CN105442532B - Pile crown expands bored pile construction method - Google Patents

Pile crown expands bored pile construction method Download PDF

Info

Publication number
CN105442532B
CN105442532B CN201510800739.5A CN201510800739A CN105442532B CN 105442532 B CN105442532 B CN 105442532B CN 201510800739 A CN201510800739 A CN 201510800739A CN 105442532 B CN105442532 B CN 105442532B
Authority
CN
China
Prior art keywords
steel pipe
pile
casing
concrete
pipe casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510800739.5A
Other languages
Chinese (zh)
Other versions
CN105442532A (en
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haide Design&Research Institute Co.,Ltd.
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201510800739.5A priority Critical patent/CN105442532B/en
Publication of CN105442532A publication Critical patent/CN105442532A/en
Application granted granted Critical
Publication of CN105442532B publication Critical patent/CN105442532B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Expand bored pile construction method the present invention relates to pile crown, mainly including preparation of construction, make double steel pipe casing, embedded double steel pipe casing, slurrying, pore-forming borehole cleaning, hang steel reinforcement cage, pour the step such as underwater concrete, Stake head handling.Easy construction of the present invention, can flexibly guide the discharge of mud and the recycling of superfilled concrete, and not only eliminate the later stage cuts stake operation, it is to avoid the later stage cuts the pile damage that stake is caused, and speed of application is fast, and cost is substantially reduced.

Description

Pile crown expands bored pile construction method
Technical field
Expand bored pile construction method the present invention relates to a kind of pile crown, belong to foundation treatment engineering field, it is adaptable to Structure foundation treatment, pile foundation construction.
Background technology
The cast-in-situ bored pile commonly used in current engineering has two kinds of forms, and holing with slurry wall protection bored concrete pile and bushing type drilling are filled Note stake.Holing with slurry wall protection filling pile construction is by after rig location and installation, hole being prevented in the embedded casing of required bore position Wall is caved in, and hole wall is protected with mud during drilling, and drilling carries out borehole cleaning, places steel reinforcement cage, casting concrete, concrete after finishing Conserve, superfilled part concrete is carried out to cut a stake.Bushing type bored pile construction is pressed into steel bushing by drilling machine location and installation Drilled after pipe, retaining wall is carried out by steel sleeve, bushing type cast-in-situ bored pile need not be carried out borehole cleaning operation, but bushing type drills Filling pile construction is poured and still needs to that the concrete of superfilled part is carried out to cut stake after finishing.
Bored pile construction noise is small, it is adaptable to build large diameter pile, and small by the influence of topography;But cast-in-situ bored pile into Quality of pile receives construction infection big, the difficult control of concrete quality, and pile body after the completion of pouring operation needs that superfilled part is carried out to cut stake appearance Easily pile body is damaged, Stake head handling is time-consuming.
In sum, although existing cast-in-situ bored pile achieves preferable construction effect under suitable engineering specifications, But existing bored pile construction method need to be processed pile crown, time-consuming.In consideration of it, according to the actual need of current engineering Want and technical conditions, need a kind of easy construction of invention badly, ambient influnence is small, can be prevented effectively from the Novel drilling bored concrete pile of section stake Construction method.
The content of the invention
The concrete utilization rate of cast-in-situ bored pile is poured it is an object of the invention to improve, is reduced to superfilled part pile crown Reason, superfilled part is avoided the formation of when cast-in-situ bored pile is poured, and can be saved the superfilled part of pile crown and be cut stake operation.
To achieve these goals, present invention employs following technical scheme:
Pile crown expands bored pile construction method, it is characterised in that comprise the following steps:
1) preparation of construction:Smooth, reasonable Arrangement builder's road and sequence of construction, root should be carried out before construction to construction site Mark is positioned to each position and carried out according to pile foundation drawing;
2) double steel pipe casing is made:Double steel pile castings are mainly made up of interior steel pipe casing and outer steel pipe casing, interior steel pipe casing It is cylinder, casing middle part offers 4 symmetrical slime flux holes, close ring limiting plate is provided with below slime flux hole;Outer steel Cylinder is managed and protected in cone, is mainly made up of top board, base plate, close ring, floor, positioning ring flat-plate and lower cutting plate, top is set on top board Plate opening, base plate is hinged with outer steel pipe casing, positioning ring flat-plate be located at base plate top, lower cutting plate be located at base plate bottom, close ring by Two semi-circular sheet steels composition, is connected by floor with outer steel pipe casing, and the close ring other end is provided with for through inserted link Butt hole;
3) double steel pipe casing is buried:Casing foundation ditch is excavated according to positioning, foundation ditch diameter is more smaller than outer steel pipe casing external diameter, Double steel pipe casing extruding embedment, the position in slime flux hole is located just at stake top n ear, and double steel pipe shield-tube embedment completes rear perimeter edge Packing reality is rammed with clay, the plan-position of casing is checked during compacting at any time, adjusted immediately if any off normal, until its outside rammer Real, casing is steady;
4)Slurrying:Use original soil pulping in cohesive soil, during pore-forming in hole injected clear water, rig cuts when rotating Soil bits are mixed with water rotation, form mud;
5) pore-forming borehole cleaning:Spiral-digging pore rotates the bit cutting soil body for being inlaid with bucket tooth, drilling process using unit head In, using mud off drilling process;When collecting mud, inserted link is extracted, mud is flowed into by the slime flux hole on interior steel pipe casing Outer steel pipe casing, then enters slurry transportation equipment by plate top openings;After the completion of borehole cleaning, insertion inserted link closes close ring;
6) steel reinforcement cage is hung:After the completion of fabrication of reinforcing cage, laid using crane, ensure that steel reinforcement cage is vertical during decentralization, forbidden Pendulum impact hole wall;
7) underwater concrete is poured:Pouring underwater concrete uses tremie method, and the steel pipe that will be tightly connected is used as concrete The passage of conveying, isolation environment water makes it not contacted with concrete;During casting concrete, deeper conduit should be kept, reduce coagulation Native rate of flooding;When concrete surface enters more than reinforcement cage skeleton base opening 4m, conduit is improved, reduces the buried depth of conduit, In filling process, the buried depth for controlling conduit mouth is 2m ~ 6m;
8) Stake head handling:After the superfilled about 1m of concrete, extract inserted link and open close ring, superfilled part concrete all flows Go out to form expansion pile head, extract outer steel pipe casing, if expansion pile head absolute altitude does not arrive stake top absolute altitude, using the concrete being scattered or The soil body is tamped, and finally extracts interior steel pipe casing.
Further, the position in slime flux hole is arranged at stake top absolute altitude in step 2;Slime flux hole is highly 100mm.
Close ring is hinged with floor, and the folding of close ring is realized by the extraction of inserted link.
The characteristics of present invention has following and beneficial effect:
(1)The present invention uses double steel pipe casing, and slime flux hole is provided with interior steel pipe casing, and slime flux hole position is in stake top absolute altitude Place, after close ring folding, shape in the cavity of the outer squeezed formation of steel pipe casing is discharged to by superfilled part concrete from interior steel pipe casing Into expansion pile head, not only eliminate the later stage cuts stake operation, it is to avoid the later stage cuts the pile damage that stake is caused, and speed of application Hurry up.
(2)Using double steel pipe casing, during filling concrete, the mud for squeezing out first passes through interior steel pipe casing streamer Hole flows into outer steel pipe casing, then enters slurry transportation equipment, collects mud very convenient, it is to avoid mud is caused in earth's surface overflow Mud contamination.
(3)Close ring is connected by floor by two semi-circular sheet steels with outer steel pipe casing, the other end set butt hole with Inserted link is communicated, and the opening and closing of close ring is realized by the plug of inserted link.The discharge of mud and the stream of superfilled concrete can flexibly be guided Enter.
Brief description of the drawings
Fig. 1 is that pile crown expands cast-in-situ bored pile bilayer steel pile casting device stereogram;
Fig. 2 is that pile crown expands steel pipe casing figure in cast-in-situ bored pile bilayer steel pile casting device;
Fig. 3 is that pile crown expands the cast-in-situ bored pile outer steel pipe casing sectional view of bilayer steel pile casting device;
Fig. 4 is that pile crown expands bored pile construction sectional drawing;
Fig. 5 is that pile crown expands cast-in-situ bored pile pile figure;
Fig. 6 is construction flow chart of the present invention;
In figure:Steel pipe casing in 1-, the outer steel pipe casings of 2-, 3- inserted links, 4- plate top openings, 5- butt holes, 6- close rings, 7- Floor, 8- close ring limiting plates, 9- top boards, 10- base plates, 11- positioning ring flat-plates, cutting plate under 12-, 13- slime fluxs hole, 14- reinforcing bars, 15-PVC sleeve pipes, 16- concrete, 17- mud, 18- foundation soils, 19- expansion pile heads, 20- pile bodies.
Specific embodiment
As shown in figure 1, pile crown expands cast-in-situ bored pile bilayer steel pile casting constructing device mainly by interior steel pipe casing 1 and outer steel Cylinder 2 is managed and protected to constitute.According to Fig. 2, interior steel pipe casing 1 is cylinder, and internal diameter is 600mm, thick from 12mm, and strength grade is Q235 hot-rolled coils are rolled and formed.Along offering 4 symmetrical slime flux holes 13, perforate ring week on the interior tube wall of steel pipe casing 1 It is highly 100mm, there are 4 close ring limiting plates 8 near slime flux hole accordingly for being positioned to close ring.
With shown in Fig. 3, in cone, it is Q235 to use strength grade to outer steel pipe casing 2 to reference picture 1, and thickness is 15mm's Hot-rolled coil rolls, is welded.Outer steel pipe casing it is main by top board 9, base plate 10, close ring 6, floor 7, positioning ring flat-plate 11, Lower cutting plate 12, butt hole 5 and inserted link 3 are constituted.The a diameter of 1400mm of top board 9, internal diameter is identical with the external diameter of interior steel pipe casing, top board 9 are provided with a plate top openings 4, are easy to the collection of the plug and mud plant of inserted link 3 to mud.Base plate 10 is protected with outer steel pipe Cylinder 2 is hinged, and a diameter of 1000mm of base plate 10, internal diameter is identical with the external diameter of interior steel pipe casing 1.Positioning ring flat-plate 11 is annular plate, Width is 100mm, and positioned at the top of base plate 10, effect is the motion for limiting base plate 10 in the horizontal direction, and lower cutting plate 12 is along outer steel pipe The angle welding of casing 2, incision soil body during for outer steel pipe shield-tube embedment.Close ring 6 passes through floor 7 by two semi-circular sheet steels It is connected with outer steel pipe casing 2, floor 7 uses hot rolled steel plate, and thick 12mm, strength grade is Q345.The internal diameter of close ring 6 and interior steel pipe The external diameter of casing is identical, and the other end sets butt hole 5 and communicated with inserted link 3, and the upper diameter of inserted link 3 is more than base diameter, close ring 6 The folding of close ring 6 is realized by the plug of inserted link 3.
Interior steel pipe casing 1 is set in place using vibration hammer, steel pipe casing 1 in cleaning, it is ensured that slime flux hole 13 is located at stake top At designed elevation, outer steel pipe casing 2 is buried, outer steel pipe casing 2 is positioned by close ring limiting plate 8, check hanging down for steel pipe casing Straight degree and stability.Outer and inner tube casing is set after finishing, and bored pile construction is carried out using usual manner.
After cast-in-situ bored pile drilling, inserted link 3 being extracted as shown in Figure 4 and opening close ring 6, mud 17 is just along interior steel pipe casing 1 slime flux hole 13 flows to outer steel pipe casing and extrudes in the cavity to be formed, and the plate top openings 4 opened on top board 9 are used at mud plant Reason mud 17.After the completion of mud conditioning, insertion inserted link 3 is closed close ring 6 and carries out next step operation.
What Fig. 5 was represented is that pile crown expands cast-in-situ bored pile pile figure, after the completion of cast-in-place pile concrete 16 is poured, superfilled part Concrete stake top formed expansion pile head 19, when superfilled part concrete is inadequate, the concrete being scattered using job site Tamped.In work progress, PVC casing protection reinforcing bars are put on reinforcing bar 14 more than design of pile top absolute altitude.
Fig. 6 is construction flow chart of the present invention;Pile crown expands bored pile construction method, comprises the following steps:
1) preparation of construction:Smooth, reasonable Arrangement builder's road and sequence of construction should be carried out before construction to construction site, root Mark is positioned to each position and carried out according to pile foundation drawing.
2) double steel pipe casing is made;
3) double steel pipe casing is buried:Casing foundation ditch is excavated according to positioning, foundation ditch diameter should be omited than the outer external diameter of steel pipe casing 2 Small, double steel pipe casing extruding embedment, the position in slime flux hole 13 is located just at stake top n ear, and shield-tube embedment completes rear perimeter edge and uses Clay rams packing reality, checks the plan-position of casing during compacting at any time, is adjusted immediately if any off normal, until its outside rammer Real, casing is steady.
4)Slurrying:Use original soil pulping in cohesive soil, during pore-forming in hole injected clear water, rig cuts when rotating Soil bits are mixed with water rotation, form mud;Slurrying should select highly plastic clay or bentonite in other soil bodys;When preparing mud Proportion design should be carried out according to construction machinery, construction technology and situations such as passing through the soil property of soil layer.
5) pore-forming borehole cleaning:Spiral-digging pore rotates the bit cutting soil body for being inlaid with bucket tooth, drilling process using unit head In, using mud off drilling process.When collecting mud, inserted link 3 is extracted, mud 17 is by the slime flux hole on interior steel pipe casing 1 13 flow into outer steel pipe casing 2, then enter slurry transportation equipment by plate top openings 4.After the completion of borehole cleaning, insertion inserted link is closed Cyclization.
6) steel reinforcement cage is hung:After the completion of fabrication of reinforcing cage, laid using crane, ensure that steel reinforcement cage is vertical during decentralization, forbidden Pendulum impact hole wall.
7) underwater concrete is poured:Pouring underwater concrete uses tremie method, and the steel pipe that will be tightly connected is used as concrete The passage of conveying, isolation environment water makes it not contacted with concrete.During casting concrete, deeper conduit should be kept, reduce coagulation Native rate of flooding;When concrete surface enters more than reinforcement cage skeleton base opening 4m, conduit is improved, reduces the buried depth of conduit, In filling process, the buried depth for controlling conduit mouth is 2m ~ 6m.
8) Stake head handling:After the superfilled about 1m of concrete, extract inserted link and open close ring, superfilled part concrete all flows Go out to form expansion pile head, extract outer steel pipe casing, if expansion pile head absolute altitude does not arrive stake top absolute altitude, using the concrete being scattered or The soil body is tamped, and finally extracts interior steel pipe casing.

Claims (4)

1. pile crown expands bored pile construction method, it is characterised in that comprise the following steps:
1) preparation of construction:Smooth, reasonable Arrangement builder's road and sequence of construction should be carried out before construction to construction site, according to stake Base drawing is positioned to each position and is carried out mark;
2) double steel pipe casing is made:Double steel pile castings are mainly made up of interior steel pipe casing and outer steel pipe casing, and interior steel pipe casing is circle Cylindricality, casing middle part offers 4 symmetrical slime flux holes, and close ring limiting plate is provided with below slime flux hole;Outer steel pipe shield Cylinder is mainly made up of in cone top board, base plate, close ring, floor, positioning ring flat-plate and lower cutting plate, top board is set on top board and is opened Mouthful, base plate is hinged with outer steel pipe casing, and positioning ring flat-plate is located at base plate top, and lower cutting plate is located at base plate bottom, and close ring is by two Semi-circular sheet steel is constituted, and is connected with outer steel pipe casing by floor, and the close ring other end is provided with for the docking through inserted link Hole;
3) double steel pipe casing is buried:Casing foundation ditch is excavated according to positioning, foundation ditch diameter is more smaller than outer steel pipe casing external diameter, double steel Cylinder extruding embedment is managed and protected, the position in slime flux hole is located just at stake top n ear, and double steel pipe shield-tube embedment completes rear perimeter edge and uses viscous Earth rammer packing reality, checks the plan-position of casing at any time during compacting, adjusted immediately if any off normal, until its outside compacting, Casing is steady;
4)Slurrying:Original soil pulping is used in cohesive soil, during pore-forming in hole injected clear water, rig rotate when cut soil bits Mixed with water rotation, form mud;
5) pore-forming borehole cleaning:Spiral-digging pore rotates the bit cutting soil body for being inlaid with bucket tooth using unit head, in drilling process, adopts Use mud off drilling process;When collecting mud, inserted link is extracted, mud flows into outer steel pipe by the slime flux hole on interior steel pipe casing Casing, then enters slurry transportation equipment by plate top openings;After the completion of borehole cleaning, insertion inserted link closes close ring;
6) steel reinforcement cage is hung:After the completion of fabrication of reinforcing cage, laid using crane, ensure that steel reinforcement cage is vertical during decentralization, forbid to swing Collision hole wall;
7) underwater concrete is poured:Pouring underwater concrete uses tremie method, and the steel pipe that will be tightly connected is used as concrete conveyance Passage, isolation environment water makes it not contacted with concrete;During casting concrete, conduit should be kept embedding relatively deep, reduce coagulation Native rate of flooding;When concrete surface enters more than reinforcement cage skeleton base opening 4m, conduit is improved, reduces the buried depth of conduit, In filling process, the buried depth for controlling conduit mouth is 2m ~ 6m;
8) Stake head handling:After the superfilled 1m of concrete, extract inserted link and open close ring, all outflow is formed superfilled part concrete Expansion pile head, extracts outer steel pipe casing, if expansion pile head absolute altitude does not arrive stake top absolute altitude, is entered using the concrete or the soil body that are scattered Row is tamped, and finally extracts interior steel pipe casing.
2. pile crown according to claim 1 expands bored pile construction method, it is characterised in that slime flux hole in step 2 Position is arranged at stake top absolute altitude.
3. pile crown according to claim 1 expands bored pile construction method, it is characterised in that slime flux hole is high in step 2 It is 100mm to spend.
4. pile crown according to claim 1 expands bored pile construction method, it is characterised in that in step 2 close ring with Floor is hinged.
CN201510800739.5A 2015-11-19 2015-11-19 Pile crown expands bored pile construction method Active CN105442532B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510800739.5A CN105442532B (en) 2015-11-19 2015-11-19 Pile crown expands bored pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510800739.5A CN105442532B (en) 2015-11-19 2015-11-19 Pile crown expands bored pile construction method

Publications (2)

Publication Number Publication Date
CN105442532A CN105442532A (en) 2016-03-30
CN105442532B true CN105442532B (en) 2017-05-31

Family

ID=55553127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510800739.5A Active CN105442532B (en) 2015-11-19 2015-11-19 Pile crown expands bored pile construction method

Country Status (1)

Country Link
CN (1) CN105442532B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316291A (en) * 2018-04-12 2018-07-24 浙江大学城市学院 Deep mud pit cast-in-situ bored pile and construction method
CN108532637A (en) * 2018-04-27 2018-09-14 上海建工二建集团有限公司 It is inverse to make stage integration vertical support system and its installation method
CN110067245A (en) * 2019-03-22 2019-07-30 西南交通大学 It is a kind of can expanding reinforcing spiral self-drilling type piling bar and its method of construction
CN110273422A (en) * 2019-06-28 2019-09-24 中国二十冶集团有限公司 Method for chiseling pile head of filling pile
CN110700241A (en) * 2019-10-08 2020-01-17 上海建工一建集团有限公司 Cast-in-situ bored pile and construction method thereof
CN111663575B (en) * 2020-06-23 2021-09-21 中国五冶集团有限公司 Construction method for post-forming waterproof construction of pile head
CN112096326B (en) * 2020-09-19 2022-07-01 深圳鹏城岩土科技有限公司 Device and method for removing mud in cast-in-situ bored pile hole
CN113123343A (en) * 2021-04-14 2021-07-16 四川瑞云建设工程有限公司 Small-volume cast-in-place pile underwater pouring equipment and construction method
CN114032889A (en) * 2021-12-10 2022-02-11 上海建工五建集团有限公司 Combined pile foundation casing positioning device and using method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001288741A (en) * 2000-04-10 2001-10-19 Nkk Corp Screwed type steel pipe pile and method for constructing the same
CN101638891A (en) * 2009-08-18 2010-02-03 上海市第二建筑有限公司 Construction method of all casing precessing isolation pile
CN103510511A (en) * 2013-09-26 2014-01-15 鸿厦建设有限公司 Top-reinforced cast-in-place concrete thin-wall pipe pile and construction method
CN203846485U (en) * 2014-05-28 2014-09-24 宏润建设集团股份有限公司 Long pile percussion drill hole forming construction device
CN204401613U (en) * 2014-10-14 2015-06-17 安徽省交通建设有限责任公司 The structure of bored pile perforation spillage in water prevention

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001288741A (en) * 2000-04-10 2001-10-19 Nkk Corp Screwed type steel pipe pile and method for constructing the same
CN101638891A (en) * 2009-08-18 2010-02-03 上海市第二建筑有限公司 Construction method of all casing precessing isolation pile
CN103510511A (en) * 2013-09-26 2014-01-15 鸿厦建设有限公司 Top-reinforced cast-in-place concrete thin-wall pipe pile and construction method
CN203846485U (en) * 2014-05-28 2014-09-24 宏润建设集团股份有限公司 Long pile percussion drill hole forming construction device
CN204401613U (en) * 2014-10-14 2015-06-17 安徽省交通建设有限责任公司 The structure of bored pile perforation spillage in water prevention

Also Published As

Publication number Publication date
CN105442532A (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN105442532B (en) Pile crown expands bored pile construction method
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN103850249B (en) Long spire is squeezed into rock filling pile construction technology
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN106930276B (en) The construction method of the deep hole blasting of rotary digging bored concrete pile and conduit rotary digging removing obstacles
CN103122632A (en) Construction method for drilling hole and casting pile in plastic flow stratum or karst cave stratum
CN111395330B (en) Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN108589707A (en) A kind of full-sleeve long screw auger and churning driven combined type construction
CN106759288A (en) One kind building bored pile construction method
CN104452749A (en) Construction method of reinforced concrete current-poured pile
CN105780763A (en) Construction method of medium-hole vibrating casing wall protection type long spiral cast-in-situ bored pile
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN103924987A (en) SMW pile shielding portal waterproof structure and construction method thereof
CN108086342A (en) The construction method of karst strata pile foundation
CN106245654B (en) Deposited reinforced concrete pile exempts from inter-pile soil excavation construction method
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN107587502B (en) Construction method for rotary drilling hole-forming pressure-grouting cement soil occlusion curtain pile
KR101751418B1 (en) Grouting device using a reinforced network is equipped with a small steel pipe
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN108049397A (en) The construction method of Karst Geological Landscape drilled pile
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN108179759A (en) The underwater drill core slotting of driftway is without bottom sealing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181225

Address after: 266061 No. 17 Haier Road, Laoshan District, Qingdao City, Shandong Province

Patentee after: QINGDAO HAIDE ENGINEERING GROUP Co.,Ltd.

Address before: 310015 room 1901, unit 3, 3 Wanda Commercial Center, Gongshu District, Hangzhou, Zhejiang.

Patentee before: HANGZHOU JIANGRUN TECHNOLOGY Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221014

Address after: 266061 Floor 27, Building 1, No. 28, Miaoling Road, Laoshan District, Qingdao, Shandong

Patentee after: Qingdao Haide Design&Research Institute Co.,Ltd.

Address before: 266061 No. 17 Haier Road, Laoshan District, Qingdao City, Shandong Province

Patentee before: QINGDAO HAIDE ENGINEERING GROUP Co.,Ltd.

TR01 Transfer of patent right