Prior art keywords
design
bim
change
cloud platform
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011416562.6A
Other languages
Chinese (zh)
Inventor
唐小卫
陈州
孙伟
崔小波
王涛
陈萌
龚凯威
梅从剑
夏夕虹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shengwei Technology Co ltd
Original Assignee
Shengwei Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shengwei Technology Co ltd filed Critical Shengwei Technology Co ltd
Priority to CN202011416562.6A priority Critical patent/CN112381529A/en
Publication of CN112381529A publication Critical patent/CN112381529A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Computer Hardware Design (AREA)
  • Human Resources & Organizations (AREA)
  • Evolutionary Computation (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Civil Engineering (AREA)
  • Data Mining & Analysis (AREA)
  • Pure & Applied Mathematics (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention is suitable for the technical field of computers, and provides a deep design process diagram generation method based on BIM; the application and the cloud platform comprise the following processing flows: the cloud platform receives the input of process data to form a process library; receiving a design task of a building project, designing a concept scheme according to the design task, and dividing the scheme into a plurality of module tasks; distributing a plurality of module tasks to designers with authority to design the scheme in detail, and after the design is finished, adding the cloud platform into the BIM design drawing according to the process in the process library to generate a process drawing; when the change design is carried out, a change designer carries out the change design to generate a new BIM design drawing of a relevant module, and relevant processes in a process library are added into the BIM design drawing of the module to generate a change process drawing; and receiving a change application sent by a designer, logging in a cloud platform by each participant to obtain the latest change process diagram, and sending a receipt confirmation notice to other participants.

Description

BIM-based deep design process diagram generation method
Technical Field
The invention relates to the technical field of computers, in particular to a BIM-based method for generating a deep design process diagram.
Background
The BIM technology is a datamation tool applied to engineering design and construction management, integrates related information of various projects through a parameter model, and shares and transmits the related information in the whole life cycle process of project planning, operation and maintenance, so that engineering technicians can correctly understand and efficiently respond to various building information, a foundation for cooperative work is provided for design teams and all building main bodies including building operation units, and the data processing method plays an important role in improving production efficiency, saving cost and shortening construction period.
Because a plurality of participants, such as a first party, a design house, a construction party, a manufacturing party and the like, are involved in a construction project, if the project is changed in the construction process, the change is usually transmitted through paper files in the prior art, and the change is lost frequently, so that the whole construction period is affected, a deepened design process diagram generation method based on BIM is provided to solve the technical problem.
Disclosure of Invention
The invention aims to provide a method for generating a deepened design process diagram based on BIM, so as to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme:
a method for generating a deepened design process diagram based on BIM, which is applied to a cloud platform, comprises the following processing flows: the cloud platform receives the input of process data to form a process library;
receiving a design task of a building project, designing a concept scheme according to the design task, and dividing the scheme into a plurality of module tasks;
distributing a plurality of module tasks to designers with authority to design the scheme in detail, and after the design is finished, adding the cloud platform into the BIM design drawing according to the process in the process library to generate a process drawing;
when the change design is carried out, a change designer carries out the change design to generate a new BIM design drawing of a relevant module, and relevant processes in a process library are added into the BIM design drawing of the module to generate a change process drawing;
receiving a change application sent by a designer, authorizing the change application, sending the change process drawing completed by the designer to each participant after authorization, logging in a cloud platform by each participant to obtain the latest change process drawing, and sending a receipt confirmation notice to other participants.
As a further scheme of the invention: and when the cloud platform sends the changed process drawings to each party, the cloud platform sends a change reminding signal to each party.
As a still further scheme of the invention: the process library comprises a standard process library and a non-standard process library.
As a still further scheme of the invention: the cloud platform account has accounts with different levels of authority, wherein the designer has design and change authority, and other participants have authority of receiving the drawing and authority of feeding back the received drawing.
As a still further scheme of the invention: the specific design comprises the following procedures:
distributing the plurality of module tasks to designers with authority, designing the scheme by the designers, generating a sub BIM design drawing, and sending the sub BIM design drawing to a cloud platform;
merging the sub BIM design drawings according to the identification information of each module to generate a BIM design drawing of the building project;
and adding the process to the BIM design drawing according to the process in the process library to generate a process drawing.
As a still further scheme of the invention: the cloud platform comprises a cloud server and an operation terminal, and the cloud server is in communication connection with the operation terminal;
the operation terminal is used for a designer and other participants to carry out login operation;
the cloud server is used for receiving design tasks of the building project, designing a preliminary scheme according to the design tasks, and dividing the preliminary scheme into a plurality of module tasks; distributing a plurality of module tasks to designers with authority, designing a scheme by the designers to generate a sub BIM design drawing, sending the sub BIM design drawing to a cloud platform, merging the sub BIM design drawings according to identification information of each module to generate a BIM design drawing of a building project, and adding the BIM design drawing into the BIM design drawing according to a process in a process library to generate a process drawing; when the change design is carried out, a change designer carries out the change design, generates a BIM design drawing of the changed relevant module, and adds the relevant process in the process library to the BIM design drawing of the module to generate a change process drawing; and the designer sends a change notice to the project participants, and each project party logs in the cloud platform to obtain the latest change process diagram and sends a confirmation notice to each party.
As a still further scheme of the invention: the cloud server comprises a concept unit, a design unit, a process unit, a change unit and a reminding confirmation unit; the concept unit, the design unit, the process unit and the change unit are in communication connection with each other;
the concept unit is used for receiving design tasks of the building project, designing a preliminary scheme according to the design tasks, and dividing the preliminary scheme into a plurality of module tasks;
the design unit is used for distributing a plurality of module tasks to designers with authority to design the scheme in detail, and after the design is finished, the cloud platform is added into the BIM design drawing according to the process in the process library to generate a process drawing;
