CN112434366A - Cable crane arrangement and scheduling method based on BIM - Google Patents

Cable crane arrangement and scheduling method based on BIM Download PDF

Info

Publication number
CN112434366A
CN112434366A CN202011619128.8A CN202011619128A CN112434366A CN 112434366 A CN112434366 A CN 112434366A CN 202011619128 A CN202011619128 A CN 202011619128A CN 112434366 A CN112434366 A CN 112434366A
Authority
CN
China
Prior art keywords
cable
arrangement
unit
pouring
poured
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011619128.8A
Other languages
Chinese (zh)
Other versions
CN112434366B (en
Inventor
陈文夫
彭华
谭尧升
林恩德
周天刚
张攀峰
李俊平
王法瑜
周孟夏
冯博
高世奎
裴磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Ins Engineering Technology Corp
China Three Gorges Corp
China Three Gorges Projects Development Co Ltd CTG
Original Assignee
Wuhan Ins Engineering Technology Corp
China Three Gorges Corp
China Three Gorges Projects Development Co Ltd CTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Ins Engineering Technology Corp, China Three Gorges Corp, China Three Gorges Projects Development Co Ltd CTG filed Critical Wuhan Ins Engineering Technology Corp
Priority to CN202011619128.8A priority Critical patent/CN112434366B/en
Publication of CN112434366A publication Critical patent/CN112434366A/en
Application granted granted Critical
Publication of CN112434366B publication Critical patent/CN112434366B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Geometry (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Computer Hardware Design (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Architecture (AREA)
  • Development Economics (AREA)
  • General Engineering & Computer Science (AREA)
  • Educational Administration (AREA)
  • Evolutionary Computation (AREA)
  • Game Theory and Decision Science (AREA)
  • Mathematical Optimization (AREA)
  • Civil Engineering (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Computational Mathematics (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a cable machine arrangement and scheduling method based on BIM, the method is based on BIM technology, establishes a three-dimensional BIM model of a dam, dynamically arranges the cable machines based on the real-time pouring progress image of the dam and the position and the shape characteristics of a unit to be poured according to the arrangement sequence and the safety interval requirement of the cable machines, determines the operation range of the cable machines and the arrangement number of the cable machines, adjusts the upstream and downstream arrangement position and sequence of the cable machines, measures and calculates the covering area, the concrete square amount and other indexes in the range, ensures that the arrangement scheme meets the requirements of equipment operation safety, blank layer covering time and pouring strength, forms a cable machine arrangement scheme of multilayer staggered arrangement and multi-cabin simultaneous pouring under the coupling of multiple factors of cable machine covering range, unit shape characteristics, blank layer covering time and equipment safety anti-collision, and fully excavates the working efficiency of a cable machine group on the premise of ensuring safety, the pouring strength and efficiency are improved, and an important means is provided for safe and efficient construction of dam concrete.

Description

Cable crane arrangement and scheduling method based on BIM
Technical Field
The invention belongs to the field of hydraulic structure engineering, and particularly relates to a cable crane arrangement and scheduling method based on BIM.
Background
The hydroelectric engineering concrete high arch dam is generally positioned in a high mountain canyon, a cable crane is often used as a concrete warehousing means, in order to ensure warehousing strength and pouring efficiency, a plurality of cable cranes arranged in one or more layers are generally adopted to jointly schedule concrete warehousing, and the operation safety and the transportation efficiency of the cable crane are the keys for determining the pouring progress of the dam. The arrangement and scheduling of the cable machines need to comprehensively consider factors such as the positions, the body type characteristics and the square quantities of the pouring units, the safety intervals among the cable machines, the small warehousing strength requirement of concrete, the blank layer covering time and the maximum interval limit. The traditional cable crane arrangement method is often determined by experienced engineers, and has the problems of inaccurate arrangement parameters, incapability of dynamically checking the square amount and the pouring strength, incapability of realizing dynamic scheme allocation, incapability of meeting the balanced construction requirements of all blank layers, difficulty in multi-cabin simultaneous pouring arrangement and the like; therefore, the applicant considers that the BIM technology is adopted to build a model of cable crane arrangement in advance, so as to solve the optimization problem of multi-cable crane dynamic allocation.
The prior art is provided with a cable hoisting arrangement system based on a BIM technology and a design method, namely, a hoisting range model of a rope crane at different positions is established through the BIM technology, and a hoisting position which does not meet the requirement of a safety coefficient is found out, so that the arrangement of the cable crane is further optimized, but the method is not suitable for the warehousing scheduling of a cable crane in the concrete dam pouring process; the method is characterized in that the concrete dam is poured in units, and the positions, body type characteristics and square quantities of all pouring units are different; on the other hand, a plurality of cable machines are operated simultaneously, and the arrangement of the cable machines is influenced by factors such as the safety distance among the cable machines, the small warehousing strength requirement of concrete, the blank layer covering time and the maximum interval limit; therefore, how to establish a dynamic allocation model of a plurality of cable machines by using a BIM technology and how to introduce a dynamic adjustment method can automatically and alternately set the plurality of cable machines according to an optimal model on the premise of meeting the setting process and safety rules while considering a multi-factor coupling relation, and realize the automatic scheduling with the highest efficiency by simultaneously casting a plurality of bins under the premise of meeting the requirements of a construction process and control indexes, thereby excavating the working efficiency of a cable machine group and improving the concrete pouring strength and efficiency, and is a problem to be solved by the applicant.
Disclosure of Invention
The invention aims to solve the technical problem of providing a cable machine arrangement and scheduling method based on BIM (building information modeling), which is used for solving the problem that the arrangement and scheduling of a cable machine group in the existing concrete dam construction are influenced by various factors such as cable machine coverage range, casting unit body type characteristics and square quantity, blank layer coverage time and maximum interval limitation and safety and collision prevention among equipment, so that the optimal arrangement of multi-cable machine allocation is difficult to carry out through the existing construction experience or conventional technical means; the problems that the arrangement parameters are not accurate, the amount and the pouring strength cannot be dynamically checked, the dynamic scheme allocation cannot be realized, the balanced construction requirements of each blank layer cannot be met, the multi-bin simultaneous pouring arrangement is difficult and the like exist, due to the fact that coupling relations exist among the influence factors of multiple targets, construction technicians cannot simultaneously achieve multi-target optimization, unreasonable arrangement intervals are caused to bring safety risks, unbalanced strip partitions influence the pouring work efficiency, and the overall progress of dam engineering is further influenced.
The method is based on the BIM technology, a dam three-dimensional model and a pouring unit model are established, the pile number range and the body type characteristics of a pouring bin are analyzed, the pouring areas and the square quantities of different strip subareas under different arrangement conditions are dynamically obtained, the cable crane batch arrangement under multilayer arrangement is supported, the visual scheme display is realized, the multi-bin simultaneous pouring is supported, the cable crane arrangement and scheduling efficiency is greatly improved, and the reasonability of the cable crane arrangement scheme is improved.
In order to achieve the technical purpose, the technical scheme adopted by the invention is as follows: a cable crane arrangement and scheduling method based on BIM comprises the following steps:
s1, setting the state of the dam unit: according to the actual construction progress of the dam, dynamically setting and updating the pouring time of each poured unit and the standby bin completion state of the unit to be poured;
s2, establishing a dam three-dimensional progress image: establishing a dam layered block BIM according to the state of each pouring unit; displaying the actual progress image of the dam in a three-dimensional scene according to the completion time of the pouring unit in the layered block model or the standby bin state;
s3, the pouring unit is preferably: acquiring each unit to be poured of the currently finished spare warehouse, respectively calculating the intermission period of the units in the spare warehouse, sequencing according to the intermission period duration, and guiding a user to preferentially select one or more units to be poured as a to-be-poured unit of the cable crane arrangement; calculating the pile number range, area and square quantity of the selected unit to be poured by using a BIM (building information modeling);
s4, setting cable crane arrangement parameters: setting the number of layers, the number of the cable cranes, the serial number, the elevation of each layer, the distance between a left bank and a right bank, the arrangement sequence, the translation azimuth angle, the track pile number range and the movable pile number range of each cable crane according to the actual cable crane arrangement scheme of the engineering;
s5, setting process and safety rules: setting the layering number of units to be poured, the rated hour transport strength, the maximum concrete pouring blank layer covering time, the left and right minimum safety spacing of the same cable arrangement machine and the interlayer minimum safety spacing;
s6, drawing a three-dimensional space distribution schematic diagram of the cable crane: drawing a schematic layout of the cable crane in a three-dimensional scene according to the cable crane layout parameters of S4 and the setting process and safety rules of S5; dynamically adjusting the cable arrangement diagram in the three-dimensional scene according to the actual cable arrangement condition;
s7, dynamically arranging a cable crane: an operator selects one or more appointed cable machines, and the system evenly distributes the operation coverage range of the to-be-poured unit corresponding to each cable machine according to the pile number range, the area and the square quantity of the to-be-poured unit, the arrangement parameters and the process and safety rules of the selected cable machine; (ii) a The average distribution means that all the cable machines are distributed according to the safety interval rule, the cable machine coverage range, the pushing requirement of a leveling car, the average distribution bin surface area and the pouring amount so as to ensure the principle that the output of each cable machine is balanced;
s8, calculating a cable arrangement scheme: dynamically cutting a unit BIM model according to the distributed cable crane arrangement scheme to form a pouring subarea model, and calculating the area and the square amount of each subarea and the blank layer covering time; synchronously setting and updating the pouring time of each poured unit and the standby bin completion state of the units to be poured, thereby synchronously updating the three-dimensional arrangement image of the dam;
s9, analyzing feasibility of the cable crane arrangement scheme: according to the cable machine setting process and the safety rules of S5, judging whether the current scheme meets the cable machine operation safety requirement, the blank layer covering time requirement and the requirement of balanced warehousing of each subarea;
s10, manually adjusting the arrangement parameters of the cable crane according to the analysis result of S9, wherein the adjustment method comprises the following steps: selecting different cable machines to participate in pouring, adjusting the coverage range of the cable machines and selecting different cable machine cross-region operation; after the arrangement parameters of one cable crane are adjusted, dynamically adjusting the arrangement parameters of each adjacent cable crane;
s11, loop execution: the adjusted cable crane arrangement scheme is substituted into the step S8 again, and the steps are sequentially executed downwards; ending the loop when the generated cable arrangement scheme satisfies the feasibility analysis of S9; and storing and releasing the cable arrangement scheme, and visually displaying the arrangement scheme in the BIM scene as the basis for scheduling and executing the cable.
Preferably, the intermittent period calculation method in step S3 is as follows:
obtaining the unit to be poured of the current finished standby bin, and recording the current time T1Then recording the pouring completion time T of the lower layer unit of the prepared bin unit2Through T1- T2And obtaining the intermittence period of the unit to be poured.
Preferably, the dynamic adjustment method in steps S6 and S10 is as follows:
after the coverage range of one cable machine is adjusted, the arrangement and the coverage range of each cable machine adjacent to the cable machine are dynamically adjusted in a linkage manner according to the minimum safety distance requirement of the cable machine and the relative position relationship between the cable machines until the plurality of cable machines realize the updating of the whole arrangement scheme and the real-time calculation and checking of each index.
Preferably, the range of dynamic adjustment does not exceed the cable crane range of motion and the minimum spacing limit; and when the cable crane adjustment reaches the cable crane movable range limit or the cable crane arrangement reaches the minimum working range and the minimum spacing limit of each cable crane, forbidding to perform adjustment again.
Preferably, the cable crane operation safety requirement in step S9 indicates that the cable crane spacing meets the requirement of minimum spacing between the same layer and the same layer; the blank layer covering time requirement means that the ratio of the partition square amount/rated hour transportation strength/the number of the layered layers meets the requirement.
Preferably, the method of dynamically cutting the unit BIM model in step S8 is as follows:
based on the geometric shapes of the concrete pouring units, automatically cutting the models according to the pile number coverage range distributed by a plurality of current cable cranes, calculating the upper surface area and the volume of each cutting model, and calculating the blank layer coverage time according to the theoretical pouring strength of each cutting model corresponding to the cable crane; the covering time interval of the connected blank layers does not exceed the maximum interval limit, and cold seams generated by initial setting of the concrete poured in advance are prevented.
The cable crane arrangement and scheduling method based on the BIM has the beneficial effects that:
the invention establishes a three-dimensional BIM model of a dam based on BIM technology, dynamically arranges cable machines based on the position and the shape characteristics of a dam real-time pouring progress image and a unit to be poured according to the arrangement sequence and the safety distance requirement of the cable machines, determines the working range of the cable machines and the arrangement scheme of the cable machines, checks after substituting the scheme into the scheme for calculation, ensures that the arrangement scheme meets the requirements of equipment operation safety, blank layer covering time and pouring strength by adjusting the upstream and downstream arrangement position and sequence of the cable machines, measuring and calculating the covering area, the concrete square amount and other indexes in the range, forms the cable machine arrangement scheme of cable machine group multilayer staggered arrangement and multi-bin simultaneous pouring under the coupling of multiple factors such as cable machine covering range, unit body shape characteristic, blank layer covering time, equipment safety collision prevention and the like, and fully excavates the working efficiency of the cable machine group on the premise of ensuring safety, the pouring strength and efficiency are improved, and an important means is provided for safe and efficient construction of dam concrete.
Drawings
The invention is further illustrated by the following examples in conjunction with the accompanying drawings:
FIG. 1 is a schematic flow chart of the present invention.
Fig. 2 is a main interface of a scheduling program established based on the scheduling method when the present invention is implemented.
Fig. 3 is a result of a cable arrangement scheme executed by a scheduler built based on the scheduling method in the embodiment of the present invention.
Fig. 4 is an excel output table of a cable arrangement scheme result executed by a scheduling program established based on the scheduling method in the specific implementation of the present invention.
Detailed Description
As shown in fig. 1, a cable crane arranging and scheduling method based on BIM includes the following steps:
s1, setting the state of the dam unit: according to the actual construction progress of the dam, dynamically setting and updating the pouring time of each poured unit and the standby bin completion state of the unit to be poured;
s2, establishing a dam three-dimensional progress image: establishing a dam layered block BIM according to the state of each pouring unit; displaying the actual progress image of the dam in a three-dimensional scene according to the completion time of the pouring unit in the layered block model or the standby bin state;
s3, the pouring unit is preferably: acquiring each unit to be poured of the currently finished spare warehouse, respectively calculating the intermission period of the units in the spare warehouse, sequencing according to the intermission period duration, and guiding a user to preferentially select one or more units to be poured as a to-be-poured unit of the cable crane arrangement; calculating the pile number range, area and square quantity of the selected unit to be poured by using a BIM (building information modeling);
s4, setting cable crane arrangement parameters: setting the number of layers, the number of the cable cranes, the serial number, the elevation of each layer, the distance between a left bank and a right bank, the arrangement sequence, the translation azimuth angle, the track pile number range and the movable pile number range of each cable crane according to the actual cable crane arrangement scheme of the engineering;
s5, setting process and safety rules: setting the number of layers of units to be poured to be 50cm per layer, the rated hour transportation strength, the maximum concrete pouring blank layer covering time to be 4 hours, the left and right minimum safety spacing of the cable arrangement machines in the same row to be 10m, and the minimum safety spacing between the layers to be 15 m; when the working environment is strong wind, the distance is adjusted and increased by 5 m-10 m;
s6, drawing a three-dimensional space distribution schematic diagram of the cable crane: drawing a schematic layout of the cable crane in a three-dimensional scene according to the cable crane layout parameters of S4 and the setting process and safety rules of S5; dynamically adjusting the cable arrangement diagram in the three-dimensional scene according to the actual cable arrangement condition;
s7, dynamically arranging a cable crane: an operator selects one or more appointed cable machines, and the system evenly distributes the operation coverage range of the to-be-poured unit corresponding to each cable machine according to the pile number range, the area and the square quantity of the to-be-poured unit, the arrangement parameters and the process and safety rules of the selected cable machine; (ii) a The average distribution means that all the cable machines are distributed according to the safety interval rule, the cable machine coverage range, the pushing requirement of a leveling car, the average distribution bin surface area and the pouring amount so as to ensure the principle that the output of each cable machine is balanced;
s8, calculating a cable arrangement scheme: dynamically cutting a unit BIM model according to the distributed cable crane arrangement scheme to form a pouring subarea model, and calculating the area and the square amount of each subarea and the blank layer covering time; synchronously setting and updating the pouring time of each poured unit and the standby bin completion state of the units to be poured, thereby synchronously updating the three-dimensional arrangement image of the dam;
s9, analyzing feasibility of the cable crane arrangement scheme: according to the cable machine setting process and the safety rules of S5, judging whether the current scheme meets the cable machine operation safety requirement, the blank layer covering time requirement and the requirement of balanced warehousing of each subarea;
s10, manually adjusting the arrangement parameters of the cable crane according to the analysis result of S9, wherein the adjustment method comprises the following steps: selecting different cable machines to participate in pouring, adjusting the coverage range of the cable machines and selecting different cable machine cross-region operation; after the arrangement parameters of one cable crane are adjusted, dynamically adjusting the arrangement parameters of each adjacent cable crane;
s11, loop execution: the adjusted cable crane arrangement scheme is substituted into the step S8 again, and the steps are sequentially executed downwards; ending the loop when the generated cable arrangement scheme satisfies the feasibility analysis of S9; and storing and releasing the cable arrangement scheme, and visually displaying the arrangement scheme in the BIM scene as the basis for scheduling and executing the cable.
Preferably, the intermittent period calculation method in step S3 is as follows:
obtaining the unit to be poured of the current completed standby bin, and recording the currentTime T1Then recording the pouring completion time T of the lower layer unit of the prepared bin unit2Through T1- T2And obtaining the intermittence period of the unit to be poured.
Preferably, the dynamic adjustment method in steps S6 and S10 is as follows:
after the coverage range of one cable machine is adjusted, the arrangement and the coverage range of each cable machine adjacent to the cable machine are dynamically adjusted in a linkage manner according to the minimum safety distance requirement of the cable machine and the relative position relationship between the cable machines until the plurality of cable machines realize the updating of the whole arrangement scheme and the real-time calculation and checking of each index.
Preferably, the range of dynamic adjustment does not exceed the cable crane range of motion and the minimum spacing limit; and when the cable crane adjustment reaches the cable crane movable range limit or the cable crane arrangement reaches the minimum working range and the minimum spacing limit of each cable crane, forbidding to perform adjustment again.
Preferably, the cable crane operation safety requirement in step S9 indicates that the cable crane spacing meets the requirement of minimum spacing between the same layer and the same layer; the blank layer covering time requirement means that the ratio of the partition square amount/rated hour transportation strength/the number of the layered layers meets the requirement.
Preferably, the method of dynamically cutting the unit BIM model in step S8 is as follows:
based on the geometric shapes of the concrete pouring units, automatically cutting the models according to the pile number coverage range distributed by a plurality of current cable cranes, calculating the upper surface area and the volume of each cutting model, and calculating the blank layer coverage time according to the theoretical pouring strength of each cutting model corresponding to the cable crane; the covering time interval of the connected blank layers does not exceed the maximum interval limit, and cold seams generated by initial setting of the concrete poured in advance are prevented.
Aiming at the problems of double-layer cable crane arrangement, multi-bin simultaneous casting scheme construction organization optimization and construction safety, a BIM-based cable crane visual scheduling scheme compilation tool is established, and the layout, the scheduling scheme compilation, the verification and the optimization of double-layer cable cranes in specific engineering are realized; the research and the application of the system lead the cable machine dispatching work to be upgraded from the original manual drawing work to the automatic cable machine distribution system and 5 schemes are provided for selection, thereby greatly improving the efficiency of the cable machine dispatching configuration work, the original manual work needs several hours or half a day, and the problem can be solved only by using the system for several minutes at present; in addition, the cable machine visual scheduling system based on the BIM enables cable machine scheduling configuration work to be more visual, results to be more scientific and reasonable, and the cable machine visual scheduling system is better than original working modes and working methods in terms of working efficiency, working quality and working results.
The above-described embodiments are merely preferred embodiments of the present invention, and should not be construed as limiting the present invention, and features in the embodiments and examples in the present application may be arbitrarily combined with each other without conflict. The protection scope of the present invention is defined by the claims, and includes equivalents of technical features of the claims. I.e., equivalent alterations and modifications within the scope hereof, are also intended to be within the scope of the invention.

Claims (6)

1. A cable crane arrangement and scheduling method based on BIM is characterized in that: the method comprises the following steps:
s1, setting the state of the dam unit: according to the actual construction progress of the dam, dynamically setting and updating the pouring time of each poured unit and the standby bin completion state of the unit to be poured;
s2, establishing a dam three-dimensional progress image: establishing a dam layered block BIM according to the state of each pouring unit; displaying the actual progress image of the dam in a three-dimensional scene according to the completion time of the pouring unit in the layered block model or the standby bin state;
s3, the pouring unit is preferably: acquiring each unit to be poured of the currently finished spare warehouse, respectively calculating the intermission period of the units in the spare warehouse, sequencing according to the intermission period duration, and guiding a user to preferentially select one or more units to be poured as a to-be-poured unit of the cable crane arrangement; calculating the pile number range, area and square quantity of the selected unit to be poured by using a BIM (building information modeling);
s4, setting cable crane arrangement parameters: setting the number of layers, the number of the cable cranes, the serial number, the elevation of each layer, the distance between a left bank and a right bank, the arrangement sequence, the translation azimuth angle, the track pile number range and the movable pile number range of each cable crane according to the actual cable crane arrangement scheme of the engineering;
s5, setting process and safety rules: setting the layering number of units to be poured, the rated hour transport strength, the maximum concrete pouring blank layer covering time, the left and right minimum safety spacing of the same cable arrangement machine and the interlayer minimum safety spacing;
s6, drawing a three-dimensional space distribution schematic diagram of the cable crane: drawing a schematic layout of the cable crane in a three-dimensional scene according to the cable crane layout parameters of S4 and the setting process and safety rules of S5; dynamically adjusting the cable arrangement diagram in the three-dimensional scene according to the actual cable arrangement condition;
s7, dynamically arranging a cable crane: an operator selects one or more appointed cable machines, and the system evenly distributes the operation coverage range of the to-be-poured unit corresponding to each cable machine according to the pile number range, the area and the square quantity of the to-be-poured unit, the arrangement parameters and the process and safety rules of the selected cable machine; the average distribution means that all the cable machines are distributed according to the safety interval rule, the cable machine coverage range, the pushing requirement of a leveling car, the average distribution bin surface area and the pouring amount so as to ensure the principle that the output of each cable machine is balanced;
s8, calculating a cable arrangement scheme: dynamically cutting a unit BIM model according to the distributed cable crane arrangement scheme to form a pouring subarea model, and calculating the area and the square amount of each subarea and the blank layer covering time; synchronously setting and updating the pouring time of each poured unit and the standby bin completion state of the units to be poured, thereby synchronously updating the three-dimensional arrangement image of the dam;
s9, analyzing feasibility of the cable crane arrangement scheme: according to the cable machine setting process and the safety rules of S5, judging whether the current scheme meets the cable machine operation safety requirement, the blank layer covering time requirement and the requirement of balanced warehousing of each subarea;
s10, manually adjusting the arrangement parameters of the cable crane according to the analysis result of S9, wherein the adjustment method comprises the following steps: adjusting and selecting different cable machines to participate in pouring, adjusting the coverage range of the cable machine and selecting different cable machine cross-region operation; after the arrangement parameters of one cable crane are adjusted, dynamically adjusting the arrangement parameters of each adjacent cable crane;
s11, loop execution: the adjusted cable crane arrangement scheme is substituted into the step S8 again, and the steps are sequentially executed downwards; ending the loop when the generated cable arrangement scheme satisfies the feasibility analysis of S9; and storing and releasing the cable arrangement scheme, and visually displaying the arrangement scheme in the BIM scene as the basis for scheduling and executing the cable.
2. The BIM-based cable routing and scheduling method of claim 1, wherein: the method of calculating the rest period in step S3 is as follows:
obtaining the unit to be poured of the current finished standby bin, and recording the current time T1Then recording the pouring completion time T of the lower layer unit of the prepared bin unit2Through T1- T2And obtaining the intermittence period of the unit to be poured.
3. The BIM-based cable routing and scheduling method of claim 1, wherein: the dynamic adjustment method in steps S6 and S10 is as follows:
after the coverage range of one cable machine is adjusted, the arrangement and the coverage range of each cable machine adjacent to the cable machine are dynamically adjusted in a linkage manner according to the minimum safety distance requirement of the cable machine and the relative position relationship between the cable machines so as to meet the setting process and the safety rule of S5, and the updating of the overall arrangement scheme of a plurality of cable machines and the real-time calculation and checking of each index are realized.
4. The BIM-based cable routing and scheduling method of claim 3, wherein: the dynamic adjustment range does not exceed the cable crane moving range and the minimum spacing limit; and when the cable crane adjustment reaches the cable crane movable range limit or the cable crane arrangement reaches the minimum working range and the minimum spacing limit of each cable crane, forbidding to perform adjustment again.
5. The BIM-based cable routing and scheduling method of claim 1, wherein: the operation safety requirement of the cable crane in the step S9 means that the distance between the cable cranes meets the requirement of the minimum distance between the same layer and the interlayer; the blank layer covering time requirement means that the ratio of the partition square amount/rated hour transportation strength/the number of the layered layers meets the requirement.
6. The BIM-based cable routing and scheduling method of claim 1, wherein: the method of dynamically cutting the unit BIM model in step S8 is as follows:
based on the geometric shapes of the concrete pouring units, automatically cutting the models according to the pile number coverage range distributed by a plurality of current cable cranes, calculating the upper surface area and the volume of each cutting model, and calculating the blank layer coverage time according to the theoretical pouring strength of each cutting model corresponding to the cable crane; the covering time interval of the connected blank layers does not exceed the maximum interval limit, and cold seams generated by initial setting of the concrete poured in advance are prevented.
CN202011619128.8A 2020-12-31 2020-12-31 Cable crane arrangement and scheduling method based on BIM Active CN112434366B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011619128.8A CN112434366B (en) 2020-12-31 2020-12-31 Cable crane arrangement and scheduling method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011619128.8A CN112434366B (en) 2020-12-31 2020-12-31 Cable crane arrangement and scheduling method based on BIM

Publications (2)

Publication Number Publication Date
CN112434366A true CN112434366A (en) 2021-03-02
CN112434366B CN112434366B (en) 2022-07-15

Family

ID=74697111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011619128.8A Active CN112434366B (en) 2020-12-31 2020-12-31 Cable crane arrangement and scheduling method based on BIM

Country Status (1)

Country Link
CN (1) CN112434366B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112883580A (en) * 2021-03-09 2021-06-01 中国三峡建设管理有限公司 Dam pouring plan dynamic adjustment method based on BIM

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130339078A1 (en) * 2012-06-18 2013-12-19 Coaxis, Inc. System and method linking building information modeling and enterprise resource planning
CN106855901A (en) * 2016-12-16 2017-06-16 天津大学 The high arch dam construction progress real-time emulation method of Coupling Temperature Field
CN108537440A (en) * 2018-04-09 2018-09-14 四川交通职业技术学院 A kind of building scheme project management system based on BIM
CN109072621A (en) * 2016-04-07 2018-12-21 利勃海尔工厂比伯拉赫有限公司 For constructing the devices, systems, and methods of stationary structure on working face
CN109117520A (en) * 2018-07-21 2019-01-01 中铁十八局集团有限公司 A kind of cable hoisting arrangement system and design method based on BIM
US20190205484A1 (en) * 2017-12-28 2019-07-04 ALICE Technologies, Inc. Systems and methods for construction planning
CN110516361A (en) * 2019-08-28 2019-11-29 中国三峡建设管理有限公司 The multidimensional emulation mode of intermittent phase is poured based on storehouse surface
CN111622225A (en) * 2020-06-04 2020-09-04 中国电建集团成都勘测设计研究院有限公司 Multi-cable machine adjusting method
DE102019108689A1 (en) * 2019-04-03 2020-10-08 Liebherr-Werk Biberach Gmbh Method and device for controlling a material handling and / or construction machine
CN112035932A (en) * 2020-09-02 2020-12-04 中国电建集团成都勘测设计研究院有限公司 Arch dam intelligent progress simulation method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130339078A1 (en) * 2012-06-18 2013-12-19 Coaxis, Inc. System and method linking building information modeling and enterprise resource planning
CN109072621A (en) * 2016-04-07 2018-12-21 利勃海尔工厂比伯拉赫有限公司 For constructing the devices, systems, and methods of stationary structure on working face
CN106855901A (en) * 2016-12-16 2017-06-16 天津大学 The high arch dam construction progress real-time emulation method of Coupling Temperature Field
US20190205484A1 (en) * 2017-12-28 2019-07-04 ALICE Technologies, Inc. Systems and methods for construction planning
CN108537440A (en) * 2018-04-09 2018-09-14 四川交通职业技术学院 A kind of building scheme project management system based on BIM
CN109117520A (en) * 2018-07-21 2019-01-01 中铁十八局集团有限公司 A kind of cable hoisting arrangement system and design method based on BIM
DE102019108689A1 (en) * 2019-04-03 2020-10-08 Liebherr-Werk Biberach Gmbh Method and device for controlling a material handling and / or construction machine
CN110516361A (en) * 2019-08-28 2019-11-29 中国三峡建设管理有限公司 The multidimensional emulation mode of intermittent phase is poured based on storehouse surface
CN111622225A (en) * 2020-06-04 2020-09-04 中国电建集团成都勘测设计研究院有限公司 Multi-cable machine adjusting method
CN112035932A (en) * 2020-09-02 2020-12-04 中国电建集团成都勘测设计研究院有限公司 Arch dam intelligent progress simulation method

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
FENG DAI等: "Focal mechanism determination for microseismic events and its application to the left bank slope of the Baihetan hydropower station in China", 《ENVIRONMENTAL EARTH SCIENCES》 *
TAO GUAN等: "CONSTRUCTION SCHEDULE OPTIMIZATION FOR HIGH ARCH DAMS BASED ON REAL-TIME INTERACTIVE SIMULATION", 《JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION》 *
张世保等: "《缆索起重机管理总结》", 31 July 2017, 北京:中国三峡出版社 *
王仁超等: "基于BIM的混凝土坝浇筑仿真智能建模方法研究", 《水电能源科学》 *
王仁超等: "混凝土坝浇筑仿真中的缆机干扰与联合问题研究", 《水资源与水工程学报》 *
谢意乐等: "高拱坝混凝土施工中缆机双仓联合浇筑模拟优化研究", 《水电能源科学》 *
谭尧升等: "特高拱坝施工智能化信息管理系统水电工程边坡施工全过程信息模型研究与应用发与实践", 《清华大学学报(自然科学版)》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112883580A (en) * 2021-03-09 2021-06-01 中国三峡建设管理有限公司 Dam pouring plan dynamic adjustment method based on BIM

Also Published As

Publication number Publication date
CN112434366B (en) 2022-07-15

Similar Documents

Publication Publication Date Title
CN102082434B (en) Optimal strategy and performance evaluation method controlled by multi-target section tidal current
CN109783949A (en) A kind of external scaffolding Intelligentized design method based on BIM
KR20130016620A (en) 3d process management method for bim(building information modeling)
CN112434366B (en) Cable crane arrangement and scheduling method based on BIM
CN101908092A (en) Iron-making and steel-making continuous casting integrated dispatching system
CN110119516A (en) A kind of reinforcement detailing method based on BIM technology
CN105731262A (en) Tower crane plane arranging system and method based on BIM (building information modeling) technology
CN111242414A (en) Plan scheduling system applied to steelmaking-continuous casting process in steel industry
CN103628483B (en) The concrete dam pouring mechanically combining that puts in storage builds simulation and optimum method
CN113032872A (en) BIM technology-based integrated resource management and control method for assembly type building progress plan
CN102677635B (en) Method for simulating interference between hoisting of steel lining of cable crane and concrete pouring in concrete construction process of high arch dam
KR101603441B1 (en) method for auto calculating for examination of block lifting safety
CN100570757C (en) The modular construction method that is used for nuclear island of nuclear power station
CN104122861B (en) The conflict resolution method lax based on the waiting time and Optimization Scheduling
CN111046488B (en) Three-dimensional wiring method for spacecraft cable
CN101752017A (en) Modularization construction method for nuclear power station nuclear island
CN101736925A (en) Modular construction method for nuclear island of nuclear power station
CN103020355B (en) Method for realizing spatial arrangement scheduling of curved section of ship
CN115033963A (en) Method for establishing curtain grouting BIM model based on 3DE
CN103065004B (en) The method of a kind of ship surface sectional construction dynamic dispatching
CN101748915A (en) Modularization construction method for nuclear power station nuclear island
CN117195375A (en) Simulation modeling method for two-bin combined pouring system of high arch dam
KR20160113941A (en) System for exzmination of block lifting safety based on 3-dimensional model
CN110689201A (en) Multi-project collaborative plan optimization method based on immune genetic algorithm
CN116992699B (en) Concrete dam block division strip pouring process diagram simulation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant