CN112431990B - Method for repairing trenchless coating lining of large-diameter drainage pipeline - Google Patents

Method for repairing trenchless coating lining of large-diameter drainage pipeline Download PDF

Info

Publication number
CN112431990B
CN112431990B CN202011460601.2A CN202011460601A CN112431990B CN 112431990 B CN112431990 B CN 112431990B CN 202011460601 A CN202011460601 A CN 202011460601A CN 112431990 B CN112431990 B CN 112431990B
Authority
CN
China
Prior art keywords
construction
pipeline
batch
repairing
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011460601.2A
Other languages
Chinese (zh)
Other versions
CN112431990A (en
Inventor
李春雷
张立军
付祖俊
胡荣华
王建军
石叶
秦慧程
赵全峰
范维维
徐谦
何彪
郑良
邱涛
冯均才
邓成冬
吴娜
陈昱弛
胡长令
徐晶
钟毅
贾东浩
陈章
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Original Assignee
Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd filed Critical Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Priority to CN202011460601.2A priority Critical patent/CN112431990B/en
Publication of CN112431990A publication Critical patent/CN112431990A/en
Application granted granted Critical
Publication of CN112431990B publication Critical patent/CN112431990B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/16Devices for covering leaks in pipes or hoses, e.g. hose-menders
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/16Devices for covering leaks in pipes or hoses, e.g. hose-menders
    • F16L55/168Devices for covering leaks in pipes or hoses, e.g. hose-menders from outside the pipe
    • F16L55/175Devices for covering leaks in pipes or hoses, e.g. hose-menders from outside the pipe by using materials which fill a space around the pipe before hardening

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a method for repairing a large-diameter drainage pipeline trenchless coating lining. The method comprises the steps of preparation before construction, repair construction and construction quality detection; the method comprises the following steps: construction preparation, ventilation detection, pipeline plugging, construction drainage guide, pipeline dredging, repair point identification, grouting in a pipe, joint crack treatment, joint surface treatment, coating repair construction, edge sealing maintenance, quality inspection and site cleaning. The invention adopts the high molecular polymer emulsion and the inorganic powder to form the double-component composite waterproof film coating material to form the high-strength tough waterproof film, which has the double advantages of high elasticity of organic materials and good durability of inorganic materials; the glass fiber gridding cloth layer is additionally arranged, so that the integral tensile strength of the waterproof film can be greatly improved; the three-base-layer construction process is adopted, and comprises bottom batch construction, grid cloth laying and surface batch construction, and has the advantages of firm repair base layer, stable coverage combination and the like.

Description

Method for repairing trenchless coating lining of large-diameter drainage pipeline
Technical Field
The invention relates to the technical field of drainage pipeline repair construction, in particular to a method for repairing a large-diameter drainage pipeline trenchless coating lining.
Background
With the rapid development of urban construction, the number of various public underground pipelines and the scale of structures are also continuously enlarged, the available underground space is smaller and smaller, especially for old urban areas which are built and have no large-scale comprehensive transformation plan, the laying difficulty of newly-built drainage pipelines is larger and larger, meanwhile, the structural defects of dislocation, leakage, corrosion and the like of the original pipelines are more serious along with the time lapse, and the corresponding treatment of the original pipelines becomes a necessary choice in the urban development process. If the traditional grooving construction method is adopted for pipeline replacement, a series of problems of long construction period, large environmental pollution, serious traffic influence, prominent safety risk and the like are faced, so that the traditional excavation repair construction is high in cost, and the trenchless repair technology is forced to be developed quickly.
Disclosure of Invention
The invention discloses a method for repairing a large-diameter drainage pipeline trenchless coating lining. The invention aims to solve the defects of leakage, corrosion, disjointing and the like of the pipeline, avoid the problems of large environmental pollution, prominent safety risk and the like caused by excavation repair construction, and provide a repair method for the pipeline without structural damage or the pipeline with potential corrosion leakage risk for protective pre-repair.
The invention is realized by the following technical scheme:
a method for repairing a large-diameter drainage pipeline trenchless coating lining comprises the following steps: preparation before construction, repair construction and construction quality detection; the method specifically comprises the following steps:
preparation before construction:
(1) construction preparation: before formal construction, the administrative examination and approval procedures of road occupation construction need to be handled, and traffic relief and construction site arrangement are carried out according to examination and approval conditions.
(2) And (3) ventilation detection: and respectively erecting a blower and an exhaust fan at two well mouths of the section to be repaired, continuously supplying air and ventilating to the well bottom, and assigning a specially-assigned person to use a detector to detect harmful gas.
(3) Pipeline plugging: in the pipe section repairing construction, safe blocking is carried out on the pipeline, and an air bag blocking method or a brick blocking method is adopted as a blocking method.
(4) Construction and guide row: and (3) guiding the incoming water of the branch pipes related to the upstream pipeline and the construction section, and simultaneously pumping and draining the accumulated water in the pipeline to be repaired.
(5) Dredging a pipeline: according to the deposition condition of the pipeline, the pipeline is dredged by adopting a high-pressure water jet method or a manual underground clearing method.
(6) Interpretation repair point: and determining the repair points and points according to CCTV (closed Circuit Television) detection results and the inspection condition of the underground well of the personnel.
Repairing construction:
(7) grouting in the pipe: and grouting and reinforcing the soil body around the pipe to fill the slurry into the soil layer and gaps to form an anti-seepage curtain, so that the stability of the soil body is enhanced, and the soil body loss is prevented.
(8) Interface crack treatment: according to the width of the interface crack, a cement accelerator method is adopted for embedding or polyurethane injection is adopted for filling and sealing after rapid water plugging mortar is adopted for embedding.
(9) Interface surface treatment: the method comprises the steps of chiseling the sundries and dirt on the joint part of the pipeline higher than the pipe wall, and then roughening the surface of the pipe wall to be lined by using an electric grinding wheel.
(10) Coating repair construction: adding water into the bottom batch of dry powder, stirring into thick paste, and fully batching the paste on the surface of a roughened part by using a mud plate; paving glass fiber mesh cloth after the bottom batch is dried and hardened; after the gridding cloth is laid, the waterproof membrane surface is constructed in batches, liquid materials are poured into powder materials and stirred into mortar, the mortar is scraped on the bottom batch in three batches by using a mud plate, and the fiber gridding cloth is covered.
(11) Sealing and maintaining: and (3) sealing edges of two side openings of the waterproof film lining by using solvent-free epoxy resin, and unsealing and introducing water after curing for at least 7 days under natural conditions of drying and ventilation.
And (3) construction quality detection:
(12) quality inspection: and (4) adopting CCTV detection equipment to perform appearance inspection after repair so as to ensure that the defect part to be repaired is completely covered. Sampling and inspecting on site, detecting the mechanical property and ensuring to meet the requirements of specification and design.
(13) Cleaning the site: and (4) plugging and dismantling, and removing the used construction equipment, waste materials, construction wastes and temporary facilities out of the construction site after the repair is finished.
Preferably, the pipeline plugging in the step (3) is specifically that a brick plugging is adopted at an upstream pipe orifice of an upstream inspection well of the pipeline to be repaired, and a plurality of valves are reserved on the brick plugging according to upstream water inflow so as to facilitate drainage in a non-construction period; and a downstream pipe orifice of the downstream inspection well is sealed by an air bag.
Preferably, the step (5) of dredging the pipeline specifically comprises the step of adopting a high-pressure water jet method when the deposition amount of the pipeline is not large, namely, driving a spray head with a water guide system to advance and wash by using high-pressure water, and controlling the water jet angle to be 30-35 degrees; when the deposition amount of the pipeline is large, a professional goes into the well to clean the pipeline, and high-pressure water washing is performed after the pipeline is cleaned.
Preferably, the pipeline grouting in the step (7) adopts an in-pipe outward drilling grouting method, and the grouting ranges are 2.0m below the bottom of the pipeline, 1.5m on the left side and the right side and 1.0m on the upper part of the pipeline; the arrangement of the grouting holes is determined according to the pipe diameter of the pipeline, and four points are arranged when the pipe diameter is less than or equal to 1600 mm; when the pipe diameter is larger than 1600mm, five points are arranged; the arrangement distance of the longitudinal grouting holes of the pipe joints is 1.0-2.0 m; the grouting material is cement mortar, and the mortar consistency is determined according to factors such as the leakage condition of the pipeline, the size of a gap at a water leakage position and the like. The pressure is gradually adjusted from small to large in the grouting process, the sandy soil is controlled within the range of 0.2-0.5 MPa, and the cohesive soil is controlled within the range of 0.2-0.3 MPa.
Preferably, when the interface crack is treated in the step (8), when the crack width is 1-3 mm, a cement accelerator method is adopted for repairing; the width of the crack is 4-10 mm, and the crack is filled and embedded by adopting rapid water plugging mortar and then is filled and sealed by polyurethane injection.
Preferably, the coating repair construction in the step (10) specifically comprises the following steps:
firstly, bottom batch construction: adding water into the bottom batch dry powder, wherein the water-cement ratio is 1: and 4, continuously stirring the mixture into thick paste by using a special electric stirring tool, fully coating the surface of the roughened part by using a mud plate, wherein the width of the mud plate is 30cm on each of two sides with the interface as the center, the thickness of the mud plate is not less than 2mm, and the hardening time of the bottom coating is about 5-6 h.
Secondly, laying mesh cloth: a layer of glass fiber mesh cloth is laid on a hardened bottom batch, the perimeter of the mesh cloth is lapped by more than 10cm, the mesh cloth needs to be smoothly and tightly attached to the bottom batch, the phenomena of corner warping, arching, creasing and the like cannot occur, the mesh cloth at the top of the pipe needs to be temporarily supported and stabilized by a wooden frame, and the pipe is prevented from drooping and falling.
And finally, performing surface batch construction: pouring liquid materials into the powder materials, liquid: powder 4: and 5, continuously stirring the mixture into uniform mortar by adopting a special electric stirring tool, scraping the mortar on the bottom batch by using a mud plate in three batches, and covering the fiber grids with cloth. And after the surface of the last waterproof film is dry, performing secondary scraping and tertiary scraping, wherein the thickness of the dough is not less than 4.5mm, the total thickness of the bottom batch and the dough is about 6.5mm, and two edges are made into small chamfers.
Preferably, the base material is polymer cement-based elastic waterproof membrane base (dry powder), and the surface material is polymer cement-based elastic waterproof membrane surface group A component (dry powder) and polymer cement-based elastic waterproof membrane surface group B component (emulsion).
Preferably, the glass fiber mesh cloth is medium-alkali plastic-coated glass fiber mesh cloth with the tensile force not lower than 1600N.
Preferably, the plug is removed in the step (13) by a water pressure balance method, a valve reserved at the upstream brick plug is opened to raise the water level in the repaired pipeline, when the water level heights in the upstream and downstream inspection wells are basically consistent, the brick plug is removed, and then the downstream plug air bag is deflated and taken out.
Compared with the prior art, the invention has the beneficial effects that: (1) the two-component composite waterproof film coating material formed by the high-molecular polymer emulsion and the inorganic powder can form a high-strength tough waterproof film after the two components are mixed, and the waterproof film has the double advantages of high elasticity of organic materials and good durability of inorganic materials. (2) The cement-based polymer coating has the characteristics of high-strength bonding, toughness and composite elasticity with an original body, and a layer of glass fiber gridding cloth is additionally arranged in the manufacturing process of the waterproof membrane, so that the integral tensile strength of the waterproof membrane can be greatly improved. (3) The repairing construction has the advantages of small environmental pollution, high construction speed, less resource investment, small safety risk, small loss of the water passing section, small interference to peripheral traffic, life and commercial activities and the like. (4) The cement-based polymer waterproof film coating has the characteristics of water resistance, no toxicity, no pollution, good flexibility, no joint, good integrity, high setting speed, light weight, rigidity and flexibility, alkali resistance, easiness in repairing and the like. (5) The three-base-layer construction process is adopted, and comprises bottom batch construction, grid cloth laying and surface batch construction, and has the advantages of firm repair base layer, stable coverage combination and the like.
Drawings
FIG. 1 is a flow chart of a method for repairing a large-diameter drainage pipeline trenchless coating lining of the invention.
Detailed Description
The present invention is further described below in conjunction with the following detailed description, which is intended to further illustrate the principles of the invention and is not intended to limit the invention in any way, but is equivalent or analogous to the present invention without departing from its scope.
With reference to the attached drawings.
The method for repairing the trenchless coating lining of the large-caliber drainage pipeline comprises the following steps:
(1) construction preparation: before formal construction, the administrative examination and approval procedures of road occupation construction need to be handled, and traffic relief and construction site arrangement are carried out according to examination and approval conditions.
(2) And (3) ventilation detection: and (3) erecting a blower and an exhaust fan at two well mouths of a construction section respectively, continuously supplying air and ventilating to a well bottom, and assigning a specially-assigned person to continuously detect harmful gas by using a detector.
(3) Pipeline plugging: adopting brick blocks to block upstream pipe orifices of an upstream inspection well of a pipeline to be repaired, and reserving a plurality of valves on the brick blocks according to upstream water inflow so as to facilitate drainage in a non-construction period; and a downstream pipe orifice of the downstream inspection well is sealed by an air bag.
(4) Construction and guide row: and (3) guiding the incoming water of the branch pipes related to the upstream pipeline and the construction section, and simultaneously pumping and draining the accumulated water in the pipeline to be repaired.
(5) Dredging the pipeline: when the deposition amount of the pipeline is not large, a high-pressure water jet method is adopted, namely high-pressure water is utilized to drive a spray head with a water guide system to advance and wash, and the water jet angle is controlled to be 30-35 degrees; when the deposition amount of the pipeline is large, a professional goes down the well to clean the pipeline, and high-pressure water washing is performed after the pipeline is cleaned.
(6) Interpretation repair point: and determining the number and the point position of the repair points according to the CCTV detection result and the underground checking condition of personnel.
(7) Grouting in the pipe: adopting an in-pipe outward drilling grouting method, wherein the grouting range is 2.0m below the bottom of the pipeline, 1.5m on the left side and the right side and 1.0m on the upper part; the arrangement of the grouting holes is determined according to the pipe diameter of the pipeline, and four points are arranged when the pipe diameter is less than or equal to 1600 mm; when the pipe diameter is larger than 1600mm, five points are arranged; the arrangement distance of the longitudinal grouting holes of the pipe joints is 1.0-2.0 m; the grouting material is cement mortar, and the mortar consistency is determined according to factors such as the leakage condition of the pipeline, the size of a gap at a water leakage position and the like. The pressure is gradually adjusted from small to large in the grouting process, the sandy soil is controlled within the range of 0.2-0.5 MPa, and the cohesive soil is controlled within the range of 0.2-0.3 MPa.
(8) Interface crack treatment: when the width of the crack is 1-3 mm, embedding and repairing by adopting a cement accelerator method; the width of the crack is 4-10 mm, and the crack is filled and embedded by adopting rapid water plugging mortar and then is filled and sealed by polyurethane injection.
(9) Interface surface treatment: the method comprises the steps of chiseling the dirt and the like on the joint part of the pipeline higher than the pipe wall, and then roughening the surface of the pipe wall to be lined by using an electric grinding wheel.
(10) Coating repair construction: adding water into the bottom batch of dry powder, stirring into thick paste, and fully batching the paste on the surface of a roughened part by using a mud plate; paving glass fiber gridding cloth after the bottom batch is dried and hardened; after the gridding cloth is laid, the waterproof membrane surface is constructed in batches, liquid materials are poured into powder materials and stirred into mortar, the mortar is scraped on the bottom batch in three batches by using a mud plate, and the fiber gridding cloth is covered.
Firstly, surface batch construction: adding water into the bottom batch dry powder, wherein the water-cement ratio is 1: and 4, continuously stirring the mixture into thick paste by using a special electric stirring tool, fully coating the surface of the roughened part by using a mud plate, wherein the width of the mud plate is 30cm on each of two sides with the interface as the center, the thickness of the mud plate is not less than 2mm, and the hardening time of the bottom coating is about 5-6 h.
Secondly, laying mesh cloth: a layer of glass fiber mesh cloth is laid on a hardened bottom batch, the perimeter of the mesh cloth is lapped by more than 10cm, the mesh cloth needs to be smoothly and tightly attached to the bottom batch, the phenomena of corner warping, arching, creasing and the like cannot occur, the mesh cloth at the top of the pipe needs to be temporarily supported and stabilized by a wooden frame, and the pipe is prevented from drooping and falling.
And finally, performing surface batch construction: pouring liquid materials into the powder materials, liquid: powder 4: and 5, continuously stirring the mixture into uniform mortar by adopting a special electric stirring tool, scraping the mortar on the bottom batch by using a mud plate in three batches, and covering the fiber grids with cloth. And after the surface of the last waterproof film is dry, performing secondary scraping and tertiary scraping, wherein the thickness of the dough is not less than 4.5mm, the total thickness of the bottom batch and the dough is about 6.5mm, and two edges are made into small chamfers.
(11) Sealing and maintaining: and (3) sealing edges of two side openings of the waterproof film lining by using solvent-free epoxy resin, and unsealing and introducing water after curing for at least 7 days under natural conditions of drying and ventilation.
(12) Quality inspection: and (4) adopting CCTV detection equipment to perform appearance inspection after repair so as to ensure that the defect part to be repaired is completely covered. Sampling and inspecting on site, detecting the mechanical property and ensuring to meet the requirements of specification and design.
(13) Cleaning the site: and (4) plugging and removing, and removing the used construction machines, waste materials, construction wastes and temporary facilities out of the construction site after repairing.

Claims (8)

1. A method for repairing a large-diameter drainage pipeline trenchless coating lining comprises the following steps: preparation before construction, repair construction and construction quality detection; the method is characterized by comprising the following steps:
preparation before construction:
(1) construction preparation: carrying out construction permission preparation and construction environment arrangement before formal construction;
(2) and (3) ventilation detection: respectively erecting a blower and an exhaust fan at two inspection well mouths of the section to be repaired, continuously supplying air and ventilating to a well bottom, and detecting harmful gas by using a detector;
(3) pipeline plugging: adopting an air bag plugging method or a brick plugging method;
(4) construction and guide row: guiding the incoming water of the branch pipes related to the upstream pipeline and the construction section, and simultaneously pumping and draining the accumulated water in the pipeline to be repaired;
(5) Dredging the pipeline: according to the deposition condition of the pipeline, dredging the pipeline by adopting a high-pressure water jet method or an artificial underground well cleaning method;
(6) interpretation repair point: determining repair point positions and points according to CCTV detection results and personnel underground checking conditions;
repairing construction:
(7) grouting in the pipe: grouting and reinforcing the soil body around the pipe to fill the inside and gaps of the soil layer with the grout to form an anti-seepage curtain, so that the stability of the soil body is enhanced, and the soil body is prevented from losing;
(8) interface crack treatment: according to the width of the interface crack, a cement accelerator method is adopted for embedding or polyurethane is used for injecting, filling and sealing after rapid water plugging mortar is adopted for embedding;
(9) interface surface treatment: firstly, chiseling the sundries on the pipeline interface part higher than the pipe wall, and then roughening the surface of the pipe wall to be lined by using an electric grinding wheel;
(10) coating repair construction: adopting a three-base-layer construction method, including bottom batch construction, grid cloth laying and surface batch construction; adding water into the bottom batch of dry powder, stirring into thick paste, and fully batching the paste on the surface of a roughened part by using a mud plate; paving glass fiber mesh cloth after the bottom batch is dried and hardened; after the gridding cloth is laid, the waterproof membrane surface batch construction is carried out, liquid materials are poured into powder materials and stirred into mortar, the mortar is scraped on the bottom batch in three batches by using a mud plate, and the fiber gridding cloth is covered; the bottom batch dry powder is polymer cement-based elastic waterproof membrane bottom batch dry powder, the surface batch powder is polymer cement-based elastic waterproof membrane surface batch dry powder, and the surface batch liquid material is polymer cement-based elastic waterproof membrane surface batch emulsion;
(11) Edge sealing and maintaining: sealing edges of two side openings of the waterproof film lining by using solvent-free epoxy resin, and unsealing and communicating water after curing for at least 7 days under natural conditions of drying and ventilation;
and (3) construction quality detection:
(12) and (4) quality inspection: performing appearance inspection after repair by adopting CCTV detection equipment to ensure that the defect part to be repaired is completely covered; sampling and submitting on site, and detecting the mechanical property to ensure that the standard and design requirements are met;
(13) cleaning the site: and (4) plugging and removing, namely removing the construction machines, the waste materials, the construction wastes and the temporary facilities out of the construction site.
2. The method for repairing the trenchless coating lining of the large-caliber drainage pipeline according to claim 1, wherein the method comprises the following steps: in the step (3), the pipeline plugging is to plug the upstream pipe orifice of the upstream inspection well of the pipeline to be repaired by adopting bricks, and a plurality of valves are reserved on the bricks according to the upstream water inflow amount so as to facilitate drainage in the non-construction period; and a downstream pipe orifice of the downstream inspection well is sealed by an air bag.
3. The method for repairing the trenchless coating lining of the large-caliber drainage pipeline according to claim 1, wherein the method comprises the following steps: the step (5) of dredging the pipeline comprises the following steps: adopting high-pressure water jet method, i.e. using high-pressure water to drive spray head with water guide system to make advance and flushing, and controlling water jet angle at 30 o ~35 o (ii) a Or, a professional manually goes into the well to clean the well, and high-pressure water washing is carried out after cleaning.
4. The method for repairing the trenchless coating lining of the large-caliber drainage pipeline according to claim 1, wherein the method comprises the following steps: in the step (7), the pipeline grouting adopts an in-pipe outward drilling grouting method, and the grouting ranges are 2.0m below the bottom of the pipeline, 1.5m on the left side and the right side and 1.0m on the upper part; the arrangement of the grouting holes is determined according to the pipe diameter of the pipeline, and four points are arranged when the pipe diameter is less than or equal to 1600 mm; when the pipe diameter is larger than 1600mm, five points are arranged; the arrangement distance of the longitudinal grouting holes of the pipe joints is 1.0-2.0 m; the grouting material is cement mortar, the pressure is gradually adjusted from small to large in the grouting process, the sandy soil is controlled within the range of 0.2-0.5 MPa, and the cohesive soil is controlled within the range of 0.2-0.3 MPa.
5. The method for repairing the trenchless coating lining of the large-caliber drainage pipeline according to claim 1, wherein the method comprises the following steps: during the interface crack treatment in the step (8), when the crack width is 1-3 mm, a cement accelerator method is adopted for repairing; the width of the crack is 4-10 mm, and the crack is filled and embedded with rapid water plugging mortar and then is filled and sealed by polyurethane injection.
6. The method for repairing the trenchless coating lining of the large-caliber drainage pipeline according to claim 2, wherein the method comprises the following steps: and (3) removing the plug in the step (13) by adopting a water pressure balance method, firstly opening a reserved valve at the upstream brick plug to enable the water level in the repaired pipeline to rise, removing the brick plug when the water levels in the upstream and downstream inspection wells are consistent, and then deflating and taking out the downstream plug air bag.
7. The method for repairing a large-caliber drainage pipeline trenchless coating liner as claimed in any one of claims 1 to 6, wherein the method comprises the following steps: the bottom batch construction, the grid cloth laying and the surface batch construction in the coating repairing construction step in the step (10) are as follows:
firstly, bottom batch construction: adding water into the bottom batch dry powder, wherein the water-cement ratio is 1: 4, continuously stirring the mixture into thick paste by using an electric stirring tool, fully coating the surface of the roughened part with mud plates, wherein the width of each mud plate is 30cm on each side of the interface, the thickness of each mud plate is not less than 2mm, and the hardening time of the bottom coating is about 5-6 h;
secondly, laying mesh cloth: laying a layer of glass fiber mesh cloth on the hardened bottom batch, wherein the girth of the mesh cloth is lapped by more than 10cm, the mesh cloth needs to be smoothly and tightly attached to the bottom batch, the phenomena of corner warping, arching, creasing and the like cannot occur, and the mesh cloth at the top part of the pipe needs to be temporarily supported and stabilized by a wooden frame to prevent sagging and falling;
and finally, performing surface batch construction: pouring dough batch liquid material into dough batch powder material, liquid: powder = 4: 5, continuously stirring the mixture into uniform mortar by using an electric stirring tool, scraping the mortar on the bottom batch by using a mud plate in three batches, and covering the fiber grids; and after the surface of the last waterproof film is dry, performing secondary scraping and tertiary scraping, wherein the thickness of the dough is not less than 4.5mm, the total thickness of the bottom batch and the dough is not less than 6.5mm, and two edges are made into small chamfers.
8. The method for repairing the trenchless coating lining of the large-caliber drainage pipeline according to claim 7, wherein the method comprises the following steps: the glass fiber mesh cloth is medium-alkali plastic-coated glass fiber mesh cloth with the tensile force not lower than 1600N.
CN202011460601.2A 2020-12-11 2020-12-11 Method for repairing trenchless coating lining of large-diameter drainage pipeline Active CN112431990B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011460601.2A CN112431990B (en) 2020-12-11 2020-12-11 Method for repairing trenchless coating lining of large-diameter drainage pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011460601.2A CN112431990B (en) 2020-12-11 2020-12-11 Method for repairing trenchless coating lining of large-diameter drainage pipeline

Publications (2)

Publication Number Publication Date
CN112431990A CN112431990A (en) 2021-03-02
CN112431990B true CN112431990B (en) 2022-07-29

Family

ID=74691589

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011460601.2A Active CN112431990B (en) 2020-12-11 2020-12-11 Method for repairing trenchless coating lining of large-diameter drainage pipeline

Country Status (1)

Country Link
CN (1) CN112431990B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113898817A (en) * 2021-10-05 2022-01-07 中国水利水电第七工程局成都水电建设工程有限公司 Trenchless crack embedding repair method for large-diameter drainage pipeline
CN114215994A (en) * 2021-12-14 2022-03-22 武汉致远市政建设工程有限公司 Pipeline repairing construction method
CN114263804B (en) * 2022-01-04 2023-05-23 河南省禹志建设工程有限公司 On-line plugging construction method with water pressure
CN114088307B (en) * 2022-01-24 2022-04-08 东营昱辰技术有限公司 Anti-seepage detection device for cement drainage pipe for oilfield pollution discharge construction
CN115727195A (en) * 2022-09-15 2023-03-03 周蕾 Municipal large-diameter pipe jacking pipeline slippage repairing method under complex terrain

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE713941A (en) * 1968-04-19 1968-10-21
CN1296577C (en) * 2004-02-17 2007-01-24 上海市普陀区市政工程管理署 Method for repairing sewer using water-proof film lining
CN101344208B (en) * 2008-08-19 2010-06-16 北京力强基业工程技术有限公司 Pipe renovation method and its special renovation material system
CN102486247B (en) * 2010-12-02 2014-04-09 杨兵 Water supply and drainage pipeline repair technique adopting size film lining method
CN110762331A (en) * 2019-10-31 2020-02-07 中铁十八局集团建筑安装工程有限公司 Local resin curing construction process for reconstruction and expansion of drainage pipe network
CN111075994A (en) * 2019-12-03 2020-04-28 上海市基础工程集团有限公司 Flexible pipeline repairing construction method

Also Published As

Publication number Publication date
CN112431990A (en) 2021-03-02

Similar Documents

Publication Publication Date Title
CN112431990B (en) Method for repairing trenchless coating lining of large-diameter drainage pipeline
CA2032217C (en) Method of rehabilitating manholes by custom lining/relining
CN103233520B (en) Self-waterproof construction method of building external wall structure
CN104153400B (en) Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof
CN106640154A (en) Treatment method and structure for water seepage of tunnel lining circular construction joint crack
CN112412496A (en) Full-section advanced curtain grouting construction method for water-rich broken geological zone tunnel
CN113898817A (en) Trenchless crack embedding repair method for large-diameter drainage pipeline
CN105464194A (en) Water proofing and leak repairing construction method for sewage pipe network below underground water level
CN111424613A (en) Method for treating through cracks of roller compacted concrete dam
CN113847050A (en) Construction method of extra-long highway tunnel in lava mountain area
CN111140264A (en) Method for treating water leakage of cracks of tunnel concrete lining structure
CN1296577C (en) Method for repairing sewer using water-proof film lining
CN112942432A (en) Construction method of anti-leakage brick inspection well
CN113374295A (en) Old steel-wood structure roof truss dismantling and rebuilding construction method
CN113356229A (en) Safe and efficient comprehensive construction method for garage under high-speed railway base
CN112195970A (en) River-crossing tunnel engineering waterproof construction method
CN104975623A (en) Non-excavation leaking inspection well repairing method and repairing structure
CN214194878U (en) Drainage ditch box prosthetic devices
CN110172978A (en) A kind of subway open-cut station waterproof basal plane construction method
CN110258680A (en) A kind of diaphram wall restorative procedure
DE19643175A1 (en) Reconstruction method for stacks of e.g. water pipes
CN115653005B (en) Construction method of high permeable layer underground inspection well
CN216839297U (en) Upstream anti-seepage structure of roller compacted concrete gravity dam
CN112901222B (en) Treatment process for concrete water seepage cracks of inverted arch of tunnel
CN204875889U (en) Structure is restoreed to seepage inspection shaft of non - excavation mode

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant