CN112459328A - 一种大面积楼板采用分段流水作业的施工方法 - Google Patents
一种大面积楼板采用分段流水作业的施工方法 Download PDFInfo
- Publication number
- CN112459328A CN112459328A CN202011092353.0A CN202011092353A CN112459328A CN 112459328 A CN112459328 A CN 112459328A CN 202011092353 A CN202011092353 A CN 202011092353A CN 112459328 A CN112459328 A CN 112459328A
- Authority
- CN
- China
- Prior art keywords
- area
- hours
- worker
- construction
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
一种大面积楼板采用分段流水作业的施工方法,属于混凝土楼板施工技术领域。工艺步骤:将整体楼板划均分两个区域施工,即第一区域(1)、第二区域(2);模板工在第一区域支模(3)用47‑49小时;模板工对第二区域支模(4)用47‑49小时,同时钢筋工对第一区域绑筋(5)同步进行,用47‑49小时;钢筋工对第二区域绑筋(6用47‑49小时,同时打灰工对第一区域打灰(7同步进行,用47‑49小时;打灰工对第二区域打灰(8用47‑49小时。优点在于,该分段流水施工作业方法,简单易操作,通过分区域流水作业的方式,既节省了施工时间,有减少了工种窝工,大大降低了施工成本。
Description
技术领域
本发明属于混凝土楼板施工技术领域,特别是提供了一种大面积楼板采用分段流水作业的施工方法。
背景技术
混凝土楼板施工作业时,对于大面积混凝土楼板的施工一般也都是采用整体楼板工序施工的方式,即先对整体楼板支模,之后对整体楼板绑筋,最后对整体楼板打灰,这样施工一是需要很长时间,二是各工种存在窝工,比如,整体楼板支模需要4天时间,之后整体楼板绑筋需要4天时间,最后打灰需要4天时间,总计需要12天时间,期间钢筋工需要等4天时间才能绑筋,打灰工需要等8天时间才能打灰。
发明内容
本发明的目的在于提供一种大面积楼板采用分段流水作业的施工方法,通过对楼板区域施工分段,使支模、绑筋、打灰形成流水段施工作业,使施工作业时间缩短,同时也减少了工种窝工现象。具体步骤如下:
第一步,将整体楼板划均分两个区域施工,即第一区域1、第二区域2(图1);
第二步,模板工在第一区域支模3用47-49小时(图2);
第三步,模板工对第二区域支模4用47-49小时,同时钢筋工对第一区域绑筋5同步进行,用47-49小时(图3);
第四步,钢筋工对第二区域绑筋6用47-49小时,同时打灰工对第一区域打灰7同步进行,用47-49小时(图4);
第五步,打灰工对第二区域打灰8用47-49小时(图5);
该分段流水施工作业方法,简单易操作,通过分区域流水作业的方式,既节省了施工时间,有减少了工种窝工,大大降低了施工成本,为公司取得了良好的经济效益。
附图说明
图1为楼板均分两个区域俯视图
图2为第一区域支模俯视图
图3为第二区域支模及第一区域绑筋俯视图
图4为第二区域绑筋及第一区域打灰俯视图
图5为第二区域打灰俯视图
图中,第一区域1、第二区域2、第一区域支模3、第二区域支模4、第一区域绑筋5、第二区域绑筋6、第一区域打灰7、第二区域打灰8。
具体实施方式
图1-图5为本发明的一种具体实施方式。具体实施方式如下:
第一步,将整体楼板划均分两个区域施工,即第一区域1、第二区域2;
第二步,模板工在第一区域支模3用48小时;
第三步,模板工对第二区域支模4用48小时,同时钢筋工对第一区域绑筋5同步进行,用48小时;
第四步,钢筋工对第二区域绑筋6用48小时,同时打灰工对第一区域打灰7同步进行,用48小时;
第五步,打灰工对第二区域打灰8用48小时。
在对滨湖办公楼楼板施工时采用了本发明。将整体楼板划均分两个区域施工,即第一区域、第二区域,施工时,模板工第一区域支模需用2天时间,之后模板工对第二区域支模需用2天时间,同时钢筋工对第一区域绑筋,需用2天时间;之后钢筋工对第二区域绑筋需用2天时间,同时打灰工对第一区域打灰需用2天时间;最后打灰工对第二区域打灰需用2天时间,最后实际第一区域及第二区域混凝土楼板施工完用时8天时间,比整体楼板同时施工用12天节省了4天时间,也减少了各工种的窝工。该分段流水施工作业方法,简单易操作,通过分区域流水作业的方式,既节省了施工时间,有减少了工种窝工,大大降低了施工成本,取得了较好效果,为以后类似施工积累了宝贵的经验。
Claims (1)
1.一种大面积楼板采用分段流水作业的施工方法,其特征在于,具体工艺步骤如下:
第一步,将整体楼板划均分两个区域施工,即第一区域(1)、第二区域(2);
第二步,模板工在第一区域支模(3)用47-49小时;
第三步,模板工对第二区域支模(4)用47-49小时,同时钢筋工对第一区域绑筋(5)同步进行,用47-49小时;
第四步,钢筋工对第二区域绑筋(6用47-49小时,同时打灰工对第一区域打灰(7同步进行,用47-49小时;
第五步,打灰工对第二区域打灰(8用47-49小时。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011092353.0A CN112459328A (zh) | 2020-10-13 | 2020-10-13 | 一种大面积楼板采用分段流水作业的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011092353.0A CN112459328A (zh) | 2020-10-13 | 2020-10-13 | 一种大面积楼板采用分段流水作业的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112459328A true CN112459328A (zh) | 2021-03-09 |
Family
ID=74833064
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011092353.0A Pending CN112459328A (zh) | 2020-10-13 | 2020-10-13 | 一种大面积楼板采用分段流水作业的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112459328A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011064580A (ja) * | 2009-09-17 | 2011-03-31 | Toshiba Corp | 原子力発電所における機器先行搬入エリアのフロア施工方法 |
CN203547126U (zh) * | 2013-09-17 | 2014-04-16 | 中联世纪建设集团有限公司 | 一种楼板施工模板组件 |
CN104736779A (zh) * | 2013-03-29 | 2015-06-24 | (株)韩美顾乐博建筑事事务所 | 每两天上升一个楼层的混凝土结构体施工方法 |
CN106285001A (zh) * | 2016-08-31 | 2017-01-04 | 中天建设集团有限公司天津分公司 | 一种小面积分段快速交叉流水施工方法 |
-
2020
- 2020-10-13 CN CN202011092353.0A patent/CN112459328A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011064580A (ja) * | 2009-09-17 | 2011-03-31 | Toshiba Corp | 原子力発電所における機器先行搬入エリアのフロア施工方法 |
CN104736779A (zh) * | 2013-03-29 | 2015-06-24 | (株)韩美顾乐博建筑事事务所 | 每两天上升一个楼层的混凝土结构体施工方法 |
CN203547126U (zh) * | 2013-09-17 | 2014-04-16 | 中联世纪建设集团有限公司 | 一种楼板施工模板组件 |
CN106285001A (zh) * | 2016-08-31 | 2017-01-04 | 中天建设集团有限公司天津分公司 | 一种小面积分段快速交叉流水施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103410332B (zh) | 一种混凝土空心砌块加筋墙施工工艺 | |
CN103266767A (zh) | 混凝土结构与填充墙间裂缝防治施工工法 | |
CN104947719A (zh) | 地下室顶板后浇带吊支模结构及其后浇带施工方法 | |
CN107653894A (zh) | 一种通过砼预制板制作基础承台的施工工艺 | |
CN103821253A (zh) | 加气混凝土砌块填充墙砌筑工艺 | |
CN105064579A (zh) | 一种保证卫生间止水坎台浇筑成型的施工方法 | |
CN108005118A (zh) | 地下管廊主体结构整合施工方法 | |
CN105649235A (zh) | Ms密实薄壁填充砌块施工工艺 | |
CN105780992B (zh) | 一种正交正放钢筋混凝土空腹夹层板楼盖施工工法 | |
CN104594655A (zh) | 一种砖混结构墙体拆除临时支撑的应用方法 | |
CN103899072A (zh) | 一种用于湿挂石材或瓷砖的挂件及湿挂方法 | |
CN112459328A (zh) | 一种大面积楼板采用分段流水作业的施工方法 | |
CN202391140U (zh) | 现浇混凝土楼板厚度控制模具 | |
CN108979205B (zh) | 超高层住宅结构错层流水施工方法 | |
CN206829428U (zh) | 一种轻钢轻质混凝土免拆模墙体结构 | |
CN104234425B (zh) | 一种剪力墙结构免抹灰工艺 | |
CN203546726U (zh) | 一种玻璃纤维增强水泥板胎膜 | |
CN204112586U (zh) | 一种建筑施工用预制板支模 | |
CN105569214A (zh) | 一种密实薄壁填充砌块施工工艺 | |
CN103590581A (zh) | 混凝土烟道顶板保温层施工方法 | |
CN102605895B (zh) | 天棚板保温砂浆预制块安装施工方法 | |
CN110307010A (zh) | 水工隧洞边墙与底板衬砌施工用模板系统 | |
CN204311621U (zh) | 一种现浇钢筋混凝土清水填充墙 | |
CN108560926A (zh) | 装配式钢结构住宅带钢梁、钢支撑的内墙板安装方法 | |
CN203821590U (zh) | 一种无模板配筋砌体体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20210309 |