CN112922272A - EPS line construction method - Google Patents

EPS line construction method Download PDF

Info

Publication number
CN112922272A
CN112922272A CN202110124032.2A CN202110124032A CN112922272A CN 112922272 A CN112922272 A CN 112922272A CN 202110124032 A CN202110124032 A CN 202110124032A CN 112922272 A CN112922272 A CN 112922272A
Authority
CN
China
Prior art keywords
eps
mortar
line
layer
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110124032.2A
Other languages
Chinese (zh)
Other versions
CN112922272B (en
Inventor
何磊
刘志国
吴傅国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN202110124032.2A priority Critical patent/CN112922272B/en
Publication of CN112922272A publication Critical patent/CN112922272A/en
Application granted granted Critical
Publication of CN112922272B publication Critical patent/CN112922272B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings

Abstract

The invention discloses an EPS line construction method, which comprises the following steps: treating a wall base layer; determining a reference line; preparing mortar; pasting an EPS board, smearing prepared mortar to the EPS board, then paving the EPS board on a wall base layer, paving the EPS board on the wall base layer, horizontally and vertically staggered and paved the EPS board from bottom to top, forcibly extruding the EPS board to completely adhere to a wall surface, wherein the saturation is not less than 80%, the width of a bonding seam is not more than 3mm, the bonding seam is adhered with a hook, the mortar seam is full, and the cleanness of the surface of the EPS board is kept; installing an anchoring nail; performing seam treatment; and (3) line repairing, namely cleaning a part to be repaired, cutting the EPS board into EPS materials with the same volume and shape as the defect area, sticking the EPS materials in place by using a binder, covering the surface with plastering mortar and alkali-resistant mesh cloth, and lapping the surface to the periphery by more than 50mm to finally complete the integration of the surface and the large surface of the periphery. The EPS line construction method can avoid quality problems of falling, surface mortar cracking, poor plate joint flatness, line joint cracking and the like in the later construction period.

Description

EPS line construction method
Technical Field
The invention relates to the field of building construction, in particular to an EPS line construction method.
Background
The EPS decorative line can prevent fire and does not emit toxic substances, and is an environment-friendly high-quality decorative building material product. The novel outer wall decoration line and the novel outer wall decoration component are more suitable for installation, can embody European classical and elegant decoration styles on heat-insulating walls of outer walls EPS and XPS, and can ensure that the outer wall of a main building does not have cold and heat bridge effects. Has the advantages of convenient installation, economy, long durability and the like. With the continuous development of the existing architectural decoration industry, more and more novel materials are continuously distinguished, and EPS lines are more and more people favored objects. The EPS lines are not affected by temperature change, and are cold-resistant and heat-resistant; is not affected by humid weather and acid rain. The EPS decorative line can prevent fire and does not emit toxic substances, and is an environment-friendly high-quality decorative building material product. The EPS decorative lines are cut by computer numerical control, are fast to manufacture, have various varieties and models, such as lines, Roman columns, window sleeves, bracket arches and the like, and can be arranged on four sides of a window, a door edge, an eave corner and a wall body; the outer facade of the building is more beautiful, and brand-new and unique originality is brought to architects. But the current EPS lines can appear in the later stage and drop, surface mortar fracture, the panel piece seam roughness is relatively poor, line seam fracture quality problems such as fracture when being under construction, cause time limit for a project extension and cost of maintenance increase.
Disclosure of Invention
The invention aims to provide an EPS line construction method which can avoid quality problems of falling off, surface mortar cracking, poor plate seam planeness, line seam cracking and the like in the later construction period.
In order to achieve the purpose, the invention provides the following technical scheme:
an EPS line construction method comprises the following steps:
(1) treating a wall base layer: cleaning and drying a wall body base layer, and cleaning, drying and leveling a base layer wall surface to ensure that the surface strength of the base layer surface is not less than 0.5 Mpa;
(2) determining a reference line: determining the vertical squareness of each internal corner and each external corner by using a line supporting plate and a square ruler, marking the repairing range and the thickness of the wall surface, determining and marking the vertical flatness of each large-surface wall by using a guiding ruler and a line supporting plate, and measuring and calculating the mortar consumption of a leveling layer according to the repairing range and the thickness;
(3) preparing mortar: mixing the bonding mortar with water according to the mass ratio of 4:1, stirring the mixture by using a handheld electric stirrer until the mixture is uniform and has moderate consistency, standing the mixture for 5min after the bonding mortar is prepared, stirring the mixture again before use, and using the stirred mortar within 2 hours;
(4) pasting an EPS plate: coating the prepared mortar on an EPS board, then paving and pasting the EPS board on a wall body base layer, paving and pasting the EPS board on the wall body base layer from bottom to top in a horizontal and vertical staggered joint mode, forcibly extruding the EPS board to enable the EPS board to be completely pasted on a wall surface, enabling the adhesive joint width to be not more than 3mm and the adhesive joint to be hooked along with adhesion, enabling the mortar joint to be full, and keeping the cleanness and tidiness of the surface of the EPS board;
(5) installing an anchoring nail: when the thickness of the line is more than or equal to 500mm, after the line is installed in place and maintained for 24 hours, punching holes at the set position of the line by using a percussion drill, enabling the holes to penetrate through the EPS line and the outer wall heat-insulating layer and enter the base layer wall body to be not less than 50mm, installing anchoring nails into the holes, and embedding the discs of the anchoring parts into the surface of the line so as not to expose the disc;
(6) seam treatment: coating a layer of plastering mortar on the joint of the EPS boards, immediately paving a layer of alkali-resistant grid cloth, covering the whole EPS boards with the grid cloth, then coating a layer of plastering mortar, paving a layer of reinforced grid cloth on the contact positions of the EPS boards, then coating a layer of plastering mortar, and waiting to dry;
(7) line repairing: the method comprises the steps of cleaning a part to be repaired, cutting an EPS plate into EPS materials with the same volume and shape as a defect area, adhering the EPS materials in place by using an adhesive, covering surface mortar and alkali-resistant mesh cloth on the surface, and overlapping the surface to the periphery by more than 50mm, so that the finished surface and the large surface of the periphery form a whole, and the flatness and smoothness are ensured.
Preferably, in the step (3), the bonding mortar comprises, by weight, 300-350 parts of cement, 510-550 parts of quartz sand, 10-15 parts of epoxy resin, 1-3 parts of hydroxypropyl methyl cellulose, 2-8 parts of lignocellulose and 4-6 parts of a waterproof agent.
Preferably, in the step (4), the mortar is distributed on the EPS plate in any one of point bonding, frame point bonding and strip bonding.
Preferably, in the step (5), the anchoring sequence of each EPS board is that the periphery is anchored firstly, the middle part is anchored secondly, the distance between every two adjacent expansion anchor bolts and the edge distance are both 50-100 mm, and each expansion anchor bolt penetrates through the EPS boards and reaches the mortar leveling layer.
Preferably, in the step (6), the width of the reinforcing mesh cloth is 100 mm.
Preferably, in the step (6), the alkali-resistant glass fiber net is laid from top to bottom, and is stretched and flattened vertically and horizontally, so that the alkali-resistant glass fiber net is tightly attached to the bottom layer of the plastering mortar.
