CN112780073A - Prefabricated wallboard strutting arrangement is used in room construction - Google Patents

Prefabricated wallboard strutting arrangement is used in room construction Download PDF

Info

Publication number
CN112780073A
CN112780073A CN202011520197.3A CN202011520197A CN112780073A CN 112780073 A CN112780073 A CN 112780073A CN 202011520197 A CN202011520197 A CN 202011520197A CN 112780073 A CN112780073 A CN 112780073A
Authority
CN
China
Prior art keywords
fixedly connected
supporting
plate
sliding
building construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011520197.3A
Other languages
Chinese (zh)
Inventor
申海洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Architectural College
Original Assignee
Shanxi Architectural College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Architectural College filed Critical Shanxi Architectural College
Priority to CN202011520197.3A priority Critical patent/CN112780073A/en
Publication of CN112780073A publication Critical patent/CN112780073A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a prefabricated wallboard supporting device for building construction, which comprises a movable box, wherein positioning plates are fixedly connected at the front and back positions on the left side of the top of the movable box, one opposite sides of the two positioning plates are rotatably connected with a rotating shaft through a bearing, and the left side of the rotating shaft is fixedly connected with an L-shaped plate, thereby further avoiding affecting the support effect.

Description

Prefabricated wallboard strutting arrangement is used in room construction
Technical Field
The invention relates to the technical field of assembly type building installation and construction, in particular to a prefabricated wallboard supporting device for building construction.
Background
The prefabricated concrete wall panels are adopted to build the large assembled plate building, so that the industrialized and mechanized construction degree can be improved, the field wet operation is reduced, the field labor is saved, the seasonal influence is overcome, the building construction period is shortened, and when the prefabricated wall panels are installed, most prefabricated wall panel supporting devices are needed, but the traditional supporting devices have the following defects; firstly, the supporting position of the traditional supporting device is mostly fixed, and the supporting position cannot be adjusted according to the actual condition of the prefabricated wall panel in such a way, so that the supporting effect is influenced; secondly, the supporting angle of the traditional supporting device is mostly fixed, and the supporting angle cannot be adjusted according to the actual installation condition of the prefabricated wall panel in the mode, so that the supporting effect is further influenced; thirdly, traditional strutting arrangement places when appointed support position, because the road surface height is uneven for strutting arrangement rocks, thereby easily appears the installation error, so there is the defect of not convenient to use, has increased staff's the work degree of difficulty simultaneously, for this we propose a room and build with prefabricated wallboard strutting arrangement, solve above problem of proposing.
Disclosure of Invention
The invention aims to provide a prefabricated wallboard supporting device for building construction, which has the advantages that the supporting position and the supporting angle can be adjusted when the supporting device is used, the use is convenient, and the problems that the supporting position and the supporting angle cannot be adjusted and the use is inconvenient when the original supporting device is used are solved.
In order to achieve the purpose, the invention provides the following technical scheme: a prefabricated wallboard supporting device for building construction comprises a moving box, wherein positioning plates are fixedly connected to the left front and back positions of the top of the moving box, a rotating shaft is rotatably connected to one opposite side of the two positioning plates through a bearing, an L-shaped plate is fixedly connected to the left side of the rotating shaft, slide rails are fixedly connected to the left upper and lower positions of the L-shaped plate, slide plates are slidably connected to the front and back sides of the upper and lower slide rails, a supporting plate is fixedly connected to the left side of each slide plate through a connecting block, mounting holes are uniformly formed in the left top and bottom of the supporting plate, screw rods are rotatably connected to the left and right sides of an inner cavity of the moving box through bearings, sleeves are connected to the outer surface threads of the screw rods, sliding columns are fixedly connected to the left and right sides of the inner, two slide cartridge and telescopic top fixedly connected with loading board, the position all has the push pedal through loose axle swing joint around the loading board top, the one end that the loading board was kept away from in the push pedal passes through the loose axle and the junction swing joint of L template, the four corners of removal bottom of the case portion all is fixed and is provided with supporting component.
Preferably, the supporting component comprises a supporting cylinder, the top of the supporting cylinder is fixedly connected with the connecting part of the movable box, the inner surface of the supporting cylinder is in threaded connection with a solenoid, the bottom of the solenoid penetrates through the supporting cylinder and is connected with a base in a rotating mode through a bearing, and the left side and the right side of the solenoid are respectively and fixedly connected with a driving block below the supporting cylinder.
Preferably, four corners of the bottom of the mobile box and the inner sides of the supporting cylinders are movably connected with universal wheels, and moving grooves matched with the push plate for use are formed in the front and rear positions of the top of the mobile box.
Preferably, the bottom of the sleeve is fixedly connected with a guide plate, the bottom of the inner cavity of the movable box is provided with a guide groove matched with the guide plate, and the outer surface of the guide plate is in sliding connection with the inner surface of the guide groove.
Preferably, the top and the bottom of the sliding plate are both in threaded connection with limiting bolts, and one side, opposite to the limiting bolts, of the sliding plate penetrates through the sliding plate and is tightly attached to the joint of the sliding rail.
Preferably, the left side of L template is located two the equal fixedly connected with limiting plate in the outside of slide rail, the surface of limiting plate closely laminates with the junction of slide rail.
Preferably, the right end of the screw rod penetrates through the movable box and extends to the outer side of the movable box, and the right end of the screw rod is fixedly connected with a handle.
Preferably, the right side of the top of the movable box is fixedly connected with a balancing weight, and the front side of the movable box is movably connected with a box door through a hinge.
Compared with the prior art, the invention has the following beneficial effects:
1. the L-shaped plate can conveniently rotate by arranging the structure, has the advantage that the supporting angle can be adjusted when the supporting device is used, and further avoids influencing the supporting effect by arranging the structure.
2. The supporting device can be conveniently supported by arranging the supporting cylinder, the screw tube, the base and the driving block, and by arranging the structure, the supporting device has the advantage of convenience in use when in use, and the problem that the original supporting device is inconvenient to use when in use is solved, so that the supporting device is prevented from shaking and causing installation errors, and the labor difficulty of workers is effectively reduced;
the universal wheels are arranged, so that the device can move conveniently, and the moving grooves are arranged, so that the push plate can move conveniently;
by arranging the guide plate and the guide groove, the sleeve can be conveniently guided and limited;
the limiting bolt is arranged, so that the connecting position of the sliding plate and the sliding rail can be limited conveniently;
the limiting plate is arranged, so that the sliding plate can be conveniently limited;
the handle is arranged, so that the screw can be conveniently rotated;
through setting up the balancing weight, can improve the device's stability, through setting up the chamber door, can make things convenient for the staff to regularly change and maintain the part of removal incasement chamber.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a perspective view of the connection of the screw and bushing arrangement of the present invention;
FIG. 3 is a side view of the skateboard configuration of the present invention;
FIG. 4 is a cross-sectional view of a support cartridge structure of the present invention;
fig. 5 is a front view of the structure of the mobile box of the present invention.
In the figure: 1. a mobile box; 2. positioning a plate; 3. a rotating shaft; 4. an L-shaped plate; 5. a slide rail; 6. a slide plate; 7. a support plate; 8. mounting holes; 9. a screw; 10. a sleeve; 11. a traveler; 12. a slide cylinder; 13. a carrier plate; 14. pushing the plate; 15. a support assembly; 151. a support cylinder; 152. a solenoid; 153. a base; 154. a drive block; 16. a universal wheel; 17. a moving groove; 18. a guide plate; 19. a guide groove; 20. a limit bolt; 21. a limiting plate; 22. and a balancing weight.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Examples
Referring to fig. 1-5, a prefabricated wall panel supporting device for building construction comprises a movable box 1, positioning plates 2 are fixedly connected to the front and rear positions of the left side of the top of the movable box 1, one opposite sides of the two positioning plates 2 are rotatably connected with a rotating shaft 3 through bearings, the left side of the rotating shaft 3 is fixedly connected with an L-shaped plate 4, slide rails 5 are fixedly connected to the upper and lower positions of the left side of the L-shaped plate 4, slide plates 6 are slidably connected to the front and rear sides of the upper and lower slide rails 5, a supporting plate 7 is fixedly connected to the left side of the slide plate 6 through a connecting block, mounting holes 8 are uniformly formed in the top and the bottom of the left side of the supporting plate 7, screw rods 9 are rotatably connected to the left and right sides of the inner cavity of the movable box 1 through bearings, sleeves 10 are threadedly connected to the outer surfaces of the screw rods, the top parts of the two sliding cylinders 12 and the sleeve 10 are fixedly connected with a bearing plate 13, the front and back positions of the top part of the bearing plate 13 are movably connected with a push plate 14 through a movable shaft, one end, far away from the bearing plate 13, of the push plate 14 is movably connected with the joint of the L-shaped plate 4 through the movable shaft, four corners of the bottom part of the movable box 1 are fixedly provided with supporting components 15, the supporting plate 7 can be moved by arranging the L-shaped plate 4, the sliding rails 5, the sliding plates 6 and the limiting bolts 20, through the arrangement of the structure, the supporting device has the advantage that the supporting position can be adjusted when the supporting device is used, the problem that the supporting position cannot be adjusted when the original supporting device is used is solved, and therefore the supporting effect is prevented from being influenced, through the arrangement of the positioning plate 2, the rotating shaft 3, the screw rod 9, the sleeve 10, the sliding column 11, the, possess strutting arrangement when using, can adjust the advantage of support angle, solved original strutting arrangement when using, can not adjust the problem of support angle to further avoid influencing the supporting effect.
Referring to fig. 1 and 4, the supporting assembly 15 includes a supporting cylinder 151, a joint of the top of the supporting cylinder 151 and the movable box 1 is fixedly connected, a threaded pipe 152 is connected to an inner surface of the supporting cylinder 151 through a thread, a base 153 is rotatably connected to the bottom of the threaded pipe 152 through the supporting cylinder 151 through a bearing, anti-slip bumps are uniformly and fixedly connected to the bottom of the base 153, friction between the base 153 and a road surface can be increased, driving blocks 154 are fixedly connected to both left and right sides of the threaded pipe 152 and below the supporting cylinder 151, by arranging the supporting cylinder 151, the solenoid 152, the base 153 and the driving block 154, the device can be conveniently supported, by arranging the structure, the utility model has the advantage of convenient use when the supporting device is used, solves the problem that the original supporting device is inconvenient to use when in use, thereby avoided strutting arrangement to rock, the condition of installation error appears, the effectual work degree of difficulty that has reduced the staff.
Please refer to fig. 1, four corners of the bottom of the movable box 1 and the inner side of the supporting cylinder 151 are movably connected with universal wheels 16, the universal wheels 16 are provided with locking plates, the front and rear positions of the top of the movable box 1 are provided with movable grooves 17 matched with the push plate 14 for use, the movable box can be moved conveniently by the aid of the universal wheels 16, and the push plate 14 can be moved conveniently by the aid of the movable grooves 17.
Referring to fig. 1, a guide plate 18 is fixedly connected to the bottom of the sleeve 10, a guide groove 19 used in cooperation with the guide plate 18 is formed in the bottom of the inner cavity of the movable box 1, the outer surface of the guide plate 18 is slidably connected with the inner surface of the guide groove 19, and the guide plate 18 and the guide groove 19 are arranged to guide the sleeve 10 and limit the sleeve.
Referring to fig. 1 and 3, the top and the bottom of the sliding plate 6 are both connected with the limiting bolts 20 through threads, one side of each of the two limiting bolts 20 opposite to each other penetrates through the sliding plate 6 and is tightly attached to the joint of the sliding rail 5, and the joint of the sliding plate 6 and the sliding rail 5 can be limited conveniently by arranging the limiting bolts 20.
Please refer to fig. 1 and fig. 3, the left side of the L-shaped plate 4 is located at the outer side of the two slide rails 5 and is fixedly connected with a limiting plate 21, the outer surface of the limiting plate 21 is tightly attached to the joint of the slide rails 5, and the sliding plate 6 can be conveniently limited by the limiting plate 21.
Referring to fig. 1, the right end of the screw 9 penetrates through the movable box 1 and extends to the outside of the movable box 1, and the right end of the screw 9 is fixedly connected with a handle, so that the screw 9 can be conveniently rotated by the handle.
Please refer to fig. 1 and 5, a counterweight 22 is fixedly connected to the right side of the top of the movable box 1, the front side of the movable box 1 is movably connected to a box door through a hinge, the stability of the device can be improved by arranging the counterweight 22, and the box door can be convenient for a worker to regularly replace and maintain parts in the inner cavity of the movable box 1.
When the device is used, the device is moved to a designated position through the universal wheel 16, then the driving block 154 is shifted according to the actual condition of the road surface, the driving block 154 drives the solenoid 152 to rotate on the inner surface thread of the supporting cylinder 151, so that the solenoid 152 drives the base 153 to move, the base 153 is tightly attached to the road surface, then the driving blocks 154 at the four corners of the bottom of the movable box 1 are sequentially adjusted, thereby the adjustment of the horizontal state of the movable box 1 is completed, the situation of installation error caused by the swinging of the supporting device can be avoided by the matching use of the above structures, the labor difficulty of workers is effectively reduced, then the handle is rotated according to the installation angle of the prefabricated wall panel, the handle drives the screw rod 9 to rotate on the inner surface thread of the sleeve 10, the sleeve 10 drives the bearing plate 13 to move, meanwhile, the bearing plate 13 drives the sliding cylinder 12 to slide on the outer surface of the sliding column 11, so that, push pedal 14 drives L template 4 and rotates, simultaneously L template 4 drives pivot 3 and rotates, thereby accomplish the regulation to prefabricated wallboard installation angle, then according to the supported position of prefabricated wallboard, stir backup pad 7, make backup pad 7 drive slide 6 slide at the surface of slide rail 5, when backup pad 7 removes suitable supported position, rotate limit bolt 20, it is spacing to slide 6 and slide rail 5's junction to make limit bolt 20, thereby accomplish the regulation to prefabricated wallboard supported position, then fix between prefabricated wallboard and the backup pad 7 through mounting hole 8, cooperation through setting up above structure is used, the effectual work degree of difficulty that has reduced the staff, the supporting effect has been improved simultaneously.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a room is built with prefabricated wallboard strutting arrangement, includes movable box (1), its characterized in that: the front and back positions of the left side of the top of the movable box (1) are fixedly connected with positioning plates (2), one opposite side of the two positioning plates (2) is rotatably connected with a rotating shaft (3) through a bearing, the left side of the rotating shaft (3) is fixedly connected with an L-shaped plate (4), the upper and lower positions of the left side of the L-shaped plate (4) are fixedly connected with sliding rails (5), the front and back sides of the upper and lower sliding rails (5) are respectively and slidably connected with sliding plates (6), the left side of each sliding plate (6) is fixedly connected with a supporting plate (7) through a connecting block, the top and the bottom of the left side of each supporting plate (7) are respectively and uniformly provided with mounting holes (8), the left and right sides of the inner cavity of the movable box (1) are rotatably connected with a screw rod (9) through a bearing, the outer surface of each screw rod (9) is, the surface sliding connection of traveller (11) has a slide cartridge (12), two the top fixedly connected with loading board (13) of slide cartridge (12) and sleeve (10), the position all has push pedal (14) through loose axle swing joint around loading board (13) top, the junction swing joint of loose axle and L template (4) is passed through to the one end that loading board (13) were kept away from in push pedal (14), the four corners of removal case (1) bottom is all fixed and is provided with supporting component (15).
2. The prefabricated wall panel supporting device for building construction according to claim 1, wherein: the supporting component (15) comprises a supporting cylinder (151), the top of the supporting cylinder (151) is fixedly connected with the joint of the moving box (1), the inner surface of the supporting cylinder (151) is in threaded connection with a solenoid (152), the bottom of the solenoid (152) penetrates through the supporting cylinder (151) and is connected with a base (153) through a bearing in a rotating mode, and the left side and the right side of the solenoid (152) are located on the lower portion of the supporting cylinder (151) and are respectively and fixedly connected with a driving block (154).
3. The prefabricated wall panel supporting device for building construction according to claim 2, wherein: the four corners of the bottom of the moving box (1) and the inner sides of the supporting cylinders (151) are movably connected with universal wheels (16), and moving grooves (17) matched with the push plates (14) for use are formed in the front and rear positions of the top of the moving box (1).
4. The prefabricated wall panel supporting device for building construction according to claim 1, wherein: the bottom fixedly connected with deflector (18) of sleeve (10), guide way (19) that use with deflector (18) cooperation are seted up to the bottom of removal case (1) inner chamber, the surface of deflector (18) and the internal surface sliding connection of guide way (19).
5. The prefabricated wall panel supporting device for building construction according to claim 1, wherein: the top and the bottom of the sliding plate (6) are both in threaded connection with limiting bolts (20), and one side, opposite to the limiting bolts (20), of the sliding plate (6) penetrates through the sliding plate (6) and is tightly attached to the joint of the sliding rail (5).
6. The prefabricated wall panel supporting device for building construction according to claim 1, wherein: the left side of L template (4) is located two the equal fixedly connected with limiting plate (21) in the outside of slide rail (5), the surface of limiting plate (21) closely laminates with the junction of slide rail (5).
7. The prefabricated wall panel supporting device for building construction according to claim 1, wherein: the right end of screw rod (9) runs through removal case (1) and extends to the outside of removal case (1), the right-hand member fixedly connected with handle of screw rod (9).
8. The prefabricated wall panel supporting device for building construction according to claim 1, wherein: the right side of the top of the movable box (1) is fixedly connected with a balancing weight (22), and the front side of the movable box (1) is movably connected with a box door through a hinge.
CN202011520197.3A 2020-12-21 2020-12-21 Prefabricated wallboard strutting arrangement is used in room construction Pending CN112780073A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011520197.3A CN112780073A (en) 2020-12-21 2020-12-21 Prefabricated wallboard strutting arrangement is used in room construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011520197.3A CN112780073A (en) 2020-12-21 2020-12-21 Prefabricated wallboard strutting arrangement is used in room construction

Publications (1)

Publication Number Publication Date
CN112780073A true CN112780073A (en) 2021-05-11

Family

ID=75751462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011520197.3A Pending CN112780073A (en) 2020-12-21 2020-12-21 Prefabricated wallboard strutting arrangement is used in room construction

Country Status (1)

Country Link
CN (1) CN112780073A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113494035A (en) * 2021-06-30 2021-10-12 徐州市政建设集团有限责任公司 Municipal road extension structure and road extension method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184757A (en) * 2018-08-28 2019-01-11 郑光茂 Small mine pillar
AU2019100763A4 (en) * 2019-07-10 2019-08-15 TAJ Australia Pty Ltd Improved edge protection bracket, system and method
CN211647401U (en) * 2019-12-31 2020-10-09 罗傲 Be fit for multiplex condition building wall bearing structure
CN111945707A (en) * 2020-09-25 2020-11-17 广东穗晟建设工程有限公司 Construction method of underground diaphragm wall in underground air-raid shelter area
CN212002428U (en) * 2020-04-08 2020-11-24 姜晓龙 Building structure reinforced structure
CN212005001U (en) * 2020-04-24 2020-11-24 沈阳工学院 Make things convenient for height-adjusting's mining machinery strutting arrangement
CN111980429A (en) * 2020-09-16 2020-11-24 金螳螂精装科技(苏州)有限公司 Supporting structure of assembled interior wallboard

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109184757A (en) * 2018-08-28 2019-01-11 郑光茂 Small mine pillar
AU2019100763A4 (en) * 2019-07-10 2019-08-15 TAJ Australia Pty Ltd Improved edge protection bracket, system and method
CN211647401U (en) * 2019-12-31 2020-10-09 罗傲 Be fit for multiplex condition building wall bearing structure
CN212002428U (en) * 2020-04-08 2020-11-24 姜晓龙 Building structure reinforced structure
CN212005001U (en) * 2020-04-24 2020-11-24 沈阳工学院 Make things convenient for height-adjusting's mining machinery strutting arrangement
CN111980429A (en) * 2020-09-16 2020-11-24 金螳螂精装科技(苏州)有限公司 Supporting structure of assembled interior wallboard
CN111945707A (en) * 2020-09-25 2020-11-17 广东穗晟建设工程有限公司 Construction method of underground diaphragm wall in underground air-raid shelter area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113494035A (en) * 2021-06-30 2021-10-12 徐州市政建设集团有限责任公司 Municipal road extension structure and road extension method

Similar Documents

Publication Publication Date Title
CN113266159B (en) Prefabricated post installation device that installation accuracy is high
CN111236533A (en) Steel structure supporting beam for building construction
CN112780073A (en) Prefabricated wallboard strutting arrangement is used in room construction
CN213572609U (en) Ceiling conversion layer structure
CN213539631U (en) Civil engineering construction support
CN111622500B (en) Template reinforcing apparatus for building
CN219196719U (en) Cantilever support template for water inlet tower construction
CN215631887U (en) Building structure design roof beam reinforced structure
CN215830099U (en) Bed-jig is used in steel construction equipment of adjustable elevation
CN116122594A (en) Assembling system for steel structure net rack
CN212004941U (en) Surveying and mapping device for constructional engineering
CN214035537U (en) Deviation device is prevented with probing to geotechnical engineering reconnaissance
CN110640861B (en) Timber shop front butt-joint equipment for fitment
CN112814401A (en) Liftable support for construction engineering construction
CN112627050A (en) Box girder template for municipal administration road and bridge construction
CN220014375U (en) Adjustable construction platform of bracing
CN220747712U (en) Prefabricated filled wall body group builds fixing device
CN219471651U (en) Novel template support for building construction
CN218597836U (en) Post-cast strip supporting bracket structure
CN219570004U (en) Climbing ladder
CN220868889U (en) Anti-tilting assembled building structure
CN219826053U (en) Novel scaffold convenient to equipment
CN220550894U (en) Building wall body strutting arrangement
CN220432135U (en) Combined light crane convenient to install
CN220395223U (en) Leveling device for cast-in-situ box girder concrete construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210511