CN112727147A - 一种室外悬空台阶拆除方法 - Google Patents
一种室外悬空台阶拆除方法 Download PDFInfo
- Publication number
- CN112727147A CN112727147A CN202011531885.XA CN202011531885A CN112727147A CN 112727147 A CN112727147 A CN 112727147A CN 202011531885 A CN202011531885 A CN 202011531885A CN 112727147 A CN112727147 A CN 112727147A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- dismantled
- pipe scaffold
- dismantling
- steps
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/08—Wrecking of buildings
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/08—Wrecking of buildings
- E04G23/082—Wrecking of buildings using shears, breakers, jaws and the like
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明提供一种室外悬空台阶拆除方法,包括设置防护栏并拆除待拆除台阶顶面的踏步装饰面;切断电缆和水、电、气管道;采用钢管脚手架将待拆除台阶两端头部位进行加固,钢管脚手架的顶部采用顶托及方木顶住待拆除台阶的底部;在待拆除台阶上固定多根起吊用钢丝绳,并将钢丝绳的一端与起吊设备连接;采用切割设备将待拆除台阶的两端进行切割,钢管脚手架上部的构件不进行破除;通过起吊设备将拆除台阶进行吊起后放置到地面;通过破碎机对钢管脚手架上的待拆除台阶进行破碎性拆除;拆除钢管脚手架,清理工程垃圾;在拆除时配好喷雾机及洒水车对施工现象的扬尘进行控制。不会对主体建筑造成损伤,操作简单,施工方便,工作效率高,安全性高。
Description
技术领域
本发明涉及建筑施工技术领域,具体涉及一种室外悬空台阶拆除方法。
背景技术
目前,在对体育场主会场周边的大台阶、人行天桥及相关搁置牛腿进行拆除时,一般首先架起护栏,然后先切断电缆、水、电、气、管道等,再通过破碎机直接对主会场周边的大台阶、人行天桥及相关搁置牛腿进行破坏性拆除,最后再对拆卸下来的工程垃圾进行清理,虽然可以进行拆除,但是,在通过破碎机直接对主会场周边的大台阶、人行天桥及相关搁置牛腿进行破坏性拆除时,在拆除过程中会产生大量的垃圾,且垃圾比较破碎,而且在没有脚手架对拆除物进行支撑,当拆除物掉落时容易对地面造成损伤,对于周围环境也容易造成损伤,而且拆除物悬空长度较大时,还容易在拆除过程中出现直接断裂掉落的现象,危险性高,如果不是一次性拆除,安全维护难度高,因此,对于需要长时间或者悬空长度较大的工程进行拆除时,一般会增加脚手架对拆除主体进行支撑,以避免出现建筑物断裂的现象,但是,该结构在拆除时,需要陆续对脚手架进行拆除后才能再次施工,施工效率低,因此,在通过破碎机直接对主会场周边的大台阶、人行天桥及相关搁置牛腿进行破坏性拆除的过程中,需要提供一种不需要设置大量脚手架对拆除物进行支撑的情况下,也能够进行安全快速拆除的方法。
发明内容
为了解决现有技术中存在的某种或某些技术问题,本发明提供一种室外悬空台阶拆除方法,不会对主体建筑造成损伤,操作简单,施工方便,工作效率高,安全性高。
为解决上述现有的技术问题,本发明采用如下方案:
一种室外悬空台阶拆除方法,其特征在于:包括
步骤一:设置防护栏并拆除待拆除台阶顶面的踏步装饰面;
步骤二:切断待拆除台阶两端的电缆和水、电、气管道;
步骤三:采用钢管脚手架将待拆除台阶两端头部位进行加固,所述钢管脚手架的顶部采用顶托及方木顶住待拆除台阶的底部;
步骤四:在待拆除台阶上固定多根起吊用钢丝绳,并将钢丝绳的一端与起吊设备连接;
步骤五:采用切割设备将待拆除台阶的两端进行切割,钢管脚手架上部的构件不进行破除,使待拆除台阶与钢管脚手架支撑部分的待拆除台阶进行分离;
步骤六:通过起吊设备将两端切断后的待拆除台阶进行吊起后放置到地面;
步骤七:通过破碎机对所述钢管脚手架上的待拆除台阶进行破碎性拆除;
步骤八:全部破除完成后,拆除钢管脚手架,清理工程垃圾;
步骤九:在拆除时配好喷雾机及洒水车对施工现象的扬尘进行控制。
进一步地,所述待拆除台阶两端头部位的加固距离为0.5~1米。
进一步地,所述钢管脚手架中每根立杆所承受荷载的计算方式为:X=1.2*(Nkg*60%)/(a1*b1)*a2*b2,其中Nkg为待拆除台阶总重量,a1和b1分别为所述钢管脚手架支撑部分的长宽,a2和b2分别为所述钢管脚手架中相邻两根立杆之间的横向间距和纵向间距。
进一步地,所述钢管脚手架的底部设有槽钢或50mm左右厚度的垫木。
进一步地,在拆除前采用围护对建筑物周边的门窗进行覆盖防护。
进一步地,所述步骤五中的切割设备包括长壁液压剪、绳锯或液压剪中的一种或多种。
相比现有技术,本发明的有益效果在于:
1、在拆除前先通过钢管脚手架对当前需要拆除区域的两端进行支撑固定,钢管脚手架的顶部采用顶托及方木顶住待拆除台阶的底部,在钢管底部增加槽钢或50mm厚垫木,以便当前拆除阶梯没有后其他部分不会出现掉落现象,在拆除过程中由于有脚手架的支撑,可以随时停止作业,而且脚手架只需要对两端进行支撑,本身材料的需求量更小,拆装效率也更高;
2、采用切割设备将待拆除台阶的两端进行切割时,钢管脚手架上部的区域不进行破除,使待拆除台阶与钢管脚手架支撑部分的待拆除台阶进行分离,从而使拆除部分与主体建筑物之间形成一个安全区域,在切割拆除时即保证了主体建筑物的安全,施工时又更加方便,从而避免了常规拆除过程中容易出现主体建筑物被动破损的情况;
3、在对大台阶两端进行切断前,还需在待拆除台阶段固定上多根起吊用钢丝绳,并将钢丝绳的一端与起吊设备连接,以便切割段落后可以通过起吊设备直接对两端分离的台阶进行吊起到安全区域后再进行破碎施工,即有效的降低了高空作业的难度,提高了施工安全性,又提高了施工效率和工程垃圾搬运效率,而且在拆除过程中不会再出现大量的飞溅垃圾以及大块的废料掉落,不会再对地面造成严重损伤,即使对于悬空长度较大的阳台进行拆除时,也不会再出现还未拆除区域直接断裂掉落的现象。
具体实施方式
下面,对本发明做进一步描述,需要说明的是,在不相冲突的前提下,以下描述的各实施例之间或各技术特征之间可以任意组合形成新的实施例。
一种室外悬空台阶拆除方法,包括
步骤一:设置防护栏并拆除待拆除台阶顶面的踏步装饰面;
步骤二:切断待拆除台阶两端的电缆和水、电、气管道;
步骤三:采用钢管脚手架将待拆除台阶两端头部位进行加固,所述钢管脚手架的顶部采用顶托及方木顶住待拆除台阶的底部;
步骤四:在待拆除台阶上固定多根起吊用钢丝绳,并将钢丝绳的一端与起吊设备连接;
步骤五:采用切割设备将待拆除台阶的两端进行切割,钢管脚手架上部的构件不进行破除,使待拆除台阶与钢管脚手架支撑部分的待拆除台阶进行分离;
步骤六:通过起吊设备将两端切断后的待拆除台阶进行吊起后放置到地面;
步骤七:通过破碎机对所述钢管脚手架上的待拆除台阶进行破碎性拆除;
步骤八:全部破除完成后,拆除钢管脚手架,清理工程垃圾;
步骤九:在拆除时配好喷雾机及洒水车对施工现象的扬尘进行控制。
进一步地改进为,所述待拆除台阶两端头部位的加固距离为0.5~1米;所述钢管脚手架的底部设有槽钢或50mm左右厚度的垫木;在拆除前采用围护对建筑物周边的门窗进行覆盖防护;所述步骤五中的切割设备包括长壁液压剪、绳锯或液压剪中的一种或多种。
在工作人员进入施工现场对大台阶、人行天桥或相关搁置牛腿进行实际施工拆除时,以拆除大台阶为例,首先设置防护栏,确保行人安全,以防止非工作人员以外闯入,然后拆除待拆除台阶顶面的踏步装饰面(大理石),并且拆除与拆除物相连的电缆、管道、设备、电气、照明等设施,拆除前需切断水电电源,在拆除前还需要对于待拆除台阶周围不需要拆除的建筑物门窗进行覆盖防护,以防止拆除时飞溅物砸伤门窗,同时,在拆除现场每个施工区域放置2台喷雾机,采用湿法作业,控制施工扬尘,砂石飞溅,拆除时采用先上后下、先非承重结构后承重结构、先板、梁后墙、柱的原则,然后,采用钢管脚手架将待拆除台阶两端头部位进行加固,钢管脚手架的顶部采用顶托及方木顶住待拆除台阶的底部,为防止底部基础不平或拆除中不均匀变形,在钢管底部增加槽钢或50mm厚垫木,当台阶具有多层时,采用分层从上往下拆除,在拆除前先通过钢管脚手架对当前需要拆除区域的两端进行支撑固定,以便当前拆除阶梯没有后其他部分不会出现掉落现象,在对大台阶两端进行切断前,还需在待拆除台阶段固定上多根起吊用钢丝绳,并将钢丝绳的一端与起吊设备连接,以便切割段落后可以通过起吊设备直接对两端分离的台阶进行吊起到安全区域。
在对台阶两端进行实际切割时,采用切割设备将待拆除台阶的两端进行切割,在切割过程中,钢管脚手架上部的区域不进行破除,使待拆除台阶与钢管脚手架支撑部分的待拆除台阶进行分离;从而使拆除部分与主体建筑物之间形成一个安全区域,在切割拆除时即保证了主体建筑物的安全,施工时又更加方便,从而避免了常规拆除过程中容易出现主体建筑物被动破损的情况,且拆除时整体直接采用起吊设备吊到安全地带后再进行破碎施工,即有效的降低了高空作业的难度,提高了施工安全性,又提高了施工效率和工程垃圾搬运效率,而且在拆除过程中不会再出现大量的飞溅垃圾以及大块的废料掉落,不会再对地面造成严重损伤,即使对于悬空长度较大的阳台进行拆除时,也不会再出现还未拆除区域直接断裂掉落的现象,在拆除过程中由于有脚手架的支撑,可以随时停止作业,而且脚手架只需要对两端进行支撑,本身材料的需求量更小,拆装效率也更高。
当待拆除台阶的主体部分通过起吊设备吊起到地面后,再通过破碎机正对性的对钢管脚手架上的待拆除台阶进行破碎性拆除,当距离墙面较近时,还可以辅助人工拆除,从而保证了外墙面的整体性,使墙面不会因台阶的拆除而造成实质性破坏,全部破除完成后,拆除钢管脚手架,清理工程垃圾,切割设备一般包括长壁液压剪、绳锯或液压剪中的一种或多种,根据不同的情况可以进行不同的设备选取,从而实现宽度很小的情况下进行切断处理。建筑物完全解体后,用挖掘机装车,自卸汽车运到垃圾破碎机处处理后外运,地上部分建筑物完全拆除后,拆除地下部分,破除砼地坪。
施工前查看图纸,是否会碰到地下管线,遇到地下管线时,先确认管线是否是废弃的,能否拆除,确定后确认切断水电后方可用冷法切割,明确管内无易燃、易爆物后,才可动火使用氧气乙炔焰切割。与地下室相关的框架柱拆除时,需注意拆除至地面以上原有施工缝部位,接缝处采用人工风镐破除,并随后进行凿毛修补恢复。严禁继续向下拆除破坏地下室结构。
进一步地改进为,所述钢管脚手架中每根立杆所承受荷载的计算方式为:X=1.2*(Nkg*60%)/(a1*b1)*a2*b2,其中Nkg为待拆除台阶总重量,a1和b1分别为所述钢管脚手架支撑部分的长宽,a2和b2分别为所述钢管脚手架中相邻两根立杆之间的横向间距和纵向间距。
钢管脚手架支撑计算方式以下列为例:
例一、大台阶宽度10m,跨度8m,梁高0.8/1.29m,梁宽0.3m,板厚按0.15m计算
板:10m*8m*0.15m*25KN/m3=300KN=30t
梁:(4m*0.3m*0.8m+4m*1.29m*0.3m)*25KN/m3=62.7KN;0.3m*0.8m*10m*25=60KN 62.7KN*5+60KN=373.5KN=37.35t
(1)大台阶重量计算:
总重量:30+37.35=67.35t
(2)端头(1.5m)重量:60KN+(255+300)*1.5/8=164KN=16.4t
(3)钢管架回顶重量按总体重量的60%计算
1.钢管特性
2.每根立杆所承受荷载
1)大台阶荷载设计值:
立杆承受的最大竖向力设计值:N=32.328×0.5×0.5=8.082kN
3.立杆刚度、稳定性
其中l0由附录D得:l0=kμh=1.167×1.272×1.5=2.227m;
例二、小台阶宽度3.5m,跨度9.3m,梁高0.8(WL-14)/1.15m(WL-13),梁宽0.3m,板厚按0.15m计算
板:3.5m*9.3m*0.15m*25KN/m3=122KN
梁:(9.3m*0.3m*0.8m+9.3m*1.15m*0.3m)*25KN/m3=136KN;
0.3m*0.8m*3.5m*25=21KN
136KN+21KN=157KN
(1)大台阶重量计算:
总重量:122+157=279KN
(2)端头(4.7m)重量:21KN+(136+122)*4.7/9.3=151KN
(3)钢管架回顶重量按总体重量的60%计算
1.钢管特性
2.每根立杆所承受荷载
1)小台阶荷载设计值:
立杆承受的最大竖向力设计值:N=12.21×1×1=12.21kN
3.立杆刚度、稳定性
其中l0由附表D得:l0=kμh=1.167×1.473×1.5=2.578m;
上述实施方式仅为本发明的优选实施方式,不能以此来限定本发明保护的范围,本领域的技术人员在本发明的基础上所做的任何非实质性的变化及替换均属于本发明所要求保护的范围。
Claims (6)
1.一种室外悬空台阶拆除方法,其特征在于:包括
步骤一:设置防护栏并拆除待拆除台阶顶面的踏步装饰面;
步骤二:切断待拆除台阶两端的电缆和水、电、气管道;
步骤三:采用钢管脚手架将待拆除台阶两端头部位进行加固,所述钢管脚手架的顶部采用顶托及方木顶住待拆除台阶的底部;
步骤四:在待拆除台阶上固定多根起吊用钢丝绳,并将钢丝绳的一端与起吊设备连接;
步骤五:采用切割设备将待拆除台阶的两端进行切割,钢管脚手架上部的构件不进行破除,使待拆除台阶与钢管脚手架支撑部分的待拆除台阶进行分离;
步骤六:通过起吊设备将两端切断后的待拆除台阶进行吊起后放置到地面;
步骤七:通过破碎机对所述钢管脚手架上的待拆除台阶进行破碎性拆除;
步骤八:全部破除完成后,拆除钢管脚手架,清理工程垃圾;
步骤九:在拆除时配好喷雾机及洒水车对施工现象的扬尘进行控制。
2.根据权利要求1所述的一种室外悬空台阶拆除方法,其特征在于:所述待拆除台阶两端头部位的加固距离为0.5~1米。
3.根据权利要求2所述的一种室外悬空台阶拆除方法,其特征在于:所述钢管脚手架中每根立杆所承受荷载的计算方式为:X=1.2*(Nkg*60%)/(a1*b1)*a2*b2,其中Nkg为待拆除台阶总重量,a1和b1分别为所述钢管脚手架支撑部分的长宽,a2和b2分别为所述钢管脚手架中相邻两根立杆之间的横向间距和纵向间距。
4.根据权利要求1所述的一种室外悬空台阶拆除方法,其特征在于:所述钢管脚手架的底部设有槽钢或50mm左右厚度的垫木。
5.根据权利要求1所述的一种室外悬空台阶拆除方法,其特征在于:在拆除前采用围护对建筑物周边的门窗进行覆盖防护。
6.根据权利要求1所述的一种室外悬空台阶拆除方法,其特征在于:所述步骤五中的切割设备包括长壁液压剪、绳锯或液压剪中的一种或多种。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011531885.XA CN112727147A (zh) | 2020-12-23 | 2020-12-23 | 一种室外悬空台阶拆除方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011531885.XA CN112727147A (zh) | 2020-12-23 | 2020-12-23 | 一种室外悬空台阶拆除方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112727147A true CN112727147A (zh) | 2021-04-30 |
Family
ID=75604178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011531885.XA Pending CN112727147A (zh) | 2020-12-23 | 2020-12-23 | 一种室外悬空台阶拆除方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112727147A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114592717A (zh) * | 2022-03-08 | 2022-06-07 | 深圳市天健(集团)股份有限公司 | 建筑废弃物的绿色拆除方法 |
CN115110798A (zh) * | 2022-08-02 | 2022-09-27 | 中建二局第三建筑工程有限公司 | 一种轻钢管架体系结构液压剪切拆除方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419918A (zh) * | 2017-07-27 | 2017-12-01 | 上海二十冶建设有限公司 | 一种历史建筑物外围单片框架保留拆除方法 |
CN110685459A (zh) * | 2019-10-21 | 2020-01-14 | 中国水利水电第三工程局有限公司 | 一种启闭机排架从下部拆除的破碎锤拆除施工方法 |
CN110820608A (zh) * | 2019-12-18 | 2020-02-21 | 中铁七局集团郑州工程有限公司 | 既有铁路旅客进站天桥拆除方法 |
CN110905232A (zh) * | 2019-11-29 | 2020-03-24 | 上海宝冶市政工程有限公司 | 一种混凝土结构机械静力拆除方法 |
CN111535190A (zh) * | 2020-05-08 | 2020-08-14 | 安徽伟宏钢结构集团股份有限公司 | 一种安全性高的桥梁安拆施工方法 |
-
2020
- 2020-12-23 CN CN202011531885.XA patent/CN112727147A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419918A (zh) * | 2017-07-27 | 2017-12-01 | 上海二十冶建设有限公司 | 一种历史建筑物外围单片框架保留拆除方法 |
CN110685459A (zh) * | 2019-10-21 | 2020-01-14 | 中国水利水电第三工程局有限公司 | 一种启闭机排架从下部拆除的破碎锤拆除施工方法 |
CN110905232A (zh) * | 2019-11-29 | 2020-03-24 | 上海宝冶市政工程有限公司 | 一种混凝土结构机械静力拆除方法 |
CN110820608A (zh) * | 2019-12-18 | 2020-02-21 | 中铁七局集团郑州工程有限公司 | 既有铁路旅客进站天桥拆除方法 |
CN111535190A (zh) * | 2020-05-08 | 2020-08-14 | 安徽伟宏钢结构集团股份有限公司 | 一种安全性高的桥梁安拆施工方法 |
Non-Patent Citations (3)
Title |
---|
毛以卫 金天红 祝自强: ""建筑物拆除及建筑垃圾处理分析"", 《第26届华东六省一市土木建筑工程建造技术交流会论文集(下册)施工技术编辑部会议论文集》 * |
潘鸿宝等: "城市立交桥拆除改造技术", 《施工技术》 * |
王东升等: "《水利水电工程施工安全生产技术》", 30 April 2018, 中国矿业大学出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114592717A (zh) * | 2022-03-08 | 2022-06-07 | 深圳市天健(集团)股份有限公司 | 建筑废弃物的绿色拆除方法 |
CN115110798A (zh) * | 2022-08-02 | 2022-09-27 | 中建二局第三建筑工程有限公司 | 一种轻钢管架体系结构液压剪切拆除方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110512895A (zh) | 一种高层现浇混凝土建筑拆除施工方法 | |
CN107419918B (zh) | 一种历史建筑物外围单片框架保留拆除方法 | |
JP4461434B2 (ja) | 解体養生ユニットおよびそれを用いた超高層建物の解体工法 | |
CN112727147A (zh) | 一种室外悬空台阶拆除方法 | |
CN110904867B (zh) | 上跨既有线拱桥拆除施工方法 | |
CN113833309A (zh) | 一种建筑楼群机械拆除施工方法及应用 | |
CN110820608A (zh) | 既有铁路旅客进站天桥拆除方法 | |
Gromysz | Rectification an 11-storey vertically deflected residential building | |
CN110685459B (zh) | 一种启闭机排架从下部拆除的破碎锤拆除施工方法 | |
CN104234447B (zh) | 深基坑用工具式吊挂楼梯 | |
JP2019190274A (ja) | 多層階建屋解体時の上方飛散防止養生システム及び上方飛散防止養生方法 | |
Li et al. | Study on construction technology of hydraulic climbing formwork for super high-rise building under aluminum formwork system | |
CN215978575U (zh) | 有限空间内钢筋混凝土水塔拆除用安全防护系统 | |
CN106193621A (zh) | 装配式结构叠合板串吊施工方法 | |
CN112227814B (zh) | 直筒型混凝土塔体拆除方法 | |
CN104963344B (zh) | 砼支撑拆除和结构施工同步进行的深基坑地下施工方法 | |
Andresen | Investigation of a collapsed scaffold structure | |
CN210239201U (zh) | 一种推车式电梯井口与井道防护装置 | |
CN111608376B (zh) | 一种定型构件的综合性施工工法 | |
CN109208936B (zh) | 一种既有建筑电梯井道结构加建结构及其施工方法 | |
CN212001103U (zh) | 一种地下空间垂直清淤装置 | |
CN206844680U (zh) | 钢连廊地面拼装荷载转移装置 | |
Gromysz | Analysis of removal method of a 19th church‘s deflection | |
CN218205607U (zh) | 一种防护式悬臂操作平台 | |
CN204703533U (zh) | 一种提升式卸料防护双用平台 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210430 |