Preferably, in the step (7), a plurality of straight steel plates are adhered along the inner wall of the area surrounded by the part to be repaired, so that the distance between the straight steel plates and the part to be repaired is not more than 4mm, the plurality of steel plates are connected end to surround a defect area, and the gaps between the straight steel plates and the peripheral EPS plates thereof are filled with plastering mortar.
Preferably, the straight steel plate is fixed with the wall body through expansion bolts, and the thickness of the straight steel plate is 1-3 mm.
Compared with the prior art, the invention has the beneficial effects that:
1) the invention adopts the specially-made adhesive mortar, so that the EPS boards can be bonded more firmly, and the alkali-resistant mesh cloth is paved comprehensively, thereby preventing the EPS boards from falling off in the later period; secondly, a layer of reinforcing grid cloth is paved at the joint, so that the joint can be prevented from cracking;
2) because damaged department shape is unsmooth, be difficult to cut into the EPS board that supplements with the same shape size of damaged department, install straight steel sheet earlier in damaged department, the EPS board that not only can conveniently supply cuts the repair, can also play the supporting role, alleviates the load of EPS board, and has guaranteed the roughness of panel piece.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
An EPS line construction method comprises the following steps:
(1) treating a wall base layer: cleaning and drying a wall body base layer, and cleaning, drying and leveling a base layer wall surface to ensure that the surface strength of the base layer surface is not less than 0.5 Mpa;
(2) determining a reference line: determining the vertical squareness of each internal corner and each external corner by using a line supporting plate and a square ruler, marking the repairing range and the thickness of the wall surface, determining and marking the vertical flatness of each large-surface wall by using a guiding ruler and a line supporting plate, and measuring and calculating the mortar consumption of a leveling layer according to the repairing range and the thickness;
(3) preparing mortar: mixing bonding mortar with water according to the mass ratio of 4:1, stirring the mixture by using a handheld electric stirrer until the mixture is uniform and has moderate consistency, standing the mixture for 5min after the bonding mortar is prepared, stirring the mixture again before use, and using the stirred mortar within 2 hours, wherein the bonding mortar comprises the following components in parts by weight, 300 parts of cement, 510 parts of quartz sand, 10 parts of epoxy resin, 1 part of hydroxypropyl methyl cellulose, 2 parts of lignocellulose and 4 parts of a waterproof agent;
(4) pasting an EPS plate: coating the prepared mortar on an EPS board, wherein the mortar is coated on the EPS board in any one of point bonding, frame point bonding or strip bonding, then the EPS board is laid on a wall base layer, the EPS board is horizontally and vertically staggered and laid from bottom to top, the EPS board is extruded forcefully to be completely attached to a wall surface, the bonding seam width is not less than 80% of the plumpness and is not more than 3mm, the bonding seam is hooked along with bonding, the mortar joint is full, and the cleanness and tidiness of the surface of the EPS board are kept;
(5) installing an anchoring nail: when the thickness of the line is more than or equal to 500mm, after the line is installed in place and maintained for 24 hours, punching holes on a set part of the line by using a percussion drill, enabling the holes to penetrate through the EPS line and an outer wall heat insulation layer and enter a base layer wall body to be not less than 50mm, enabling anchoring nails to be installed into the holes, embedding discs of anchoring parts into the surface of the line and preventing the discs from being exposed, wherein the anchoring sequence of each EPS plate is that the periphery is anchored firstly, the middle part is anchored later, the distance between adjacent expansion anchor bolts and the edge distance are both 50-100 mm, and each expansion anchor bolt penetrates through the EPS plate and reaches a mortar;
(6) seam treatment: coating a layer of plastering mortar at the joint of the EPS board, immediately paving a layer of alkali-resistant mesh cloth, covering the whole EPS board with the mesh cloth, paving an alkali-resistant glass fiber net from top to bottom, straightening and flattening along the vertical and horizontal directions to enable the alkali-resistant glass fiber net to be tightly attached to the plastering mortar at the bottom layer, then coating a layer of plastering mortar, paving a layer of reinforced mesh cloth at the contact position of the EPS board, wherein the width of the reinforced mesh cloth is 100mm, then coating a layer of plastering mortar, and waiting for drying;
(7) line repairing: the method comprises the steps of cleaning a part to be repaired, adhering a plurality of straight steel plates along the inner wall of an area surrounded by the part to be repaired, enabling the distance between the straight steel plates and the part to be repaired to be not more than 4mm, enabling the plurality of steel plates to be connected end to surround a defect area, fixing the straight steel plates with a wall body through expansion bolts, enabling the thickness of the straight steel plates to be 1.5mm, filling gaps between the straight steel plates and peripheral EPS plates with plastering mortar, cutting the EPS plates into EPS materials with the same size and shape as the defect area, adhering the EPS materials in place with a binder, covering the surface with the plastering mortar and alkali-resistant mesh cloth, and overlapping the plastering mortar and the alkali-resistant mesh cloth to the periphery by more than 50mm, and finally forming a whole body by the.
Example 2
The present embodiment is different from embodiment 1 in that: the adhesive mortar comprises, by weight, 325 parts of cement, 530 parts of quartz sand, 13 parts of epoxy resin, 2 parts of hydroxypropyl methyl cellulose, 6 parts of lignocellulose and 5 parts of a water-proofing agent.
Example 3
The present embodiment is different from embodiment 1 in that: the adhesive mortar comprises, by weight, 350 parts of cement, 550 parts of quartz sand, 15 parts of epoxy resin, 3 parts of hydroxypropyl methyl cellulose, 8 parts of lignocellulose and 6 parts of a waterproof agent.
The foregoing is merely exemplary and illustrative of the present invention and various modifications, additions and substitutions may be made by those skilled in the art to the specific embodiments described without departing from the scope of the present invention as defined in the accompanying claims.

Claims (8)

1. The EPS line construction method is characterized by comprising the following steps:
(1) treating a wall base layer: cleaning and drying a wall body base layer, and cleaning, drying and leveling a base layer wall surface to ensure that the surface strength of the base layer surface is not less than 0.5 Mpa;
(2) determining a reference line: determining the vertical squareness of each internal corner and each external corner by using a line supporting plate and a square ruler, marking the repairing range and the thickness of the wall surface, determining and marking the vertical flatness of each large-surface wall by using a guiding ruler and a line supporting plate, and measuring and calculating the mortar consumption of a leveling layer according to the repairing range and the thickness;
(3) preparing mortar: mixing the bonding mortar with water according to the mass ratio of 4:1, stirring the mixture by using a handheld electric stirrer until the mixture is uniform and has moderate consistency, standing the mixture for 5min after the bonding mortar is prepared, stirring the mixture again before use, and using the stirred mortar within 2 hours;
(4) pasting an EPS plate: coating the prepared mortar on an EPS board, then paving and pasting the EPS board on a wall body base layer, paving and pasting the EPS board on the wall body base layer from bottom to top in a horizontal and vertical staggered joint mode, forcibly extruding the EPS board to enable the EPS board to be completely pasted on a wall surface, enabling the adhesive joint width to be not more than 3mm and the adhesive joint to be hooked along with adhesion, enabling the mortar joint to be full, and keeping the cleanness and tidiness of the surface of the EPS board;
(5) installing an anchoring nail: when the thickness of the line is more than or equal to 500mm, after the line is installed in place and maintained for 24 hours, punching holes at the set position of the line by using a percussion drill, enabling the holes to penetrate through the EPS line and the outer wall heat-insulating layer and enter the base layer wall body to be not less than 50mm, installing anchoring nails into the holes, and embedding the discs of the anchoring parts into the surface of the line so as not to expose the disc;
(6) seam treatment: coating a layer of plastering mortar on the joint of the EPS boards, immediately paving a layer of alkali-resistant grid cloth, covering the whole EPS boards with the grid cloth, then coating a layer of plastering mortar, paving a layer of reinforced grid cloth on the contact positions of the EPS boards, then coating a layer of plastering mortar, and waiting to dry;
(7) line repairing: the method comprises the steps of cleaning a part to be repaired, cutting an EPS plate into EPS materials with the same volume and shape as a defect area, adhering the EPS materials in place by using an adhesive, covering surface mortar and alkali-resistant mesh cloth on the surface, and overlapping the surface to the periphery by more than 50mm, so that the finished surface and the large surface of the periphery form a whole, and the flatness and smoothness are ensured.
2. The EPS line construction method according to claim 1, characterized in that: in the step (3), the bonding mortar comprises, by weight, 300-350 parts of cement, 510-550 parts of quartz sand, 10-15 parts of epoxy resin, 1-3 parts of hydroxypropyl methyl cellulose, 2-8 parts of lignocellulose and 4-6 parts of a waterproof agent.
3. The EPS line construction method according to claim 1, characterized in that: in the step (4), the mortar is distributed on the EPS boards in any one of point bonding, frame point bonding or strip bonding.
4. The EPS line construction method according to claim 1, characterized in that: in the step (5), the anchoring sequence of each EPS board is that the periphery is anchored firstly, then the middle part is anchored, the distance and the edge distance between every two adjacent expansion anchor bolts are 50-100 mm, and each expansion anchor bolt penetrates through the EPS boards to reach the mortar leveling layer.
5. The EPS line construction method according to claim 1, characterized in that: in the step (6), the width of the reinforcing mesh cloth is 100 mm.
6. The EPS line construction method according to claim 1, characterized in that: in the step (6), the alkali-resistant glass fiber net is laid from top to bottom, and is stretched and flattened vertically and horizontally, so that the alkali-resistant glass fiber net is tightly attached to the plastering mortar at the bottom layer.
7. The EPS line construction method according to claim 1, characterized in that: in the step (7), a plurality of straight steel plates are pasted along the inner wall of the area surrounded by the part to be repaired, the distance between the straight steel plates and the part to be repaired is not more than 4mm, the plurality of steel plates are connected end to surround a defect area, and gaps between the straight steel plates and the EPS plates around the straight steel plates are filled with plastering mortar.
8. The EPS line construction method of claim 7, characterized in that: the straight steel plate is fixed with the wall body through expansion bolts, and the thickness of the straight steel plate is 1-3 mm.
CN202110124032.2A 2021-01-29 2021-01-29 EPS line construction method Active CN112922272B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110124032.2A CN112922272B (en) 2021-01-29 2021-01-29 EPS line construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110124032.2A CN112922272B (en) 2021-01-29 2021-01-29 EPS line construction method

