CN112762269A - Construction method for repairing underground pipeline - Google Patents

Construction method for repairing underground pipeline Download PDF

Info

Publication number
CN112762269A
CN112762269A CN202110008968.9A CN202110008968A CN112762269A CN 112762269 A CN112762269 A CN 112762269A CN 202110008968 A CN202110008968 A CN 202110008968A CN 112762269 A CN112762269 A CN 112762269A
Authority
CN
China
Prior art keywords
pipeline
lining hose
water leakage
leakage point
plugging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110008968.9A
Other languages
Chinese (zh)
Inventor
胡枫
敖小平
周伏萍
胡培强
尧在雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Geo Engineering Group Corp
Original Assignee
Jiangxi Geo Engineering Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Geo Engineering Group Corp filed Critical Jiangxi Geo Engineering Group Corp
Priority to CN202110008968.9A priority Critical patent/CN112762269A/en
Publication of CN112762269A publication Critical patent/CN112762269A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/16Devices for covering leaks in pipes or hoses, e.g. hose-menders
    • F16L55/162Devices for covering leaks in pipes or hoses, e.g. hose-menders from inside the pipe
    • F16L55/165Devices for covering leaks in pipes or hoses, e.g. hose-menders from inside the pipe a pipe or flexible liner being inserted in the damaged section
    • F16L55/1652Devices for covering leaks in pipes or hoses, e.g. hose-menders from inside the pipe a pipe or flexible liner being inserted in the damaged section the flexible liner being pulled into the damaged section
    • F16L55/1654Devices for covering leaks in pipes or hoses, e.g. hose-menders from inside the pipe a pipe or flexible liner being inserted in the damaged section the flexible liner being pulled into the damaged section and being inflated
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/16Devices for covering leaks in pipes or hoses, e.g. hose-menders
    • F16L55/168Devices for covering leaks in pipes or hoses, e.g. hose-menders from outside the pipe
    • F16L55/175Devices for covering leaks in pipes or hoses, e.g. hose-menders from outside the pipe by using materials which fill a space around the pipe before hardening

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Lining Or Joining Of Plastics Or The Like (AREA)

Abstract

The invention discloses a construction method for repairing an underground pipeline, which belongs to the field of municipal engineering construction, and comprises a CCTV monitor, a pipeline dredging device and ultraviolet curing equipment; the method also comprises the steps of setting traffic diversion, ventilating the pipeline, plugging two ends of an upstream inspection well and a downstream inspection well, dredging the pipeline, detecting CCTV, plugging a water leakage point, pulling in a lining hose, curing the hose by ultraviolet rays, recovering the road and the like. The invention discloses a construction method for repairing an underground pipeline, which repairs the underground pipeline through an ultraviolet light curing whole pipe, and solves the problem that the underground pipeline cannot be directly excavated and repaired when water leaks from the pipeline in a special section.

Description

Construction method for repairing underground pipeline
Technical Field
The invention relates to the field of municipal engineering construction, in particular to a construction method for repairing an underground pipeline.
Background
In municipal pipelines in some main fields, if a water leakage point exists at the top of the pipeline close to a river channel, the water leakage point is difficult to repair, and the water leakage point does not have construction conditions for excavation repair, so that the water leakage point cannot be directly repaired.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention aims to provide a construction method for repairing an underground pipeline, which repairs the underground pipeline through an ultraviolet light curing whole pipe and solves the problem that the underground pipeline cannot be directly excavated and repaired when water leaks from the underground pipeline.
In order to achieve the purpose, the invention adopts the following technical scheme:
the invention provides a construction method for repairing an underground pipeline, which comprises a CCTV monitor, a pipeline dredging device and ultraviolet curing equipment;
also comprises the following steps:
s1, arranging a closed construction area around the inspection well, conducting traffic diversion, and ventilating the underground pipeline to be repaired;
s2, plugging a water inlet of the upstream inspection well and a water outlet of the downstream inspection well by using an air bag after the pipeline is ventilated, and cleaning sludge in the pipeline by using dredging equipment after plugging;
s3, scanning the basic situation in the pipeline through CCTV detection equipment, and determining the position of a water leakage point;
s4, plugging the position of a water leakage point in the pipeline;
s5, after the water leakage point is blocked, whether the water leakage condition exists is determined visually, if the water leakage condition does not exist, the lining hose is immediately placed into the water leakage point, and the lining hose is cured through ultraviolet curing equipment;
and S6, taking out the blocking air bags at the upstream and downstream, recovering the drainage function of the pipeline, and recovering the normal operation of the road.
Preferably, in step S4, the step of plugging the water leakage point in the pipeline is as follows:
a. a timber pile is driven into the center of the water leakage point to extrude soil outside the pipeline of the water leakage point, and the top of the timber pile is sunk into the inner wall of the pipeline;
b. symmetrically driving wood piles along the periphery of the center of the wood pile to further extrude soil outside the water leakage point, wherein the wood piles are symmetrically crossed from bottom to top left and right, the surrounding wood pile tops sink into the inner wall of the pipeline, and the wood pile tops form an arc shape which is the same as that of the inner wall of the pipeline;
c. after the water flow at the water leakage point is obviously reduced and becomes leakage, the rapid-setting cement is adopted to be mixed into the mucilage, and the mucilage is rapidly divided into three layers to be smeared at the water leakage point.
Preferably, in step S5, the specific steps of placing the lining hose are as follows:
and placing a winch at a wellhead of a downstream outlet, manually dragging a steel wire rope of the winch from the downstream to an upstream wellhead through an existing pipeline, slowly dragging the steel wire rope into an underground pipeline after the steel wire rope is connected with a lining hose, plugging a port of the downstream lining hose by using an anchor ear after the lining hose is placed in place, blowing air from the upstream to the lining hose by using an air blower, and unfolding the lining hose.
Preferably, in step S5, the step of curing the lining hose by the ultraviolet curing apparatus is as follows:
and (3) feeding the ultraviolet lamp row from the upstream to the downstream, sealing the upper opening of the lining hose by using a lantern ring plate, opening a switch of the ultraviolet lamp row, and slowly pulling back the lamp row.
Preferably, after the lining hose is cured, the lining hose with two ends exceeding the pipeline is cut along the wall of the inspection well, and epoxy resin is adopted between the lining hose and the original concrete pipe for floating and plugging.
The invention has the beneficial effects that:
the ultraviolet photocuring whole pipe is repaired aiming at the special water leakage point existing at the top of the pipeline close to the river channel, and the problem that the pipeline in the section cannot be directly excavated and repaired when leaking water is solved.
Drawings
Fig. 1 is a construction diagram of a construction method for repairing an underground pipe according to an embodiment of the present invention.
Detailed Description
In practical engineering, for example, municipal pipelines in Kun mountain Yu river have the length of 192m, no well room in the middle, the pipe diameter of 800mm, the burial depth of about 9m, the water level in the river channel is about 1.2m below the road surface and is close to the river channel. A water leakage point is arranged at a position close to the top of one side of the river channel in the pipeline and is 108.5m away from the upstream well chamber. The surface of the pipeline at the water leakage point is seriously damaged to form an irregular circle with the diameter of about 20cm, the water flow is sprayed and has the diameter of about 9cm, and because the road section is a main traffic road, the traffic flow is larger, the road section is close to a river channel, the excavation repairing construction condition is not provided, and the ultraviolet light curing whole-pipe repairing is determined. Before the lining hose is placed into the pipeline, the leakage point needs to be subjected to leakage stoppage treatment.
The technical scheme of the invention is further explained by the specific implementation mode in combination with the attached drawings.
As shown in fig. 1, the construction method for repairing an underground pipeline provided in this embodiment includes a CCTV monitor, a pipeline dredging device, and an ultraviolet curing device;
also comprises the following steps:
s1, arranging a closed construction area around the inspection well, conducting traffic diversion, and ventilating the underground pipeline to be repaired;
s2, plugging a water flow inlet of the upstream inspection well and a water flow outlet of the downstream inspection well by using an air bag after the pipeline is ventilated, and cleaning sludge in the pipeline by using dredging equipment after plugging is finished so as to ensure the cleanness of the pipeline;
s3, scanning the basic situation in the pipeline through CCTV detection equipment, and determining the position of a water leakage point;
s4, plugging the position of a water leakage point in the pipeline;
s5, after the water leakage point is blocked, whether the water leakage condition exists is determined visually, if the water leakage condition does not exist, the lining hose is immediately placed into the water leakage point, and the lining hose is cured through ultraviolet curing equipment;
and S6, taking out the blocking air bags at the upstream and downstream, recovering the drainage function of the pipeline, and recovering the normal operation of the road.
In order to realize the plugging of the water leakage point, further, in step S4, the steps for plugging the water leakage point in the pipeline are as follows:
a. a timber pile with the length of 40cm and the diameter of 5cm is driven into the center of the water leakage point, soil outside the pipeline of the water leakage point is extruded, and the top of the timber pile is sunk into the inner wall of the pipeline by 5 cm;
b. symmetrically driving wood piles with the length of 35cm and the diameter of 5cm along the periphery of the center of the wood pile to further extrude soil outside a water leakage point, wherein the wood piles are symmetrical in a left-right mode from bottom to top, the tops of the surrounding wood piles are sunk into the inner wall of the pipeline by 5cm, and the tops of the wood piles form an arc shape which is the same as that of the inner wall of the pipeline;
c. after the water flow at the water leakage point is obviously reduced and becomes leakage, adopting quick-setting cement according to the water-cement ratio of 1: 4, mixing the mixture into mucilage, quickly dividing the mucilage into three layers, smearing the mucilage on a water leakage point, wherein the thickness of the first layer is 2.5cm, the thickness of the second layer is 1.5cm, and the third layer is leveled to form an arc shape which is the same as that of the inner wall of the pipeline;
and (b) ventilating the pipeline before the timber pile is driven in the step a, detecting gas in a limited space, and enabling an operator to enter a water leakage point after the standard is met.
In order to place the lining hose, further, in step S5, the concrete steps of placing the lining hose are as follows:
and placing a winch at a wellhead of a downstream outlet, manually dragging a steel wire rope of the winch from the downstream to an upstream wellhead through an existing pipeline, slowly dragging the steel wire rope into an underground pipeline after the steel wire rope is connected with a lining hose, plugging a port of the downstream lining hose by using a hoop after the lining hose is placed in place, blowing air from the upstream to the lining hose by using an air blower, unfolding the lining hose, and enabling the thickness of the lining hose to be 8 mm.
In order to realize the ultraviolet curing, further, in step S5, the step of curing the lining hose by the ultraviolet curing apparatus is as follows:
and (3) feeding the ultraviolet lamp row from the upstream to the downstream, sealing the upper opening of the lining hose by using a lantern ring plate, opening a switch of the ultraviolet lamp row, and slowly pulling back the lamp row at the pulling speed of 5 mm/s.
In order to plug the lining hose, further, after the lining hose is cured, the lining hose with two ends exceeding the pipeline is cut along the wall of the inspection well, and epoxy resin is adopted between the lining hose and the original concrete pipe for floating plugging.
While the invention has been described with reference to a preferred embodiment, it will be understood by those skilled in the art that various changes may be made and equivalents may be substituted for elements thereof without departing from the spirit and scope of the invention. The present invention is not to be limited by the specific embodiments disclosed herein, and other embodiments that fall within the scope of the claims of the present application are intended to be within the scope of the present invention.

Claims (6)

1. A construction method for repairing underground pipelines is characterized in that:
comprises a CCTV monitor, a pipeline dredging device and ultraviolet curing equipment;
also comprises the following steps:
s1, arranging a closed construction area around the inspection well, conducting traffic diversion, and ventilating the underground pipeline to be repaired;
s2, plugging a water inlet of the upstream inspection well and a water outlet of the downstream inspection well by using an air bag after the pipeline is ventilated, and cleaning sludge in the pipeline by using dredging equipment after plugging;
s3, scanning the basic situation in the pipeline through CCTV detection equipment, and determining the position of a water leakage point;
s4, plugging the position of a water leakage point in the pipeline;
s5, after the water leakage point is blocked, whether the water leakage condition exists is determined visually, if the water leakage condition does not exist, the lining hose is immediately placed into the water leakage point, and the lining hose is cured through ultraviolet curing equipment;
and S6, taking out the blocking air bags at the upstream and downstream, recovering the drainage function of the pipeline, and recovering the normal operation of the road.
2. A construction method for repairing an underground pipe according to claim 1, wherein:
in step S4, the steps for plugging the water leakage point in the pipeline are as follows:
a. a timber pile is driven into the center of the water leakage point to extrude soil outside the pipeline of the water leakage point, and the top of the timber pile is sunk into the inner wall of the pipeline;
b. symmetrically driving wood piles along the periphery of the center of the wood pile to further extrude soil outside the water leakage point, wherein the wood piles are symmetrically crossed from bottom to top left and right, the surrounding wood pile tops sink into the inner wall of the pipeline, and the wood pile tops form an arc shape which is the same as that of the inner wall of the pipeline;
c. after the water flow at the water leakage point is obviously reduced and becomes leakage, the rapid-setting cement is adopted to be mixed into the mucilage, and the mucilage is rapidly divided into three layers to be smeared at the water leakage point.
3. A construction method for repairing an underground pipe according to claim 1, wherein:
in step S5, the specific steps of placing the lining hose are as follows:
and placing a winch at a wellhead of a downstream outlet, manually dragging a steel wire rope of the winch from the downstream to an upstream wellhead through an existing pipeline, slowly dragging the steel wire rope into an underground pipeline after the steel wire rope is connected with a lining hose, plugging a port of the downstream lining hose by using an anchor ear after the lining hose is placed in place, blowing air from the upstream to the lining hose by using an air blower, and unfolding the lining hose.
4. A construction method for repairing an underground pipe according to claim 3, wherein:
before the lining hose is dragged into the underground pipeline, detergent is coated on the outer surface of the lining hose to reduce friction between the lining hose and the inner wall of the pipeline.
5. A construction method for repairing an underground pipe according to claim 1, wherein:
in step S5, the step of curing the lining hose by the ultraviolet curing apparatus is as follows:
and (3) feeding the ultraviolet lamp row from the upstream to the downstream, sealing the upper opening of the lining hose by using a lantern ring plate, opening a switch of the ultraviolet lamp row, and slowly pulling back the lamp row.
6. A construction method for repairing an underground pipe according to claim 5, wherein:
and after the lining hose is cured, cutting the lining hose with two ends exceeding the pipeline along the wall of the inspection well, and trowelling and plugging the lining hose and the original concrete pipe by adopting epoxy resin.
CN202110008968.9A 2021-01-05 2021-01-05 Construction method for repairing underground pipeline Pending CN112762269A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110008968.9A CN112762269A (en) 2021-01-05 2021-01-05 Construction method for repairing underground pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110008968.9A CN112762269A (en) 2021-01-05 2021-01-05 Construction method for repairing underground pipeline

Publications (1)

Publication Number Publication Date
CN112762269A true CN112762269A (en) 2021-05-07

Family

ID=75699491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110008968.9A Pending CN112762269A (en) 2021-01-05 2021-01-05 Construction method for repairing underground pipeline

Country Status (1)

Country Link
CN (1) CN112762269A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236900A (en) * 2021-06-11 2021-08-10 广州市卓建工程有限公司 Drainage pipeline lining repairing construction method
CN114658953A (en) * 2022-03-31 2022-06-24 广州易探科技有限公司 Ultraviolet curing pipeline trenchless repairing system and processing method
CN115163964A (en) * 2022-07-14 2022-10-11 哈工大机器人(合肥)国际创新研究院 Reducing gasbag shutoff robot system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5829920A (en) * 1997-04-14 1998-11-03 Christenson; John Method of testing wrapped submerged piling for infestation
CN101914917A (en) * 2010-08-10 2010-12-15 中铁一局集团有限公司 Anti-seepage and leak-blocking construction method for excavation of subway foundation pit in soft soil area
CN108331996A (en) * 2018-01-09 2018-07-27 辽宁省水利水电科学研究院 A kind of emergent method for blocking of concrete pressure pipeline
CN209114478U (en) * 2018-09-18 2019-07-16 浙江海北勘察股份有限公司 A kind of composite anchor pole foundation pit enclosing structure
CN110307440A (en) * 2019-06-19 2019-10-08 北京四达基业市政建设工程有限公司 A kind of pipeline inverted liner restorative procedure
CN110735992A (en) * 2019-10-31 2020-01-31 中铁十八局集团建筑安装工程有限公司 CIPP ultraviolet curing repair construction method
CN210069249U (en) * 2019-01-22 2020-02-14 中电建十一局工程有限公司 Ultraviolet curing repair construction device for underground pipe network
US20200318774A1 (en) * 2019-09-25 2020-10-08 Infrastructure Renewal Insitute of Southern China Local repair method combining internally bonded CFRP and polymer grouting for cracks in drainage pipe
CN111750207A (en) * 2020-06-17 2020-10-09 上海懿诚市政工程有限公司 CIPP non-excavation pipeline repairing method
CN112049219A (en) * 2020-08-31 2020-12-08 厦门顶巢建筑修缮研究院有限公司 Construction method of repairing system for leakage water of sewage pipe network

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5829920A (en) * 1997-04-14 1998-11-03 Christenson; John Method of testing wrapped submerged piling for infestation
CN101914917A (en) * 2010-08-10 2010-12-15 中铁一局集团有限公司 Anti-seepage and leak-blocking construction method for excavation of subway foundation pit in soft soil area
CN108331996A (en) * 2018-01-09 2018-07-27 辽宁省水利水电科学研究院 A kind of emergent method for blocking of concrete pressure pipeline
CN209114478U (en) * 2018-09-18 2019-07-16 浙江海北勘察股份有限公司 A kind of composite anchor pole foundation pit enclosing structure
CN210069249U (en) * 2019-01-22 2020-02-14 中电建十一局工程有限公司 Ultraviolet curing repair construction device for underground pipe network
CN110307440A (en) * 2019-06-19 2019-10-08 北京四达基业市政建设工程有限公司 A kind of pipeline inverted liner restorative procedure
US20200318774A1 (en) * 2019-09-25 2020-10-08 Infrastructure Renewal Insitute of Southern China Local repair method combining internally bonded CFRP and polymer grouting for cracks in drainage pipe
CN110735992A (en) * 2019-10-31 2020-01-31 中铁十八局集团建筑安装工程有限公司 CIPP ultraviolet curing repair construction method
CN111750207A (en) * 2020-06-17 2020-10-09 上海懿诚市政工程有限公司 CIPP non-excavation pipeline repairing method
CN112049219A (en) * 2020-08-31 2020-12-08 厦门顶巢建筑修缮研究院有限公司 Construction method of repairing system for leakage water of sewage pipe network

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘景春: "《建筑工程与施工技术》", 30 June 2019 *
西安鸿飞建筑工程有限公司: "基坑堵漏方案", 《HTTPS://WWW.BMLINK.COM/HONGFEICC/NEWS/970010.HTML》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113236900A (en) * 2021-06-11 2021-08-10 广州市卓建工程有限公司 Drainage pipeline lining repairing construction method
CN113236900B (en) * 2021-06-11 2022-03-11 广州市卓建工程有限公司 Drainage pipeline lining repairing construction method
CN114658953A (en) * 2022-03-31 2022-06-24 广州易探科技有限公司 Ultraviolet curing pipeline trenchless repairing system and processing method
CN115163964A (en) * 2022-07-14 2022-10-11 哈工大机器人(合肥)国际创新研究院 Reducing gasbag shutoff robot system
CN115163964B (en) * 2022-07-14 2023-07-04 哈工大机器人(合肥)国际创新研究院 Reducing gasbag shutoff robot system

Similar Documents

Publication Publication Date Title
CN112762269A (en) Construction method for repairing underground pipeline
US9353888B2 (en) Polymer bag grouting method for repairing settlement of underground pipelines
US9777881B2 (en) Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines
CN102486247B (en) Water supply and drainage pipeline repair technique adopting size film lining method
CN110645440A (en) Trenchless repairing device and method for large-diameter concrete drain pipe disjointing
CN107859141B (en) Modification method for upstream sewage pipeline of sewage station of nuclear power plant
CN110747965B (en) Expansion-draw pipe construction process for reconstruction and expansion of drainage pipe network
KR101060510B1 (en) How to repair pipeline
CN112524390A (en) Municipal pipeline UV lining method in-situ curing repair construction method
CN111424613B (en) Method for treating through cracks of roller compacted concrete dam
CN105464194A (en) Water proofing and leak repairing construction method for sewage pipe network below underground water level
CN113531274A (en) Pipeline non-excavation repairing method
CN107763362A (en) Interior piston ring method pipe joint method for repairing and constructing
US4921374A (en) Method for repairing underground sewer lines
CN115492215A (en) Non-excavation dredging and repairing construction method for drainage pipeline
CN110985808A (en) Drainage pipeline steel hoop repairing construction method
CN103615044B (en) Inner sleeve blocking method for leakage of small-diameter concrete drainage pipeline
US11585467B2 (en) Trenchless methods for forming curved hole channel with steel sleeve and pipeline lifting
CN113818539B (en) Inspection well interface device
CN114703878A (en) Plugging and draining device for dewatering well and construction method
JP6382053B2 (en) Intake system
US20230235546A1 (en) System and method for lining pipe while maintaining flow therethrough
CN112112248A (en) Method for repairing defect of channel box
CN111677972B (en) Prefabricated steel ring construction method applied to rapid repair of pressure pipeline
DE4436375C2 (en) Rapid process for the repair of leaky socket connections in accessible pipelines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210507

RJ01 Rejection of invention patent application after publication