CN116716879A - An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed - Google Patents
An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed Download PDFInfo
- Publication number
- CN116716879A CN116716879A CN202310601568.8A CN202310601568A CN116716879A CN 116716879 A CN116716879 A CN 116716879A CN 202310601568 A CN202310601568 A CN 202310601568A CN 116716879 A CN116716879 A CN 116716879A
- Authority
- CN
- China
- Prior art keywords
- casing
- hole
- outer casing
- inner casing
- hard rock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000011435 rock Substances 0.000 title claims abstract description 46
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 238000004080 punching Methods 0.000 claims abstract description 22
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 18
- 229910000831 Steel Inorganic materials 0.000 claims description 22
- 239000010959 steel Substances 0.000 claims description 22
- 238000005553 drilling Methods 0.000 claims description 19
- 238000000034 method Methods 0.000 claims description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 7
- 239000004576 sand Substances 0.000 claims description 6
- 239000002893 slag Substances 0.000 claims description 5
- 239000013049 sediment Substances 0.000 claims description 4
- 238000007789 sealing Methods 0.000 claims description 3
- 238000001514 detection method Methods 0.000 claims 1
- 239000004744 fabric Substances 0.000 claims 1
- 230000015572 biosynthetic process Effects 0.000 abstract description 2
- 239000010410 layer Substances 0.000 description 37
- 230000000694 effects Effects 0.000 description 4
- 239000004927 clay Substances 0.000 description 3
- 238000005422 blasting Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 230000035508 accumulation Effects 0.000 description 1
- 238000009825 accumulation Methods 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000009933 burial Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 238000009527 percussion Methods 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/04—Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
- E02D15/06—Placing concrete under water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种适用于具有硬岩层海床的水下双护筒灌注桩施工方法,属于灌注桩技术领域,包括以下步骤:S1、吊放外护筒,采用冲孔打桩机钻设出供外护筒自然下沉至硬岩层上的外护筒孔,对外护筒孔进行扩孔,在扩孔内对外护筒进行支护和封堵;S2、将内护筒吊放至外护筒内,采用冲孔打桩机钻设出深度为0.5m~1m的内护筒孔,对内护筒进行支护和封堵;S3、采用潜孔钻钻设出锚杆孔并下放锚杆;S4、向内护筒内灌注混凝土砂浆,待混凝土砂浆达到预设强度后,撤出内护筒和外护筒之间的支护,向内护筒和外护筒之间灌入混凝土砂浆。避免对冲孔打桩机的桩锤造成“咬边”和“爆锤”的同时,利用锚杆确保桩基的承载能力及稳定性,加快施工进度,大大减少了成孔成本。
The invention discloses a construction method for underwater double-casing cast-in-place piles suitable for seabeds with hard rock layers. It belongs to the technical field of cast-in-place piles and includes the following steps: S1. Hang the outer casing, and use a punching pile driver to drill out the cast-in-place piles. Allow the outer casing to naturally sink to the outer casing hole on the hard rock layer, expand the outer casing hole, and support and seal the outer casing in the expanded hole; S2. Hoist the inner casing to the outer casing hole. In the barrel, a punching pile driver is used to drill an inner casing hole with a depth of 0.5m~1m, and the inner casing is supported and blocked; S3. A down-the-hole drill is used to drill the anchor hole and lower the anchor rod. ;S4. Pour concrete mortar into the inner casing. After the concrete mortar reaches the preset strength, withdraw the support between the inner casing and the outer casing, and pour concrete mortar between the inner casing and the outer casing. . While avoiding "undercut" and "burst" caused by the pile hammer of the punching pile driver, anchor rods are used to ensure the load-bearing capacity and stability of the pile foundation, speed up the construction progress, and greatly reduce the cost of hole formation.
Description
技术领域Technical field
本发明涉及灌注桩技术领域,特别是涉及一种适用于具有硬岩层海床的水下双护筒灌注桩施工方法。The present invention relates to the technical field of cast-in-place piles, and in particular to a construction method of underwater double-casing cast-in-place piles suitable for seabeds with hard rock layers.
背景技术Background technique
在复杂海域进行水下双护筒灌注桩的施工过程中,多采用冲孔打桩机进行钻进作业打出桩孔,并布置不同埋深的内外钢护筒,然后再向桩孔内灌注混凝土至预定高度,待混凝土凝固后形成双护筒灌注桩,双护筒灌注桩可克服钢护筒在高强度裸岩或斜岩海床上埋设时常出现的钢护筒底口卷边、筒底口漏浆、护筒滑移等问题。但由于复杂海域的特殊性及复杂性,水下基岩存在复杂覆盖层,上覆层多为泥沙等松散堆积物或沉积物,下覆层则多为硬岩,如专利号为“201910087227.7”,所公开的“灌注桩双护筒施工工艺”中便公开了使用桩锤穿过砂浆层继续钻进,直至在硬岩层上钻出孔。当冲击钻机进行钻进作业至硬岩层时,由于硬岩较为坚硬,随着钻进深入,很容易造成钻头的损坏,继而严重延长工期进而增加时间及经济成本。During the construction of underwater double-casing cast-in-place piles in complex sea areas, punching pile drivers are often used to drill pile holes, and internal and external steel casings with different burial depths are arranged, and then concrete is poured into the pile holes to Predetermined height, after the concrete solidifies, a double-casing cast-in-place pile is formed. The double-casing cast-in-place pile can overcome the problems of steel casing bottom opening curling and drum bottom opening leakage that often occur when steel casings are buried on high-strength bare rock or inclined rock seabed. Problems such as slurry and casing slippage. However, due to the particularity and complexity of complex sea areas, there are complex covering layers in the underwater bedrock. The upper covering layer is mostly loose accumulations or sediments such as silt, and the lower covering layer is mostly hard rock. For example, the patent number is "201910087227.7 ", the disclosed "Construction Technology of Double Casing Casings for Grouted Piles" discloses the use of a pile hammer to continue drilling through the mortar layer until a hole is drilled in the hard rock layer. When a percussion drill drills into a hard rock layer, because the hard rock is relatively hard, it is easy to cause damage to the drill bit as the drilling goes deeper, which will seriously extend the construction period and increase time and economic costs.
发明内容Contents of the invention
本发明的目的是解决上述技术问题,提供一种适用于具有硬岩层海床的水下双护筒灌注桩施工方法,在传统冲孔打桩机钻孔施工的基础上,引用了潜孔钻施工工艺,避免对冲孔打桩机的桩锤造成“咬边”和“爆锤”等现象的同时,利用锚杆确保桩基的承载能力及稳定性,加快施工进度的同时也大大减少了成孔成本。The purpose of the present invention is to solve the above technical problems and provide a construction method of underwater double-casing cast-in-place piles suitable for seabeds with hard rock layers. On the basis of the traditional punching pile driver drilling construction, the down-the-hole drilling construction is introduced. process to avoid "undercutting" and "blasting hammer" caused by the pile hammer of the punching pile driver. At the same time, anchor rods are used to ensure the load-bearing capacity and stability of the pile foundation, speeding up the construction progress and greatly reducing the cost of hole formation. .
为实现上述目的,本发明提供了如下方案:本发明公开了一种适用于具有硬岩层海床的水下双护筒灌注桩施工方法,包括以下步骤:In order to achieve the above object, the present invention provides the following solution: The present invention discloses a construction method of underwater double casing cast-in-place piles suitable for seabeds with hard rock layers, which includes the following steps:
S1、将外护筒竖向吊放至海床的成桩区域处,在所述成桩区域内采用冲孔打桩机钻设出供所述外护筒自然下沉至硬岩层上的外护筒孔,对所述外护筒孔进行扩孔,在扩孔内对所述外护筒的底端进行支护和封堵;S1. Lift the outer casing vertically to the piling area of the seabed, and use a punching pile driver to drill an outer casing for the outer casing to naturally sink to the hard rock layer in the piling area. Barrel hole, the outer casing hole is expanded, and the bottom end of the outer casing is supported and blocked in the expanded hole;
S2、将内护筒竖向吊放至所述外护筒内,采用所述冲孔打桩机对所述内护筒底部的硬岩层钻设出供所述内护筒自然下沉的内护筒孔,所述内护筒孔深度为0.5m~1m,从所述内护筒和所述外护筒之间对所述内护筒的底端进行支护和封堵;S2. Lift the inner casing vertically into the outer casing, and use the punching pile driver to drill the hard rock layer at the bottom of the inner casing to create an inner protection for the inner casing to sink naturally. Barrel hole, the depth of the inner casing hole is 0.5m~1m, and the bottom end of the inner casing is supported and blocked from between the inner casing and the outer casing;
S3、采用潜孔钻在所述内护筒内的硬岩层、所述内护筒与所述外护筒之间的硬岩层上钻设出锚杆孔并下放锚杆;S3. Use down-the-hole drilling to drill anchor holes on the hard rock layer in the inner casing and between the inner casing and the outer casing and lower the anchor rod;
S4、向所述内护筒内灌注混凝土砂浆,待混凝土砂浆达到预设强度后,撤出所述内护筒和所述外护筒之间的支护,向所述内护筒和所述外护筒之间灌入混凝土砂浆。S4. Pour concrete mortar into the inner casing. After the concrete mortar reaches the preset strength, withdraw the support between the inner casing and the outer casing, and add water to the inner casing and the outer casing. Concrete mortar is poured between the outer casings.
优选地,步骤S1、步骤S2以及步骤S3中,采用空气压缩机送气方式及时清理所述外护筒孔、所述内护筒孔以及所述锚杆孔内的钻渣。Preferably, in step S1, step S2 and step S3, air compressor air supply is used to promptly clean the drilling slag in the outer casing hole, the inner casing hole and the anchor hole.
优选地,步骤S1中,潜水员下水,摸清所述外护筒周边情况,人工对所述外护筒孔进行扩孔和清理。Preferably, in step S1, the diver goes into the water, finds out the surrounding conditions of the outer casing, and manually expands and cleans the outer casing hole.
优选地,步骤S1和S2中,支护和封堵选用堆砌砂袋的方式。Preferably, in steps S1 and S2, stacking sand bags are used for support and sealing.
优选地,步骤S3中,所述内护筒与所述外护筒之间的硬岩层上周向均匀设置四个锚杆孔,所述内护筒内钻设八个锚杆孔,两个所述锚杆孔互为一组,多组所述锚杆孔周向排布。Preferably, in step S3, four anchor holes are evenly arranged in the circumferential direction of the hard rock layer between the inner casing and the outer casing, and eight anchor holes are drilled in the inner casing. The anchor holes are in one group with each other, and multiple groups of the anchor holes are arranged circumferentially.
优选地,采用钢筋探笼检测所述锚杆孔的垂直度和孔径,采用测量绳测量所述锚杆孔的深度和孔底沉渣厚度。Preferably, a steel cage is used to detect the verticality and hole diameter of the anchor hole, and a measuring rope is used to measure the depth of the anchor hole and the thickness of the sediment at the bottom of the hole.
优选地,步骤S1之前还包括步骤S0,搭设钢平台,在钢平台上设置十字控制网、基准点,标出与所述成桩区域处相对应的孔位,然后对钢平台上的所述孔位进行切割形成钢护筒下放孔,在钢平台上安装护筒定位架。Preferably, step S1 also includes step S0, which is to set up a steel platform, set a cross control net and a reference point on the steel platform, mark the hole positions corresponding to the pile forming area, and then perform the above-mentioned step on the steel platform. The holes are cut to form holes for lowering the steel casing, and the casing positioning frame is installed on the steel platform.
优选地,所述外护筒和所述内护筒之间距离为0.3~0.5m。Preferably, the distance between the outer casing and the inner casing is 0.3~0.5m.
优选地,所述外护筒和所述内护筒之间的同轴度偏差不大于0.05m。Preferably, the coaxiality deviation between the outer casing and the inner casing is not greater than 0.05m.
优选地,所述锚杆孔的深度为0.5~1.0m,直径为0.1m~0.12m。Preferably, the depth of the anchor hole is 0.5~1.0m, and the diameter is 0.1m~0.12m.
本发明相对于现有技术取得了以下技术效果:Compared with the prior art, the present invention achieves the following technical effects:
本发明在传统冲孔打桩机钻孔施工的基础上,引用了潜孔钻施工工艺,冲孔打桩机只需在硬岩层上钻设0.5m~1m浅孔即可,不会对冲孔打桩机造成“咬边”和“爆锤”等现象,剩下由潜孔钻钻出锚杆孔,并下入锚杆确保桩基的承载能力及稳定性,加快施工进度的同时也大大减少了成孔成本。This invention is based on the drilling construction of the traditional punching pile driver, and adopts the down-the-hole drilling construction technology. The punching pile driver only needs to drill a 0.5m~1m shallow hole in the hard rock layer, and will not cause any damage to the punching pile driver. Causes phenomena such as "undercut" and "blasting hammer". The remaining anchor holes are drilled by down-the-hole drills and the anchor rods are lowered to ensure the load-bearing capacity and stability of the pile foundation. This speeds up the construction progress and greatly reduces the cost. hole cost.
附图说明Description of the drawings
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the drawings needed to be used in the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some of the drawings of the present invention. Embodiments, for those of ordinary skill in the art, other drawings can also be obtained based on these drawings without exerting creative efforts.
图1为水下双护筒灌注桩的结构透视图;Figure 1 is a structural perspective view of an underwater double-casing cast-in-place pile;
图2为水下双护筒灌注桩的俯视结构图。Figure 2 is a top structural view of the underwater double-casing cast-in-place pile.
附图标记说明:1、外护筒;2、内护筒;3、锚杆;4、混凝土桩身;5、海平面;6、砂土层;7、黏土层;8、碎岩层;9、砾石层;10、硬岩层;11、混凝土芯;12、砂袋。Explanation of reference signs: 1. Outer casing; 2. Inner casing; 3. Anchor rod; 4. Concrete pile body; 5. Sea level; 6. Sand layer; 7. Clay layer; 8. Crushed rock layer; 9 , Gravel layer; 10. Hard rock layer; 11. Concrete core; 12. Sand bag.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts fall within the scope of protection of the present invention.
本实施例提供了一种适用于具有硬岩层海床的水下双护筒灌注桩施工方法,如图1至图2所示,包括以下步骤:This embodiment provides an underwater double-casing cast-in-place pile construction method suitable for seabeds with hard rock layers. As shown in Figures 1 to 2, it includes the following steps:
S1、将外护筒1竖向吊放至海床的成桩区域处,然后冲孔打桩机的桩锤竖向伸入外护筒1内,在成桩区域内钻设出外护筒孔,外护筒孔由海床表层一直打到硬岩层10上方,在外护筒孔成型后,外护筒1因自身重力可自然下落至外护筒孔内,对外护筒孔进行扩孔,在扩孔内对外护筒1的底端进行支护和封堵;海床表层通常由上到下依次为砂土层6、黏土层7、碎岩层8、砾石层9、硬岩层10,当然也可能仅有黏土层7、碎岩层8、砾石层9、硬岩层10,但无论合种成分,外护筒孔仅需由上到下钻至硬岩层10上表面即可;S1. Lift the outer casing 1 vertically to the piling area of the seabed, then extend the pile hammer of the punching pile driver vertically into the outer casing 1, and drill the outer casing hole in the piling area. The outer casing hole is drilled from the surface of the seabed to the top of the hard rock layer 10. After the outer casing hole is formed, the outer casing 1 can naturally fall into the outer casing hole due to its own gravity, and the outer casing hole is expanded. The bottom end of the outer casing 1 is supported and blocked in the hole; the surface layer of the seabed is usually sand layer 6, clay layer 7, crushed rock layer 8, gravel layer 9, and hard rock layer 10 from top to bottom. Of course, it is also possible There are only clay layer 7, crushed rock layer 8, gravel layer 9, and hard rock layer 10. However, regardless of the seed composition, the outer casing hole only needs to be drilled from top to bottom to the upper surface of the hard rock layer 10;
S2、将内护筒2竖向吊放至外护筒1内,冲孔打桩机更换桩锤后,桩锤伸入内护筒2内,对内护筒2底部的硬岩层10钻设出内护筒孔,内护筒孔深度为0.5m~1m,成孔时内护筒2因自身重力下沉至内护筒孔中,该内护筒孔深度不会造成冲孔打桩机的桩锤损坏,从内护筒2和外护筒1之间对内护筒2的底端进行支护和封堵;S2. Lift the inner casing 2 vertically into the outer casing 1. After the pile hammer is replaced by the punching pile driver, the pile hammer extends into the inner casing 2 and drills out the hard rock layer 10 at the bottom of the inner casing 2. The depth of the inner casing hole is 0.5m~1m. When the hole is formed, the inner casing 2 sinks into the inner casing hole due to its own gravity. The depth of the inner casing hole will not cause the pile punching pile driver to If the hammer is damaged, support and seal the bottom end of the inner casing 2 from between the inner casing 2 and the outer casing 1;
S3、采用潜孔钻在内护筒2内的硬岩层、内护筒2与外护筒1之间的硬岩层上钻设出锚杆孔并下放锚杆3;S3. Use down-the-hole drilling to drill the anchor hole in the hard rock layer inside the inner casing 2 and between the inner casing 2 and the outer casing 1 and lower the anchor rod 3;
S4、向内护筒2内灌注混凝土砂浆,混凝土砂浆会下渗至内护筒2的锚杆孔中,待混凝土砂浆达到预设强度后,撤出内护筒2和外护筒1之间的支护,向内护筒2和外护筒1之间灌入混凝土砂浆,混凝土砂浆会下渗至内护筒2和外护筒1之间的锚杆孔中,内护筒2、内护筒2和外护筒1之间的混凝土砂浆会形成混凝土桩身4,锚杆孔中的混凝土砂浆会形成混凝土芯11,锚杆3可有效保证双护筒灌注桩和硬岩层10的连接稳定性。S4. Pour concrete mortar into the inner casing 2. The concrete mortar will seep down into the anchor hole of the inner casing 2. After the concrete mortar reaches the preset strength, withdraw between the inner casing 2 and the outer casing 1. For support, pour concrete mortar between the inner casing 2 and the outer casing 1. The concrete mortar will penetrate into the anchor hole between the inner casing 2 and the outer casing 1. The concrete mortar between the casing 2 and the outer casing 1 will form the concrete pile body 4, the concrete mortar in the anchor hole will form the concrete core 11, and the anchor 3 can effectively ensure the connection between the double casing cast-in-place pile and the hard rock layer 10 stability.
本实施例中,如图1至图2所示,步骤S1、步骤S2以及步骤S3中,采用空气压缩机送气方式及时清理外护筒孔、内护筒孔以及锚杆孔内的钻渣。In this embodiment, as shown in Figures 1 to 2, in steps S1, S2 and S3, the air compressor air supply method is used to promptly clean the drilling slag in the outer casing hole, the inner casing hole and the anchor hole.
具体的:步骤S1中,冲孔打桩机就位,冲孔打桩机的桩锤伸入外护筒1内冲击海床,在冲击过程中加入少量泥浆,当桩锤至硬岩层10时停止钻进,形成外护筒孔,利用空气压缩机往外护筒孔内的水加入压缩空气,其产生的压强可将渣样从外护筒1口喷出,便可移走冲孔打桩机。Specifically: in step S1, the punching pile driver is in place, the pile hammer of the punching pile driver extends into the outer casing 1 to impact the seabed, a small amount of mud is added during the impact process, and drilling stops when the pile hammer reaches the hard rock layer 10 Then, the outer casing hole is formed, and the air compressor is used to add compressed air to the water in the outer casing hole. The pressure generated can eject the slag sample from the outer casing port 1, and the punching pile driver can be removed.
步骤S2中,冲孔打桩机更换新的桩锤后,冲孔打桩机再次就位,桩锤伸入内护筒2内冲击硬岩层10,形成内护筒孔,利用空气压缩机往内护筒孔内的水加入压缩空气,其产生的压强可将渣样从内护筒2口喷出,便可移走冲孔打桩机。In step S2, after the punching pile driver is replaced with a new pile hammer, the punching pile driver is in position again, and the pile hammer extends into the inner casing 2 to impact the hard rock layer 10 to form an inner casing hole, and the air compressor is used to protect the inner casing. When compressed air is added to the water in the cylinder hole, the pressure generated can eject the slag sample from the inner casing 2, and the punching pile driver can be removed.
步骤S3中,为了保证灌浆效果,采用空气压缩机进行两次清孔,以保证步骤S4中的灌浆质量。In step S3, in order to ensure the grouting effect, an air compressor is used to clean the holes twice to ensure the grouting quality in step S4.
本实施例中,如图1至图2所示,步骤S1中,潜水员下水,摸清外护筒1周边情况,人工对外护筒孔进行扩孔和清理。In this embodiment, as shown in Figures 1 to 2, in step S1, the diver goes into the water, finds out the surrounding conditions of the outer casing 1, and manually expands and cleans the outer casing hole.
进一步,本实施例中,如图1至图2所示,步骤S1和S2中,支护和封堵选用堆砌砂袋12的方式。具体的步骤S1中,在外护筒1底端四周堆砌(或抛投)高的砂袋12,砂袋12堆砌严密并填满外护筒孔,达到堵漏和固定外护筒1的效果。步骤S2中,采用抛投方式,向外护筒1和内护筒2之间抛投砂袋12,砂袋12堆砌严密,达到堵漏和固定内护筒2的效果。Furthermore, in this embodiment, as shown in Figures 1 to 2, in steps S1 and S2, the method of stacking sand bags 12 is used for support and sealing. In specific step S1, high sandbags 12 are piled (or thrown) around the bottom end of the outer casing 1. The sandbags 12 are stacked tightly and fill the outer casing holes to achieve the effect of plugging leaks and fixing the outer casing 1. In step S2, the throwing method is used to throw sandbags 12 between the outer casing 1 and the inner casing 2. The sandbags 12 are stacked tightly to achieve the effect of blocking leakage and fixing the inner casing 2.
本实施例中,如图1至图2所示,步骤S3中,内护筒2与外护筒1之间的硬岩层10上周向均匀设置四个锚杆孔,内护筒2内钻设八个锚杆孔,两个锚杆孔互为一组,多组锚杆孔周向排布。In this embodiment, as shown in Figures 1 to 2, in step S3, four anchor holes are evenly arranged in the circumferential direction of the hard rock layer 10 between the inner casing 2 and the outer casing 1, and the inner casing 2 is drilled Eight anchor holes are provided, two anchor holes form a group with each other, and multiple groups of anchor holes are arranged circumferentially.
本实施例中,如图1至图2所示,采用钢筋探笼检测锚杆孔的垂直度和孔径,采用测量绳测量锚杆孔的深度和孔底沉渣厚度。In this embodiment, as shown in Figures 1 to 2, a steel cage is used to detect the verticality and hole diameter of the anchor hole, and a measuring rope is used to measure the depth of the anchor hole and the thickness of the sediment at the bottom of the hole.
本实施例中,如图1至图2所示,步骤S1之前还包括步骤S0施工准备:搭设钢平台,在钢平台上设置十字控制网、基准点,标出与成桩区域处相对应的孔位,然后对钢平台上的孔位进行切割形成钢护筒下放孔,在钢平台上安装护筒定位架,调整好定位架位置,即可下放外护筒1。做好施工前的准备工作,严格按照相关规范和操作规程,确保施工过程的安全和质量。In this embodiment, as shown in Figures 1 to 2, step S1 also includes step S0 construction preparation: setting up a steel platform, setting a cross control network and reference points on the steel platform, and marking the pile corresponding to the pile area. hole position, and then cut the hole position on the steel platform to form a hole for lowering the steel casing. Install the casing positioning frame on the steel platform. After adjusting the positioning frame, the outer casing 1 can be lowered. Make preparations before construction and strictly follow relevant specifications and operating procedures to ensure the safety and quality of the construction process.
本实施例中,如图1至图2所示,外护筒1和内护筒2之间距离需保证在0.3~0.5m。外护筒1和内护筒2的长度需要实际工程需要设置,但需要保证下沉至外护筒孔内的外护筒1和下沉至内护筒孔内的内护筒2的顶部均位于海平面5以上。外护筒1和内护筒2之间的长度差通常在0.5m~1m之间,以在内护筒2下沉至内护筒孔内后,外护筒1和内护筒2的顶面平齐。混凝土砂浆灌注时需灌注至内护筒2的顶面。外护筒1和内护筒2一般均采用钢护筒。In this embodiment, as shown in Figures 1 to 2, the distance between the outer casing 1 and the inner casing 2 needs to be guaranteed to be 0.3~0.5m. The lengths of the outer casing 1 and the inner casing 2 need to be set in actual engineering, but it is necessary to ensure that the tops of the outer casing 1 sinking into the outer casing hole and the tops of the inner casing 2 sinking into the inner casing hole are evenly spaced. Located 5 above sea level. The length difference between the outer casing 1 and the inner casing 2 is usually between 0.5m~1m, so that after the inner casing 2 sinks into the inner casing hole, the top of the outer casing 1 and the inner casing 2 The surfaces are flush. When pouring concrete mortar, it needs to be poured to the top surface of the inner casing 2. The outer casing 1 and the inner casing 2 are generally made of steel casings.
浇筑混凝土的速度要快,一气呵成,首次浇筑,导管第一次埋深应大于1.0m。随着灌注连续进行,随时拔管,中途停歇时间不得超过30分钟。在整个灌注过程中,导管在混凝土中埋深以2.0m-6.0m为宜,既不能小于2m也不能大于6m,要设专人测量导管埋置深度及内护筒2内外混凝土面的高差,及时填写水下混凝土灌注记录。The concrete must be poured quickly and in one go. During the first pouring, the first buried depth of the conduit should be greater than 1.0m. As the perfusion continues, the tube can be extubated at any time, and the pause time should not exceed 30 minutes. During the entire pouring process, the buried depth of the conduit in the concrete is preferably 2.0m-6.0m, which cannot be less than 2m or greater than 6m. A dedicated person must be assigned to measure the buried depth of the conduit and the height difference between the inner and outer concrete surfaces of the inner casing 2. Fill in the underwater concrete pouring records in a timely manner.
进一步,本实施例中,如图1至图2所示,外护筒1和内护筒2之间的同轴度偏差不大于0.05m。内护筒2倾斜度的偏差应不大于1%,最终下放的内护筒2满足水平位置跟垂直度要求。Furthermore, in this embodiment, as shown in Figures 1 to 2, the coaxiality deviation between the outer casing 1 and the inner casing 2 is not greater than 0.05m. The deviation of the inclination of the inner casing 2 should not be greater than 1%, and the finally lowered inner casing 2 meets the horizontal position and verticality requirements.
本实施例中,锚杆孔的深度为0.5~1.0m,直径为0.1m~0.12m。钻孔时,固定好潜孔钻,开启潜孔钻机,根据地形及地质情况,调整好钻机的钻进角度方可钻进。开钻后要控制,避免二次对位钻进,满足引孔的要求。锚杆孔达到设计标高后,对孔位、孔径、孔深、孔形和孔底地质情况等进行检查,孔位偏差均不得大于0.05m,倾斜度不大于5‰。In this embodiment, the depth of the anchor hole is 0.5~1.0m, and the diameter is 0.1m~0.12m. When drilling, fix the down-the-hole drill, turn on the down-the-hole drilling rig, and adjust the drilling angle of the drill rig according to the terrain and geological conditions before drilling. It is necessary to control after drilling to avoid secondary alignment drilling and meet the requirements of the pilot hole. After the anchor hole reaches the design elevation, check the hole position, hole diameter, hole depth, hole shape, and geological conditions at the bottom of the hole. The hole position deviation shall not be greater than 0.05m, and the inclination shall not be greater than 5‰.
本发明中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处。综上所述,本说明书内容不应理解为对本发明的限制。Specific examples are used in the present invention to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea; at the same time, for those of ordinary skill in the art, based on this The idea of the invention will be subject to change in the specific implementation and scope of application. In summary, the contents of this description should not be construed as limitations of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310601568.8A CN116716879A (en) | 2023-05-26 | 2023-05-26 | An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310601568.8A CN116716879A (en) | 2023-05-26 | 2023-05-26 | An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116716879A true CN116716879A (en) | 2023-09-08 |
Family
ID=87872527
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310601568.8A Pending CN116716879A (en) | 2023-05-26 | 2023-05-26 | An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116716879A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118273312A (en) * | 2024-05-30 | 2024-07-02 | 保利长大工程有限公司 | Reinforcement cage construction technology for solving karst cave |
-
2023
- 2023-05-26 CN CN202310601568.8A patent/CN116716879A/en active Pending
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN118273312A (en) * | 2024-05-30 | 2024-07-02 | 保利长大工程有限公司 | Reinforcement cage construction technology for solving karst cave |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106988302B (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
| CN112761076A (en) | Lock catch steel pipe pile cofferdam applied to water level change condition and construction method | |
| CN111236216A (en) | Construction method of bridge drilled pile | |
| CN102286984A (en) | Water-stop curtain and construction method thereof | |
| CN109056706A (en) | A kind of Karst Geological Landscape poured pile base construction method | |
| CN104196044B (en) | Cofferdam construction method with percussion drilling limit hole milling combined with steel sheet piles | |
| CN112392400B (en) | Hole forming construction process for slope protection pile in complex geological environment | |
| CN112031017A (en) | Construction method suitable for deep water pile foundation steel casing under bare rock geological condition | |
| CN112627212B (en) | Water-faced cofferdam inner tube well dewatering dry excavation construction method | |
| CN107653878A (en) | Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction | |
| CN102535490A (en) | Method for dewatering foundation pit by using bored cast-in-place pile | |
| CN112281880A (en) | A kind of construction method of long spiral guide hole inserting and locking steel pipe pile cofferdam in complex stratum | |
| CN211113598U (en) | A karst cave disposal system for deep foundation pit pile foundation construction in karst areas | |
| CN116716879A (en) | An underwater double-casing cast-in-place pile construction method suitable for hard rock seabed | |
| CN111287177A (en) | Construction method of large-diameter overlong punched cast-in-place pile in dense pebble bed area | |
| CN102979087B (en) | Construction method for rotary excavation pile | |
| CN105672309A (en) | Encasing method for hole forming of socketed piles at karst terrain through recoverable extra-long steel pile casings | |
| CN114837171A (en) | Construction method of dry sand gravel stratum cast-in-place pile | |
| CN111305209A (en) | Sinking method for super-long steel casing of large-diameter super-deep cast-in-place pile | |
| CN106930274A (en) | Construction method of full-sleeve rotary bored pile with fixed reinforcement cage position | |
| CN205399410U (en) | Dig first slip casting club -footed pile of drilling soon | |
| CN214423184U (en) | Be applied to hasp steel-pipe pile cofferdam under water level variation condition | |
| CN207080242U (en) | Cup-type horizontal reinforcement structure of bamboo reinforcement grouting anchor rod at the end of shield tunnel | |
| CN115142785A (en) | Rotary drilling technology for clay compaction leaking stoppage karst cave stratum | |
| CN116378028A (en) | Construction method of large-diameter fully-embedded thick pebble cover layer bridge pile in river |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |