CN112900433A - Construction method of static pressure pipe pile with air lift and bottom cleaning - Google Patents

Construction method of static pressure pipe pile with air lift and bottom cleaning Download PDF

Info

Publication number
CN112900433A
CN112900433A CN202110068277.8A CN202110068277A CN112900433A CN 112900433 A CN112900433 A CN 112900433A CN 202110068277 A CN202110068277 A CN 202110068277A CN 112900433 A CN112900433 A CN 112900433A
Authority
CN
China
Prior art keywords
pile
section
pipe pile
pipe
air supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110068277.8A
Other languages
Chinese (zh)
Other versions
CN112900433B (en
Inventor
祁风志
鲁克涛
连文浩
连世杰
姜庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Geotechnical Engineering Group Co ltd
Shandong Jiaotong University
Original Assignee
East China Geotechnical Engineering Group Co ltd
Shandong Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Geotechnical Engineering Group Co ltd, Shandong Jiaotong University filed Critical East China Geotechnical Engineering Group Co ltd
Priority to CN202110068277.8A priority Critical patent/CN112900433B/en
Publication of CN112900433A publication Critical patent/CN112900433A/en
Application granted granted Critical
Publication of CN112900433B publication Critical patent/CN112900433B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/08Removing obstacles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Cleaning In General (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明涉及桩基施工技术领域,尤其是一种气举清底静压管桩施工方法。该施工方法将第一节管桩利用静力压桩机压至接近承载力时,停止第一节管桩的压入,将振动清孔器插入第一节管桩内部,通过气流将第一节管桩内的沙土吹出第一节管桩,沙土清理至接近桩底时,再次启动静力压桩机边吹孔边同步向下压桩,直至压到第一节管桩压好,停止压入;继续向下送风吹孔,吹至超过桩底1米左右,停止送风,接好第二节管桩,边充气别压桩,压好第二节管桩后继续向下送风吹孔,吹至超过桩底1米左右,停止送风,接好第三节管桩,重复第二节管桩压桩的步骤即可。本发明能够在海边的深厚密实的砂层地质中实现迅速施工,避免振动和噪声,节约气源,确保沉桩稳定性。

Figure 202110068277

The invention relates to the technical field of pile foundation construction, in particular to a construction method of a static pressure pipe pile with a gas lift to clear the bottom. In the construction method, when the first section of the pipe pile is pressed to the bearing capacity by a static pile driver, the pressing of the first section of the pipe pile is stopped, a vibrating hole cleaner is inserted into the first section of the pipe pile, and the first section of the pipe pile is driven by air flow. The sand in the section pipe pile is blown out of the first section of the pipe pile. When the sand and soil is cleaned to the bottom of the pile, start the static pile driver again and blow the hole while simultaneously pressing the pile downward until the first section of the pipe pile is pressed well, then stop. Press in; continue to blow down the air and blow the hole until it exceeds the bottom of the pile by about 1 meter, stop the air supply, connect the second section of the pipe pile, and do not press the pile while inflating, and continue to send down after the second section of the pipe pile is pressed. The wind blows the hole until it exceeds the bottom of the pile by about 1 meter, stops the air supply, connects the third section of the pipe pile, and repeats the steps of the second section of the pipe pile to press the pile. The invention can realize rapid construction in the deep and dense sand layer geology at the seaside, avoid vibration and noise, save air source, and ensure the stability of pile driving.

Figure 202110068277

Description

Construction method of static pressure pipe pile with air lift and bottom cleaning
Technical Field
The invention relates to the technical field of pile foundation construction, in particular to a construction method of a gas lift bottom cleaning static pressure pipe pile.
Background
The static pile pressing method is characterized in that the self weight of a static pile pressing machine and the total weight of a pile frame counterweight are used as reaction forces, a prefabricated pile is pressed into the soil, continuous operation is kept in construction, the pile length can be continuously welded and lengthened, and the requirements of the designed pile length and the bearing capacity are met. In some regions, due to the complex geological composition, obvious layering of miscellaneous fill, medium fine sand, silty clay, fine sand and medium sand and high standard penetration number, the construction efficiency of the regions is low, and even if the bearing capacity of the pile exceeds the design requirement, the requirement of the building design of more than eighteen layers on the ground of the underground layer can not be met.
Chinese patent application CN108625372A discloses a high-pressure flushing gas-lift reverse circulation guide hole pile sinking construction method for a compacted sand layer of a static pressure prestressed pipe pile, which comprises the following steps: (1) putting a pile driver in place, and sinking the prestressed pipe pile at a position where pile driving is needed; (2) putting the high-pressure gas-liquid jet pipe into the pile bottom of the pile pipe of the prestressed pipe pile, opening the high-pressure gas-liquid mixing device to jet high-pressure gas and liquid, and simultaneously putting the high-pressure gas-liquid jet pipe down until the high-pressure gas-liquid jet pipe penetrates through a compact sand layer; (3) and continuing sinking the pile until the design depth. High-pressure gas and liquid are output through the high-pressure gas and liquid jet pipe, impact cutting is carried out on a compact sand layer at the pile bottom position of the pile pipe, negative pressure is generated in the pile pipe to form gas lift reverse circulation, the high-pressure gas and liquid jet pipe ejects the pile pipe from the gap between the high-pressure gas and liquid jet pipe and the pile pipe, sand is carried to return to the ground, and pile sinking benefits of the prestressed pipe pile are greatly improved.
This patent technique mainly relies on the impact of rivers air current mixture to realize the clear hole limit in limit and presses the stake, and rivers and air current consumption are great, and if in the regional construction that is close to the sea level, groundwater is the sea water, and corrosivity is big, and the damage that rivers impact led to the fact the ground is big, influences the stability of pile sinking, and vibration and noise in the work progress also can influence resident on every side.
Disclosure of Invention
The invention aims to provide a construction method of a gas lift bottom cleaning static pressure pipe pile, which overcomes the defects of the prior art, can realize rapid construction in deep and dense sand layer geology at sea edge, avoids vibration and noise in the construction process, saves air source, does not damage a foundation and ensures pile sinking stability.
The technical scheme adopted by the invention for solving the technical problems is as follows:
a construction method of a gas lift bottom cleaning static pressure pipe pile comprises the following steps:
(1) measuring and positioning, determining the positions of a static pile press and a tubular pile, positioning the static pile press, hoisting a first section of tubular pile by using a crane, hoisting the first section of tubular pile into the static pile press, and aligning the first section of tubular pile;
(2) when the first section of tubular pile is pressed to be close to the bearing capacity by using a static pile pressing machine, stopping pressing the first section of tubular pile, wherein the first section of tubular pile is mainly pressed into a miscellaneous fill layer in the pile pressing process; the method is characterized in that a vibration hole cleaner is communicated with an air compressor through a hose, the vibration hole cleaner is inserted into a first section of tubular pile through a crane, sand in the first section of tubular pile is blown out of the first section of tubular pile through the cooperation of the air compressor and the vibration hole cleaner, only hole cleaning and pile pressing are carried out in the process, the hole cleaning efficiency is high, when the sand is cleaned to be close to the bottom of the tubular pile, a static pile press is started again, the pile is pressed downwards synchronously while hole blowing is carried out, and pressing is stopped until the first section of tubular pile is pressed to be connected with a second section of tubular pile, so that the pressing efficiency can be improved, and the first section of tubular pile can be protected from being damaged;
(3) continuing to blow air downwards to blow holes until the air is blown to a position 0.8-1.5 m above the pile bottom, stopping blowing air, lifting the vibration hole cleaner out of the first section of tubular pile through a crane, and blowing holes before installing a second section of tubular pile, so that hole blowing operation is more convenient, the pressing-in efficiency of the subsequent second section of tubular pile can be effectively improved, and the second section of tubular pile is protected from being damaged in the pressing-in process;
(4) connecting a second section of tubular pile to a first section of tubular pile, performing cooling and anticorrosion treatment, inserting a vibration hole cleaner into the second section of tubular pile and the first section of tubular pile through a crane, punching while performing pile pressing operation through the matching of an air compressor and the vibration hole cleaner until the second section of tubular pile is pressed to be connected with a third section of tubular pile, stopping pressing, vibrating while the vibration hole cleaner punches sandy soil upwards along the inner walls of the second section of tubular pile and the first section of tubular pile through air flow impact, improving the pile pressing efficiency, avoiding the bearing capacity of the tubular pile exceeding the design requirement and forming a good protection effect on the tubular pile;
(5) continuing to blow air downwards to blow holes until the air is blown to be 0.8-1.5 m above the pile bottom, stopping blowing air, lifting out the vibration hole cleaner by a crane, and continuing to blow the holes downwards before the third section of tubular pile is installed, so that the hole blowing operation is more convenient, the pressing-in efficiency of the subsequent third section of tubular pile can be effectively improved, and the third section of tubular pile is protected from being damaged in the pressing-in process;
(6) connecting a third section of tubular pile to a second section of tubular pile, performing cooling and anticorrosion treatment, inserting a vibration hole cleaner into the third section of tubular pile, the second section of tubular pile and the first section of tubular pile through a crane, punching while performing pile pressing operation through the matching of an air compressor and the vibration hole cleaner, hoisting the third section of tubular pile out of the vibration hole cleaner through the crane after the third section of tubular pile is pressed, and conveying the third section of tubular pile to a designed depth through a pile conveyor; the vibration hole cleaner can upwards wash out sand along the inner walls of the third section of tubular pile, the second section of tubular pile and the first section of tubular pile by air flow impact while vibrating, so that the pile pressing efficiency is improved, the bearing capacity of the tubular pile is prevented from exceeding the design requirement, and a good protection effect is formed on the tubular pile.
Furthermore, the vibrating hole cleaner comprises a plurality of blast pipes and a vibrator arranged on the uppermost blast pipe, the blast pipes are sequentially connected from top to bottom, the lower end of the lowermost blast pipe is provided with a conical closing-in, and the tail end of the closing-in is a side opening; air compressor passes through the hose with high-pressure draught and transmits to the blast pipe, the blast pipe is at first section tubular pile under the effect of vibrator, second section tubular pile, the interior side vibration limit blowout high-pressure draught of third section tubular pile, strike the inside sand and soil of tubular pile, upwards rush out sand and soil along the inner wall of second section tubular pile and first section tubular pile, and supplementary static air compressor machine carries out the piling operation, the efficiency of piling has not only been improved, and effectively avoid the tubular pile bearing capacity to exceed the design requirement, form good guard action to the tubular pile.
Furthermore, the diameter of the closed tail end of the air supply pipe positioned at the lowest end is 0.6-0.7 times of the diameter of the air supply pipe; the air supply pipe at the lowest end can be inserted into silt and clay in a pile hole, the pipe is not easy to block, the insertion force is large, and the footage speed is high by matching with a vibrator.
Further, the length of the vibration hole cleaner in the step (2) is matched with the length of the first section of tubular pile; the vibration hole cleaner in the step (4) is additionally connected with an air supply pipe on the basis of the vibration hole cleaner in the step (2) and is matched with the total length of the first section of tubular pile and the second section of tubular pile; and (4) adding an air supply pipe on the vibration hole cleaner in the step (6) on the basis of the vibration hole cleaner in the step (4), and matching the total length of the first section of tubular pile, the second section of tubular pile and the third section of tubular pile.
Further, the inner diameter of the main body of the blast pipe is 0.08-0.3 times of the inner diameter of the first section of tubular pile, the second section of tubular pile or the third section of tubular pile; the blast pipe is matched with the vibrator to be used in the range, and the hole cleaning effect formed by air flow impact is better.
Furthermore, the pipe wall of each blast pipe is provided with a circle of upward-inclined vent holes, part of gas is flushed out from the vent holes towards the inclined upper part, and sandy soil flushed up by the blast pipe at the lowest end is assisted to be discharged outwards.
Furthermore, the diameter of the vent hole is 0.02-0.08 times of the inner diameter of the main body of the blast pipe, the pressure of the impact airflow formed by the vent hole is large in the range, and the impact force of the blast pipe at the lowest end on the sand in the pile hole is not influenced.
The invention has the beneficial effects that: compared with the prior art, the construction method of the gas lift bottom cleaning static pressure pipe pile has the following advantages: can be under various geological rings construction, especially also can realize constructing rapidly in the deep and closely knit sand layer geology of seashore, avoid vibration and noise in the work progress, practice thrift the air supply, guarantee pile sinking stability, air compressor passes through the hose with high-pressure draught and transmits to the blast pipe, the blast pipe is at first section tubular pile under the effect of vibrator, second section tubular pile, the interior side vibration limit blowout high-pressure draught of third section tubular pile, strike the inside sand and soil of tubular pile, upwards rush out sand and soil along the inner wall of second section tubular pile and first section tubular pile, and supplementary static compressor machine carries out the pile pressing operation, the efficiency of pile pressing has not only been improved, and effectively avoid the tubular pile bearing capacity to exceed the designing requirement, form good guard action to the tubular pile.
Drawings
FIG. 1 is a schematic structural view of a vibratory hole cleaner of the present invention;
wherein, 1 blast pipe, 2 vibrators, 3 closing-in ports, 4 side openings and 5 hoses.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention.
Example 1
Item address: is positioned near West Lu 360 of Wenhai city, circui district culture;
the surrounding environment of the project: a Weigao ocean hall is arranged on the west side of the project, a residential building is arranged on the south side, and the sea is close to the north side within 100 m;
project geological conditions: according to geological reports, soil layers comprise miscellaneous fill, medium fine sand, silty clay and medium fine sand, wherein the silty clay and the fine sand have high medium sand content and high standard penetration number;
the project requirement is as follows: the building design is 1 layer underground and 18 layers above the ground;
the project requirement is as follows: the influence of vibration and noise disturbing residents is avoided;
project scheme planning: the original scheme considers long spiral piles, long spiral guide holes, CFG (cement fly-ash gravel), extruded and expanded piles, hammered piles, water flushing methods (underground water is seawater and has high corrosivity), ramming and expanding methods, bored piles, rotary excavating and cast-in-place pile methods and the like, and all the methods cannot meet the design requirements through field surveying.
The construction method for the static pressure pipe pile by adopting the gas lift bottom cleaning finally comprises the following steps:
(1) measuring and positioning, determining the positions of a static pile press and a tubular pile, positioning the static pile press, hoisting a first section of tubular pile by using a crane, hoisting the first section of tubular pile into the static pile press, and aligning the first section of tubular pile;
(2) when the first section of tubular pile is pressed to be close to the bearing capacity by using a static pile pressing machine, stopping pressing the first section of tubular pile, wherein the first section of tubular pile is mainly pressed into a miscellaneous fill layer in the pile pressing process; the method is characterized in that a vibration hole cleaner is communicated with an air compressor through a hose, the vibration hole cleaner is inserted into a first section of tubular pile through a crane, sand in the first section of tubular pile is blown out of the first section of tubular pile through the cooperation of the air compressor and the vibration hole cleaner, only hole cleaning and pile pressing are carried out in the process, the hole cleaning efficiency is high, when the sand is cleaned to be close to the bottom of the tubular pile, a static pile press is started again, the pile is pressed downwards synchronously while hole blowing is carried out, and pressing is stopped until the first section of tubular pile is pressed to be connected with a second section of tubular pile, so that the pressing efficiency can be improved, and the first section of tubular pile can be protected from being damaged;
(3) continuing to supply air and blow holes downwards until the air is blown to about 1 m above the pile bottom, stopping supplying air, lifting the vibration hole cleaner out of the first section of tubular pile through a crane, blowing holes before installing a second section of tubular pile, and thus, the hole blowing operation is more convenient, the pressing-in efficiency of the subsequent second section of tubular pile can be effectively improved, and the second section of tubular pile is protected from being damaged in the pressing-in process;
(4) connecting a second section of tubular pile to a first section of tubular pile, performing cooling and anticorrosion treatment, inserting a vibration hole cleaner into the second section of tubular pile and the first section of tubular pile through a crane, punching while performing pile pressing operation through the matching of an air compressor and the vibration hole cleaner until the second section of tubular pile is pressed to be connected with a third section of tubular pile, stopping pressing, vibrating while the vibration hole cleaner punches sandy soil upwards along the inner walls of the second section of tubular pile and the first section of tubular pile through air flow impact, improving the pile pressing efficiency, avoiding the bearing capacity of the tubular pile exceeding the design requirement and forming a good protection effect on the tubular pile;
(5) the hole blowing is continuously carried out by downward air supply until the air blowing exceeds about 1 m of the bottom of the pile, the air supply is stopped, the vibration hole cleaner is lifted out by a crane, the hole blowing is continuously carried out before the third section of tubular pile is installed, the hole blowing operation is more convenient, the press-in efficiency of the subsequent third section of tubular pile can be effectively improved, and the third section of tubular pile is protected from being damaged in the press-in process;
(6) connecting a third section of tubular pile to a second section of tubular pile, performing cooling and anticorrosion treatment, inserting a vibration hole cleaner into the third section of tubular pile, the second section of tubular pile and the first section of tubular pile through a crane, punching while performing pile pressing operation through the matching of an air compressor and the vibration hole cleaner, hoisting the third section of tubular pile out of the vibration hole cleaner through the crane after the third section of tubular pile is pressed, and conveying the third section of tubular pile to a designed depth through a pile conveyor; the vibration hole cleaner can upwards wash out sand along the inner walls of the third section of tubular pile, the second section of tubular pile and the first section of tubular pile by air flow impact while vibrating, so that the pile pressing efficiency is improved, the bearing capacity of the tubular pile is prevented from exceeding the design requirement, and a good protection effect is formed on the tubular pile.
In this embodiment, as shown in fig. 1, the vibrating hole cleaner includes a plurality of blast pipes 1 and a vibrator 2 disposed on the blast pipe 1 located at the uppermost end, the blast pipes 1 are sequentially connected from top to bottom, a tapered closing-in 3 is disposed at the lower end of the blast pipe 1 located at the lowermost end, and the tail end of the closing-in is a side opening 4; air compressor passes through hose 5 with high-pressure draught and transmits to blast pipe 1, blast pipe 1 is at first section tubular pile under the effect of vibrator 2, second section tubular pile, the interior side vibration limit blowout high-pressure draught of third section tubular pile, strike the inside sand and soil of tubular pile, upwards rush out sand and soil along the inner wall of second section tubular pile and first section tubular pile, and supplementary static air compressor machine carries out the pile pressing operation, the efficiency of pile pressing has not only been improved, and effectively avoid the tubular pile bearing capacity to exceed the design requirement, form good guard action to the tubular pile. The diameter of the tail end of the closing-in 3 of the air supply pipe 1 positioned at the lowest end is 0.6-0.7 time of the diameter of the air supply pipe 1; the air supply pipe 1 at the lowest end can be inserted into sediment and clay in a pile hole conveniently, the pipe is not easy to block, the insertion force is large, and the footage speed is high by matching with the vibrator 2.
In this embodiment, the length of the vibrating hole cleaner in the step (2) is matched with the length of the first section of tubular pile; the vibration hole cleaner in the step (4) is additionally connected with an air supply pipe 1 on the basis of the vibration hole cleaner in the step (2), and is matched with the total length of the first section of tubular pile and the second section of tubular pile; and (3) the vibration hole cleaner in the step (6) is additionally connected with the blast pipe 1 on the basis of the vibration hole cleaner in the step (4) and is matched with the total length of the first section of tubular pile, the second section of tubular pile and the third section of tubular pile.
In this embodiment, the inner diameter of the main body of the air supply pipe 1 is 0.22 times of the inner diameter of the first section of tubular pile, the second section of tubular pile or the third section of tubular pile; in the range, the blast pipe 1 is matched with the vibrator 2 for use, and the hole cleaning effect formed by air flow impact is better.
In this embodiment, a circle of upward-inclined vent holes are formed in the wall of each air supply pipe 1, part of air is flushed out from the vent holes obliquely upwards, and sandy soil flushed up by the air supply pipe 1 at the lowest end is assisted to be discharged outwards.
In this embodiment, the diameter of the vent hole is 0.05 times the inner diameter of the main body of the blast pipe 1, and the impact airflow pressure formed by the vent hole is large in this range, and the impact force of the blast pipe 1 at the lowermost end on the sand in the pile hole is not affected.
The construction method in the embodiment only consumes one third of the time of the existing construction method of the pile pressing of the common static pile pressing machine.
The above embodiments are only specific examples of the present invention, and the protection scope of the present invention includes but is not limited to the product forms and styles of the above embodiments, and any suitable changes or modifications made by those skilled in the art according to the claims of the present invention shall fall within the protection scope of the present invention.

Claims (7)

1.一种气举清底静压管桩施工方法,其特征在于:包括如下步骤:1. a construction method for static pressure pipe piles with gas lift clearing the bottom, is characterized in that: comprise the steps: (1)测量定位,确定静力压桩机和管桩的位置,静力压桩机就位,使用起重机起吊第一节管桩,将第一节管桩吊入静力压桩机中,调正第一节管桩;(1) Measure the positioning, determine the position of the static pile driver and the pipe pile, the static pile driver is in place, use a crane to lift the first section of the pipe pile, and hoist the first section of the pipe pile into the static pile driver, Adjust the first section of the pipe pile; (2)将第一节管桩利用静力压桩机压至接近承载力的时候,停止第一节管桩的压入,将振动清孔器通过软管与空气压缩机连通,通过起重机将振动清孔器插入第一节管桩内部,通过空气压缩机和振动清孔器的配合将第一节管桩内的沙土吹出第一节管桩,沙土清理至接近桩底时,再次启动静力压桩机边吹孔边同步向下压桩,直至压到第一节管桩准备接第二节管桩时,停止压入;(2) When the first section of the pipe pile is pressed to the bearing capacity by the static pile driver, stop the pressing of the first section of the pipe pile, connect the vibrating hole cleaner to the air compressor through the hose, and use the crane to The vibrating hole cleaner is inserted into the first section of the pipe pile, and the sand in the first section of the pipe pile is blown out of the first section of the pipe pile through the cooperation of the air compressor and the vibrating hole cleaner. The force pile driver presses the pile downwards simultaneously while blowing the hole, until the first section of the pipe pile is ready to be connected to the second section of the pipe pile, and then stops pressing; (3)继续向下送风吹孔,吹至超过桩底0.8-1.5米时,停止送风,通过起重机从第一节管桩中吊出振动清孔器;(3) Continue to blow down the air blowing holes, when the blowing exceeds 0.8-1.5 meters from the bottom of the pile, stop the air supply, and lift the vibrating hole cleaner from the first section of the pipe pile by a crane; (4)将第二节管桩接到第一节管桩上,做降温、防腐处理,通过起重机将振动清孔器插入第二节管桩和第一节管桩的内部,通过空气压缩机和振动清孔器的配合边冲孔边进行压桩操作,直至压到第二节管桩准备接第三节管桩时,停止压入;(4) Connect the second section of pipe piles to the first section of pipe piles, do cooling and anti-corrosion treatment, insert the vibrating hole cleaner into the second section of pipe piles and the first section of pipe piles through a crane, and pass the air compressor In cooperation with the vibrating hole cleaner, carry out the pile pressing operation while punching holes, until the second section of the pipe pile is pressed and ready to be connected to the third section of the pipe pile, stop pressing; (5)继续向下送风吹孔,吹至超过桩底0.8-1.5米时,停止送风,通过起重机吊出振动清孔器;(5) Continue to blow down the air blowing holes, when the blowing exceeds the bottom of the pile by 0.8-1.5 meters, stop the air supply, and lift the vibrating hole cleaner by the crane; (6)将第三节管桩接到第二节管桩上,做降温、防腐处理,通过起重机将振动清孔器插入第三节管桩、第二节管桩和第一节管桩的内部,通过空气压缩机和振动清孔器的配合边冲孔边进行压桩操作,第三节管桩压好后通过起重机吊出振动清孔器,通过送桩器将第三节管桩送桩至设计深度,即可。(6) Connect the third section of the pipe pile to the second section of the pipe pile, do cooling and anti-corrosion treatment, and insert the vibrating hole cleaner into the third section of the pipe pile, the second section of the pipe pile and the first section of the pipe pile through the crane. Inside, through the cooperation of the air compressor and the vibrating hole cleaner, the pile pressing operation is performed while punching. Pile to the design depth, you can. 2.根据权利要求1所述的一种气举清底静压管桩施工方法,其特征在于:所述振动清孔器包括多条送风管和设置于位于最上端的送风管上的振动器,所述送风管由上至下依次连接,位于最下端的送风管的下端设置有锥形的收口,且收口末端为侧开口。2. the construction method of a kind of gas lift bottom-cleaning static pressure pipe pile according to claim 1, is characterized in that: described vibrating hole cleaner comprises a plurality of air supply pipes and the vibration that is arranged on the air supply pipe that is positioned at the uppermost end The air supply pipes are connected in sequence from top to bottom, the lower end of the air supply pipe located at the lowermost end is provided with a conical closing, and the end of the closing is a side opening. 3.根据权利要求2所述的一种气举清底静压管桩施工方法,其特征在于:所述位于最下端的送风管的收口末端的直径为送风管直径的0.6-0.7倍。3. The construction method of a gas lift bottom-clearing static pressure pipe pile according to claim 2, characterized in that: the diameter of the closing end of the air supply pipe located at the lowermost end is 0.6-0.7 times the diameter of the air supply pipe . 4.根据权利要求2所述的一种气举清底静压管桩施工方法,其特征在于:所述步骤(2)中的振动清孔器的长度与第一节管桩的长度相配合;所述步骤(4)中的振动清孔器在步骤(2)中的振动清孔器的基础上加接送风管,并与第一节管桩和第二节管桩的总长度相配合;所述步骤(6)中的振动清孔器在步骤(4)中的振动清孔器的基础上加接送风管,并与第一节管桩、第二节管桩和第三节管桩的总长度相配合。4. the construction method of a kind of gas lift bottom-cleaning static pressure pipe pile according to claim 2 is characterized in that: the length of the vibrating hole cleaner in the described step (2) is matched with the length of the first section of pipe pile ; The vibrating hole cleaner in the step (4) adds the air delivery pipe on the basis of the vibrating hole cleaner in the step (2), and is matched with the total length of the first section of the pipe pile and the second section of the pipe pile ; The vibrating hole cleaner in the step (6) adds the air delivery pipe on the basis of the vibrating hole cleaner in the step (4), and the first pipe pile, the second pipe pile and the third pipe Match the overall length of the pile. 5.根据权利要求2所述的一种气举清底静压管桩施工方法,其特征在于:所述送风管的主体的内径为第一节管桩或第二节管桩或第三节管桩内径的0.08-0.3倍。5 . The construction method of a gas lift bottom-clearing static pressure pipe pile according to claim 2 , wherein the inner diameter of the main body of the air supply pipe is the first pipe pile or the second pipe pile or the third pipe pile. 6 . 0.08-0.3 times the inner diameter of the pipe pile. 6.根据权利要求2所述的一种气举清底静压管桩施工方法,其特征在于:每一条送风管的管壁上均设置有一圈上倾的通气孔。6 . The construction method of a gas lift bottom-clearing static pressure pipe pile according to claim 2 , wherein the pipe wall of each air supply pipe is provided with a circle of upwardly inclined ventilation holes. 7 . 7.根据权利要求6所述的一种气举清底静压管桩施工方法,其特征在于:所述通气孔的直径为送风管的主体的内径的0.02-0.08倍。7 . The construction method of a gas lift bottom-clearing static pressure pipe pile according to claim 6 , wherein the diameter of the ventilation hole is 0.02-0.08 times the inner diameter of the main body of the air supply pipe. 8 .
CN202110068277.8A 2021-01-19 2021-01-19 Construction method of static pressure pipe pile with air lift and bottom cleaning Active CN112900433B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110068277.8A CN112900433B (en) 2021-01-19 2021-01-19 Construction method of static pressure pipe pile with air lift and bottom cleaning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110068277.8A CN112900433B (en) 2021-01-19 2021-01-19 Construction method of static pressure pipe pile with air lift and bottom cleaning

Publications (2)

Publication Number Publication Date
CN112900433A true CN112900433A (en) 2021-06-04
CN112900433B CN112900433B (en) 2022-05-03

Family

ID=76115498

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110068277.8A Active CN112900433B (en) 2021-01-19 2021-01-19 Construction method of static pressure pipe pile with air lift and bottom cleaning

Country Status (1)

Country Link
CN (1) CN112900433B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4575282A (en) * 1984-06-04 1986-03-11 Pardue Sr James H System for driving open end pipe piles on the ocean floor using pneumatic evacuation and existing hydrostatic pressure
CN2915943Y (en) * 2006-06-02 2007-06-27 福州林立岩土技术咨询有限公司 Device for facilitating holding type pipe pile tip in rock by self-drilling static pressure technology
CN101319500A (en) * 2008-07-21 2008-12-10 中铁七局集团第三工程有限公司 Construction method of static pressure compaction pile
CN108625372A (en) * 2018-05-17 2018-10-09 深圳市工勘岩土集团有限公司 Static-pressure prestressed drilled pile dense sand stratum high-pressure flush gas lift reverse circulation pilot hole pile sinking construction method
DE102019104292A1 (en) * 2019-02-20 2020-08-20 Innogy Se Vibration of foundations

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4575282A (en) * 1984-06-04 1986-03-11 Pardue Sr James H System for driving open end pipe piles on the ocean floor using pneumatic evacuation and existing hydrostatic pressure
CN2915943Y (en) * 2006-06-02 2007-06-27 福州林立岩土技术咨询有限公司 Device for facilitating holding type pipe pile tip in rock by self-drilling static pressure technology
CN101319500A (en) * 2008-07-21 2008-12-10 中铁七局集团第三工程有限公司 Construction method of static pressure compaction pile
CN108625372A (en) * 2018-05-17 2018-10-09 深圳市工勘岩土集团有限公司 Static-pressure prestressed drilled pile dense sand stratum high-pressure flush gas lift reverse circulation pilot hole pile sinking construction method
DE102019104292A1 (en) * 2019-02-20 2020-08-20 Innogy Se Vibration of foundations

Also Published As

Publication number Publication date
CN112900433B (en) 2022-05-03

Similar Documents

Publication Publication Date Title
CN102383431B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
CN105442532B (en) Pile crown expands bored pile construction method
CN110158582A (en) A method of trestle steel pipe pile is set on intectate riverbed
JPS626024A (en) Method and apparatus for inserting casing so as to pierce weak ground or structure
CN106761474A (en) A kind of the full-sleeve engineering method steel sleeve and its construction method of the soil that can actively muck haulage
CN112030956A (en) Karst stratum bored pile construction method
CN110984133A (en) Construction method for foundation of deep-water shallow-covering-layer trestle
CN111576423A (en) Pile foundation sediment cleaning device and method
CN104746519A (en) Obstacle clearing construction method
CN113323584B (en) Drilling method of large-scale vibration long spiral drilling machine
CN2915943Y (en) Device for facilitating holding type pipe pile tip in rock by self-drilling static pressure technology
CN110685603A (en) An offshore large-diameter steel pipe rock-socketed pile construction platform and construction method
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam
CN111456055A (en) Foundation pit dewatering construction method
KR20090115702A (en) Ground Excavation Method for Construction of Large Diameter Foundation Piles
CN106930274B (en) A construction method of a full-sleeve rotary bored cast-in-place pile with a fixed steel cage position
CN112900433A (en) Construction method of static pressure pipe pile with air lift and bottom cleaning
CN206090541U (en) Impact holing's construction equipment
CN102758434B (en) Middle pick prestressed centrifugally pile tube pile-sinking device and pile sinking method thereof
KR101337223B1 (en) Apparatus Equipped with Double Casing for Inserting Plastic Drain Board and Process thereof
CN116716879A (en) An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed
CN109113054A (en) A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method
CN103615000A (en) Construction device of original-state earth-borrowing cast-in-place pile
CN210141098U (en) High-pressure jet grouting pile matching power device
CN109853532B (en) Ultrasonic disturbance wall-protection slurry sediment cleaning device and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant