CN112227204A - Side span pushing closure construction method for cable-stayed bridge - Google Patents

Side span pushing closure construction method for cable-stayed bridge Download PDF

Info

Publication number
CN112227204A
CN112227204A CN202010788860.1A CN202010788860A CN112227204A CN 112227204 A CN112227204 A CN 112227204A CN 202010788860 A CN202010788860 A CN 202010788860A CN 112227204 A CN112227204 A CN 112227204A
Authority
CN
China
Prior art keywords
side span
beam section
closure
span beam
secondary side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010788860.1A
Other languages
Chinese (zh)
Inventor
杜洪池
马建勇
荆刚毅
施津安
王海海
蒋能世
张毅君
李华清
乔学宁
马志青
郑珍根
梁彬彬
刘群德
彭梓松
温彪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Second Engineering Co Ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN202010788860.1A priority Critical patent/CN112227204A/en
Publication of CN112227204A publication Critical patent/CN112227204A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a side span pushing closure construction method of a cable-stayed bridge, which comprises the following steps: s001: firstly, storing side span beam sections on a side span high support and connecting the side span beam sections into a whole, and hoisting a closure opening secondary side span beam section to a closure opening when a main bridge cantilever is hoisted to a side span closure section; s002: hoisting the closure opening secondary side span beam section in place and then connecting the closure opening secondary side span beam section with the previous beam section, adjusting the closure opening secondary side span beam section elevation to be close to the side span beam section elevation through a tensioning stay cable, adjusting the closure opening secondary side span beam section axis through a chain block, pushing the side span beam section through a pushing device below the side span beam section after the adjustment is in place, and enabling the side span beam section to be sequentially connected with the closure opening secondary side span beam section; s003: and finely adjusting the elevation of the closure opening secondary side span beam section through a screw jack, and connecting the closure opening secondary side span beam section and the side span beam section through a splice plate and a high-strength bolt to complete the closure of the side span of the cable-stayed bridge.

Description

Side span pushing closure construction method for cable-stayed bridge
Technical Field
The invention belongs to the technical field of bridge construction, and particularly relates to a side span pushing closure construction method of a cable-stayed bridge.
Background
With the increasing construction scale of large-span bridges, the cable-stayed bridge is a common bridge type at home and abroad by virtue of the advantages of strong spanning capability, economy and beauty. The side span closure construction is a key process of cable-stayed bridge construction, and the closure precision is of great importance to the influence of the full-bridge quality. At present, the closure method adopted by the cable-stayed bridge in China is greatly influenced by temperature, and the closure precision and the structural stress after closure are difficult to achieve the expected effect.
Disclosure of Invention
In view of the above, the present invention provides a method for constructing a cable-stayed bridge by side span pushing closure, which overcomes the above problems or at least partially solves or alleviates the above problems.
The invention provides a side span pushing closure construction method of a cable-stayed bridge, which is characterized by comprising the following steps of: s001: firstly, storing side span beam sections on a side span high support and connecting the side span beam sections into a whole, and hoisting a closure opening secondary side span beam section to a closure opening when a main bridge cantilever is hoisted to a side span closure section; s002: hoisting the closure opening secondary side span beam section in place and then connecting the closure opening secondary side span beam section with the previous beam section, adjusting the closure opening secondary side span beam section elevation to be close to the side span beam section elevation through a tensioning stay cable, adjusting the closure opening secondary side span beam section axis through a chain block, pushing the side span beam section through a pushing device below the side span beam section after the adjustment is in place, and enabling the side span beam section to be sequentially connected with the closure opening secondary side span beam section; s003: and finely adjusting the elevation of the closure opening secondary side span beam section through a screw jack, and connecting the closure opening secondary side span beam section and the side span beam section through a splice plate and a high-strength bolt to complete the closure of the side span of the cable-stayed bridge.
In step S001: firstly, hoisting the closure opening secondary side span beam section in place, then completing the connection with the previous beam section, wherein one end of the closure opening secondary side span beam section is fixedly connected, the other end is a free end, and the elevation of the closure opening secondary side span beam section is close to that of the side span beam section by adjusting the stay cable.
In step S001, the elevation of the free end of the closure gap secondary side span beam section can be raised by tensioning the stay cable, and the elevation of the free end of the closure gap secondary side span beam section is lowered by tensioning the stay cable of the previous beam section.
In step S002, the two chain blocks are connected to the middle web of the closure opening secondary side span beam section and the side span beam section respectively, and then the two chain blocks are pulled oppositely to make the axes of the closure opening secondary side span beam section and the side span beam section coincide.
In step S002, the connection directions of the two chain blocks cross each other.
In step S002, after the pusher is disposed below the side span beam section, the reaction seat of the pusher is disposed on the rail of the side span high bracket, and the side span beam section is slid by the pusher.
In step S003, a counter-force bracket is connected to each of the middle web of the closure secondary side span and the middle web of the side span, and a screw jack is installed between the two counter-force brackets, so that the closure secondary side span and the side span are driven by the screw jack between the two counter-force brackets to perform elevation adjustment.
In step S003, the two ends of the splice plate are respectively driven into the secondary side span beam section and the side span beam section of the dynamic closure gap by using a punch nail, and finally a high-strength bolt is screwed into the splice plate.
The invention has the beneficial effects that:
the construction method for the side span pushing closure of the cable-stayed bridge is not influenced by temperature during implementation, the closure precision is high, the closure method is simple and convenient to operate, the construction efficiency is high, and the side span closure time is effectively shortened.
Drawings
FIG. 1 is a schematic view of the arrangement of the side span closure construction elevation in the invention;
FIG. 2 is a schematic plan view of the side span closure construction of the present invention;
FIG. 3 is a schematic view of the adjustment of the cross beam section axis of the closure gap minor edge of the present invention;
FIG. 4 is a schematic diagram of fine height adjustment of the closure gap secondary side span beam section.
In the above figures: 1 closing a secondary side span beam section of a closure opening; 2, a side span beam section; 3, a bridge deck crane; 4, stay cables; 5, a high bracket; 6, a pushing device; 7 a middle web plate; 8, pulling a chain block; 9 counter-force corbels; 10 a screw jack; 11, splicing plates; 12 high-strength bolts; and 13 punching the nail.
The invention will be further explained in detail with reference to the drawings and the embodiments;
Detailed Description
Example 1
Referring to fig. 1, fig. 2, fig. 3 and fig. 4, an embodiment of the present invention provides a cable-stayed bridge side span pushing closure construction method, including the following steps: s001: firstly, storing the side span beam section 2 on the side span high support 5 and connecting the side span beam section and the side span high support into a whole, and hoisting the closure opening secondary side span beam section 1 to the closure opening when the main bridge cantilever is hoisted to the side span closure section; s002: the closure opening secondary side span beam section 1 is hoisted in place and then is connected with the previous beam section, the elevation of the closure opening secondary side span beam section 1 is adjusted to be close to that of the side span beam section 2 through a tension stay cable 4, the axis of the closure opening secondary side span beam section 1 is adjusted through a chain block 8, the side span beam section 2 is pushed through a pushing device 6 below the side span beam section 2 after the adjustment is in place, and the side span beam section 2 and the closure opening secondary side span beam section 1 are connected in sequence; s003: and finely adjusting the elevation of the closure opening secondary side span beam section 1 through a screw jack 10, and connecting the closure opening secondary side span beam section 1 and the side span beam section 2 through a splice plate 11 and a high-strength bolt 12 to finish the closure of the side span of the cable-stayed bridge.
After a side span high support 5 is built in advance, a bridge section 2 is stored on the side span high support 5, connection of the side span bridge section 2 is completed according to design and monitoring requirements, when a main bridge cantilever is hoisted to a closure opening secondary side bridge section 1, the closure opening secondary side bridge section 1 is hoisted according to a normal construction flow cantilever, and after the closure opening secondary side bridge section 1 is regulated by a bridge crane 3 to meet the design and monitoring requirements when the main bridge cantilever is hoisted to the closure opening, the closure opening secondary side bridge section is connected with a previous bridge section. The elevation of one end of the closure opening secondary side span beam section 1 at the closure opening is adjusted by tensioning a stay cable 4 of the closure opening secondary side span beam section 1, the deviation of the axis of the closure opening secondary side span beam section 1 is adjusted by a chain block 8, and after the adjustment is in place, the sliding side span beam section 2 is pushed by a pushing device 6 below the side span beam section 2, so that the side span beam section 2 is in direct connection with the closure opening secondary side span beam section 1. The elevation of the closure opening secondary side span beam section 1 is finely adjusted through the screw jack 10, the closure opening secondary side span beam section 1 and the side span beam section 2 can be connected through the splicing plate 11 and the high-strength bolt 12, and the closure of the side span of the cable-stayed bridge is completed. And then, primarily screwing and finally screwing the high-strength bolts 12 of the splicing plates 11 between the webs, welding beam sections, pouring transverse wet joint concrete, and after the wet joint strength meets the design requirement, tensioning the external cables of the closure opening to finish side span closure.
Example 2
Referring to fig. 1, in step S001, the closure secondary-side beam section 1 is hoisted in place and then connected to the previous beam section, at this time, one end of the closure secondary-side beam section 1 is consolidated, and the other end is a free end, and the elevation of the closure secondary-side beam section 1 is made to approach that of the side beam section 2 by adjusting the stay cable 4.
One end of the stay cable 4 is connected to a cable tower of the cable-stayed bridge, and the other end is connected to the closure opening secondary side span beam section 1.
Example 3
Referring to fig. 1, in step S001 based on embodiment 2, the elevation of the free end of the closure secondary-side beam segment 1 can be raised by tensioning the stay cable 4, and the elevation of the free end of the closure secondary-side beam segment 1 can be lowered by tensioning the stay cable 4 of the previous beam segment.
During actual construction, elevation control is performed through the stay cables of the closure opening secondary side span beam section 1 in the second tensioning.
Example 4
Referring to fig. 3, in step S002, two chain blocks 8 are connected to the middle web 7 of the closure opening secondary side span beam section 1 and the side span beam section 2, respectively, and then the two chain blocks 8 are pulled to make the axes of the closure opening secondary side span beam section 1 and the side span beam section 2 coincide with each other.
Two people respectively operate a chain block 8 to respectively draw the secondary side span beam section 1 and the side span beam section 2 of the closure opening close until the axes of the two side span beam sections are overlapped in the horizontal direction.
Example 5
Referring to fig. 1 and 2, in step S002 of the embodiment 5, after the thruster 6 is disposed below the side span beam section 2, the reaction seat of the thruster 6 is disposed on the track of the side span high bracket 5, and the side span beam section 2 is slid by the thruster.
During actual construction, the pushing device 6 is arranged at the position of the diaphragm plate of the side-span beam section 2, the joint of the cushion block and the beam section needs to be fixed, and the cushion block and the beam section are prevented from sliding relatively when being pushed. Meanwhile, a tetrafluoro sliding plate is arranged between the cushion block and the high support 5 rail, so that the friction coefficient is reduced, and the jacking force of the jacking device 6 is reduced during jacking.
Example 6
Referring to fig. 4, on the basis of embodiment 6, in step S003, a reaction bracket 9 is connected to each of the middle web 7 of the closure secondary side span beam segment 1 and the middle web 7 of the side span beam segment 2, and then a screw jack 10 is installed between the two reaction brackets 9, and the closure secondary side span beam segment 1 and the side span beam segment 2 are driven to perform elevation adjustment by being pushed between the two reaction brackets 9 by the screw jack 10.
During actual construction, before the height of the closure secondary side span beam section 1 is finely adjusted, the axis of the beam section and the distance in the bridge direction are adjusted in place, when the vertical height is adjusted, the splice plate 11 on the lower layer of the middle web 7 is installed, the punching nail 13 on one side of the side span beam section 2 is firstly driven in, then the force is applied to the screw jack 10, and the height of the closure secondary side span beam section 2 is adjusted.
Example 7
Referring to fig. 4, in step S003 of embodiment 6, the two ends of the splice plate 11 are respectively driven into the secondary side-span beam segment 1 and the secondary side-span beam segment 2 of the dynamic closure gap by the punch nails 13, and finally the high-strength bolt 12 is screwed into the splice plate 11.
Splice plates 11 are arranged on two sides of a middle web plate 7 of the closure opening secondary side span beam section 1 and the side span beam section 2, the splice plates 11 are matched with bolt holes of the middle web plate 7, and punching nails 13 are driven into two sides of the splice plates 11 after the splice plates 11 are accurately adjusted in place through screw jacks 10, so that high-strength bolts 12 can be connected, all the high-strength bolts 12 are screwed, and the connection of the closure opening secondary side span beam section 1 and the side span beam section 2 is completed. And then, primarily screwing and finally screwing the high-strength bolts 12 of the splicing plates 11 between the webs, welding beam sections, pouring transverse wet joint concrete, and after the wet joint strength meets the design requirement, tensioning the external cables of the closure opening to finish side span closure.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention are included in the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims. The components and structures of the present embodiments that are not described in detail are well known in the art and do not constitute essential structural elements or elements.

Claims (8)

1. A side span pushing closure construction method for a cable-stayed bridge is characterized by comprising the following steps:
s001: firstly, storing a side span beam section (2) on a side span high support (5) and connecting the side span beam section and the side span high support into a whole, and hoisting a closure opening secondary side span beam section (1) to a closure opening when a main bridge cantilever is hoisted to a side span closure section;
s002: the secondary side span beam section (1) of the closure opening is hoisted in place and then is connected with the previous beam section, the elevation of the secondary side span beam section (1) of the closure opening is adjusted to be close to that of the side span beam section (2) through a tension stay cable (4), the axis of the secondary side span beam section (1) of the closure opening is adjusted through a chain block (8), the side span beam section (2) is pushed through a pushing device (6) below the side span beam section (2) after the adjustment is in place, and the side span beam section (2) is sequentially connected with the secondary side span beam section (1) of the closure opening;
s003: the elevation of the closure opening secondary side span beam section (1) is finely adjusted through a screw jack (10), and the closure opening secondary side span beam section (1) and the side span beam section (2) are connected through a splicing plate (11) and a high-strength bolt (12), so that the closure of the side span of the cable-stayed bridge is completed.
2. The cable-stayed bridge side-span pushing closure construction method according to claim 1, characterized in that in step S001, the closure secondary side-span beam section (1) is hoisted in place and then connected with the previous beam section, at this time, one end of the closure secondary side-span beam section (1) is consolidated, the other end is a free end, and the elevation of the closure secondary side-span beam section (1) is close to that of the side-span beam section (2) by adjusting a stay cable.
3. The cable-stayed bridge side span pushing closure construction method according to claim 2, characterized in that in step S001, the elevation of the free end of the closure opening secondary side span beam section (1) can be raised by tensioning the stay cable (4), and the elevation of the free end of the closure opening secondary side span beam section (1) is lowered by releasing the stay cable (4) of the previous beam section.
4. The side span pushing closure construction method of the cable-stayed bridge according to claim 1, wherein in step S002, the closure opening secondary side span beam section (1) and the middle web plate (7) of the side span beam section (2) are respectively connected through two chain blocks (8), and then the two chain blocks (8) are oppositely pulled to make the axis of the closure opening secondary side span beam section (1) coincide with the axis of the side span beam section (2).
5. The cable-stayed bridge side span pushing closure construction method according to claim 4, characterized in that in step S002, the connection directions of the two chain blocks (8) are crossed with each other.
6. The cable-stayed bridge side span jacking closure construction method according to claim 1, characterized in that in step S002, after the jacking device (6) is arranged below the side span beam section (2), the reaction seat of the jacking device (6) is arranged on the track of the side span high bracket (5), and the side span beam section (2) is made to slide by the jacking device.
7. The cable-stayed bridge side span jacking closure construction method according to claim 1, characterized in that in step S003, a reaction bracket (9) is respectively connected to the middle web (7) of the closure secondary side span beam section (1) and the middle web (7) of the side span beam section (2), a screw jack (10) is installed between the two reaction brackets (9), and the closure secondary side span beam section (1) and the side span beam section (2) are driven to perform elevation adjustment by jacking the screw jack (10) between the two reaction brackets (9).
8. The side span pushing closure construction method of the cable-stayed bridge according to claim 7, wherein in step S003, the two ends of the splice plate (11) are respectively driven into the secondary side span beam section (1) and the side span beam section (2) of the dynamic closure opening by using the punch nails (13), and finally the high-strength bolt (12) is screwed into the splice plate (11).
CN202010788860.1A 2020-08-07 2020-08-07 Side span pushing closure construction method for cable-stayed bridge Pending CN112227204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010788860.1A CN112227204A (en) 2020-08-07 2020-08-07 Side span pushing closure construction method for cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010788860.1A CN112227204A (en) 2020-08-07 2020-08-07 Side span pushing closure construction method for cable-stayed bridge

Publications (1)

Publication Number Publication Date
CN112227204A true CN112227204A (en) 2021-01-15

Family

ID=74116841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010788860.1A Pending CN112227204A (en) 2020-08-07 2020-08-07 Side span pushing closure construction method for cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN112227204A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113255039A (en) * 2021-05-26 2021-08-13 中铁大桥勘测设计院集团有限公司 Method for determining main beam closure opening of steel truss girder cable-stayed suspension cable cooperation system bridge
CN113356064A (en) * 2021-06-11 2021-09-07 中交二公局第二工程有限公司 Mid-span closure-section-free pushing closure construction method for three-tower cable-stayed bridge

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101117790A (en) * 2007-08-22 2008-02-06 中铁大桥局股份有限公司 Closure method of large-span continuous steel truss arch
JP2009144410A (en) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd Pc bridge closure method
CN101525866A (en) * 2009-04-17 2009-09-09 中铁大桥局股份有限公司 Multiple girder steel beam compel closure technique using deviation of temporary rest pier
CN101608433A (en) * 2009-07-07 2009-12-23 中铁大桥勘测设计院有限公司 The stayed-cable construction method of long-span concrete beam bridge
CN101736697A (en) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 Construction method for pushing and furling complete bracket of steel box girders
CN110409316A (en) * 2019-08-15 2019-11-05 中交路桥华南工程有限公司 End bay closure construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101117790A (en) * 2007-08-22 2008-02-06 中铁大桥局股份有限公司 Closure method of large-span continuous steel truss arch
JP2009144410A (en) * 2007-12-13 2009-07-02 Central Nippon Expressway Co Ltd Pc bridge closure method
CN101525866A (en) * 2009-04-17 2009-09-09 中铁大桥局股份有限公司 Multiple girder steel beam compel closure technique using deviation of temporary rest pier
CN101608433A (en) * 2009-07-07 2009-12-23 中铁大桥勘测设计院有限公司 The stayed-cable construction method of long-span concrete beam bridge
CN101736697A (en) * 2009-12-15 2010-06-16 中交路桥华北工程有限公司 Construction method for pushing and furling complete bracket of steel box girders
CN110409316A (en) * 2019-08-15 2019-11-05 中交路桥华南工程有限公司 End bay closure construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
由瑞凯等: "《沌口长江公路大桥主桥中跨顶推辅助合龙施工技术》", 《世界桥梁》 *
由瑞凯等: "《沌口长江公路大桥主桥中跨顶推辅助合龙施工技术》", 《世界桥梁》, vol. 46, no. 3, 28 May 2018 (2018-05-28), pages 31 - 35 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113255039A (en) * 2021-05-26 2021-08-13 中铁大桥勘测设计院集团有限公司 Method for determining main beam closure opening of steel truss girder cable-stayed suspension cable cooperation system bridge
CN113255039B (en) * 2021-05-26 2022-04-29 中铁大桥勘测设计院集团有限公司 Method for determining main beam closure opening of steel truss girder cable-stayed suspension cable cooperation system bridge
CN113356064A (en) * 2021-06-11 2021-09-07 中交二公局第二工程有限公司 Mid-span closure-section-free pushing closure construction method for three-tower cable-stayed bridge

Similar Documents

Publication Publication Date Title
CN102162774B (en) Steel-structure distribution-girder-type double-track whole opening box girder static load test device and construction method thereof
CN108978434B (en) Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge
CN112227204A (en) Side span pushing closure construction method for cable-stayed bridge
CN110761168A (en) Design and construction method of cable-first beam-second self-anchored suspension bridge
CN110205938B (en) Steel pipe arch installation method of through beam-arch combination bridge
CN109972494B (en) Design and construction method of large-segment hoisting self-anchored suspension bridge with hinges between segments
CN105862597B (en) A kind of multiple-piece composite beam bridge top and the bottom monolithic construction construction method
CN108867391A (en) A kind of construction of tubular arch and paving frame parallel operations construction method
CN111764282A (en) Rigid suspension cable stiffening steel truss bridge construction method based on inclined pull buckling hanging method
CN203768810U (en) Prefabricated bridge deck space steel pipe concrete truss combined beam
CN113481826A (en) Prefabricated assembled corrugated steel web combination box girder
CN111455874A (en) Construction method for overlong side span straight line segment of high pier of corrugated steel web PC bridge
CN103147405B (en) Method for erecting steel girder of cable-stayed bridge with diagonal main trusses
CN102493331B (en) Structure capable of realizing large-span V-shaped pier continuous rigid frame bridge and construction process thereof
CN112922210B (en) Connecting device for self-resetting anti-side frame and floor slab
CN212426753U (en) Tooth block pull rod combined cable tower anchoring structure of cable-stayed bridge
CN111101434B (en) Cable-stayed bridge with tensioned midspan girder
CN209568372U (en) A kind of interim articulated structure of suspension bridge stiffened steel girder
CN210766431U (en) Steel arch rib pushing system
CN103205930A (en) Structure for continuous transformation of existing simply supported hollow slab girder bridge and construction method of structure
CN111877168B (en) Torsion correction method for lattice type steel main beam of combined cable-stayed bridge
CN111719407B (en) Stay cable and concrete bridge tower anchoring structure of pre-buried steel plate
CN202744960U (en) Large-span steel truss suspension bridge closure device
CN105926454B (en) In large span high pier prestressed concrete box girder continuous rigid frame bridge across pushing method and its device
CN113356064A (en) Mid-span closure-section-free pushing closure construction method for three-tower cable-stayed bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210115

RJ01 Rejection of invention patent application after publication