Publications (2)

Publication Number Publication Date
CN112922272A true CN112922272A (en) 2021-06-08
CN112922272B CN112922272B (en) 2022-10-28

Family

ID=76168393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110124032.2A Active CN112922272B (en) 2021-01-29 2021-01-29 EPS line construction method

Country Status (1)

Country Link
CN (1) CN112922272B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114704116A (en) * 2022-04-20 2022-07-05 上海天补材料科技有限公司 GRC decorative line repairing and reinforcing method
CN115059299A (en) * 2022-06-01 2022-09-16 上海宝冶集团有限公司 Construction method of EPS (expandable polystyrene) line decorative column

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03194065A (en) * 1989-12-21 1991-08-23 Mitsubishi Materials Corp Repair method for concrete structure
CN101328053A (en) * 2007-06-22 2008-12-24 上海宝元化学建材有限公司 Epoxy cement-based adhesive and preparation thereof
CN102535733A (en) * 2012-01-16 2012-07-04 上海富春建业科技股份有限公司 Method for repairing autoclaved aerated concrete defected sheet material
CN104652786A (en) * 2015-01-27 2015-05-27 安徽同济建设集团有限责任公司 Fire-retardant expanded polyphenyl board molding construction method for external wall of building
CN205399965U (en) * 2016-03-11 2016-07-27 周海亮 EPS finished product moulding joint treatment node construction
CN106759975A (en) * 2016-12-05 2017-05-31 青岛天源伟业保温防水工程有限公司 A kind of construction method of EPS wall thermal insulation structures
CN108999402A (en) * 2018-09-25 2018-12-14 肖霞 A kind of plastering treatment process based on large-scale EPS lines

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03194065A (en) * 1989-12-21 1991-08-23 Mitsubishi Materials Corp Repair method for concrete structure
CN101328053A (en) * 2007-06-22 2008-12-24 上海宝元化学建材有限公司 Epoxy cement-based adhesive and preparation thereof
CN102535733A (en) * 2012-01-16 2012-07-04 上海富春建业科技股份有限公司 Method for repairing autoclaved aerated concrete defected sheet material
CN104652786A (en) * 2015-01-27 2015-05-27 安徽同济建设集团有限责任公司 Fire-retardant expanded polyphenyl board molding construction method for external wall of building
CN205399965U (en) * 2016-03-11 2016-07-27 周海亮 EPS finished product moulding joint treatment node construction
CN106759975A (en) * 2016-12-05 2017-05-31 青岛天源伟业保温防水工程有限公司 A kind of construction method of EPS wall thermal insulation structures
CN108999402A (en) * 2018-09-25 2018-12-14 肖霞 A kind of plastering treatment process based on large-scale EPS lines

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114704116A (en) * 2022-04-20 2022-07-05 上海天补材料科技有限公司 GRC decorative line repairing and reinforcing method
CN115059299A (en) * 2022-06-01 2022-09-16 上海宝冶集团有限公司 Construction method of EPS (expandable polystyrene) line decorative column

Also Published As

Publication number Publication date
CN112922272B (en) 2022-10-28

Similar Documents

Publication Publication Date Title
WO2021253808A1 (en) Building technique for low-carbon society in high-technology era
CN104018598B (en) A kind of external wall structure and construction installation method
CN101487335B (en) External wall heat-preserving decoration wall and its construction process
CN101831963A (en) Novel multipurpose composite insulation board and construction method and processing device thereof
CN112922272B (en) EPS line construction method
CN101131002A (en) Mould-locking assembled water-proof heat-insulating slab and construction method thereof
CN108589975A (en) Assembling cladding and construction technology
CN108915107B (en) Construction method of EPS inorganic infiltration insulation board
CN112031186A (en) Construction process of graphite modified cement-based insulation board external wall external insulation thin plastering system
GB2516054A (en) Cladding panel, system and methods
KR100512119B1 (en) the construction method of outer wall insulating with insulation board
CN111608280A (en) External wall heat insulation construction method
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN211774781U (en) External wall insulation decorates intergral template construction structures
CN109403520A (en) A kind of viscous anchor combination ceramic thin plate decoration wall and its installation method
CN110878594A (en) Glass wool composite board and external thermal insulation construction process for glass wool composite board external wall
CN110259144A (en) A kind of novel energy-saving environment-friendly ash concrete lightweight wall plate construction method
CN204401809U (en) Surface has the skin insulation layer of simulated decorative effect
CN108518063B (en) Environment-friendly construction method for heat insulation board
CA3177054A1 (en) Systems and methods for adhering cladding
CN207314707U (en) A kind of microcrystal inorganic heat insulation decoration integrated plate
CN216276598U (en) External thermal insulation facility for external wall
CN104481039A (en) Building outer wall heat insulation layer with surface simulation decoration effect and construction technology of building outer wall heat insulation layer
CN111287400A (en) Foamed cement or ceramic decorative component and preparation method and application thereof
CN219343615U (en) Putty composite heat-insulating outer wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: Room 21, Zhongyi film and television building, No. 8, Xiatang Road, Kunshan Development Zone, Suzhou, Jiangsu 215300

Applicant after: China Construction Seventh Engineering Bureau The Second Co.,Ltd.

Address before: 230000 No.51 Datong Road, Yaohai District, Hefei City, Anhui Province

Applicant before: China Construction Seventh Engineering Bureau The Second Co.,Ltd.

GR01 Patent grant