the process unit is used for receiving and establishing a process library and receiving process data;
the change unit is used for changing the design of designers, generating the BIM design drawing of the changed relevant module and adding the relevant process in the process unit into the BIM design drawing of the module to generate a changed process drawing;
and the reminding confirmation unit is used for sending a change notice to the project participants by designers, and all the project participants log in the cloud platform to obtain the latest change process diagram and send a receipt confirmation notice to all the project participants.
As a still further scheme of the invention: the design unit distributes a plurality of module tasks to designers with authority, the designers carry out scheme design to generate sub BIM design drawings, the sub BIM design drawings are sent to the cloud platform, the sub BIM design drawings are combined according to identification information of each module to generate building project BIM design drawings, and the building project BIM design drawings are added into the BIM design drawings according to the process in the process library to generate process drawings.
As a still further scheme of the invention: the number of the operation terminals is multiple.
Compared with the prior art, the invention has the beneficial effects that: by setting the process library, the process can be automatically generated, so that the processing processes at the same design position in the whole project are kept consistent, and the waste of materials caused by different materials used by different processing processes due to the fact that different versions are sent by a plurality of people in the same processing process in the prior art is avoided; after the change of the designer is completed, the designer sends the design information to each participant, and the participants confirm the design information after receiving the prompt, so that the design is convenient to convey to each participant, and the change loss is avoided. The invention saves the consistency of the construction process, saves the cost, ensures that the change can be accepted by all parties and avoids the loss of the change.
Drawings
FIG. 1 is a flow chart of a method for generating a deep design process diagram based on BIM.
FIG. 2 is a flow chart of specific design steps in a method for generating a BIM-based deepened design process diagram.
Fig. 3 is a schematic network structure diagram of a cloud platform in the method for generating the deep design process diagram based on the BIM.
Fig. 4 is a schematic structural diagram of a cloud platform in the method for generating the deepened design process diagram based on the BIM.
In the figure: the system comprises an operation terminal-1, a cloud server-2, a concept unit-21, a design unit-22, a process unit-23, a change unit-24 and a reminding confirmation unit-25.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
Referring to fig. 1-2, in embodiment 1 of the present invention, a flow chart of a method for generating a deepened design process diagram based on BIM according to an embodiment of the present invention is schematically shown, and the embodiment of the present invention may include the following contents:
s101: and the cloud platform receives the input of the process data to form a process library.
S102: the design task of the building project is received, a concept scheme is designed according to the design task, and the scheme is divided into a plurality of module tasks.
S103: and distributing the plurality of module tasks to designers with authority to design the scheme in detail, and after the design is finished, adding the cloud platform into the BIM design drawing according to the process in the process library to generate the process drawing.
S104: receiving a change application and a change process diagram sent by a designer, authorizing the change application, and sending the change process diagram completed by the designer to each participant after authorization.
S105: and each participant logs in the cloud platform to obtain the latest changed process diagram and sends a receipt confirmation notice to other participants.
When the cloud platform sends the change process diagram to each party, a change reminding signal is sent to each party, and the change reminding signal is a short message of a mobile phone or other short messages of WeChat. Therefore, the participating parties can accurately obtain the change reminding message.
Since the change notification issued by the designer can be executed only after being authorized, the designer can execute the change notification after being authorized by the owner.
Preferably, the process library in the embodiment of the present invention includes a standard process library and a non-standard process library; the non-standard process library is arranged to provide suitable processes according to building requirements.
The standard process library and the non-standard process library both comprise process identification information and a process step set, the standard process library is an existing standard and only can receive a standard process, and the non-standard process library can be edited and modified to meet the requirements.
And the BIM design drawing produced by setting a process library has a perfect process.
The cloud platform account has accounts with different levels of authority, wherein the designer has design and change authority, and other participants have authority of receiving the drawing and authority of feeding back the received drawing. This arrangement in turn ensures stable operation of the system.
Specifically, the process library is arranged, so that the process can be automatically generated, the processing processes at the same design position in the whole project are kept consistent, and the problem that in the prior art, different versions are sent out by a plurality of persons in the same processing process, and the materials are wasted due to the different materials used in different processing processes is avoided; after the change of the designer is completed, the designer sends the design information to each participant, and the participants confirm the design information after receiving the prompt, so that the design is convenient to convey to each participant, and the change loss is avoided. The invention saves the consistency of the construction process, saves the cost, ensures that the change can be accepted by all parties and avoids the loss of the change.
The specific design step of S103 described above;
s1031: distributing the plurality of module tasks to designers with authority, designing the scheme by the designers, generating a sub BIM design drawing, and sending the sub BIM design drawing to a cloud platform;
s1032: merging the sub BIM design drawings according to the identification information of each module to generate a BIM design drawing of the building project;
s1033: and adding the process to the BIM design drawing according to the process in the process library to generate a process drawing.
By dividing the project into a plurality of modules, a plurality of modules can be designed simultaneously, and the design progress is accelerated; time is saved.
Example 2
Referring to fig. 2 to 4, in embodiment 1 of the present invention, the cloud platform includes a cloud server 2 and an operation terminal 1, and the cloud server and the operation terminal 1 are in communication connection, and may be in wireless connection or in wired connection.
The operation terminal 1 is used for a designer and other participants to log in.
The cloud server 2 is used for receiving design tasks of the building project, designing a preliminary scheme according to the design tasks, and dividing the preliminary scheme into a plurality of module tasks; distributing a plurality of module tasks to designers with authority, designing a scheme by the designers to generate a sub BIM design drawing, sending the sub BIM design drawing to a cloud platform, merging the sub BIM design drawings according to identification information of each module to generate a BIM design drawing of a building project, and adding the BIM design drawing into the BIM design drawing according to a process in a process library to generate a process drawing; when the change design is carried out, a change designer carries out the change design, generates a BIM design drawing of the changed relevant module, and adds the relevant process in the process library to the BIM design drawing of the module to generate a change process drawing; and the designer sends a change notice to the project participants, and each project party logs in the cloud platform to obtain the latest change process diagram and sends a confirmation notice to each party.
The cloud server 2 comprises a concept unit 21, a design unit 22, a process unit 23, a change unit 24 and a reminding confirmation unit 25; the concept unit 21, the design unit 22, the process unit 23 and the change unit 24 are in communication connection with each other;
the concept unit 21 is configured to receive a design task of a building project, design a preliminary scheme according to the design task, and divide the preliminary scheme into a plurality of module tasks;
the design unit 22 distributes a plurality of module tasks to designers with authority, the designers carry out scheme design to generate sub BIM design drawings, the sub BIM design drawings are sent to the cloud platform, the sub BIM design drawings are combined according to identification information of each module to generate building project BIM design drawings, and the building project BIM design drawings are added into the BIM design drawings according to the process in the process library to generate process drawings;
the process unit 23 is used for receiving and establishing a process library and receiving process data; thereby ensuring the consistency of the construction process with the same design and saving materials.
A changing unit 24, configured to change the design of the designer, generate a modified BIM design drawing of the relevant module, and add the relevant process in the process unit 23 to the BIM design drawing of the module to generate a changed process drawing; the change electronization can be realized, and the phenomenon that the change is lost due to the fact that the change in the prior art is transmitted through the paper material is avoided.
And a reminding confirmation unit 25, wherein the designer sends a change notice to the project participants, and each project party logs in the cloud platform to obtain the latest change process diagram and sends a confirmation notice to each party. The arrangement further ensures that all the participants can receive the changed process diagram, and the change can be smoothly carried out.
The operation terminal 1 is a plurality of operation terminals which are convenient for different users to operate simultaneously.
It should be understood that, although the steps in the flowcharts of the embodiments of the present invention are shown in sequence as indicated by the arrows, the steps are not necessarily executed in sequence as indicated by the arrows. The steps are not performed in the exact order shown and described, and may be performed in other orders, unless explicitly stated otherwise. Moreover, at least a portion of the steps in various embodiments may include multiple sub-steps or multiple stages that are not necessarily performed at the same time, but may be performed at different times, and the order of performance of the sub-steps or stages is not necessarily sequential, but may be performed in turn or alternately with other steps or at least a portion of the sub-steps or stages of other steps.
The technical features of the embodiments described above may be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the embodiments described above are not described, but should be considered as being within the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
The above-mentioned embodiments only express several embodiments of the present invention, and the description thereof is more specific and detailed, but not construed as limiting the scope of the present invention. It should be noted that, for a person skilled in the art, several variations and modifications can be made without departing from the inventive concept, which falls within the scope of the present invention. Therefore, the protection scope of the present patent shall be subject to the appended claims.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (9)

1. A method for generating a deepened design process diagram based on BIM is applied to a cloud platform and is characterized by comprising the following processing flows: the cloud platform receives the input of process data to form a process library;
receiving a design task of a building project, designing a concept scheme according to the design task, and dividing the scheme into a plurality of module tasks;
distributing a plurality of module tasks to designers with authority to design the scheme in detail, and after the design is finished, adding the cloud platform into the BIM design drawing according to the process in the process library to generate a process drawing;
receiving a change application and a change process diagram sent by a designer, authorizing the change application, and sending the change process diagram completed by the designer to each participant after authorization;
and each participant logs in the cloud platform to obtain the latest changed process diagram and sends a receipt confirmation notice to other participants.
2. The BIM-based deepened design process diagram generation method of claim 1, wherein the cloud platform sends change reminding signals to all parties when sending the change process diagram to all parties.
3. The BIM-based deepened design process map generation method of claim 1, wherein the process library comprises a standard process library and a non-standard process library.
4. The BIM-based deepened design process diagram generation method of claim 2, wherein the cloud platform account has accounts with different levels of authority, wherein a designer has design and change authority, and other participants have authority to accept a drawing and authority to feedback that the drawing is received.
5. The BIM-based deepened design process diagram generation method of claim 1, wherein the concrete design comprises the following processes:
distributing the plurality of module tasks to designers with authority, designing the scheme by the designers, generating a sub BIM design drawing, and sending the sub BIM design drawing to a cloud platform;
merging the sub BIM design drawings according to the identification information of each module to generate a BIM design drawing of the building project;
and adding the process to the BIM design drawing according to the process in the process library to generate a process drawing.
6. The BIM-based deepened design process diagram generation method according to any one of claims 1 to 5, wherein the cloud platform comprises a cloud server and an operation terminal, and the cloud server is in communication connection with the operation terminal;
the operation terminal is used for a designer and other participants to carry out login operation;
the cloud server is used for receiving design tasks of the building project, designing a preliminary scheme according to the design tasks, and dividing the preliminary scheme into a plurality of module tasks; distributing a plurality of module tasks to designers with authority, designing a scheme by the designers to generate a sub BIM design drawing, sending the sub BIM design drawing to a cloud platform, merging the sub BIM design drawings according to identification information of each module to generate a BIM design drawing of a building project, and adding the BIM design drawing into the BIM design drawing according to a process in a process library to generate a process drawing; receiving a change application and a change process diagram sent by a designer, authorizing the change application, and sending the change process diagram completed by the designer to each participant after authorization; and each participant logs in the cloud platform to obtain the latest changed process diagram and sends a receipt confirmation notice to other participants.
7. The BIM-based deepened design process diagram generation method according to claim 6, wherein the cloud server comprises a concept unit, a design unit, a process unit, a change unit and a prompt confirmation unit; the concept unit, the design unit, the process unit and the change unit are in communication connection with each other;
the concept unit is used for receiving design tasks of the building project, designing a preliminary scheme according to the design tasks, and dividing the preliminary scheme into a plurality of module tasks;
the design unit is used for distributing a plurality of module tasks to designers with authority to design the scheme in detail, and after the design is finished, the cloud platform is added into the BIM design drawing according to the process in the process library to generate a process drawing;
the process unit is used for receiving and establishing a process library and receiving process data;
the change unit is used for receiving the change application and the change process diagram sent by the designer, authorizing the change application and sending the change process diagram completed by the designer to each participant after authorization; each participant logs in a cloud platform to obtain the latest changed process drawing;
and the reminding confirmation unit is used for sending a change notice to the project participants by designers, and all the project participants log in the cloud platform to obtain the latest change process diagram and send a receipt confirmation notice to all the project participants.
8. The BIM-based deepened design process diagram generation method of claim 7, wherein the design unit distributes a plurality of module tasks to designers with authority, the designers design schemes, generate sub BIM design diagrams, send the sub BIM design diagrams to the cloud platform, merge the sub BIM design diagrams according to identification information of each module to generate building project BIM design diagrams, and add the building project BIM design diagrams to the BIM design diagrams according to processes in a process library to generate process diagrams.
9. The BIM-based deepened design process map generation method of claim 6, wherein the number of the operation terminals is plural.
CN202011416562.6A 2020-12-04 2020-12-04 BIM-based deep design process diagram generation method Pending CN112381529A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011416562.6A CN112381529A (en) 2020-12-04 2020-12-04 BIM-based deep design process diagram generation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011416562.6A CN112381529A (en) 2020-12-04 2020-12-04 BIM-based deep design process diagram generation method

Publications (1)

Publication Number Publication Date
CN112381529A true CN112381529A (en) 2021-02-19

Family

ID=74590528

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011416562.6A Pending CN112381529A (en) 2020-12-04 2020-12-04 BIM-based deep design process diagram generation method

Country Status (1)

Country Link
CN (1) CN112381529A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113434946A (en) * 2021-07-05 2021-09-24 升维科技有限公司 Building model checking system and method based on BIM
CN117951102A (en) * 2024-03-26 2024-04-30 北京鸿鹄云图科技股份有限公司 Cloud-based engineering graphic information multi-platform real-time sharing method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107918831A (en) * 2017-11-23 2018-04-17 深圳拎得清软件有限公司 BIM Schedule managements method and its system based on browser
CN108269071A (en) * 2018-03-15 2018-07-10 叶枫 The method that buildings model is shared cloud platform and project management is carried out using platform
CN108427784A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 Assembled technological design data processing method based on BIM and device
CN108427802A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of Deepen Design technique drawing generating method and device based on BIM
CN111768091A (en) * 2020-06-22 2020-10-13 中国电建集团华东勘测设计研究院有限公司 BIM-based standard process library and establishment and application method and system thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108427784A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 Assembled technological design data processing method based on BIM and device
CN108427802A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of Deepen Design technique drawing generating method and device based on BIM
CN107918831A (en) * 2017-11-23 2018-04-17 深圳拎得清软件有限公司 BIM Schedule managements method and its system based on browser
CN108269071A (en) * 2018-03-15 2018-07-10 叶枫 The method that buildings model is shared cloud platform and project management is carried out using platform
CN111768091A (en) * 2020-06-22 2020-10-13 中国电建集团华东勘测设计研究院有限公司 BIM-based standard process library and establishment and application method and system thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113434946A (en) * 2021-07-05 2021-09-24 升维科技有限公司 Building model checking system and method based on BIM
CN113434946B (en) * 2021-07-05 2023-09-29 深圳比目鱼平方科技有限公司 Building model checking system and method based on BIM
CN117951102A (en) * 2024-03-26 2024-04-30 北京鸿鹄云图科技股份有限公司 Cloud-based engineering graphic information multi-platform real-time sharing method
CN117951102B (en) * 2024-03-26 2024-06-11 北京鸿鹄云图科技股份有限公司 Cloud-based engineering graphic information multi-platform real-time sharing method

Similar Documents

Publication Publication Date Title
CN109165944B (en) Multi-party signature authentication method, device, equipment and storage medium based on block chain
CN112381529A (en) BIM-based deep design process diagram generation method
CN105357223A (en) Three dimensional cooperation conference system based on instant messaging protocol and realization method thereof
CN111245886B (en) Multi-party collaboration system, method and storage medium based on block chain
CN112053041B (en) Province-region integrated source network load storage real-time control system and control method
CN107908680A (en) Management method, electronic device and the computer-readable recording medium of wechat public platform
CN111340340B (en) Event processing method and device
CN204204022U (en) A kind of live supervisory system based on operation of power networks state
CN114024927B (en) Information sharing method and device
CN109299333B (en) Block chain network account book member management method, device, equipment and storage medium
CN101471803B (en) Conference service system and method
CN111563727A (en) Method and system for multi-person online collaborative editing of 3D house type data
CN114389933A (en) Platform alliance treatment system and method
CN104753756A (en) Group creating and group sharing methods, devices and systems
CN104835004A (en) Guest room information management method and system
CN202421839U (en) Monitoring center for engineering machinery remote monitoring system
CN113706106A (en) Government affair cooperation system constructed based on block chain
CN108629557A (en) Business witnesses method, apparatus, computer equipment and storage medium
CN1905702B (en) Method, system and apparatus for implementing short message group sending
CN102291686B (en) Emergency short message group sending method and system, centralized control center and short message group sender
CN115564382A (en) Patent management system and method
CN112001611A (en) Infrastructure task tracking system
CN112381528B (en) Method for real-time data interaction in production process
CN101340646A (en) Cluster communication system and method for a scheduler to participate in multiple callings
CN112968824A (en) Chat group establishing method and system with encrypted identity

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination