The invention relates to the technical field of pipe gallery construction, in particular to a prefabricated buttress structure for a pipeline in a pipe gallery and a construction method.
Background
With the rapid development of economy, the land use of cities is increasingly tense, so that the development of underground spaces is inevitably carried out. In the development of underground space, an urban underground comprehensive pipe gallery is also an important one. The system integrates various engineering pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like, and is an important infrastructure and a 'life line' for guaranteeing urban operation. However, in the construction of the pipe gallery, the construction of the buttress is often very complicated. At present, the conventional method for constructing the buttress needs to face the problems of difficult feeding, inconvenient construction and the like. If meet bad weather, can not in time pour the concrete after the reinforcement is accomplished, still can lead to the corrosion of reinforcing bar. Under the requirements of increasing the construction cost of projects and saving the construction period as much as possible, optimization and improvement on the pier construction in the gallery are a technical problem at present.
Disclosure of Invention
The invention aims to solve the technical problem of providing a prefabricated buttress structure for a pipeline in a pipeline and a construction method aiming at the defects in the prior art.
The technical scheme adopted by the invention for solving the technical problem is as follows:
the invention provides a prefabricated buttress structure for a pipeline in a pipeline corridor, which comprises a main structure at the top of the pipeline corridor, a buttress prefabricated block and a channel, wherein the buttress prefabricated block and the channel are arranged above the main structure; wherein:
the bottom of the buttress prefabricated block is provided with four pulleys; two channels are arranged below each buttress prefabricated block; the bottom of the channel is provided with a plurality of bottom supporting mechanisms, and the bottom supporting mechanisms of the channel are arranged at the top of the main body structure; the top of the channel comprises a long groove and two short grooves, the long groove is a rectangular groove, and the two short grooves are respectively arranged at one side and the middle part of the channel;
two liang of relative settings of four pulleys of buttress prefabricated section bottom arrange the long recess of channel respectively in, when transversely moving the buttress prefabricated section to one side of channel along long recess, remove the vertical short recess removal of following of buttress prefabricated section again, remove to the interior back of short recess, establish the billet through adding at the pulley rear and fix.
Furthermore, a main structure top steel bar is arranged in the main structure, and when the channel is pre-buried in the main structure, the bottom supporting mechanism is welded to the main structure top steel bar.
Furthermore, the top of the buttress prefabricated block is provided with a U-shaped groove, and a pipeline is installed through the U-shaped groove.
Further, two adjacent channels of the present invention are disposed parallel to each other.
Furthermore, at least 5 bottom supporting mechanisms are arranged at the bottom of each channel, one bottom supporting mechanism is arranged below each short groove, and at least 3 bottom supporting mechanisms are arranged below the long groove.
The invention provides a construction method of a prefabricated buttress structure for pipelines in a pipeline, which comprises the following steps:
the method comprises the following steps: after the embedded positions of the buttress and the channel are determined, paying off and positioning are carried out, and the channel with the size corresponding to the bottom of the buttress prefabricated block is customized;
step two: after the top steel bars of the main body structure are bound, welding a bottom supporting mechanism of the embedded channel to the top steel bars of the main body structure;
step three: after welding, pouring concrete at the bottom of the channel and the main structure together;
step four: after pouring is completed, the buttress prefabricated block is pushed into the position of the channel, the pulley on the lower portion of the buttress prefabricated block slides to one end along the long groove in the channel, and then slides to the turning position along the short groove, and then a wood block with the same size as the channel is plugged in the channel for fixing, so that the pulley is ensured not to slide any more.
The invention has the following beneficial effects: the pipe gallery internal pipeline prefabricated buttress structure and the construction method have the following advantages:
compared with a steel-wood template combined formwork, the aluminum template can be adopted during prefabrication. Which circumvents the disadvantages of steel and wood templates. For the steel form, the steel form is heavy, and the construction operation of workers is inconvenient. For the wood template, the wood template is easy to deform, has low repeated utilization rate and is not beneficial to the protection of forest resources. The invention adopts the aluminum template when erecting the formwork, thereby having the advantages of difficult deformation in operation, high construction efficiency, low manufacturing cost and better integrity.
Second, in traditional buttress formwork and concrete placement, because of the pipe gallery inner space is narrow and small, the workman is under construction inconveniently, and often can meet the problem of throwing the material difficulty. The prefabricated block used in the invention can well avoid the problems, is convenient for construction, and can reduce unnecessary material waste. In addition, the number of people for pier construction operation in the pipe gallery is reduced, the construction period is greatly shortened, and the construction cost is effectively reduced.
Three, compare in traditional buttress reinforcement form, if meet unfavorable weather factor and cause the inside ponding of pipe gallery, then can not in time carry out concrete placement after reinforcement accomplishes, the reinforcing bar can appear the condition of corrosion, and the pipe gallery inner space is originally just narrow and small, exposes for a long time like the reinforcing bar, not only is not convenient for construction operation personnel to walk in the pipe gallery, can cause the hidden danger to constructor's safety moreover. The prefabricated block can be used for well avoiding the problems, effectively eliminating the influence of external factors and ensuring the safety of workers.
And fourthly, compared with the ductile cast iron pipeline buttress, the cover pressing plate and the rib arrangement process of the ductile cast iron pipeline buttress are complicated, and the risk of rusting can be caused by using an iron metal material. The invention omits the complicated installation and splicing steps and uses precast concrete materials. Compared with the prior art, the method has the advantages of fewer construction processes, more convenience in construction and good durability.
Compared with the common precast block, the bottom of the pier precast block is provided with the pulley. When carrying out the material transportation, the input of manpower and materials that can significantly reduce reduces construction operation personnel, makes the construction more convenient. And, under the construction environment that the piping lane originally is unfavorable, simplify the material transportation flow and also can let construction operation personnel's safety more secure to a certain extent.
Drawings
The invention will be further described with reference to the accompanying drawings and examples, in which:
FIG. 1 is a schematic view of the overall structure of an embodiment of the present invention;
FIG. 2 is a diagrammatic representation of a prefabricated buttress block in accordance with an embodiment of the present invention;
FIG. 3 is a front view of a channel of an embodiment of the present invention;
FIG. 4 is a top view of a channel of an embodiment of the present invention;
figure 5 is a side view of a channel of an embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and do not limit the invention.
As shown in fig. 1-5, the pipe gallery internal pipe prefabricated buttress structure of the embodiment of the invention comprises a main structure 5 at the top of a pipe gallery, buttress prefabricated blocks 1 and a channel 3 which are arranged above the main structure 5; wherein:
the bottom of the buttress prefabricated block 1 is provided with four pulleys 2; two channels 3 are arranged below each buttress precast block 1; the bottom of the channel 3 is provided with a plurality of bottom supporting mechanisms 4, and the bottom supporting mechanisms 4 of the channel 3 are arranged at the top of the main structure 5; the top of the channel 3 comprises a long groove and two short grooves, the long groove is a rectangular groove, and the two short grooves are respectively arranged at one side and the middle part of the channel 3;
four pulley 2 two liang of relative settings of buttress prefabricated section 1 bottom, arrange the long recess of channel 3 respectively in, when transversely moving buttress prefabricated section 1 to one side of channel 3 along long recess, move the vertical short recess of following of buttress prefabricated section 1 again, remove to the short recess in the back, establish the billet through adding at pulley 2 rear and fix.
Be provided with major structure top reinforcing bar 6 in the major structure 5, when 3 pre-buried to major structure 5 in of channel, weld bottom sprag mechanism 4 to major structure top reinforcing bar 6 on. The top of the buttress prefabricated block 1 is provided with a U-shaped groove, and a pipeline is installed through the U-shaped groove. Two adjacent channels 3 are arranged parallel to each other. 3 bottoms of every channel are provided with and are no less than 5 bottom sprag mechanisms 4, and every short recess below all is provided with a bottom sprag mechanism 4, and long recess below is provided with and is no less than 3 bottom sprag mechanisms 4.
The construction method of the prefabricated buttress structure for the pipeline in the pipe gallery provided by the embodiment of the invention comprises the following steps of:
before the pier precast block is constructed, the main structure is required to be completed. Firstly, determining the embedded positions of the buttress and the channel, then setting out and positioning, and customizing the channel with the size corresponding to the bottom of the buttress prefabricated block. After the binding of the steel bars at the top of the main body structure is finished, the lower part of the embedded channel is welded to the position of the steel bars at the top of the main body structure. And pouring concrete together after welding. After pouring is completed, the buttress prefabricated block is pushed into the position of the channel, and after the pulley on the lower portion of the buttress prefabricated block slides to the turning position in the channel, a wood block with the same size as the channel is plugged in the pulley for fixing, so that the pulley is ensured not to slide any more.
The method comprises the following steps: determining the pre-buried positions of the buttress and the channel, and then paying off and positioning to customize the channel with the size corresponding to the bottom of the buttress precast block;
step two: after the top steel bars of the main body structure are bound, welding a bottom supporting mechanism of the embedded channel to the top steel bars of the main body structure;
step three: after welding, pouring concrete together with the main structure at the bottom of the channel;
step four: after pouring is completed, the buttress prefabricated block is pushed into the position of the channel, a pulley on the lower portion of the buttress prefabricated block slides to one end along the long groove in the channel, and then slides to a turning position along the short groove, and then a wood block with the same size as the channel is plugged in the channel for fixing, so that the pulley is ensured not to slide any more.
It will be appreciated that modifications and variations are possible to those skilled in the art in light of the above teachings, and it is intended to cover all such modifications and variations as fall within the scope of the appended claims.
Claims (2)
1. A prefabricated buttress structure for an inner pipeline of a pipeline, which is characterized by comprising a main structure (5) at the top of the pipeline, and a buttress prefabricated block (1) and a channel (3) which are arranged above the main structure (5); wherein:
the bottom of the buttress prefabricated block (1) is provided with four pulleys (2); two channels (3) are arranged below each buttress prefabricated block (1); a plurality of bottom supporting mechanisms (4) are arranged at the bottom of the channel (3), and the bottom supporting mechanisms (4) of the channel (3) are arranged at the top of the main body structure (5); the top of the channel (3) comprises a long groove and two short grooves, the long groove is a rectangular groove, and the two short grooves are respectively arranged at one side and the middle part of the channel (3);
the four pulleys (2) at the bottom of the buttress prefabricated block (1) are arranged oppositely in pairs and are respectively arranged in the long grooves of the channel (3), when the buttress prefabricated block (1) transversely moves to one side of the channel (3) along the long grooves, the buttress prefabricated block (1) vertically moves along the short grooves, and after the buttress prefabricated block moves into the short grooves, the rear of the pulleys (2) is fixed by additionally arranging wood blocks;
a main structure top steel bar (6) is arranged in the main structure (5), and when the channel (3) is pre-buried in the main structure (5), the bottom supporting mechanism (4) is welded on the main structure top steel bar (6);
the top of the buttress precast block (1) is provided with a U-shaped groove, and a pipeline is installed through the U-shaped groove;
two adjacent channels (3) are arranged in parallel;
at least 5 bottom supporting mechanisms (4) are arranged at the bottom of each channel (3), one bottom supporting mechanism (4) is arranged below each short groove, and at least 3 bottom supporting mechanisms (4) are arranged below each long groove.
2. A construction method of a prefabricated buttress structure for pipelines in a pipeline, which adopts the prefabricated buttress structure for pipelines in the pipeline as claimed in claim 1, and is characterized by comprising the following steps of:
the method comprises the following steps: after the embedded positions of the buttress and the channel are determined, paying off and positioning are carried out, and the channel with the size corresponding to the bottom of the buttress prefabricated block is customized;
step two: after the top steel bars of the main body structure are bound, welding a bottom supporting mechanism of the pre-buried channel to the top steel bars of the main body structure;
step three: after welding, pouring concrete at the bottom of the channel and the main structure together;
step four: after pouring is completed, the buttress prefabricated block is pushed into the position of the channel, a pulley on the lower portion of the buttress prefabricated block slides to one end along the long groove in the channel, and then slides to a turning position along the short groove, and then a wood block with the same size as the channel is plugged in the channel for fixing, so that the pulley is ensured not to slide any more.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110111697.XA CN112942420B (en) | 2021-01-27 | 2021-01-27 | Prefabricated buttress structure for pipeline in pipeline and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110111697.XA CN112942420B (en) | 2021-01-27 | 2021-01-27 | Prefabricated buttress structure for pipeline in pipeline and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112942420A CN112942420A (en) | 2021-06-11 |
CN112942420B true CN112942420B (en) | 2022-07-15 |
Family
ID=76237878
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110111697.XA Active CN112942420B (en) | 2021-01-27 | 2021-01-27 | Prefabricated buttress structure for pipeline in pipeline and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112942420B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202532021U (en) * | 2012-03-22 | 2012-11-14 | 中国石油天然气股份有限公司 | Movable pipeline buttress |
CN207553133U (en) * | 2017-07-28 | 2018-06-29 | 江苏省苏中建设集团股份有限公司 | A kind of underground pipe gallery structure |
CN208011066U (en) * | 2018-01-11 | 2018-10-26 | 泉州台商投资区可砬建材科技有限公司 | A kind of petroleum pipeline slidable adjustment formula interlocking seat of high sealing characteristic |
CN109577368A (en) * | 2018-12-10 | 2019-04-05 | 中国建筑第七工程局有限公司 | A kind of quick method for supporting of Urban Underground piping lane interior conduit |
CN208703280U (en) * | 2018-07-11 | 2019-04-05 | 深圳辉达建筑工程有限公司 | A kind of cross a river pipe bridge |
-
2021
- 2021-01-27 CN CN202110111697.XA patent/CN112942420B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202532021U (en) * | 2012-03-22 | 2012-11-14 | 中国石油天然气股份有限公司 | Movable pipeline buttress |
CN207553133U (en) * | 2017-07-28 | 2018-06-29 | 江苏省苏中建设集团股份有限公司 | A kind of underground pipe gallery structure |
CN208011066U (en) * | 2018-01-11 | 2018-10-26 | 泉州台商投资区可砬建材科技有限公司 | A kind of petroleum pipeline slidable adjustment formula interlocking seat of high sealing characteristic |
CN208703280U (en) * | 2018-07-11 | 2019-04-05 | 深圳辉达建筑工程有限公司 | A kind of cross a river pipe bridge |
CN109577368A (en) * | 2018-12-10 | 2019-04-05 | 中国建筑第七工程局有限公司 | A kind of quick method for supporting of Urban Underground piping lane interior conduit |
Also Published As
Publication number | Publication date |
---|---|
CN112942420A (en) | 2021-06-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207348091U (en) | A kind of assembled pipe gallery | |
CN108149706A (en) | Prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and laminated slabs and construction method thereof | |
CN106703077A (en) | Prefabricated and assembled integral type underground pipe gallery structure | |
CN107012887B (en) | Prefabricated pin-connected panel node of arc top utility tunnel piecemeal | |
CN107503382B (en) | End template fixed rubber water stop belt structure and construction method thereof | |
CN108166525A (en) | Semi-prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof | |
CN101363224A (en) | Movable foundation pit support system and construction method | |
CN111608662B (en) | Shaft oversized-diameter integral moving metal template | |
CN109853625B (en) | Integrated concrete comprehensive pipe gallery connected and assembled in mixed mode | |
CN112942420B (en) | Prefabricated buttress structure for pipeline in pipeline and construction method | |
CN209040349U (en) | A kind of ring muscle fastening shear wall structure being easily installed | |
CN109137983A (en) | Assembled integral solid exposed wall plate pipe gallery and its construction method | |
CN113668849A (en) | Post-cast strip pouring equipment and construction method thereof | |
CN210562299U (en) | Prefabricated assembled underground comprehensive pipe gallery | |
CN210395437U (en) | Utility tunnel and prefabricated pipe thereof with self-repairing function | |
CN207846469U (en) | Pre-buried C type channel-section steel device on piping lane centre form platform truck template | |
CN207392238U (en) | A kind of assembled under-traverse tunnel | |
CN218373333U (en) | Steel concrete combined bridge deck segment connecting structure for rapid construction | |
Zhang et al. | Development and application of mechanized matching equipment for high-speed railway tunnel construction | |
CN109869044A (en) | A kind of modularization dismounting enclosure wall | |
CN212405248U (en) | Underground compression-resistant comprehensive pipe gallery structure | |
CN213572042U (en) | Positioning device for semi-prefabricated double-sided overlapped comprehensive pipe gallery side wall with concealed columns | |
CN212175859U (en) | Fixing device for embedded part on side wall of concrete pipe gallery | |
CN214194660U (en) | Prefabricated cable shaft of cordwood system equipment | |
CN210712958U (en) | Prefabricated cast-in-situ superposed cable working well top plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |