CN112411839B - Building glass curtain wall and construction method thereof - Google Patents

Building glass curtain wall and construction method thereof Download PDF

Info

Publication number
CN112411839B
CN112411839B CN202011462232.0A CN202011462232A CN112411839B CN 112411839 B CN112411839 B CN 112411839B CN 202011462232 A CN202011462232 A CN 202011462232A CN 112411839 B CN112411839 B CN 112411839B
Authority
CN
China
Prior art keywords
curtain wall
fixing
fixed
wall
glass plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011462232.0A
Other languages
Chinese (zh)
Other versions
CN112411839A (en
Inventor
叶提勇
方海涛
方海燕
俞剑锋
史云峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Classic Construction Co.,Ltd.
Original Assignee
Zhejiang Classic Building Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Classic Building Decoration Co ltd filed Critical Zhejiang Classic Building Decoration Co ltd
Priority to CN202011462232.0A priority Critical patent/CN112411839B/en
Publication of CN112411839A publication Critical patent/CN112411839A/en
Application granted granted Critical
Publication of CN112411839B publication Critical patent/CN112411839B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • E04B2/965Connections of mullions and transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Abstract

The invention discloses a building glass curtain wall and a construction method thereof, relating to the technical field of glass curtain walls; in order to improve the firmness of the assembly; the glass curtain wall comprises a stand column, wherein first assembly parts for installing the stand column are fixed on the outer walls of two sides of the stand column through bolts, cross beams which are uniformly and symmetrically distributed are respectively installed on the outer walls of two sides of the stand column through second assembly parts, curtain wall units are installed between the cross beams and the stand column, and the construction method of the glass curtain wall comprises the following steps: mounting the upright post on the building main body through a first assembly part; and the cross beams are equidistantly and symmetrically arranged on two sides of the upright post through a second assembly part. The curtain wall unit fixing device is provided with the fixing seat, the fixing piece and other structures, so that the curtain wall unit can be conveniently assembled, in addition, the fixing convex strips are arranged, on the basis of press fit and fixation, the fixing piece can be limited by the inner walls of the fixing grooves through the fixing convex strips, the fixing piece is prevented from rotating, and the structural firmness is effectively improved.

Description

Building glass curtain wall and construction method thereof
Technical Field
The invention relates to the technical field of glass curtain walls, in particular to a building glass curtain wall and a construction method thereof.
Background
The glass curtain wall is a building external protective structure or a decorative structure which has a certain displacement capacity relative to the main structure and does not bear the action of the main structure; in the assembly of glass curtain wall, often utilize the mounting of various differences to fix it, and partial mounting easily appears becoming flexible when using for a long time, leads to structural firmness not to obtain the guarantee, and has the risk of droing.
Through the retrieval, chinese patent application number is CN 201922389348.5's patent, discloses a glass curtain wall mounting structure, stand including a plurality of vertical settings, it is adjacent be provided with a plurality of crossbeams between the stand, the crossbeam sets up with the stand is perpendicular, and is adjacent be provided with cavity glass between the crossbeam, cavity glass passes through fixed subassembly and crossbeam fixed connection, one side that cavity glass kept away from the crossbeam is provided with the clamp plate, clamp plate and cavity glass laminating, clamp plate and crossbeam pass through spliced pole fixed connection, one side and crossbeam fixed connection, opposite side and clamp plate fixed connection of spliced pole, cavity glass sets up between clamp plate and crossbeam, it is sealed through sealed glue between clamp plate and the cavity glass, be provided with the heat insulating strip between crossbeam and the cavity glass. The glass curtain wall mounting structure in the patent has the following defects: although certain construction requirements are met, the structural firmness is poor.
Disclosure of Invention
The invention aims to solve the defects in the prior art and provides a building glass curtain wall and a construction method thereof.
In order to achieve the purpose, the invention adopts the following technical scheme:
a building glass curtain wall comprises a stand column, wherein first assembly parts for installing the stand column are fixed on the outer walls of two sides of the stand column through bolts, cross beams which are uniformly and symmetrically distributed are installed on the outer walls of two sides of the stand column through second assembly parts respectively, and curtain wall units are installed between the cross beams and the stand column; the curtain wall unit comprises a first glass plate, a second glass plate and a third glass plate, a connecting strip is bonded between the first glass plate and the third glass plate, the second glass plate is bonded on the inner wall of the connecting strip, a fixed groove and a filling layer for filling the fixed groove are arranged between the first glass plate and the third glass plate, the fixed groove, the filling layer and the connecting strip are all arranged along the edges of the first glass plate and the third glass plate, a fixed rail is integrally arranged on the outer wall of one side of the upright column and the cross beam close to the first glass plate, a fixed seat is installed in the fixed rail, a fixed screw is connected to the inner wall of one side of the fixed seat through threads, two limiting rings are integrally arranged on the circumferential outer wall of the fixed screw, the same fixing piece is rotatably connected between the two limiting rings, and fixing convex strips extending towards the first glass plate are integrally arranged at the two ends of the fixing piece, the fixing piece is clamped in the fixing groove through the fixing convex strip.
Preferably: the fixed rails of the stand column and the cross beam are internally provided with the same cross connecting piece, and the cross connecting pieces are fixed on the outer wall of one side of the stand column through reinforcing screws.
Further: all install the connecting seat on the fixed rail of stand and crossbeam, connecting seat one side joint has outer sealing strip, the size adaptation of interval between outer sealing strip and stand and crossbeam and two adjacent curtain units, it has the glue film to fill between outer sealing strip one side outer wall and the curtain unit.
Further preferred is: draw-in groove has all been seted up to fixed rail both sides inner wall, one side outer wall homogeneous style that fixing base, cross connecting piece and connecting seat are close to the fixed rail is provided with two elasticity cardboards, two elasticity cardboard size and the interval adaptation of fixed rail, and elasticity cardboard one end lateral wall integral type be provided with the reinforcement arch of draw-in groove adaptation, the elasticity cardboard is respectively through consolidating protruding joint in the draw-in groove of fixed rail.
As a preferable aspect of the present invention: two adhesive tape mounting rails are integrally arranged on the outer wall of one side of each of the upright column and the cross beam, and the adhesive tape mounting rails are of two parallel T-shaped structures; the vertical adhesive tape and the horizontal adhesive tape are respectively clamped in the adhesive tape mounting rails of the stand column and the cross beam, and the vertical adhesive tape and the horizontal adhesive tape are in elastic deformation contact with the outer wall of one side of the first glass plate.
Further preferred as the invention: and the vertical adhesive tape and the horizontal adhesive tape are both provided with a shape variable cavity.
As a still further scheme of the invention: the rubber strip mounting rail on the cross beam is internally and uniformly clamped with a hollow rubber column, and the hollow rubber column is elastically deformed and contacted with the outer wall of one end of the transverse rubber strip and the outer wall of one side of the vertical rubber strip.
On the basis of the scheme: reinforcing ribs are uniformly arranged inside the upright posts and the cross beams and are of honeycomb structures.
A construction method of a building glass curtain wall comprises the following steps:
s1: mounting the upright post on the building main body through a first assembly part;
s2: the cross beams are equidistantly and symmetrically arranged on two sides of the upright post through a second assembly part;
s3: clamping the reinforcing bulges of the cross connecting piece in clamping grooves arranged on the upright post and the cross beam, and fixing the reinforcing bulges through reinforcing screws;
s4: a vertical adhesive tape, a hollow adhesive column and a transverse adhesive tape are sequentially arranged in the adhesive tape mounting rails of the upright column and the transverse beam;
s5: mounting the four connecting seats and the fixed seats on the fixed rails of the upright posts and the cross beam respectively to enable the angles of the fixed parts and the fixed seats to be consistent;
s6: buckling two adjacent curtain wall units on vertical adhesive tapes and horizontal adhesive tapes of the stand columns and the cross beams, and rotating the fixing piece to enable the two fixing convex strips to be transferred into fixing grooves of the two curtain wall units;
s7: fixing the fixing piece with the fixing groove of the curtain wall unit by screwing the fixing screw;
s8: the outer sealing strips are flatly arranged on the fixed seat, so that no large gap is formed among the curtain wall unit, the stand column and the cross beam;
s9: coating a glue layer on the surface of the outer layer sealing strip, and filling the glue layer in the gap between every two adjacent third glass plates;
s10: and repeating the actions until the construction is completed.
The invention has the beneficial effects that:
1. the curtain wall unit assembling device is provided with the fixing seat, the fixing piece and other structures, so that the curtain wall unit can be conveniently assembled, in addition, the fixing convex strips are arranged, on the basis of press fit and fixation, the fixing piece can be limited by the inner walls of the fixing grooves through the fixing convex strips, the fixing piece is prevented from rotating, the structural firmness is effectively improved, the construction safety is ensured, in addition, the three-layer glass structure is adopted, the connecting strips and the filling layer are arranged, the sealing performance is improved, the heat insulation effect is enhanced, and the reliability is improved.
2. Through setting up the cross connecting piece, can further strengthen the firmness between stand and the crossbeam, and ensured the regularity of assembly, avoid taking place the phenomenon of skew each other, through setting up outer sealing strip and glue film, strengthened the sealing performance between each curtain unit, ensured holistic pleasing to the eye degree again simultaneously.
3. Through setting up elasticity cardboard and reinforcement arch, further strengthened the firmness of being connected between each structure and stand and the crossbeam, it is simple convenient to assemble, has promoted reliability and practicality simultaneously.
4. The vertical adhesive tape and the horizontal adhesive tape are arranged, so that the sealing performance of the connection among the first glass plate, the stand column and the cross beam is enhanced, the heat insulation capability is improved, and a certain shock absorption effect is achieved; through setting up the deformation chamber, can promote the deformability of horizontal adhesive tape to sealing performance has further been promoted.
5. By arranging the hollow rubber columns, the phenomenon that a gap exists between the transverse rubber strip and the vertical rubber strip due to the difference of the lengths of the transverse rubber strips can be avoided, and the installation firmness of the transverse rubber strips is effectively guaranteed; through the reinforcing rib that sets up honeycomb structure, effectively promoted the resistance to compression and the shock resistance of stand and crossbeam, promoted the security performance.
Drawings
FIG. 1 is a schematic view of a structure of a partial back surface of a glass curtain wall of a building according to the present invention;
FIG. 2 is a schematic structural view of a partial front surface of a building glass curtain wall according to the present invention;
FIG. 3 is a schematic structural view of a column and a beam of the architectural glass curtain wall according to the present invention;
FIG. 4 is a schematic view of the assembly structure of the architectural glass curtain wall fixing member and the curtain wall unit according to the present invention;
FIG. 5 is a cross-sectional structural view of a cross-shaped connector for a glass curtain wall of a building according to the present invention;
FIG. 6 is a schematic structural view of a hollow rubber column of a building glass curtain wall according to the present invention;
fig. 7 is a schematic sectional structural view of a fixing member for a glass curtain wall of a building according to the present invention.
In the figure: 1 stand, 2 crossbeams, 3 curtain wall unit, 4 first assembly parts, 5 second assembly parts, 6 reinforcing screws, 7 glue layers, 8 vertical adhesive tapes, 9 horizontal adhesive tapes, 10 cross connecting pieces, 11 connecting seats, 12 fixing pieces, 13 fixing seats, 14 deformation cavities, 15 adhesive tape mounting rails, 16 elastic clamping plates, 17 reinforcing protrusions, 18 reinforcing ribs, 19 fixing rails, 20 first glass plates, 21 second glass plates, 22 third glass plates, 23 connecting strips, 24 filling layers, 25 fixing grooves, 26 fixing screws, 27 outer-layer sealing strips, 28 fixing protruding strips, 29 hollow adhesive columns, 30 clamping grooves and 31 limiting rings.
Detailed Description
The technical solution of the present patent will be described in further detail with reference to the following embodiments.
Reference will now be made in detail to embodiments of the present patent, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are exemplary only for the purpose of explaining the present patent and are not to be construed as limiting the present patent.
In the description of this patent, it is to be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in the orientations and positional relationships indicated in the drawings for the convenience of describing the patent and for the simplicity of description, and are not intended to indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the patent.
In the description of this patent, it is noted that unless otherwise specifically stated or limited, the terms "mounted," "connected," and "disposed" are to be construed broadly and can include, for example, fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed. The specific meaning of the above terms in this patent may be understood by those of ordinary skill in the art as appropriate.
Example 1:
a building glass curtain wall is shown in figures 1-7 and comprises a vertical column 1, wherein first assembly parts 4 for mounting the vertical column 1 are fixed on the outer walls of two sides of the vertical column 1 through bolts, cross beams 2 which are uniformly and symmetrically distributed are mounted on the outer walls of two sides of the vertical column 1 through second assembly parts 5 respectively, and curtain wall units 3 are mounted between the cross beams 2 and the vertical column 1; the curtain wall unit 3 comprises a first glass plate 20, a second glass plate 21 and a third glass plate 22, a connecting strip 23 is bonded between the first glass plate 20 and the third glass plate 22, the second glass plate 21 is bonded on the inner wall of the connecting strip 23, a fixing groove 25 and a filling layer 24 for filling the fixing groove 25 are arranged between the first glass plate 20 and the third glass plate 22, the fixing groove 25, the filling layer 24 and the connecting strip 23 are all arranged along the edges of the first glass plate 20 and the third glass plate 22, a fixing rail 19 is integrally arranged on the outer wall of one side of the upright post 1 and the outer wall of one side of the cross beam 2 close to the first glass plate 20, a fixing seat 13 is arranged in the fixing rail 19, a fixing screw 26 is connected on the inner wall of one side of the fixing seat 13 through a thread, two limiting rings 31 are integrally arranged on the outer wall of the circumference of the fixing screw 26, and the same fixing part 12 is rotatably connected between the two limiting rings 31, the two ends of the fixing piece 12 are integrally provided with fixing convex strips 28 extending towards the first glass plate 20, and the fixing piece 12 is clamped in the fixing grooves 25 through the fixing convex strips 28; through setting up fixing base 13, mounting 12 isotructure, can be convenient assemble curtain unit 3, furthermore, owing to set up fixed sand grip 28, on the fixed basis of pressfitting, make the inner wall of fixed slot 25 can carry on spacingly through fixed sand grip 28 to mounting 12, avoid it to take place to rotate, the firmness of structure has effectively been promoted, construction safety has been ensured, furthermore, adopt three-layer glass structure, set up connecting strip 23 and filling layer 24 again and promote sealing performance, the temperature effect that separates has been strengthened, the reliability has been promoted.
In order to enhance structural firmness; as shown in fig. 3-6, the same cross connecting piece 10 is installed in the fixing rails 19 of the upright post 1 and the cross beam 2, and the cross connecting piece 10 is fixed on the outer wall of one side of the upright post 1 through a reinforcing screw 6; through setting up cross connecting piece 10, can further strengthen the firmness between stand 1 and the crossbeam 2, and ensured the regularity of assembly, avoid taking place the phenomenon of mutual skew.
In order to enhance the sealing performance; as shown in fig. 4 and 5, all install connecting seat 11 on the fixed rail 19 of stand 1 and crossbeam 2, connecting seat 11 one side joint has outer sealing strip 27, the size adaptation of interval between outer sealing strip 27 and stand 1 and crossbeam 2 and two adjacent curtain unit 3, it has glue film 7 to fill between outer sealing strip 27 one side outer wall and the curtain unit 3, through setting up outer sealing strip 27 and glue film 7, has strengthened the sealing performance between each curtain unit 3, has ensured holistic pleasing to the eye degree again simultaneously.
To further enhance structural integrity; as shown in fig. 4-7, the inner walls of both sides of the fixed rail 19 are provided with a clamping groove 30, the outer walls of one side of the fixed seat 13, the cross-shaped connector 10 and the connecting seat 11, which is close to the fixed rail 19, are provided with two elastic clamping plates 16 in an integrated manner, the size of the two elastic clamping plates 16 is adapted to the distance between the fixed rail 19, the side wall of one end of each elastic clamping plate 16 is provided with a reinforcing protrusion 17 adapted to the clamping groove 30 in an integrated manner, and the elastic clamping plates 16 are clamped in the clamping grooves 30 of the fixed rail 19 through the reinforcing protrusions 17; through setting up elasticity cardboard 16 and reinforcement protrusion 17, further strengthened the firmness of being connected between each structure and stand 1 and crossbeam 2, it is simple convenient to assemble, has promoted reliability and practicality simultaneously.
In order to improve the sealing performance; as shown in fig. 3 and 6, two rubber strip mounting rails 15 are integrally arranged on the outer walls of one sides of the upright post 1 and the cross beam 2, and the rubber strip mounting rails 15 are of two parallel T-shaped structures; a vertical adhesive tape 8 and a horizontal adhesive tape 9 are respectively clamped in the adhesive tape mounting rails 15 of the upright column 1 and the cross beam 2, and the vertical adhesive tape 8 and the horizontal adhesive tape 9 are elastically deformed and contacted with the outer wall of one side of the first glass plate 20; through setting up vertical adhesive tape 8 and horizontal adhesive tape 9, strengthened the sealing performance of being connected between first glass board 20 and stand 1 and the crossbeam 2 to promote and separate the temperature ability, and played certain shock attenuation effect.
In order to further improve the sealing performance; as shown in fig. 4, the vertical rubber strip 8 and the horizontal rubber strip 9 are both provided with a deformation cavity 14, and the deformation capacity of the horizontal rubber strip 9 can be improved by arranging the deformation cavity 14, so that the sealing performance is further improved.
In order to improve the installation firmness of the transverse rubber strip 9; as shown in fig. 6, hollow rubber columns 29 are clamped in the rubber strip mounting rails 15 on the cross beam 2, and the hollow rubber columns 29 are in elastic deformation contact with the outer wall of one end of the transverse rubber strip 9 and the outer wall of one side of the vertical rubber strip 8; through setting up hollow gluey post 29, can avoid horizontal adhesive tape 9 length difference and make and have the hole between horizontal adhesive tape 9 and the perpendicular adhesive tape 8, effectively ensured the firmness of horizontal adhesive tape 9 installation.
To further enhance structural integrity; as shown in fig. 1 and 4, reinforcing ribs 18 are uniformly arranged inside the upright column 1 and the cross beam 2, the reinforcing ribs 18 are in a honeycomb structure, and by arranging the reinforcing ribs 18 in the honeycomb structure, the compression resistance and the impact resistance of the upright column 1 and the cross beam 2 are effectively improved, and the safety performance is improved.
Example 2:
a construction method of a building glass curtain wall comprises the following steps:
s1: the upright post 1 is arranged on a building main body through a first assembly part 4;
s2: the cross beam 2 is equidistantly and symmetrically arranged on two sides of the upright post 1 through a second assembly part 5;
s3: clamping the reinforcing protrusions 17 of the cross connecting piece 10 in clamping grooves 30 arranged on the upright post 1 and the cross beam 2, and fixing the reinforcing protrusions through reinforcing screws 6;
s4: a vertical adhesive tape 8, a hollow adhesive column 29 and a transverse adhesive tape 9 are sequentially arranged in the adhesive tape mounting rails 15 of the upright column 1 and the cross beam 2;
s5: the four connecting seats 11 and the fixed seats 13 are respectively arranged on the fixed rails 19 of the upright post 1 and the cross beam 2, so that the angles of the fixed parts 12 and the fixed seats 13 are consistent;
s6: buckling two curtain wall units 3 on vertical adhesive tapes 8 and transverse adhesive tapes 9 of the upright posts 1 and the cross beams 2 adjacently, and rotating the fixing pieces 12 to enable the two fixing convex strips 28 to be transferred into fixing grooves 25 of the two curtain wall units 3;
s7: the fixing piece 12 is fixed with the fixing groove 25 of the curtain wall unit 3 by screwing the fixing screw 26;
s8: the outer layer sealing strips 27 are flatly arranged on the fixed seat 13, so that no large gap is formed between the curtain wall unit 3 and the upright posts 1 and the cross beams 2;
s9: coating the glue layer 7 on the surface of the outer layer sealing strip 27, and enabling the glue layer 7 to fill the gap between every two adjacent third glass plates 22;
s10: and repeating the actions until the construction is completed.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (9)

1. The building glass curtain wall comprises a stand column (1), and is characterized in that first assembly parts (4) for installing the stand column (1) are fixed on the outer walls of two sides of the stand column (1) through bolts, cross beams (2) which are uniformly and symmetrically distributed are respectively installed on the outer walls of two sides of the stand column (1) through second assembly parts (5), and curtain wall units (3) are installed between the cross beams (2) and the stand column (1); the curtain wall unit (3) comprises a first glass plate (20), a second glass plate (21) and a third glass plate (22), a connecting strip (23) is bonded between the first glass plate (20) and the third glass plate (22), the second glass plate (21) is bonded on the inner wall of the connecting strip (23), a fixing groove (25) and a filling layer (24) used for filling the fixing groove (25) are arranged between the first glass plate (20) and the third glass plate (22), the fixing groove (25), the filling layer (24) and the connecting strip (23) are all arranged along the edges of the first glass plate (20) and the third glass plate (22), a fixing rail (19) is uniformly arranged on the outer wall of one side, close to the first glass plate (20), of the upright column (1) and the cross beam (2), a fixing seat (13) is installed in the fixing rail (19), and a fixing screw (26) is connected on the inner wall of one side of the fixing seat (13) through a screw thread, fixed screw (26) circumference outer wall integral type is provided with two spacing rings (31), and rotates between two spacing rings (31) and be connected with same mounting (12), mounting (12) both ends integral type is provided with fixed sand grip (28) that extend to first glass board (20), mounting (12) are through fixed sand grip (28) joint in fixed slot (25).
2. The architectural glass curtain wall according to claim 1, wherein the same cross connecting piece (10) is mounted in the fixing rails (19) of the vertical columns (1) and the transverse beams (2), and the cross connecting piece (10) is fixed on the outer wall of one side of the vertical column (1) through the reinforcing screw (6).
3. The building glass curtain wall according to claim 2, wherein the fixing rails (19) of the upright posts (1) and the cross beams (2) are respectively provided with a connecting seat (11), one side of each connecting seat (11) is connected with an outer sealing strip (27) in a clamping manner, the outer sealing strips (27) are matched with the upright posts (1), the cross beams (2) and two adjacent curtain wall units (3) in the size of the space, and glue layers (7) are filled between the outer wall of one side of each outer sealing strip (27) and each curtain wall unit (3).
4. The architectural glass curtain wall according to claim 3, wherein the inner walls of two sides of the fixed rail (19) are provided with clamping grooves (30), the outer wall of one side of the fixed seat (13), the cross-shaped connecting piece (10) and the connecting seat (11) close to the fixed rail (19) is integrally provided with two elastic clamping plates (16), the size of the two elastic clamping plates (16) is matched with the distance of the fixed rail (19), the side wall of one end of each elastic clamping plate (16) is integrally provided with a reinforcing protrusion (17) matched with the clamping grooves (30), and the elastic clamping plates (16) are respectively clamped in the clamping grooves (30) of the fixed rail (19) through the reinforcing protrusions (17).
5. The building glass curtain wall as claimed in claim 4, wherein two rubber strip mounting rails (15) are integrally arranged on the outer wall of one side of each of the upright post (1) and the cross beam (2), and the rubber strip mounting rails (15) are of two parallel T-shaped structures; the vertical adhesive tape (8) and the horizontal adhesive tape (9) are respectively clamped in the adhesive tape mounting rails (15) of the upright column (1) and the cross beam (2), and the vertical adhesive tape (8) and the horizontal adhesive tape (9) are in elastic deformation contact with the outer wall of one side of the first glass plate (20).
6. The building glass curtain wall as claimed in claim 5, wherein the vertical adhesive strips (8) and the transverse adhesive strips (9) are provided with a variable cavity (14) inside.
7. The building glass curtain wall as claimed in claim 6, wherein hollow rubber columns (29) are clamped in the rubber strip mounting rails (15) on the cross beams (2), and the hollow rubber columns (29) are in elastic deformation contact with the outer wall of one end of the transverse rubber strip (9) and the outer wall of one side of the vertical rubber strip (8).
8. The architectural glass curtain wall according to claim 7, wherein the uprights (1) and the cross-members (2) are internally provided with stiffening ribs (18) in a uniform manner, the stiffening ribs (18) having a honeycomb structure.
9. A method for constructing an architectural glass curtain wall according to any one of claims 1 to 8, comprising the steps of:
s1: the upright post (1) is arranged on a building main body through a first assembly part (4);
s2: the cross beam (2) is equidistantly and symmetrically arranged on two sides of the upright post (1) through a second assembly part (5);
s3: clamping reinforcing protrusions (17) of the cross connecting piece (10) in clamping grooves (30) arranged on the upright post (1) and the cross beam (2) and fixing the reinforcing protrusions through reinforcing screws (6);
s4: a vertical adhesive tape (8), a hollow adhesive column (29) and a transverse adhesive tape (9) are sequentially arranged in the adhesive tape mounting rails (15) of the upright column (1) and the cross beam (2);
s5: the four connecting seats (11) and the fixed seats (13) are respectively arranged on the fixed rails (19) of the upright post (1) and the cross beam (2), so that the angles of the fixed piece (12) and the fixed seats (13) are consistent;
s6: buckling two curtain wall units (3) on vertical adhesive tapes (8) and transverse adhesive tapes (9) of the upright columns (1) and the cross beams (2) adjacently, and rotating the fixing piece (12) to enable the two fixing convex strips (28) to be transferred into fixing grooves (25) of the two curtain wall units (3);
s7: the fixing piece (12) is fixed with a fixing groove (25) of the curtain wall unit (3) by screwing a fixing screw (26);
s8: the outer layer sealing strips (27) are flatly arranged on the fixed seat (13), so that no large gap is formed among the curtain wall unit (3), the upright post (1) and the cross beam (2);
s9: coating an adhesive layer (7) on the surface of the outer layer sealing strip (27), and enabling the adhesive layer (7) to fill the gap between every two adjacent third glass plates (22);
s10: and repeating the actions until the construction is completed.
CN202011462232.0A 2020-12-14 2020-12-14 Building glass curtain wall and construction method thereof Active CN112411839B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011462232.0A CN112411839B (en) 2020-12-14 2020-12-14 Building glass curtain wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011462232.0A CN112411839B (en) 2020-12-14 2020-12-14 Building glass curtain wall and construction method thereof

Publications (2)

Publication Number Publication Date
CN112411839A CN112411839A (en) 2021-02-26
CN112411839B true CN112411839B (en) 2021-07-30

Family

ID=74776131

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011462232.0A Active CN112411839B (en) 2020-12-14 2020-12-14 Building glass curtain wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN112411839B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293784A (en) * 2022-01-18 2022-04-08 浙江经典建筑装饰有限公司 Construction auxiliary installation device and construction method thereof
CN115961790A (en) * 2022-12-29 2023-04-14 北京城建集团有限责任公司 Installation method of glass curtain wall for building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4031680A (en) * 1974-05-29 1977-06-28 Richard Lewis Stoakes Structural assemblies
CN101994357A (en) * 2010-12-09 2011-03-30 华东建筑设计研究院有限公司 Metal laminated composite glass
CN202047507U (en) * 2010-12-09 2011-11-23 华东建筑设计研究院有限公司 Composite glass with metal interlayer
CN204662735U (en) * 2015-06-08 2015-09-23 广东高登铝业有限公司 A kind of column of curtain wall and beam connecting structure
CN207436336U (en) * 2017-11-13 2018-06-01 青岛被动房环境科技有限公司 A kind of two chamber curtain wall of energy saving building aluminium Bao Musan glass
CN210421562U (en) * 2019-08-05 2020-04-28 无锡革新幕墙装饰工程有限公司 Hidden frame curtain wall structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4031680A (en) * 1974-05-29 1977-06-28 Richard Lewis Stoakes Structural assemblies
CN101994357A (en) * 2010-12-09 2011-03-30 华东建筑设计研究院有限公司 Metal laminated composite glass
CN202047507U (en) * 2010-12-09 2011-11-23 华东建筑设计研究院有限公司 Composite glass with metal interlayer
CN204662735U (en) * 2015-06-08 2015-09-23 广东高登铝业有限公司 A kind of column of curtain wall and beam connecting structure
CN207436336U (en) * 2017-11-13 2018-06-01 青岛被动房环境科技有限公司 A kind of two chamber curtain wall of energy saving building aluminium Bao Musan glass
CN210421562U (en) * 2019-08-05 2020-04-28 无锡革新幕墙装饰工程有限公司 Hidden frame curtain wall structure

Also Published As

Publication number Publication date
CN112411839A (en) 2021-02-26

Similar Documents

Publication Publication Date Title
CN112411839B (en) Building glass curtain wall and construction method thereof
CN112554385A (en) Internal corner structure of toilet
CN217517828U (en) Passive assembly type building outer wall
CN211646795U (en) Transition type external wall insulation board
CN213089434U (en) Bridge-cut-off aluminum profile capable of effectively insulating heat
CN211312941U (en) Quick assembly structure of prefabricated building
CN212053447U (en) Assembled foamed ceramic partition wall
CN211499580U (en) Decorative board with effect gives sound insulation
CN114045964A (en) Large-span broken line cell cube curtain system
CN215368088U (en) Curtain wall aluminum-plastic panel convenient to mount
CN217840500U (en) Quick firm mounting structure of glass curtain wall
CN218814506U (en) Radiation-proof wallboard connecting structure
CN218265637U (en) Glass fiber-free perlite fireproof door core plate
CN216238965U (en) Green building steel construction of unit-installment
TWI811180B (en) Reinforced lightweight fire brick wall structure
CN215888728U (en) External corner structure of toilet
CN215291080U (en) PVC revetment of conveniently assembling
CN214364173U (en) Composite heat-insulation board for external wall
CN215106252U (en) Enclosing structure additionally provided with two sides of hoistway door surface of elevator glass curtain wall
CN217000474U (en) Colored doubling glass of antidetonation
CN216267918U (en) Honeycomb foam composite board
CN215660777U (en) Sound insulation plywood with anti-deformation function
CN218933684U (en) Assembled external wall panel
CN215888693U (en) Bathroom shingle assembly
CN214461398U (en) Section bar, combined wall and water treatment plant

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A building glass curtain wall and its construction method

Effective date of registration: 20220629

Granted publication date: 20210730

Pledgee: Jinhua Bank Co.,Ltd. Yongkang sub branch

Pledgor: Zhejiang classic building decoration Co.,Ltd.

Registration number: Y2022330001097

CP03 Change of name, title or address

Address after: 321300 16th Floor, Jindian Building, Dongcheng Street Headquarters Center, Yongkang City, Jinhua City, Zhejiang Province

Patentee after: Zhejiang Classic Construction Co.,Ltd.

Address before: 321300 No.136, 138, Lizhou North Road, Dongcheng Street, Yongkang City, Jinhua City, Zhejiang Province

Patentee before: Zhejiang classic building decoration Co.,Ltd.

CP03 Change of name, title or address
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230612

Granted publication date: 20210730

Pledgee: Jinhua Bank Co.,Ltd. Yongkang sub branch

Pledgor: Zhejiang classic building decoration Co.,Ltd.

Registration number: Y2022330001097

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A Kind of Architectural Glass Curtain Wall and Its Construction Method

Effective date of registration: 20230728

Granted publication date: 20210730

Pledgee: Jinhua Bank Co.,Ltd. Yongkang sub branch

Pledgor: Zhejiang Classic Construction Co.,Ltd.

Registration number: Y2023980050171

PE01 Entry into force of the registration of the contract for pledge of patent right