CN112482120A - Construction process for juglans sigillata massage sole pavement - Google Patents

Construction process for juglans sigillata massage sole pavement Download PDF

Info

Publication number
CN112482120A
CN112482120A CN202011533561.XA CN202011533561A CN112482120A CN 112482120 A CN112482120 A CN 112482120A CN 202011533561 A CN202011533561 A CN 202011533561A CN 112482120 A CN112482120 A CN 112482120A
Authority
CN
China
Prior art keywords
maintaining
rouge
thickness
pavement
days
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011533561.XA
Other languages
Chinese (zh)
Inventor
赵致明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangbi Yi Autonomous County Cangyang Tourism Investment Development Co ltd
Original Assignee
Yangbi Yi Autonomous County Cangyang Tourism Investment Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangbi Yi Autonomous County Cangyang Tourism Investment Development Co ltd filed Critical Yangbi Yi Autonomous County Cangyang Tourism Investment Development Co ltd
Priority to CN202011533561.XA priority Critical patent/CN112482120A/en
Publication of CN112482120A publication Critical patent/CN112482120A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • AHUMAN NECESSITIES
    • A61MEDICAL OR VETERINARY SCIENCE; HYGIENE
    • A61HPHYSICAL THERAPY APPARATUS, e.g. DEVICES FOR LOCATING OR STIMULATING REFLEX POINTS IN THE BODY; ARTIFICIAL RESPIRATION; MASSAGE; BATHING DEVICES FOR SPECIAL THERAPEUTIC OR HYGIENIC PURPOSES OR SPECIFIC PARTS OF THE BODY
    • A61H39/00Devices for locating or stimulating specific reflex points of the body for physical therapy, e.g. acupuncture
    • A61H39/04Devices for pressing such points, e.g. Shiatsu or Acupressure

Landscapes

  • Health & Medical Sciences (AREA)
  • Rehabilitation Therapy (AREA)
  • Epidemiology (AREA)
  • Pain & Pain Management (AREA)
  • Physical Education & Sports Medicine (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Animal Behavior & Ethology (AREA)
  • General Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Veterinary Medicine (AREA)
  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to a juglans sigillata fruit massage sole pavement construction process, which comprises the following steps: leveling a roadbed, compacting and maintaining for 3-5 days, paving a broken stone cushion layer with the thickness of 100mm, pouring a concrete cushion layer with the thickness of 15cm, maintaining for 10-15 days, pouring cement mortar with the thickness of 80mm on a surface layer, uniformly paving juglans sigillata on the surface layer, compacting and integrally forming, and maintaining for 15-20 days; the juglans sigillata fruit embedded concrete pavement for foot massage has the advantages that juglans sigillata fruits are not easy to fall off, the massage effect is good, the service life is long, the time for repairing, repairing and maintaining can be saved, the use cost is low, the manufacturing method provided by the invention ensures that the first matrix and the second matrix can be solidified as a whole, the operation is simple, the operation process is easy to control, and the success rate of products is extremely high.

Description

Construction process for juglans sigillata massage sole pavement
Technical Field
The invention relates to a pavement construction process, in particular to a juglans sigillata massage sole pavement construction process.
Background
The sole massage is a health care mode which achieves certain prevention and treatment effects by stimulating sole acupuncture points, the sole massage has a long history in China, nowadays, along with the development of technological level and the further improvement of processing level, the health care consciousness of people is enhanced, various sole massages are widely available, so that the benefits of the masses are not shallow, the life is greatly facilitated, in parks or lakesides, the sole massage effect is often achieved by laying stone paths, however, the stone paths at the present stage are easy to fall off from concrete, and the massage effect is not achieved along with the falling off of the stone paths at the present stage, if the sole massages are repaired, the whole path can only be re-laid, the cost is high, and the waste of concrete materials is caused.
Disclosure of Invention
The invention aims to provide a construction process of a juglans sigillata fruit massage sole pavement, aiming at overcoming the defects in the prior art, the juglans sigillata fruit massage sole pavement is paved, so that not only can the resource be effectively utilized, but also the repair is convenient.
The invention is realized by the following technical scheme: the construction process of the juglans sigillata massage sole pavement comprises the following steps:
(1) a first substrate: leveling the roadbed, compacting and maintaining for 3-5 days, paving a broken stone cushion layer with the thickness of 100mm, and then pouring a concrete cushion layer with the thickness of 15cm, and maintaining for 10-15 days;
(2) a second substrate: and (3) pouring cement mortar with the thickness of 80mm on the surface layer, uniformly spreading the juglans sigillata on the surface layer, compacting and integrally forming, and maintaining for 15-20 days.
Further, the surface cement mortar is a soil color cement mortar doped with rouge and rouge, 30-60 jin of rouge and rouge are respectively added into 100 jin of cement, wherein the proportion of the rouge is 30%, the proportion of the rouge is 70%, and the required color is similar to the color of the juglans sigillata. The soil color cement mortar refers to the color of the cement mortar doped with rouge and rouge.
Furthermore, the length and the width of the juglans sigillata are all 3-5cm, and the distance is 350-450 mm.
Furthermore, the edges of the oak strips are covered by antiseptic oak strips with the thickness of 5cm and the width of 8cm, and the edges of the oak strips are surrounded by crushed walnut shells with the width of 50 cm.
Compared with the prior art, the pecan fruit embedded concrete pavement for foot massage has the advantages that the pecan fruits are not easy to fall off, the massage effect is good, the service life is long, the time for repair, repair and maintenance can be saved, and the use cost is low.
The pecan fruit embedded concrete pavement has the advantages that:
1. environmental protection, low cost and renewable resources. The conventional cobblestones are high in price and cannot be regenerated.
2. The surface textures of the juglans sigillata are various, and the juglans sigillata is firmly embedded with a road surface. The cobblestone surface is smooth and easy to fall off.
3. The massage effect is obvious, the effect of environmental compatibility is prominent, and local characteristics can be embodied.
4. Long service life and low maintenance cost.
Drawings
Fig. 1 is a schematic view of a pecan fruit pavement of the present invention.
Detailed Description
The process schemes in the embodiments of the present invention are clearly and completely described below with reference to the specific embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention.
The specific techniques, connections, conditions, or the like, which are not specified in the examples, are performed according to the techniques, connections, conditions, or the like described in the literature in the art or according to the product specification. The materials or equipment used are not indicated by manufacturers, and all are conventional products available by purchase.
In the embodiment of the invention, the pecan pavement is paved among the walnut forests of the applicant, as shown in figure 1. The required materials are as follows: the walnut shell paste is prepared from the raw materials of yangbi walnut fruits, yangbi large-bubble walnut shells, anti-corrosion oak wood strips, water-washed sand, cement, crushed stone, wood piles, wood, native bluestone, red and yellow iron powder pigments. The process flow comprises the following steps: leveling and tamping a roadbed, paving a 10 cm-thick broken stone cushion layer, pouring a 15 cm-thick C20 concrete cushion layer, doping rouge and rouge into No. 100 cement mortar to obtain soil color cement mortar, pouring the soil color cement mortar into an 8 cm-thick surface layer, uniformly paving juglans sigillata on the surface layer, compacting into a road surface embedded with juglans sigillata fruits and having a width of 2m, and maintaining for 15-20 days.
The length and width of each juglans sigillata fruit adopted in construction are between 3cm and 5cm, and the distance between every two juglans sigillata fruits is about 400mm during paving. And then using an antiseptic oak batten with the thickness of 5cm and the width of 8cm for edge covering, using crushed walnut shells with the width of 50cm for edge surrounding on two sides, planting a wood pile road edge, and using No. 75 mortar for supporting and building a wood step and a native bluestone step. The road surface of the walnuts yangbi constructed by the technical scheme of the invention is coordinated with the peripheral walnuts, so that the effective utilization of the walnuts yangbi and the walnuts yangbi is realized, and the characteristic of walnuts is highlighted. The walking Yangbi Juglans sigillata fruit pavement can stimulate sole acupuncture points to dredge channels, relieve fatigue, regulate metabolism, harmonize viscera, increase body resistance, increase foot blood flow and improve the blood circulation condition of the whole body.
The method for repairing the iron walnut fruit pavement comprises the following steps:
1. if each repairing point only has less than 5 walnut fruits damaged or fall off, the repairing is carried out in the cross-shaped range of each walnut, namely, at least more than 5 adjacent walnut fruits and corresponding second matrixes are completely removed from each repairing point, and the stability and the attractiveness of the repairing position are ensured.
2. Mixing rouge and rouge in a proper proportion into a mixture with the same color as that of a pecan fruit, mixing the mixture into M10 concrete, pouring the mixture to a repairing point, and enabling the concrete to have the same elevation as that of a second matrix.
3. And embedding the iron walnut fruits according to the iron walnut fruit embedding rule of the repairing points, keeping the repairing points consistent with the original iron walnut fruit pavement, and flattening the iron walnut fruits to the same elevation.
4. Maintaining for 7-10 days.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made in the embodiments or portions thereof without departing from the spirit and scope of the invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (4)

1. A juglans sigillata massage sole pavement construction process is characterized by comprising the following steps:
(1) a first substrate: leveling the roadbed, compacting and maintaining for 3-5 days, paving a broken stone cushion layer with the thickness of 100mm, and then pouring a concrete cushion layer with the thickness of 15cm, and maintaining for 10-15 days;
(2) a second substrate: and (3) pouring cement mortar with the thickness of 80mm on the surface layer, uniformly spreading the juglans sigillata on the surface layer, compacting and integrally forming, and maintaining for 15-20 days.
2. The pecan massage sole pavement construction process according to claim 1, wherein the cement mortar poured on the surface layer in the step (2) is a soil color cement mortar doped with rouge and rouge, and 30-60 jin of rouge and rouge are respectively added according to 100 jin of cement, wherein the rouge accounts for 30%, and the rouge accounts for 70%.
3. The pecan massage sole pavement construction process as claimed in claim 1, wherein the pecans in step (2) are all 3cm-5cm long and wide and are paved in the pavement according to the distance of 350-450 mm.
4. The pecan fruit massage sole pavement construction process according to claim 1, wherein the second substrate is wrapped with antiseptic oak strips with the thickness of 5cm and the width of 8cm, and two sides are wrapped with crushed walnut shells with the width of 50 cm.
CN202011533561.XA 2020-12-23 2020-12-23 Construction process for juglans sigillata massage sole pavement Pending CN112482120A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011533561.XA CN112482120A (en) 2020-12-23 2020-12-23 Construction process for juglans sigillata massage sole pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011533561.XA CN112482120A (en) 2020-12-23 2020-12-23 Construction process for juglans sigillata massage sole pavement

Publications (1)

Publication Number Publication Date
CN112482120A true CN112482120A (en) 2021-03-12

Family

ID=74915430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011533561.XA Pending CN112482120A (en) 2020-12-23 2020-12-23 Construction process for juglans sigillata massage sole pavement

Country Status (1)

Country Link
CN (1) CN112482120A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1098019A (en) * 1994-03-16 1995-02-01 张先成 Multifunctional body-building pedal
CN2372356Y (en) * 1999-04-30 2000-04-05 操定平 Colour composite paving brick
CN101307588A (en) * 2008-07-11 2008-11-19 胡雪辉 Stone-emulating roads plate fabrication process
CN201453638U (en) * 2009-07-30 2010-05-12 孙志海 Pedicure massage cushion
CN101798790A (en) * 2009-12-17 2010-08-11 浙江中联建设集团有限公司 Wet-lime embedded once-molding construction process of cobblestone garden path and landscape floor
CN103711054A (en) * 2013-12-11 2014-04-09 常州市建筑科学研究院股份有限公司 Color recycled concrete road brick and preparation process thereof
CN207812230U (en) * 2018-01-22 2018-09-04 无锡耘林养老产业投资发展有限公司 A kind of Novel body building pavement
KR20190083440A (en) * 2018-01-04 2019-07-12 박노윤 Road paving method
CN210101432U (en) * 2019-07-16 2020-02-21 江西宜春客车厂有限公司 Massage foot rest plate for automobile
CN111470808A (en) * 2020-03-02 2020-07-31 武汉路城建设科技有限公司 Composite material system surface layer permeable sand base and preparation method and application thereof

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1098019A (en) * 1994-03-16 1995-02-01 张先成 Multifunctional body-building pedal
CN2372356Y (en) * 1999-04-30 2000-04-05 操定平 Colour composite paving brick
CN101307588A (en) * 2008-07-11 2008-11-19 胡雪辉 Stone-emulating roads plate fabrication process
CN201453638U (en) * 2009-07-30 2010-05-12 孙志海 Pedicure massage cushion
CN101798790A (en) * 2009-12-17 2010-08-11 浙江中联建设集团有限公司 Wet-lime embedded once-molding construction process of cobblestone garden path and landscape floor
CN103711054A (en) * 2013-12-11 2014-04-09 常州市建筑科学研究院股份有限公司 Color recycled concrete road brick and preparation process thereof
KR20190083440A (en) * 2018-01-04 2019-07-12 박노윤 Road paving method
CN207812230U (en) * 2018-01-22 2018-09-04 无锡耘林养老产业投资发展有限公司 A kind of Novel body building pavement
CN210101432U (en) * 2019-07-16 2020-02-21 江西宜春客车厂有限公司 Massage foot rest plate for automobile
CN111470808A (en) * 2020-03-02 2020-07-31 武汉路城建设科技有限公司 Composite material system surface layer permeable sand base and preparation method and application thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
一场繁华谢幕: "用文玩核桃铺的路,踩上去和足底按摩一样", 《HTTPS://V.YOUKU.COM/V_SHOW/ID_XNDK1NTCXMDG0MA==》 *

Similar Documents

Publication Publication Date Title
CN104452510B (en) Immediate construction method of rural road
CN112482120A (en) Construction process for juglans sigillata massage sole pavement
CN105948595B (en) The anti-isolation framework compact Cement Stable Macadam Mixture of one kind, its application and paving method
CN108252181A (en) A kind of pervious concrete pavement structure and construction method
CN207079437U (en) A kind of discharge structure of town road
CN208293330U (en) A kind of water-permeable brick paving structure
CN205115945U (en) Double -deck synchronous surface dressing stress absorption structure
JPS63315710A (en) Execution of sports surface having water permeability
CN208884292U (en) Soft soil roadbed and normal roadbed intersection anti-settling structure
CN108218308B (en) Method for protecting sandstone slope by using modified sandstone blocks
CN108103874A (en) A kind of road construction method
CN113235350B (en) Method for realizing concrete road reconstruction by additionally paving asphalt concrete surface layer
CN204849516U (en) Resistant lawn of trampleing on
KR102659611B1 (en) Earthing red clay for creating a red clay road and its manufacturing method
CN107759147A (en) A kind of preparation method of water-permeable brick
CN210481937U (en) White and black pavement structure adopting high-viscosity modified asphalt
JP2544970B2 (en) Curable soil composition and soil hardening method
JP6850001B2 (en) How to improve surface soil
KR102625770B1 (en) A walkway construction method
CN107869099A (en) A kind of easy-to-dismount draining gardens floor tile
CN207143630U (en) A kind of permeable, anti-settling pavement bricks
CN101761024B (en) Hot recycling and sand-adding treatment method for flushing asphalt pavement
CN205711618U (en) A kind of regenerated aggregate full pervious concrete pavement structure
KR101682142B1 (en) Construction method using the composition for light load street
CN205420943U (en) A ceramic tile for laying gardens road

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20210312