CN112348464A - Power transmission and transformation project construction preparation stage management system and method - Google Patents

Power transmission and transformation project construction preparation stage management system and method Download PDF

Info

Publication number
CN112348464A
CN112348464A CN202011209964.9A CN202011209964A CN112348464A CN 112348464 A CN112348464 A CN 112348464A CN 202011209964 A CN202011209964 A CN 202011209964A CN 112348464 A CN112348464 A CN 112348464A
Authority
CN
China
Prior art keywords
task
power transmission
project
information
management module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011209964.9A
Other languages
Chinese (zh)
Inventor
孔祥美
陈文奇
刘程
曾挺
常扬
陈锐林
周元山
刘晓枫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Shantou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Shantou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Shantou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN202011209964.9A priority Critical patent/CN112348464A/en
Publication of CN112348464A publication Critical patent/CN112348464A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention discloses a management system and a management method for a construction preparation stage of a power transmission and transformation project. This power transmission and transformation project construction preparation phase management system includes: the project management module is used for receiving newly-built power transmission and transformation project information input by a user and automatically generating a task list corresponding to the newly-built power transmission and transformation project according to the newly-built power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed; and the task management module is used for sending task information of the task to be processed to corresponding participants, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time. The invention provides a management system and a management method for a construction preparation stage of a power transmission and transformation project, which are used for solving the problem that the construction preparation stage of the power transmission and transformation project cannot be completed on time.

Description

Power transmission and transformation project construction preparation stage management system and method
Technical Field
The embodiment of the invention relates to the field of computer programs, in particular to a management system and a management method for a construction preparation stage of a power transmission and transformation project.
Background
The power transmission and transformation construction project has the characteristics of large space span and more participators, and people in the area are usually required to cooperate in the project construction process.
However, in the matching process, team communication is insufficient, task content and time requirements of task responsible persons are unclear, project resource information is asynchronous, file storage is disordered, and problems in the execution process cannot be effectively fed back and solved, so that work in the construction preparation stage of the power transmission and transformation project faces huge challenges, and project operation construction progress is influenced.
Disclosure of Invention
The invention provides a management system and a management method for a construction preparation stage of a power transmission and transformation project, which aim to solve the problem that the construction preparation stage of the power transmission and transformation project in the prior art cannot be completed on time.
In a first aspect, an embodiment of the present invention provides a management system for a preparation phase of power transmission and transformation engineering construction, including:
the project management module is used for receiving newly-built power transmission and transformation project information input by a user and automatically generating a task list corresponding to the newly-built power transmission and transformation project according to the newly-built power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed;
and the task management module is used for sending task information of the task to be processed to corresponding participants, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
Optionally, the system further includes:
and the problem feedback module is used for receiving the problem information and the problem answer information in real time, and classifying the problem information according to preset classification conditions to obtain a classification result, so that the participators perform post-evaluation on the newly-built power transmission and transformation project according to the classification result.
Optionally, the task management module is further configured to automatically calculate the earliest starting time and the latest upgrade handling time of the new power transmission and transformation project according to preset data and the received task required completion time, where the preset data at least includes a logical relationship between tasks and the shortest completion time.
Optionally, the file management module is configured to modify a preset supporting file directory according to the received modification information, where the preset supporting file directory is automatically generated according to the task list.
Optionally, the file management module is further configured to receive the uploaded process file, and generate a corresponding process file directory according to the process file.
Optionally, the task management module is further configured to prompt for the latest upgrade time, and includes:
and when detecting that any task is not completed in time at the latest grading time, the task management module sends task grading handling information to the task responsible person of the power transmission and transformation project so that the task responsible person can handle the task grading in time according to the task grading information.
Optionally, the task management module is further configured to establish a task progress chart, where the task progress chart is used to display the completion progress of each project and an association relationship between tasks included in each project.
In a second aspect, an embodiment of the present invention further provides a method for managing a preparation phase of a power transmission and transformation project, where the method includes:
receiving new power transmission and transformation project information input by a user through a project management module, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed;
and sending task information of the task to be processed to corresponding participants at a task management module, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
In a third aspect, an embodiment of the present invention further provides a server, where the server includes:
one or more processors;
storage means for storing one or more programs;
when the one or more programs are executed by the one or more processors, the one or more processors implement the method for managing the preparation phase of the power transmission and transformation project construction provided by any embodiment of the invention.
In a fourth aspect, an embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored, where the computer program, when executed by a processor, implements the method for managing a preparation phase of power transmission and transformation engineering construction provided in any embodiment of the present invention.
According to the technical scheme of the power transmission and transformation project construction preparation stage system, the project management module is used for receiving new power transmission and transformation project information input by a user, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed, and the task information of the task to be processed is sent to corresponding participants through the task management module, and comprises at least one item of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time. And the participators can reasonably arrange the task progress according to the task information, so that the construction project of the corresponding power transmission and transformation project can be completed within the limited period of completion time.
Drawings
Fig. 1 is a block diagram of a management system in a preparation phase of power transmission and transformation project construction according to a first embodiment of the present invention;
fig. 2 is a block diagram of a management system in a preparation phase of power transmission and transformation project construction in a second embodiment of the present invention;
fig. 3 is a flowchart of a management method in a preparation phase of power transmission and transformation project construction in a third embodiment of the present invention;
fig. 4 is a schematic structural diagram of a server in the fourth embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention. It should be further noted that, for the convenience of description, only some of the structures related to the present invention are shown in the drawings, not all of the structures.
Example one
Fig. 1 is a schematic structural diagram of a power transmission and transformation project construction preparation phase system according to an embodiment of the present invention, where this embodiment is applicable to a situation of project management in a new power transmission and transformation project construction preparation phase, and the system may be implemented in a hardware and/or software manner, and includes:
a project management module 110 and a task management module 120. The project management module 110 is configured to receive newly-built power transmission and transformation project information input by a user, and automatically generate a task list corresponding to the newly-built power transmission and transformation project according to the newly-built power transmission and transformation project information, where the task list at least includes task information of a task to be processed; the task management module 120 is configured to send task information of the task to be processed to corresponding participants, where the task information includes at least one of task content, task responsible persons, required completion time, earliest start time, and latest upgrade time.
The project management module 110 is configured to receive information of the newly-built power transmission and transformation project to establish the newly-built power transmission and transformation project, generate a task list and support materials required by each task, and provide work guidance for relevant participators, so that the project participators can make clear of relevant information such as task content, work steps, and task specified time. The item management module 110 is further configured to query existing power transmission and transformation items according to the received item query information; and editing the corresponding information of the newly-built power transmission and transformation project according to the received editing information. And the project management list can modify the task list according to the received list modification information. In order to prevent the new power transmission and transformation project from being compromised, the present embodiment preferably only authorizes personnel to use the project management module. Wherein, the authorized person can be a department leader or a project responsible person.
The system also comprises a login module, wherein a user inputs a user name, a password, an authentication code and a role into the login module, and the login module enters the system after the user name, the password, the authentication code and the role are all authenticated.
Illustratively, a project principal inputs a correct user name and password, a correct verification code and a correct role in a login interface of a management system in a power transmission and transformation construction preparation phase, enters the project management interface, can establish at least one power transmission and transformation management project in the project management interface, can inquire other existing power transmission and transformation projects in the power transmission and transformation system, and can add or modify information of any power transmission and transformation project.
The task management module 120 is configured to send task information of the task to be processed to corresponding participants, where the task information includes at least one of task content, task responsible persons, required completion time, earliest start time, and latest upgrade time.
Specifically, after receiving the information of the newly-built power transmission and transformation project, the project management module 110 automatically generates a task list under the project, and the task management module may also modify the task list according to the received modification information of the task list, and the task management module 120 performs task allocation according to the information of the newly-built power transmission and transformation project. The task management module 120 automatically calculates the earliest starting time and the latest upgrade processing time according to preset data after inputting the required completion time and obtaining the actual completion time of the immediately preceding task, and sends task information to the task responsible person, wherein the preset data can determine the earliest starting time and the latest upgrade time of the project according to the completion time of the existing tasks of the same type, the association relationship among the tasks and the latest upgrade time, wherein the task information comprises task content, the task responsible person, the earliest starting time, the latest upgrade processing time and the required completion time, and the setting of the earliest starting time and the latest upgrade processing time has the advantage of ensuring that the task has sufficient working time.
It should be noted that there is an association relationship between tasks in the task management module, for example, task B must be started after task a is completed. The embodiment preferably adopts a visual interface to dynamically and intuitively display the incidence relation and the interest relation among the tasks, and can easily position the task link causing the project delay when the project is delayed.
For example, when a newly-built power transmission and transformation project is completed, a project principal enters a task management interface corresponding to the project to perform task allocation on tasks in the project, and specifies a task principal. The task management module 120 distributes task information to task managers. For example, a responsible person newly builds a power transmission and transformation project a in the project management module 110, the project responsible person divides the project a into task 1, task 2, and task 3 in the task management module 120, where the task 1 is an immediately previous task of the task 2, and when a required completion time of the task 2 is input and an actual completion time of the task 1 are input, the task management module 120 automatically calculates an earliest start time and a latest upgrade transaction time of the task 2 according to preset data and the input required completion time, and sends task information to the task responsible person, and optionally, the task management module 120 arranges the project time arrangement information according to the completion required time of the existing tasks of the same type.
Specifically, when a project leader inputs a task name and a deadline completion time in the task management module 120, the system gives and displays the earliest starting time and the latest upgrade transaction time of the task according to the time preset data and the logical relationship between the tasks. For example, the project manager creates at least one electric transmission and transformation project in the project management module 110 of the electric transmission and transformation project preparation phase management system, inputs the task required completion time and the actual completion time of the pre-task, and sends the project time information to the task manager in the task management module 120 corresponding to any newly created electric transmission and transformation project.
According to the technical scheme of the management system for the power transmission and transformation project preparation phase, the project management module is used for receiving new power transmission and transformation project information input by a user, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed, and the task management module is used for sending the task information of the task to be processed to corresponding participators, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time. And the participators can reasonably arrange the task progress according to the task information, so that the construction project of the corresponding power transmission and transformation project can be completed within the limited period of completion time.
On the basis of the above technical solution, optionally, the task management module 120 stores all the participant information of the power transmission and transformation project that is originally set. The advantage of setting up like this is that the project person in charge can in time send the task information to corresponding task person in charge.
On the basis of the above technical solution, optionally, the management system at the preparation stage of power transmission and transformation project construction may further include a system maintenance module, and an administrator enters the system maintenance module through the login module to perform maintenance on the system and import and maintain basic data.
Example two
Fig. 2 is a schematic structural diagram of a management system in a preparation phase for power transmission and transformation project construction according to a second embodiment of the present invention, which further improves the management system in the preparation phase for power transmission and transformation project construction based on the second embodiment, refines a task management module, and adds a problem feedback module and a file management module, where explanations of terms identical to or corresponding to the above-mentioned examples are not repeated herein. Accordingly, the system comprises: a project management module 110, a task management module 120, a problem feedback module 130, and a file management module 140.
The project management module 110 is configured to receive newly-built electric transmission and transformation project information input by a user, and automatically generate a task list corresponding to the newly-built electric transmission and transformation project according to the newly-built electric transmission and transformation project information, where the task list at least includes task information of a task to be processed; the task management module 120 is configured to send task information of the task to be processed to corresponding participants, where the task information includes at least one of task content, task responsible person, required completion time, earliest start time, and latest upgrade time; the problem feedback module 130 is configured to receive problem information and problem answer information in real time, and classify the problem information according to preset classification conditions to obtain a classification result, so that a participant performs post-evaluation on a newly-built power transmission and transformation project according to the classification result; the file management module 140 is configured to modify a preset supporting file directory according to the received modification information, where the preset supporting file directory is automatically generated according to the task list.
When detecting that any task information corresponds to a relevant file, the task management module pushes the relevant file to a task principal so that the principal can look up the relevant file in time, and time waste is avoided.
In some embodiments, the participators input the problems encountered in the task execution process to the problem feedback module, and classify the received problems according to the preset problem reasons, so that the participators can share the problems, the group force is timely solved, and the smooth task execution is ensured. Meanwhile, based on big data, the system automatically pushes important questions to corresponding task responsible persons.
In one embodiment, the participator can check all the questions in the question feedback module at any time and solve any one of the questions, so that the inexperienced personnel of the project can obtain the solution of the corresponding question in time. Meanwhile, when the task is carried out, the system automatically pushes key problems which easily exist in the task to a corresponding task responsible person based on big data analysis, and the system reminds people of avoiding.
The problem feedback module also includes an output function. The project responsible person can output all the problems generated in the working process according to the classification result at any time, for example, when the work in the construction preparation stage of the newly constructed power transmission and transformation project is completed, so that project summary, post-project evaluation and follow-up power transmission and transformation project management decision assistance are facilitated.
And the file management module 140 is used for automatically generating a supporting file directory according to preset data when a task is issued, and supporting modification according to actual conditions. Wherein the supporting file comprises the necessary file to start the current task.
The file management module 140 and the task management module 120 are in a one-to-one correspondence relationship. The supporting file directory may be a conventional supporting file directory stored in advance by the file management module.
Specifically, the file management module 140 imports a conventional supporting file directory in advance, and a project administrator modifies the directory of the conventional supporting file directory according to the actual situation of the project, for example, adding a supporting file directory, deleting the supporting file directory, or modifying the supporting file directory.
Further, the file management module 140 is further configured to upload a process file in a transmission and transformation project completion process corresponding to the transmission and transformation project information, and generate a corresponding process file directory under a corresponding task according to the process file name. The process file may be a file formed during any task, and the process file naming rule may be at least one combination of a project name, time, and unit.
The file management module 140 may be a file upload module, and the task leader and other task participants may upload related files generated in the task process to the file management module 140.
For example, after the user confirms the task name in the task management module, the file management module automatically generates the supporting file directory under the task. And the project principal performs the operation of adding or modifying the directory to the supporting file directory according to the actual situation of the project.
And when the file management module detects that any supporting file under any task is completely prepared, marking the supporting file directories corresponding to all the supporting files as green.
Further, when detecting that any task is not completed on time, the task management module 120 sends task ranking information to the task person in charge of the newly-built power transmission and transformation project, so that the task person in charge can perform ranking in time.
Illustratively, the task management module 120 reminds the task person to handle the task in a graded manner when detecting that the task person cannot complete the task on time, thereby ensuring the task is smoothly performed.
Further, the task management module 120 is further configured to establish a task progress chart, where the task progress chart is used to display the completion progress of each project and an association relationship between tasks included in each project.
Illustratively, the task progress graph includes, but is not limited to, a project hierarchy and a task node hierarchy. Displaying the overall project progress at a project level, wherein the overall project progress comprises a project overall completion rate and an on-time completion rate, for example, a certain power transmission and transformation project reaches 5 task nodes, if 3 task nodes are actually completed at present, the overall task completion rate of the project is displayed to be 60%, and if 4 nodes are required to be completed at present, the on-time completion rate is displayed to be 75%; the method comprises the steps that the completion condition of task nodes and the logical relationship among the task nodes are displayed on a task node level, for example, a certain power transmission and transformation project comprises 5 task nodes which are respectively a task A, a task B, a task C, a task D and a task E, the task B can be started after the task A is completed, the task C can be started after the task A and the task B are completed, the task D and the task E have no logical relationship with other tasks, the logical relationship among the 5 task nodes is automatically constructed and displayed based on the association relationship among the tasks in the project, if the task A is not completed, the association line of the A-B-C is displayed in red, and the fact that all the task nodes on the line cannot be pushed is shown. If the completion is finished, the system automatically pushes the completion condition of the A to the responsible person of the B. D. And E has no logical relation with other tasks, so that the work of the task D and the task E can be normally carried out.
According to the technical scheme of the power transmission and transformation project preparation phase management system, the power transmission and transformation project preparation phase management system comprises a project management module, a task management module, a file management module and a problem feedback module, wherein in the file management module, a supporting file directory, a process file directory and corresponding files are stored and processed, in the task management module, the actual task completion condition is judged according to the task progress node time, and the task is handled in a grading mode within reasonable time, so that the task is guaranteed to be smoothly carried out.
EXAMPLE III
Fig. 3 is a flowchart of a management method in a preparation phase of power transmission and transformation project construction according to a third embodiment of the present invention. The method specifically comprises the following steps:
s210, receiving new power transmission and transformation project information input by a user through a project management module, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed.
Specifically, the project information is processed in the project management module, and the processing of the project information can be new power transmission and transformation projects, can be the inquiry of existing power transmission and transformation projects of the management system in the preparation stage of power transmission and transformation project construction, and can be the modification of the new power transmission and transformation projects and the information content of the existing power transmission and transformation projects. The operation authority of the project management module can be a department leader and can be a person in charge of the power transmission and transformation project.
Specifically, a project principal inputs a correct user name, a password, a verification code and a role through a login module of a management system in a power transmission and transformation project construction preparation stage, and enters a project management module, the project principal can newly build a power transmission and transformation project, can inquire the power transmission and transformation project existing in the system, can modify or delete and add project information content, and can modify a task list, such as delete and add the task list according to the actual condition of the project. And the department leader inputs correct user name and password through a login module of the management system in the construction preparation stage of the power transmission and transformation project, and enters a project management module, so that the department leader can check specific project contents.
Illustratively, a project principal inputs a correct user name and password, a correct verification code and a correct role in a login interface of a management system in a power transmission and transformation project construction preparation phase, enters a project management interface, can newly establish at least one power transmission and transformation management project in the project management interface, can inquire other existing power transmission and transformation projects in the power transmission and transformation system, and can add or modify information of any power transmission and transformation project.
And S220, sending task information of the task to be processed to corresponding participants in the task management module, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
Specifically, the project responsible person can select the corresponding task responsible person and the required completion time, the system automatically generates the earliest starting time and the latest upgrade time, and the system automatically sends the information to the corresponding task responsible person.
Illustratively, when a newly-built power transmission and transformation project is completed, the system automatically generates a corresponding task list, and project managers can modify the task list according to actual conditions. After the task list is determined, the project responsible person enters a task management interface corresponding to the project to perform task allocation on the tasks in the project, and the task responsible person is appointed and the required completion time is determined. The task management module 120 transmits the task information to the task person in charge. For example, a person in charge newly builds a power transmission and transformation project a in the project management module 110, and automatically generates a task 1, a task 2, a task 3 and a task 4 under the project a; the project principal selects and confirms the project only by task 1, task 2 and task 3 according to the actual condition of the project, automatically generates supporting file list files 1, file 2, file 3 and file 4 under the corresponding task after the tasks 1, 2 and 3 are confirmed, and selects and confirms the file 1 and the file 2 and adds the file 3 according to the actual condition. The responsible person selects the task responsible person at the project management module 110, and the task management module automatically generates the earliest starting time and the latest upgrade time according to the preset time information of the projects of the same type and the input required finishing time, and sends the task information to the task responsible person.
According to the technical scheme of the management system for the preparation stage of the power transmission and transformation construction project, the project management module is used for receiving information of a newly-built power transmission and transformation project and automatically generating a task list corresponding to the newly-built power transmission and transformation project according to the information of the newly-built power transmission and transformation project, wherein the task list at least comprises task information of tasks to be processed, and the task management module is used for sending the task information of the tasks to be processed to corresponding participators, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest start time and latest upgrade time, so that the participators can reasonably arrange task progress according to the task information, and accordingly construction projects of corresponding power transmission and transformation projects can be completed within limited completion time.
Example four
Fig. 4 is a schematic structural diagram of a server according to a fourth embodiment of the present invention. FIG. 4 illustrates a block diagram of an exemplary server 12 suitable for use in implementing embodiments of the present invention. The server 12 shown in fig. 4 is only an example, and should not bring any limitation to the function and the scope of use of the embodiment of the present invention.
As shown in FIG. 4, the server 12 is in the form of a general purpose computing device. The components of the server 12 may include, but are not limited to: one or more processors or processing units 16, a system memory 28, and a bus 18 that couples various system components including the system memory 28 and the processing unit 16.
Bus 18 represents one or more of any of several types of bus structures, including a memory bus or memory controller, a peripheral bus, an accelerated graphics port, and a processor or local bus using any of a variety of bus architectures. By way of example, such architectures include, but are not limited to, Industry Standard Architecture (ISA) bus, micro-channel architecture (MAC) bus, enhanced ISA bus, Video Electronics Standards Association (VESA) local bus, and Peripheral Component Interconnect (PCI) bus.
The server 12 typically includes a variety of computer system readable media. Such media may be any available media that is accessible by server 12 and includes both volatile and nonvolatile media, removable and non-removable media.
The system memory 28 may include computer system readable media in the form of volatile memory, such as Random Access Memory (RAM)30 and/or cache memory 32. The server 12 may further include other removable/non-removable, volatile/nonvolatile computer system storage media. By way of example only, storage system 34 may be used to read from and write to non-removable, nonvolatile magnetic media (not shown in FIG. 4, and commonly referred to as a "hard drive"). Although not shown in FIG. 4, a magnetic disk drive for reading from and writing to a removable, nonvolatile magnetic disk (e.g., a "floppy disk") and an optical disk drive for reading from or writing to a removable, nonvolatile optical disk (e.g., a CD-ROM, DVD-ROM, or other optical media) may be provided. In these cases, each drive may be connected to bus 18 by one or more data media interfaces. System memory 28 may include at least one program product having a set (e.g., at least one) of program modules that are configured to carry out the functions of embodiments of the invention.
A program/utility 40 having a set (at least one) of program modules 42 may be stored, for example, in system memory 28, such program modules 42 including, but not limited to, an operating system, one or more application programs, other program modules, and program data, each of which examples or some combination thereof may comprise an implementation of a network environment. Program modules 42 generally carry out the functions and/or methodologies of the described embodiments of the invention.
The server 12 may also communicate with one or more external devices 14 (e.g., keyboard, pointing device, display 24, etc.), with one or more devices that enable a user to interact with the server 12, and/or with any devices (e.g., network card, modem, etc.) that enable the server 12 to communicate with one or more other computing devices. Such communication may be through an input/output (I/O) interface 22. Also, the server 12 may communicate with one or more networks (e.g., a Local Area Network (LAN), a Wide Area Network (WAN), and/or a public network, such as the Internet) via the network adapter 20. As shown, the network adapter 20 communicates with the other modules of the server 12 via the bus 18. It should be understood that although not shown in the figures, other hardware and/or software modules may be used in conjunction with the server 12, including but not limited to: microcode, device drivers, redundant processing units, external disk drive arrays, RAID systems, tape drives, and data backup storage systems, among others.
The processing unit 16 executes various functional applications and data processing by running a program stored in the system memory 28, for example, implementing a power transmission and transformation project construction preparation phase management method provided by the embodiment of the present invention, the method including:
receiving new power transmission and transformation project information input by a user through a project management module, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed;
and sending task information of the task to be processed to corresponding participants at a task management module, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
Of course, those skilled in the art can understand that the processor may also implement the technical solution of power transmission and transformation project management provided by any embodiment of the present invention.
EXAMPLE five
This fifth embodiment provides a computer-readable storage medium, on which a computer program is stored, where the computer program, when executed by a processor, implements a method for preparing a power transmission and transformation project, according to any embodiment of the present invention, where the method includes:
receiving new power transmission and transformation project information input by a user through a project management module, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed;
and sending task information of the task to be processed to corresponding participants at a task management module, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
Computer storage media for embodiments of the invention may employ any combination of one or more computer-readable media. The computer readable medium may be a computer readable signal medium or a computer readable storage medium. The computer-readable storage medium may be, for example but not limited to: an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination thereof. More specific examples (a non-exhaustive list) of the computer readable storage medium would include the following: an electrical connection having one or more wires, a portable computer diskette, a hard disk, a Random Access Memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disc read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing. In the context of this document, a computer readable storage medium may be any tangible medium that can contain, or store a program for use by or in connection with an instruction execution system, apparatus, or device.
A computer readable signal medium may include a propagated data signal with computer readable program code embodied therein, for example, in baseband or as part of a carrier wave. Such a propagated data signal may take many forms, including, but not limited to, electro-magnetic, optical, or any suitable combination thereof. A computer readable signal medium may also be any computer readable medium that is not a computer readable storage medium and that can communicate, propagate, or transport a program for use by or in connection with an instruction execution system, apparatus, or device.
Program code embodied on a computer readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wire, fiber optic cable, RF, etc., or any suitable combination of the foregoing.
Computer program code for carrying out operations for aspects of the present invention may be written in any combination of one or more programming languages, including an object oriented programming language such as Java, Smalltalk, C + + or the like and conventional procedural programming languages, such as the "C" programming language or similar programming languages. The program code may execute entirely on the user's computer, partly on the user's computer, as a stand-alone software package, partly on the user's computer and partly on a remote computer or entirely on the remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a Local Area Network (LAN) or a Wide Area Network (WAN), or the connection may be made to an external computer (for example, through the Internet using an Internet service provider).
It will be understood by those skilled in the art that the modules or steps of the invention described above may be implemented by a general purpose computing device, they may be centralized on a single computing device or distributed across a network of computing devices, and optionally they may be implemented by program code executable by a computing device, such that it may be stored in a memory device and executed by a computing device, or it may be separately fabricated into various integrated circuit modules, or it may be fabricated by fabricating a plurality of modules or steps thereof into a single integrated circuit module. Thus, the present invention is not limited to any specific combination of hardware and software.
It is to be noted that the foregoing is only illustrative of the preferred embodiments of the present invention and the technical principles employed. It will be understood by those skilled in the art that the present invention is not limited to the particular embodiments described herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the invention. Therefore, although the present invention has been described in greater detail by the above embodiments, the present invention is not limited to the above embodiments, and may include other equivalent embodiments without departing from the spirit of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims (10)

1. The utility model provides a power transmission and transformation project construction preparation phase management system which characterized in that includes:
the project management module is used for receiving newly-built power transmission and transformation project information input by a user and automatically generating a task list corresponding to the newly-built power transmission and transformation project according to the newly-built power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed;
and the task management module is used for sending task information of the task to be processed to corresponding participants, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
2. The system of claim 1, further comprising:
and the problem feedback module is used for receiving the problem information and the problem answer information in real time, and classifying the problem information according to preset classification conditions to obtain a classification result, so that the participators perform post-evaluation on the newly-built power transmission and transformation project according to the classification result.
3. The system of claim 1, wherein the task management module is further configured to automatically calculate the earliest start time and the latest upgrade transaction time of the newly-built power transmission and transformation project according to preset data and the received task request completion time, wherein the preset data at least includes a logical relationship between tasks and the shortest completion time.
4. The system according to claim 1, further comprising a file management module, wherein the file management module is configured to modify a preset supporting file directory according to the received modification information, and the preset supporting file directory is automatically generated according to the task list.
5. The system of claim 4, wherein the file management module is further configured to receive the uploaded process files and generate a corresponding process file directory according to the process files.
6. The system of claim 1, wherein the task management module is further configured to provide a latest upgrade time reminder, comprising:
and when detecting that any task is not completed in time at the latest grading time, the task management module sends task grading handling information to the task responsible person of the power transmission and transformation project so that the task responsible person can handle the task grading in time according to the task grading information.
7. The system of claim 1, wherein the task management module is further configured to establish a task progress chart, and the task progress chart is used for displaying a completion progress of each project and an association relationship between tasks included in each project.
8. A management method for a construction preparation stage of a power transmission and transformation project is characterized by comprising the following steps:
receiving new power transmission and transformation project information input by a user through a project management module, and automatically generating a task list corresponding to the new power transmission and transformation project according to the new power transmission and transformation project information, wherein the task list at least comprises task information of a task to be processed;
and sending task information of the task to be processed to corresponding participants at a task management module, wherein the task information comprises at least one of task content, task responsible persons, required completion time, earliest starting time and latest upgrade time.
9. A server, characterized in that the server comprises:
one or more processors;
storage means for storing one or more programs;
when executed by the one or more processors, cause the one or more processors to implement the transmission and transformation project construction preparation phase management method of claim 8.
10. A computer-readable storage medium on which a computer program is stored, the program, when executed by a processor, implementing the transmission and transformation project construction preparation phase management method according to claim 8.
CN202011209964.9A 2020-11-03 2020-11-03 Power transmission and transformation project construction preparation stage management system and method Pending CN112348464A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011209964.9A CN112348464A (en) 2020-11-03 2020-11-03 Power transmission and transformation project construction preparation stage management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011209964.9A CN112348464A (en) 2020-11-03 2020-11-03 Power transmission and transformation project construction preparation stage management system and method

Publications (1)

Publication Number Publication Date
CN112348464A true CN112348464A (en) 2021-02-09

Family

ID=74356254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011209964.9A Pending CN112348464A (en) 2020-11-03 2020-11-03 Power transmission and transformation project construction preparation stage management system and method

Country Status (1)

Country Link
CN (1) CN112348464A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104392310A (en) * 2014-11-13 2015-03-04 深圳市玖昔物联科技发展有限公司 Networked work coordinated management system
CN104463558A (en) * 2014-11-13 2015-03-25 深圳市玖昔物联科技发展有限公司 Networked work cooperative system and method
CN107909349A (en) * 2017-11-30 2018-04-13 郑州云海信息技术有限公司 A kind of project management Cloud Server and its method for realizing project management
CN109472478A (en) * 2018-10-31 2019-03-15 安徽网网络科技有限公司 Schedule management system and its application method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104392310A (en) * 2014-11-13 2015-03-04 深圳市玖昔物联科技发展有限公司 Networked work coordinated management system
CN104463558A (en) * 2014-11-13 2015-03-25 深圳市玖昔物联科技发展有限公司 Networked work cooperative system and method
CN107909349A (en) * 2017-11-30 2018-04-13 郑州云海信息技术有限公司 A kind of project management Cloud Server and its method for realizing project management
CN109472478A (en) * 2018-10-31 2019-03-15 安徽网网络科技有限公司 Schedule management system and its application method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周蔚吾编著, 知识产权出版社 *

Similar Documents

Publication Publication Date Title
US8762187B2 (en) Easy process modeling platform
US10635410B2 (en) System to coordinate source code module changes
US20080270477A1 (en) Workflow method, system, and data structure
US11836655B2 (en) Project management devices, systems and methods
CN104380261A (en) Locally backed cloud-based storage
US20140047330A1 (en) Collaborative decision making in contract documents
US10091123B2 (en) System and user interface for coordinating distributed workflow between multiple computing systems
CN115398433A (en) Method, apparatus and computer program product for managing organizational connections in a group-based communication system
US11087285B2 (en) Systems and methods for providing message templates in an enterprise system
WO2023093486A1 (en) Method and apparatus for generating project flow, electronic device, and storage medium
US20130006688A1 (en) Creating a 3rd party team project story board
US20130007694A1 (en) Project story board to board communication tools
WO2024007906A1 (en) Data processing method and apparatus, electronic device, and storage medium
CN111126948A (en) Processing method and device for approval process
US11954064B2 (en) Framework for migrating applications to cloud computing environment
US8069180B1 (en) Systems and methods for automated employee resource delivery
CN115167785B (en) Label-based network disk file management method and device, network disk and storage medium
US20130006687A1 (en) Creating a sub-story for a project story board
CN113535574B (en) Automatic generation method, device, equipment and medium for test user data
CN112348464A (en) Power transmission and transformation project construction preparation stage management system and method
KR20220150847A (en) Office system and work task management method and device
CN113204790B (en) View authority processing method, device, equipment and medium
CN115130012A (en) Method and device for joining group, electronic equipment and storage medium
US20200097870A1 (en) Work task commitment manager
CN112632036B (en) Management platform, method and related equipment of data exchange system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210209