CN112285397B - Position information management method, system and storage medium of electric energy meter and acquisition terminal - Google Patents

Position information management method, system and storage medium of electric energy meter and acquisition terminal Download PDF

Info

Publication number
CN112285397B
CN112285397B CN202011122776.2A CN202011122776A CN112285397B CN 112285397 B CN112285397 B CN 112285397B CN 202011122776 A CN202011122776 A CN 202011122776A CN 112285397 B CN112285397 B CN 112285397B
Authority
CN
China
Prior art keywords
maintenance
electric energy
energy meter
acquisition terminal
position information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011122776.2A
Other languages
Chinese (zh)
Other versions
CN112285397A (en
Inventor
王述义
王亚丽
王述洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Hanlian Electric Power Technology Co ltd
Original Assignee
Wuhan Hanlian Electric Power Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Hanlian Electric Power Technology Co ltd filed Critical Wuhan Hanlian Electric Power Technology Co ltd
Priority to CN202011122776.2A priority Critical patent/CN112285397B/en
Publication of CN112285397A publication Critical patent/CN112285397A/en
Application granted granted Critical
Publication of CN112285397B publication Critical patent/CN112285397B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R11/00Electromechanical arrangements for measuring time integral of electric power or current, e.g. of consumption
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • G06Q10/047Optimisation of routes or paths, e.g. travelling salesman problem
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Navigation (AREA)

Abstract

The application relates to an electric energy meter and a position information management method of an acquisition terminal, and relates to the technical field of electric energy meter information acquisition; the method comprises the following steps: installing an electric energy meter for an electricity user, connecting the electric energy meter to an electricity acquisition terminal in a communication way, building a position information management platform, and then building communication connection between the electricity acquisition terminal and the information management platform; storing the position information of the electric energy meter and the electricity acquisition terminal in an information management platform, and drawing an electronic map according to the geographic positions of the electric energy meter and the electricity acquisition terminal; establishing maintenance sites, wherein each maintenance site comprises a plurality of maintenance personnel, establishing communication connection between the maintenance site and an information management platform, storing the position information of the maintenance site in the information management platform, and issuing maintenance tasks to the maintenance site; the application has the effect of improving maintenance efficiency.

Description

Position information management method, system and storage medium of electric energy meter and acquisition terminal
Technical Field
The application relates to the technical field of information acquisition of electric energy meters, in particular to a position information management method, a system and a storage medium of an electric energy meter and an acquisition terminal.
Background
The electric energy meter is an instrument for measuring electric energy, and the acquisition terminal is equipment for acquiring and storing electricity information and transmitting the electricity information to the main station; the acquisition terminals are classified into a special transformer acquisition terminal, a centralized meter reading terminal (comprising a concentrator and a collector), a distributed energy monitoring terminal and the like according to application places.
The related Chinese patent with the bulletin number of CN108877187B discloses an intelligent electric energy metering information acquisition method and system, wherein the system comprises the following steps: the intelligent electric energy meter comprises an electric energy meter testing device and an electric energy meter acquisition device which are respectively connected with the intelligent electric energy meter, wherein the electric energy meter testing device is connected with a load input device, the electric energy meter acquisition device is connected with a metering information acquisition device, and the electric energy meter testing device and the metering information acquisition device are respectively connected with a server; when the intelligent electric energy meter testing device works, the intelligent electric energy meter testing device controls the intelligent electric energy meter to communicate with the load input device, tests the intelligent electric energy meter according to the preprogrammed virtual electric energy meter, obtains an error value of the intelligent electric energy meter and sends the error value to the server; the server compares the error value with a preset error range, corrects the intelligent electric energy meter, and when the error value of the intelligent electric energy meter is in the preset error range, the metering information acquisition device and the electric energy meter acquisition device send and receive information, so that metering information of the intelligent electric energy meter is obtained and sent to the server.
Aiming at the related technology, the inventor considers that the existing electric energy meters and acquisition terminals are huge in installation quantity, and when the fault maintenance work is required to be carried out on the individual electric energy meters and acquisition terminals, maintenance personnel are inconvenient to quickly position the electric energy meters and the acquisition terminals to be maintained and know specific geographic positions, so that the maintenance efficiency is low.
Disclosure of Invention
In order to facilitate improvement of the problem of low maintenance efficiency of an electric energy meter and an acquisition terminal in the related art, the application provides a position information management method, a system and a storage medium of the electric energy meter and the acquisition terminal.
In a first aspect, the present application provides a method for managing position information of an electric energy meter and an acquisition terminal, which adopts the following technical scheme:
An electric energy meter and a position information management method of an acquisition terminal, comprising the following steps:
Installing an electric energy meter for an electricity user, connecting the electric energy meter to an electricity acquisition terminal in a communication way, building a position information management platform, and then building communication connection between the electricity acquisition terminal and the information management platform;
storing the position information of the electric energy meter and the electricity acquisition terminal in an information management platform, and drawing an electronic map according to the geographic positions of the electric energy meter and the electricity acquisition terminal;
Displaying the positions of each electric energy meter and each electricity acquisition terminal in the form of dots in an electronic map, displaying the working states of each electric energy meter and each electricity acquisition terminal, wherein the dots are green in normal operation, and red in abnormal operation;
establishing maintenance sites, wherein each maintenance site comprises a plurality of maintenance personnel, establishing communication connection between the maintenance site and an information management platform, and storing the position information of the maintenance site in the information management platform;
And issuing maintenance tasks to the maintenance site.
Through adopting above-mentioned technical scheme, through electronic map visual display all electric energy meter and power consumption acquisition terminal's position and operating condition, when the dot colour on electronic map is red, then indicate that electric energy meter or power consumption acquisition terminal that this dot corresponds need maintain, accessible electronic map knows the distribution condition of all electric energy meter and power consumption acquisition terminal that wait to maintain this moment, so as to plan the maintenance route, rethread information management platform retrieves the specific geographical position information of each electric energy acquisition terminal and electric energy meter, then with the information issuing to maintenance website, so that maintenance website carries out maintenance work according to position information effectively fast, improve maintenance efficiency.
Optionally, the step of establishing maintenance sites, each maintenance site including a plurality of maintenance personnel, establishing communication connection between the maintenance site and the information management platform, and storing position information of the maintenance site in the information management platform, includes the following sub-steps:
And dividing the maintenance area of the electric energy meter and the electricity acquisition terminal by taking the administrative area as a division principle, and further dividing the maintenance area into a plurality of maintenance units according to the quantity of the electric energy meter and the electricity acquisition terminal in each maintenance area and the density of the distribution positions, wherein each maintenance unit corresponds to one maintenance station.
By adopting the technical scheme, the maintenance area is divided, the regional management of the electric energy meter and the electricity acquisition terminal is realized, and the standardized maintenance of the electric energy meter and the electricity acquisition terminal is improved; the maintenance area is further divided according to the density of the electric energy meter and the electricity utilization acquisition terminals, so that the electric energy meter and the number of the electricity utilization acquisition terminals which are required to be managed and maintained are uniformly distributed for each maintenance site, and the maintenance workload of each maintenance unit is balanced.
Optionally, the step of issuing the maintenance task to the maintenance site includes the following steps:
installing a maintenance APP at the mobile terminal of each maintenance personnel, and providing a key for logging in and accessing the information management platform to a maintenance site.
By adopting the technical scheme, each maintenance personnel can access the information management platform by logging in the maintenance APP so as to conveniently check and get the task to be maintained issued by the information management platform without notifying the maintenance task and assigning the maintenance personnel in a wireless way, thereby improving the efficiency of the maintenance task in the process of getting the maintenance task and further improving the maintenance efficiency.
Optionally, the issuing the maintenance task to the maintenance site further includes the following steps:
when the maintenance task is issued, the state of the maintenance task is displayed as 'to be processed', after any maintenance personnel at the same maintenance site obtains the maintenance task, the state of the maintenance task is displayed as 'in maintenance', and after the maintenance task is completed, the state of the maintenance task is displayed as 'complete maintenance'.
By adopting the technical scheme, after the maintenance task is released, the information management platform displays the progress state of the maintenance task in real time, so that a plurality of maintenance personnel are prevented from repeatedly carrying out maintenance work on the same maintenance task, and the waste of human resources is reduced.
Optionally, the issuing the maintenance task to the maintenance site further includes the following steps:
When the number of the maintenance tasks received in the same maintenance unit is greater than the number of maintenance personnel of the maintenance unit, the area is judged to be in a maintenance saturated state, at the moment, the maintenance unit which is adjacent to the maintenance unit and is not in the maintenance saturated state is searched through the information management platform, and the maintenance tasks are sent.
By adopting the technical scheme, when a certain maintenance unit is in a maintenance saturation state, if maintenance tasks are continuously sent to the maintenance unit, the maintenance tasks are retained, so that the empty human resources can be further utilized by sending the maintenance tasks to the maintenance units which are adjacent to the maintenance unit and are not in the maintenance saturation state, and the maintenance efficiency is improved.
Optionally, the issuing the maintenance task to the maintenance site further includes the following steps:
and generating the shortest maintenance route according to the positions of the electric energy meter to be maintained, the electricity acquisition terminal and the maintenance site in the maintenance unit, and sending the shortest maintenance route to the corresponding maintenance site along with the maintenance task.
By adopting the technical scheme, the shortest maintenance route is recommended to the maintenance personnel, so that the time for planning the maintenance route by the maintenance personnel is reduced, the workload of the maintenance personnel is lightened, and the maintenance efficiency is improved.
Optionally, the method further comprises the following steps:
The method comprises the steps that maintenance personnel are positioned in real time in the maintenance process, the actual path of the maintenance personnel is compared with the shortest maintenance route recommended by the information management platform, and if the comparison result is wrong, the position management platform sends out an alarm signal to remind the maintenance personnel of route deviation;
and re-planning the shortest maintenance route for the maintainer according to the position of the maintainer, the residual electric energy meter to be maintained and the geographic position of the electricity acquisition terminal to be maintained.
By adopting the technical scheme, in the maintenance process of the maintenance personnel, the information management platform automatically compares the actual maintenance route and the shortest route of the maintenance personnel, and when the comparison is inconsistent, an alarm signal is sent to remind the maintenance personnel of route deviation, and then the information management platform immediately re-plans the shortest route for the maintenance personnel for reference by the maintenance personnel, so that the convenience degree of maintenance operation of the maintenance personnel is further optimized.
Optionally, the method further comprises the following steps:
numbering each electric energy meter and each electricity consumption acquisition terminal, and establishing a maintenance record meter in the information management platform by taking the number of the electric energy meter and the number of the electricity consumption acquisition terminal as a keyword;
After maintenance personnel finish maintenance, uploading maintenance logs to an information management platform, wherein the content of the maintenance logs comprises the maintained electric energy meter, the number of the electricity acquisition terminal, the corresponding fault reasons, the corresponding repairing method and the corresponding repairing result, and storing the maintenance logs in the maintenance record table.
By adopting the technical scheme, after maintenance is completed, maintenance personnel form maintenance records for the maintained electric energy meter and the electricity acquisition terminal and store the maintenance records in the information management platform, so that the maintenance personnel can determine an effective maintenance scheme according to the historical maintenance records when subsequent maintenance is convenient.
The application provides a position information management system of an electric energy meter and an acquisition terminal, which comprises the electric energy meter for measuring the electricity consumption of a user, the electricity acquisition terminal which is in communication connection with the electric energy meter and is used for acquiring and storing electric energy meter data, and an information management platform which is in communication connection with the electricity acquisition terminal and is used for managing the electric energy meter data; the information management platform comprises:
The position storage module is used for storing geographic position information of the electricity acquisition terminal, the electric energy meter and the maintenance site;
The position display module is used for displaying the geographic positions of the electricity acquisition terminal and the electric energy meter on the electronic map;
the position inquiry module is used for jumping from the position display module to the position storage module so as to inquire the geographical position information of the appointed electricity acquisition terminal, the electric energy meter and the maintenance site;
the state display module is used for displaying the working states of each ammeter and the electricity acquisition terminal on the electronic map;
the route generation module is used for generating the shortest maintenance route according to the position information of the electric energy meter to be maintained, the position information of the power acquisition terminal to be maintained and the position information of the maintenance station;
The route positioning module is used for tracking and positioning the position of the maintainer in real time;
the route comparison module is used for comparing the actual maintenance route of the maintenance personnel with the shortest maintenance route recommended by the information management platform;
the alarm module is used for sending an alarm signal when the maintenance route of the maintenance personnel deviates, and reminding the maintenance personnel of the deviation of the route;
the task state display module is used for displaying the state condition of the maintenance task in real time.
By adopting the technical scheme, before maintenance work is required, the positions of the electric energy meter to be maintained and the electricity acquisition terminal are found out according to the position display module, and the shortest maintenance route is generated through the route generation module; and when the route is deviated, sending an alarm signal and rescheduling the route for the maintainer, and uploading a maintenance log and storing the maintenance log in a maintenance record list after the maintenance is completed.
In a third aspect, the present application provides a computer readable storage medium storing a computer program capable of loading and executing the method of any one of claims 1 to 8.
By adopting the technical scheme, before maintenance work is required, the positions of the electric energy meter to be maintained and the electricity acquisition terminal are found out according to the position display module, and the shortest maintenance route is generated through the route generation module; and when the route is deviated, sending an alarm signal and rescheduling the route for the maintainer, and uploading a maintenance log and storing the maintenance log in a maintenance record list after the maintenance is completed.
In summary, the present application includes at least one of the following beneficial technical effects:
1. determining the position of the electric energy meter to be maintained and the position of the electricity acquisition terminal to be maintained by checking the electronic map, and then transmitting the position of the electric energy meter to be maintained and the position information of the electricity acquisition terminal to be maintained to a maintenance site so that the maintenance site can accurately and effectively carry out maintenance work according to the position information;
2. dividing a maintenance area to realize regional management of the electric energy meter and the electricity acquisition terminal; further dividing a maintenance area according to the density of the electric energy meter and the electricity acquisition terminal so as to balance the maintenance workload of each maintenance unit;
3. the shortest maintenance route is recommended to the maintenance personnel, so that the time for planning the maintenance route by the maintenance personnel is reduced, the workload of the maintenance personnel is lightened, and the maintenance efficiency is improved.
Drawings
Fig. 1 is a flow chart of a method for managing position information of an electric energy meter and an acquisition terminal according to an embodiment of the present invention;
FIG. 2 is a flow chart of sub-steps of step S500;
fig. 3 is a block diagram of a location information management system of an electric energy meter and an acquisition terminal in an embodiment.
Reference numerals illustrate: 1. an information management platform; 11. a position storage module; 12. a position display module; 13. a location query module; 14. a status display module; 15. a route generation module; 16. a route positioning module; 17. route comparison module; 18. an alarm module; 19. and a task state display module.
Detailed Description
The application is described in further detail below with reference to fig. 1-3.
The embodiment of the application discloses an electric energy meter and a position information management method of an acquisition terminal. Referring to fig. 1 and 2, the method for managing the position information of the electric energy meter and the acquisition terminal includes the steps of:
S100, installing an electric energy meter for an electricity user, connecting the electric energy meter to an electricity acquisition terminal in a communication way, building a position information management platform, and then building communication connection between the electricity acquisition terminal and the information management platform.
The electricity utilization acquisition terminal comprises an acquisition device and a concentrator, wherein the acquisition device is connected with the electric energy meter through an RS485 interface in a communication way, the concentrator is connected with the acquisition device through a carrier power line in a communication way, and the concentrator is connected with the information management platform through a GPRS (general packet radio service) wireless communication way; the electricity consumption of the user is detected through the electricity consumption meter, the electricity consumption information is automatically collected and transcribed through the electricity consumption collection terminal, and the electricity consumption information is uploaded to the information management platform.
S200, storing the position information of the electric energy meter and the electricity consumption acquisition terminal in an information management platform, and drawing an electronic map according to the geographic positions of the electric energy meter and the electricity consumption acquisition terminal;
The position information of the electric energy meter and the electricity collection terminal is geographic position information, and for low-voltage electricity users in high-rise residential areas, the position information of the electric energy meter and the electricity collection terminal is required to be embodied into a floor number and a portal number, so that maintenance personnel can find specific electric energy meters and electricity collection terminals to be maintained according to the geographic position information.
S300, displaying the positions of each electric energy meter and each electricity acquisition terminal in the form of dots in the electronic map, displaying the working states of each electric energy meter and each electricity acquisition terminal, wherein the dots are green in normal operation, and red in abnormal operation.
S400, establishing maintenance sites, wherein each maintenance site comprises a plurality of maintenance personnel, establishing communication connection between the maintenance site and the information management platform, and storing the position information of the maintenance site in the information management platform.
The maintenance site is a service point for performing fault maintenance and other works on the electric energy meter and the electricity acquisition terminal, and the two-way communication between the maintenance site and the information management platform can be realized through the GPRS wireless communication technology.
The step S400 includes the following sub-steps:
And S410, dividing the maintenance areas of the electric energy meters and the electricity acquisition terminals by taking administrative areas as division principles, and further dividing the maintenance areas into a plurality of maintenance units according to the quantity and the density of the distribution positions of the electric energy meters and the electricity acquisition terminals in each maintenance area, wherein each maintenance unit corresponds to one maintenance station.
The more the electric energy meters and the electricity utilization acquisition terminals in the maintenance area are, the more the number of the divided maintenance units are, the more the distribution positions of the electric energy meters and the electricity utilization acquisition terminals are dense, and the smaller the geographic area of the corresponding maintenance units is; therefore, the number of the electric energy meters and the electricity acquisition terminals in each maintenance unit is approximately the same, and the maintenance workload of each maintenance site is balanced.
S500, issuing maintenance tasks to the maintenance site.
The step S500 includes the following sub-steps:
S510, installing a maintenance APP at the mobile terminal of each maintenance person, and providing a key for logging in and accessing the information management platform for the maintenance site.
Maintenance personnel can conveniently access the information management platform by logging in the maintenance APP at the mobile terminal, so that maintenance tasks issued by the information management platform can be conveniently checked and received.
S520, when the maintenance task is issued, the state of the maintenance task is displayed as 'to be processed', after any maintenance personnel at the same maintenance site takes the maintenance task, the state of the maintenance task is displayed as 'in maintenance', and after the maintenance task is completed, the state of the maintenance task is displayed as 'complete maintenance'.
The state of the maintenance task is displayed in real time, and after any maintenance person receives the task, the state of the maintenance task is changed from 'to be processed' to 'in maintenance', so that the waste of human resources caused by repeated acquisition of the execution task by other maintenance persons is prevented.
And S530, when the number of the maintenance tasks received in the same maintenance unit is greater than the number of maintenance personnel of the maintenance unit, judging that the area is in a maintenance saturated state, searching the maintenance units which are adjacent to the maintenance unit and are not in the maintenance saturated state through the information management platform, and sending the maintenance tasks.
So as to better utilize the vacant human resources and improve the maintenance efficiency.
S540, generating a shortest maintenance route according to the positions of the electric energy meter to be maintained, the electricity utilization acquisition terminal and the maintenance site in the maintenance unit, and issuing the shortest maintenance route to the corresponding maintenance site along with a maintenance task.
When the number of electric energy meters and electricity acquisition terminals to be maintained is small, such as not more than 10, the shortest maintenance route can be generated through the TSP algorithm, and when the number of electric energy meters and electricity acquisition terminals to be maintained exceeds 10, the Dijkstra algorithm can be used for obtaining the shortest maintenance route.
S600, positioning maintenance personnel in real time in the maintenance process, comparing the actual path of the maintenance personnel with the shortest maintenance path recommended by the information management platform, and if the comparison result is wrong, sending an alarm signal by the position management platform so as to remind the maintenance personnel of the path deviation;
and re-planning the shortest maintenance route for the maintainer according to the position of the maintainer, the residual electric energy meter to be maintained and the geographic position of the electricity acquisition terminal to be maintained.
The shortest maintenance route is formed by sequentially arranging and combining the position information of the electric energy meter to be maintained and the position information of the electricity acquisition terminal, so that when the actual maintenance route is compared with the recommended shortest maintenance route, the position information of the electric energy meter to be maintained and the position information of the electricity acquisition terminal are matched according to the actual moving route of maintenance personnel, and if the matched position information sequence does not accord with the position information sequence of the shortest maintenance route, the route deviation is judged.
S700, numbering each electric energy meter and each electricity consumption acquisition terminal, and establishing a maintenance record meter in an information management platform by taking the electric energy meter numbers and the electricity consumption acquisition terminal numbers as keywords;
After maintenance personnel finish maintenance, uploading maintenance logs to an information management platform, wherein the content of the maintenance logs comprises the maintained electric energy meter, the number of the electricity acquisition terminal, the corresponding fault reasons, the corresponding repairing method and the corresponding repairing result, and storing the maintenance logs in the maintenance record table.
The contents of the maintenance record list comprise all electric energy meter numbers, electricity acquisition terminal numbers, maintenance time of each maintenance and maintenance logs corresponding to each maintenance time so as to provide reference for subsequent maintenance operation.
Referring to fig. 3, based on the same inventive concept, the embodiment of the application also discloses a position information management system of an electric energy meter and an acquisition terminal, which comprises the electric energy meter for measuring the electricity consumption of a user, the electricity acquisition terminal which is in communication connection with the electric energy meter and is used for acquiring and storing the data of the electric energy meter, and the information management platform 1 which is in communication connection with the electricity acquisition terminal and is used for managing the data of the electric energy meter; the information management platform 1 includes:
The position storage module 11 is used for storing geographic position information of the electricity acquisition terminal, the electric energy meter and the maintenance site;
a position display module 12 for displaying the geographical positions of the electricity collection terminal and the electric energy meter in the form of an electronic map;
The position inquiry module 13 is used for jumping from the position display module 12 to the position storage module 11 so as to call out the geographical position information of the appointed electricity acquisition terminal, the electric energy meter and the maintenance site;
The state display module 14 is used for displaying the working states of each ammeter and the electricity acquisition terminal on the electronic map;
The route generation module 15 is configured to generate a shortest maintenance route according to a position of the electric energy meter to be maintained, a position of the electricity collection terminal to be maintained, and a position of the maintenance site;
A route location module 16 for tracking and locating the position of maintenance personnel in real time;
a route comparison module 17 for comparing the actual maintenance route of the maintenance personnel with the shortest maintenance route recommended by the information management platform 1;
an alarm module 18, configured to send an alarm signal when a maintenance route of a maintenance person deviates, so as to remind the maintenance person of the deviation of the route;
The task status display module 19 is configured to display status of the maintenance task in real time.
Based on the same inventive concept, an embodiment of the present application discloses a computer-readable storage medium storing a computer program capable of being loaded by a processor and executing any one of the methods of steps S100-S700 described above.
The computer-readable storage medium described above includes, for example: a usb disk, a removable hard disk, a Read-only memory (ROM), a random access memory (RandomAccessMemory, RAM), a magnetic disk, or an optical disk, or other various media capable of storing program codes.
It will be apparent to those skilled in the art that, for convenience and brevity of description, only the above-described division of the functional modules is illustrated, and in practical application, the above-described functional allocation may be performed by different functional modules according to needs, i.e. the internal structure of the apparatus is divided into different functional modules to perform all or part of the functions described above.
In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices, and methods may be implemented in other manners.
In addition, each functional unit in the embodiments of the present application may be integrated in one processing unit, or each unit may exist alone physically, or two or more units may be integrated in one unit. The integrated units may be implemented in hardware or in software functional units.
The integrated units, if implemented in the form of software functional units and sold or used as stand-alone products, may be stored in a computer readable storage medium. Based on such understanding, the technical solution of the present application may be embodied in essence or a part contributing to the prior art or all or part of the technical solution in the form of a software product stored in a storage medium, including several instructions for causing a computer device (which may be a personal computer, a server, or a network device, etc.) or a processor (processor) to execute all or part of the steps of the method according to the embodiments of the present application. And the aforementioned storage medium includes: various media capable of storing program codes, such as a U disk, a mobile hard disk, a read-only memory, a random access memory, a magnetic disk or an optical disk.
The embodiments of the present invention are all preferred embodiments of the present invention, and are not intended to limit the scope of the present invention in this way, therefore: all equivalent changes in structure, shape and principle of the invention should be covered in the scope of protection of the invention.

Claims (9)

1. An electric energy meter and a position information management method of an acquisition terminal are characterized in that: the method comprises the following steps:
Installing an electric energy meter for an electricity user, connecting the electric energy meter to an electricity acquisition terminal in a communication way, building a position information management platform, and then building communication connection between the electricity acquisition terminal and the information management platform;
storing the position information of the electric energy meter and the electricity acquisition terminal in an information management platform, and drawing an electronic map according to the geographic positions of the electric energy meter and the electricity acquisition terminal;
Displaying the positions of each electric energy meter and each electricity acquisition terminal in the form of dots in an electronic map, displaying the working states of each electric energy meter and each electricity acquisition terminal, wherein the dots are green in normal operation, and red in abnormal operation;
establishing maintenance sites, wherein each maintenance site comprises a plurality of maintenance personnel, establishing communication connection between the maintenance site and an information management platform, and storing the position information of the maintenance site in the information management platform;
issuing maintenance tasks to maintenance sites;
The step of issuing maintenance tasks to the maintenance site further comprises the following steps:
Generating a shortest maintenance route according to the positions of the electric energy meter to be maintained, the electricity acquisition terminal and the maintenance site in the maintenance unit, and issuing the shortest maintenance route to the corresponding maintenance site along with a maintenance task; the shortest maintenance route is formed by sequentially arranging and combining the position information of the electric energy meter to be maintained and the electricity acquisition terminal;
The method comprises the steps that maintenance personnel are positioned in real time in the maintenance process, the actual path of the maintenance personnel is compared with the shortest maintenance path recommended by an information management platform, when the actual maintenance path is compared with the recommended shortest maintenance path, the position information of an electric energy meter to be maintained and an electricity acquisition terminal is matched according to the actual moving path of the maintenance personnel, and if the matched position information sequence does not accord with the position information sequence of the shortest maintenance path, the path deviation is judged; if the comparison result is wrong, the position management platform sends out an alarm signal to remind maintenance personnel of route deviation.
2. The method for managing the position information of the electric energy meter and the acquisition terminal according to claim 1, wherein the method comprises the following steps: the method comprises the following sub-steps of:
And dividing the maintenance area of the electric energy meter and the electricity acquisition terminal by taking the administrative area as a division principle, and further dividing the maintenance area into a plurality of maintenance units according to the quantity of the electric energy meter and the electricity acquisition terminal in each maintenance area and the density of the distribution positions, wherein each maintenance unit corresponds to one maintenance station.
3. The method for managing the position information of the electric energy meter and the acquisition terminal according to claim 1, wherein the method comprises the following steps: the step of issuing maintenance tasks to the maintenance site further comprises the following steps:
installing a maintenance APP at the mobile terminal of each maintenance personnel, and providing a key for logging in and accessing the information management platform to a maintenance site.
4. The method for managing the position information of the electric energy meter and the acquisition terminal according to claim 1, wherein the method comprises the following steps: the step of issuing maintenance tasks to the maintenance site further comprises the following steps:
when the maintenance task is issued, the state of the maintenance task is displayed as 'to be processed', after any maintenance personnel at the same maintenance site obtains the maintenance task, the state of the maintenance task is displayed as 'in maintenance', and after the maintenance task is completed, the state of the maintenance task is displayed as 'complete maintenance'.
5. The method for managing the position information of the electric energy meter and the acquisition terminal according to claim 1, wherein the method comprises the following steps: the step of issuing maintenance tasks to the maintenance site further comprises the following sub-steps:
When the number of the maintenance tasks received in the same maintenance unit is larger than the number of maintenance personnel of the maintenance unit, the maintenance unit is judged to be in a maintenance saturated state, at the moment, the maintenance unit which is adjacent to the maintenance unit and is not in the maintenance saturated state is searched through the information management platform, and the maintenance tasks are sent.
6. The method for managing the position information of the electric energy meter and the acquisition terminal according to claim 1, wherein the method comprises the following steps: the method also comprises the following steps:
and re-planning the shortest maintenance route for the maintainer according to the position of the maintainer, the residual electric energy meter to be maintained and the geographic position of the electricity acquisition terminal to be maintained.
7. The method for managing the position information of the electric energy meter and the acquisition terminal according to claim 1, wherein the method comprises the following steps: the method also comprises the following steps:
numbering each electric energy meter and each electricity consumption acquisition terminal, and establishing a maintenance record meter in the information management platform by taking the number of the electric energy meter and the number of the electricity consumption acquisition terminal as a keyword;
After maintenance personnel finish maintenance, uploading maintenance logs to an information management platform, wherein the content of the maintenance logs comprises the maintained electric energy meter, the number of the electricity acquisition terminal, the corresponding fault reasons, the corresponding repairing method and the corresponding repairing result, and storing the maintenance logs in the maintenance record table.
8. The utility model provides a position information management system of electric energy meter and acquisition terminal, is applied to an electric energy meter and acquisition terminal's position information management method of claim 1, characterized in that: the system comprises an electric energy meter for measuring the electricity consumption of a user, an electricity consumption acquisition terminal which is in communication connection with the electric energy meter and is used for acquiring and storing data of the electric energy meter, and an information management platform (1) which is in communication connection with the electricity consumption acquisition terminal and is used for managing the data of the electric energy meter; the information management platform (1) comprises:
The position storage module (11) is used for storing geographic position information of the electricity acquisition terminal, the electric energy meter and the maintenance site;
the position display module (12) is used for displaying the geographic positions of the electricity acquisition terminal and the electric energy meter on the electronic map;
The position inquiry module (13) is used for jumping from the position display module (12) to the position storage module (11) so as to call out the geographical position information of the appointed electricity acquisition terminal, the electric energy meter and the maintenance site;
the state display module (14) is used for displaying the working states of each ammeter and the electricity acquisition terminal on the electronic map;
the route generation module (15) is used for generating the shortest maintenance route according to the position information of the electric energy meter to be maintained, the position information of the power acquisition terminal to be maintained and the position information of the maintenance site;
a route location module (16) for tracking and locating the position of maintenance personnel in real time;
A route comparison module (17) for comparing the actual maintenance route of the maintenance personnel with the shortest maintenance route recommended by the information management platform (1);
The alarm module (18) is used for sending an alarm signal when the maintenance route of the maintenance personnel deviates, and reminding the maintenance personnel of the deviation of the route;
And the task state display module (19) is used for displaying the state condition of the maintenance task in real time.
9. A computer-readable storage medium, characterized by: a computer program being stored which can be loaded by a processor and which performs the method according to any one of claims 1 to 7.
CN202011122776.2A 2020-10-20 2020-10-20 Position information management method, system and storage medium of electric energy meter and acquisition terminal Active CN112285397B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011122776.2A CN112285397B (en) 2020-10-20 2020-10-20 Position information management method, system and storage medium of electric energy meter and acquisition terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011122776.2A CN112285397B (en) 2020-10-20 2020-10-20 Position information management method, system and storage medium of electric energy meter and acquisition terminal

Publications (2)

Publication Number Publication Date
CN112285397A CN112285397A (en) 2021-01-29
CN112285397B true CN112285397B (en) 2024-08-06

Family

ID=74423110

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011122776.2A Active CN112285397B (en) 2020-10-20 2020-10-20 Position information management method, system and storage medium of electric energy meter and acquisition terminal

Country Status (1)

Country Link
CN (1) CN112285397B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117032745B (en) * 2023-07-19 2024-07-23 零束科技有限公司 OTA-based vehicle software upgrading method, device and related equipment
CN117578740B (en) * 2024-01-15 2024-05-31 泉州市鑫盛电气设备有限公司 Digital intelligent electricity management system and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203632354U (en) * 2013-10-14 2014-06-04 国网重庆市电力公司客户服务中心 Electricity consumption information acquisition abnormity positioning system in electric network
CN109087497A (en) * 2018-11-12 2018-12-25 贵州电网有限责任公司 A kind of low-voltage collecting meter reading O&M whole process managing and control system and its application method
CN111095311A (en) * 2019-10-21 2020-05-01 深圳天源迪科信息技术股份有限公司 Charging pile information online management method and system, electronic device and storage medium
CN111860948A (en) * 2020-06-12 2020-10-30 国网浙江省电力有限公司电力科学研究院 Intelligent operation and maintenance path planning method for electric power

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101354408B (en) * 2008-07-31 2010-08-18 南京能瑞自动化设备有限公司 Electric energy acquisition and operation management system and method based on platform zone centralized service terminal
CN102608962B (en) * 2011-12-09 2016-05-11 绍兴电力局 A kind of power information collecting device automatic maintenance method from bottom to top
CN104933883A (en) * 2015-06-26 2015-09-23 北京智行者科技有限公司 Vehicle monitoring and vehicle guiding method based on mobile phone client, and system thereof
CN105072187A (en) * 2015-08-17 2015-11-18 江苏省电力公司镇江供电公司 Star network topological structure and distribution network rush repair method based on star network topological structure
CN106772499A (en) * 2016-11-16 2017-05-31 湖南华烨智能通信技术股份有限公司 A kind of method and system of automatic acquisition platform area topological diagram
CN106779421A (en) * 2016-12-21 2017-05-31 国网上海市电力公司 A kind of electric energy meter collection operation management system based on GPS location
CN106680759A (en) * 2017-01-05 2017-05-17 云南电网有限责任公司电力科学研究院 Operational monitoring estimation method and apparatus for gateway metering equipment
CN110390740A (en) * 2018-04-20 2019-10-29 成都华立达电力信息系统有限公司 A kind of intelligent electricity consumption information acquisition termination rack management system and method
CN109284891B (en) * 2018-08-01 2021-06-08 大连理工大学 Charging pile maintenance scheduling method based on time-space index
CN110322027A (en) * 2019-07-04 2019-10-11 南京大学 A kind of domestic sewage in rural areas Internet of Things management platform
WO2021077249A1 (en) * 2019-10-21 2021-04-29 深圳天源迪科信息技术股份有限公司 Online charging pile operation management method, system, electronic device, and storage medium
CN111275315A (en) * 2020-01-17 2020-06-12 重庆国翰能源发展有限公司 Charging pile maintenance scheduling method and system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203632354U (en) * 2013-10-14 2014-06-04 国网重庆市电力公司客户服务中心 Electricity consumption information acquisition abnormity positioning system in electric network
CN109087497A (en) * 2018-11-12 2018-12-25 贵州电网有限责任公司 A kind of low-voltage collecting meter reading O&M whole process managing and control system and its application method
CN111095311A (en) * 2019-10-21 2020-05-01 深圳天源迪科信息技术股份有限公司 Charging pile information online management method and system, electronic device and storage medium
CN111860948A (en) * 2020-06-12 2020-10-30 国网浙江省电力有限公司电力科学研究院 Intelligent operation and maintenance path planning method for electric power

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
智能电表嵌入式软件可维护性度量方法研究;乔舒雅;《硕士电子期刊》;20230315;全文 *

Also Published As

Publication number Publication date
CN112285397A (en) 2021-01-29

Similar Documents

Publication Publication Date Title
CN108564676B (en) Intelligent inspection system and method for hydraulic power plant
CN108053632B (en) Automatic identification system and method for user attribution relation
CN112285397B (en) Position information management method, system and storage medium of electric energy meter and acquisition terminal
CN106355357B (en) Power distribution network fault processing method and information processing system
CN207895677U (en) User attaching relationship automatic recognition system
CN110046834B (en) Workplace harmful gas health risk quantitative evaluation system and evaluation method thereof
CN107727941A (en) Environmentally sensitive areas mobile electromagnetic environment information monitoring management method and system
CN111414446A (en) Land space basic information platform
CN112686649A (en) Construction equipment management system based on artificial intelligence
CN111586729A (en) Three-network signal detection method and system based on metering terminal communication
CN105681469A (en) Mobile terminal used for hydropower station, and data management system and method
CN106908667A (en) Electromagnetic environment mobile monitoring method and system
CN111310969A (en) Unmanned repair analysis and order distribution method based on GIS map
CN107734458A (en) A kind of residential property personnel management methods and system
CN102955981A (en) Position-based assessment system, position-based assessment terminal and position-based assessment method
CN113890188A (en) Oil engine commanding and dispatching system, method and device based on 5G network
CN111105322A (en) Low-voltage power distribution real-time monitoring system
Mamo et al. Power quality indicators
CN115586310A (en) Near-surface carbon concentration monitoring system based on satellite-ground cooperation
CN115224802A (en) Information communication system based on cloud server
CN114660405A (en) Method for rapidly studying and judging fault points of power distribution network based on 5G communication
CN110518578B (en) Bus load prediction method and device, terminal equipment and storage medium
CN111697691B (en) Power distribution network planning monitoring system based on cloud computing
CN115567145B (en) Time correction method and terminal based on power grid multi-source data fusion
CN114638554B (en) Marketing business health index evaluation joint control method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant