Disclosure of Invention
In order to overcome the defects of the prior art, the invention aims to provide a construction process of a compaction pile for improving water stability, which can improve the water stability of the compaction pile and improve the deformation resistance of the compaction pile when meeting water; the pile has the advantages of compact pile body, strong water stability, strong bearing capacity, low cost and strong practicability.
In order to achieve the purpose, the invention adopts the following technical scheme:
a construction process of a compaction pile for improving water stability comprises the following steps:
the method comprises the following steps: determining engineering quantity of lime-soil compaction pile
The bottom of the compaction pile is high h10.4-0.5 m, diameter d10.5-0.7 m cone with a height h at the top27.5m-10m, diameter d1The engineering quantity of the compacted pile is as follows:
wherein pi is 3.1400-3.1415;
step two: drilling a pile hole according to the engineering quantity determined in the step one, and then preparing the lime soil
Preparing limestone soil with 20-30% of lime and 70-80% of clay by volume, and uniformly mixing the limestone soil and the clay for backfilling the compaction pile;
step three: configuring CaCl2Solutions, CaCl2Comprises the following components in percentage by mass:
Cacl2 0.1kg-0.15kg
water 3.471L-4.538L
0.1kg-0.15kg of CaCl2Adding into 3.471L-4.538L water, heating until the solution temperature reaches 60-80 deg.C and the concentration reaches 2.8% -3.2%;
step four: backfilling
Before backfilling, bottom ramming is firstly carried out, then the lime soil prepared in the step two is backfilled into the pile hole, and each layer of the lime soil is 0.174m3-0.457m3Adding oneSubcl2The solution is 0.446L-0.586L, then tamping, and backfilling the next layer of soil until the backfilling is completed.
During backfilling, manually matching with a rammer to continuously ram, configuring a cast steel rammer with the diameter of 0.35-0.4 m and the weight of 45-50 kg, wherein the height of the drop hammer is not less than 2m, so that the construction continuity is ensured, the rammer needs to be flat and stable, and the rammer and a pile hole are mutually aligned, so that the rammer can freely fall; the tamping of each layer is not less than 10 hammers.
After the backfilling in the fourth step is finished, the dry density of the pile body 2 of the lime-soil compaction pile is not less than 15.5kN/m, and the compactness of the pile body 2 is not less than 97%; the dry volume weight of the soil between piles is not less than 15kN/m, the average compaction coefficient of the soil between piles is not less than 93 percent, and the minimum compaction coefficient is not less than 88 percent.
Compared with the prior art, the invention has the beneficial effects that:
1. the CaCl is added into the lime soil with 20-30% of lime and 70-80% of clay in volume ratio2The solution improves the water stability of the lime-soil compaction pile, and further improves the cohesive force of particles in the lime-soil compaction pile.
2. Due to CaCl2The density has little influence on the permeability coefficient of the soil body and is along with CaCl2The content is increased, and the permeability coefficient is gradually reduced, so that the lime soil is gradually hardened, the connection force among soil particles is increased, and the bearing capacity of the lime soil compaction pile is improved.
In conclusion, the invention has the advantages of improved water stability, compact pile body, strong bearing capacity, low cost and strong practicability.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Example 1:
a construction process of a compaction pile for improving water stability comprises the following steps:
step one, determining the engineering quantity
According to the formula, determining the soil extrusionThe pile density engineering quantity is 1.393m3;
Step two: drilling a pile hole according to the engineering quantity determined in the step one, and then preparing the lime soil
Lime is prepared to be 0.279m3Clay of 1.114m3Uniformly mixing, and backfilling the compaction pile;
step three: configuring CaCl2Solutions of
Adding 0.1kgCaCl2Adding into 3.471L water, heating to 60 deg.C to make the concentration reach 2.8%;
step four: backfilling
Bottom ramming is carried out before backfilling, then the pile holes are backfilled with the lime soil prepared in the step two, and each layer of the lime soil is 0.174m3Adding once CaCl2The solution is 0.446L, then is tamped, and then the next layer of soil is backfilled until the backfilling is finished.
Example 2:
a construction process of a compaction pile for improving water stability comprises the following steps:
step one, determining the engineering quantity
According to the formula, the engineering quantity of the lime-soil compaction pile is determined to be 1.5m3;
Step two: drilling a pile hole according to the engineering quantity determined in the step one, and then preparing lime with the lime soil to be 0.3m3Clay of 1.2m3Uniformly mixing, and backfilling the compaction pile;
step three: configuring CaCl2Solutions of
Mixing 0.12kg of CaCl2Adding into 3.6L water, heating to 65 deg.C to make its concentration reach 2.9%;
step four: backfilling
Bottom ramming is carried out before backfilling, then the pile holes are backfilled with the lime soil prepared in the step two, and each layer of the lime soil is 0.188m3Adding once CaCl2The solution is 0.465L, then the rammed soil is tamped, and the next layer of soil is backfilled until the backfilling is completed.
Example 3:
a construction process of a compaction pile for improving water stability comprises the following steps:
step one, determining the engineering quantity
According to a formula, determining the engineering quantity of the lime-soil compaction pile to be 2m3;
Step two: drilling a pile hole according to the engineering quantity determined in the step one, and then preparing lime with the lime soil to be 0.5m3Clay of 1.5m3Uniformly mixing, and backfilling the compacted pile;
step three: configuring CaCl2Solutions of
Adding 0.13kg of CaCl2Adding into 4.04L water, heating to 70 deg.C to make the concentration reach 3.0%;
step four: backfilling
Bottom ramming is carried out before backfilling, then the pile holes are backfilled with the lime soil prepared in the step two, and each layer of the lime soil is 0.25m3Adding once CaCl2The solution is 0.543L, then is tamped, and then the next layer of soil is backfilled until the backfilling is completed.
Example 4:
a construction process of a compaction pile for improving water stability comprises the following steps:
step one, determining the engineering quantity
According to a formula, determining the engineering quantity of the lime-soil compaction pile to be 3m3;
Step two: drilling a pile hole according to the engineering quantity determined in the step one, and then preparing lime with lime soil to prepare lime of 0.75m3Clay of 2.25m3Uniformly mixing, and backfilling the compacted pile;
step three: configuring CaCl2Solutions of
0.14kg of CaCl was added2Adding into 4.213L water, heating to 75 deg.C to reach concentration of 3.1%;
step four: backfilling
Bottom ramming is carried out before backfilling, then the pile holes are backfilled with the lime soil prepared in the step two, and each layer of the lime soil is 0.375m3Adding once CaCl2The solution is 0.544L, then is tamped, and the next layer of soil is backfilled until the backfilling is finishedAfter that, the process is finished.
Example 5:
a construction process of a compaction pile for improving water stability comprises the following steps:
step one, determining the engineering quantity
According to the formula, the engineering quantity of the lime-soil compaction pile is determined to be 3.656m3;
Step two: drilling a pile hole according to the engineering quantity determined in the step one, and then preparing the lime soil
Lime is prepared to be 0.914m3Clay of 2.742m3Uniformly mixing, and backfilling the compacted pile;
step three: configuring CaCl2Solutions of
Adding 0.15kg of CaCl2Adding into 4.538L water, and heating to 80 deg.C to reach concentration of 3.2%;
step four: backfilling
Bottom ramming is carried out before backfilling, then the pile holes are backfilled with the lime soil prepared in the step two, and each layer of the lime soil is 0.457m3Adding once CaCl2The solution is 0.586L, then the ramming is carried out, and the backfilling of the next layer of soil is carried out until the backfilling is completed.
Experiments show that the Cacl has the same dry density2The higher the solution concentration, the better the water stability of the structure, the maximum structural parameters, when CaCl is added2When the concentration of the solution reaches 3.2%, the influence of the water stability of the structure and the concentration of the solution is small, which indicates that the CaCl is added2The joint strength of the sample with a solution concentration of 3.2% has reached a maximum value, and the bearing capacity of the compacted pile is the highest.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.