JP2009144410A - Pc bridge closure method - Google Patents

Pc bridge closure method Download PDF

Info

Publication number
JP2009144410A
JP2009144410A JP2007322649A JP2007322649A JP2009144410A JP 2009144410 A JP2009144410 A JP 2009144410A JP 2007322649 A JP2007322649 A JP 2007322649A JP 2007322649 A JP2007322649 A JP 2007322649A JP 2009144410 A JP2009144410 A JP 2009144410A
Authority
JP
Japan
Prior art keywords
web
bridge
construction
closing
floor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007322649A
Other languages
Japanese (ja)
Inventor
Keiichi Aoki
圭一 青木
Naoki Hagiwara
直樹 萩原
Akio Kasuga
昭夫 春日
Yoshihiko Taira
喜彦 平
Takeshi Hirose
毅 廣瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Central Nippon Expressway Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Central Nippon Expressway Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd, Central Nippon Expressway Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2007322649A priority Critical patent/JP2009144410A/en
Publication of JP2009144410A publication Critical patent/JP2009144410A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a PC bridge closure method which can shorten the construction period by enhancing construction efficiency in a cantilever erection method, even in the case of any bridge type and even if the front of an abutment has any terrain. <P>SOLUTION: In this first PC bridge closure method, a difference between temperatures of upper and lower floor slabs (21 and 22) of a girder section (2) already cantilevered is set small; deflection of an overhanging end (23) is adjusted; and a web (1) is erected and fixed on a closure section (6) before the construction of floor slab concrete. In the first PC bridge closure method, the web (1) is erected and fixed on the closure portion (6) before the construction of the floor slab concrete, and an auxiliary member (23), which is brought into close contact with regions facing each other across the closure portion, is installed above the web. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、片持ち式でブロックを順次張り出して橋梁を構築する張出し架設工法で構築されるPC橋の閉合方法に関するものである。   The present invention relates to a PC bridge closing method constructed by an overhanging construction method in which a bridge is constructed by sequentially projecting blocks in a cantilever manner.

橋脚から片持ち式でブロックを順次張出して橋梁を構築する張出し架設工法は、以前から実施されている。この張出し架設工法における橋脚間の橋梁架設作業は、閉合部(隣接する橋脚からそれぞれ張り出されたブロックの張出し端部が最終的に結合される部分)の施工により終了となるが、この閉合部の施工作業には、吊り支保工設備が必要となる。そこで、特開昭63−284304号公報(特許文献1)に開示されている施工方法のように、閉合部の下側から吊り支保工設備を設置する。   The overhang construction method of building a bridge by sequentially overhanging blocks from the pier in a cantilever manner has been practiced. The bridge erection work between the piers in this overhanging construction method is completed by the construction of the closing part (the part where the overhanging ends of the blocks protruding from the adjacent piers are finally joined). For this construction work, suspension support facilities are required. Therefore, as in the construction method disclosed in Japanese Patent Laid-Open No. 63-284304 (Patent Document 1), a suspension support facility is installed from below the closing portion.

ただし、急峻な地形などでは閉合部の下側から吊り支保工設備を設置することはできない。そこで、そのような場合には、特開2000−45230号公報(特許文献2)に開示されている閉合方法のように、ブロックの張り出しに使用された架設作業車を使用して、吊り支保工を設置することになる。
特開昭63−284304号公報 特開2000−045230号公報
However, in the case of steep terrain, the suspension support facility cannot be installed from below the closed part. Therefore, in such a case, as shown in Japanese Patent Application Laid-Open No. 2000-45230 (Patent Document 2), a suspension work is performed using an erection work vehicle used for projecting a block. Will be installed.
JP 63-284304 A JP 2000-045230 A

しかしながら、上記吊り支保工を設置する場合、橋梁形式によってはその規模が非常に大きくなり、施工日数が増加する、または工事費が増大するということがあった。更に、橋脚から張出し施工した桁部は橋台または隣接する桁部にも接合されることとなるが、この橋台等前の地形が急峻であると、接合作業に必要となる場所打ち支保工の施工が困難となる。そのような場合、深礎杭などによる中間支点を設置したり、或いは大型架設材を使用する等といった施工方法が考えられるが、このような施工方法も、やはり施工日数が増加する、または工事費が増大するという問題があった。   However, when the above suspension support is installed, the scale of the bridge becomes very large depending on the type of bridge, which increases the number of construction days or increases the construction cost. In addition, the girder part that is overhanged from the pier will be joined to the abutment or the adjacent girder part, but if the terrain in front of this abutment is steep, construction of the cast-in-place support work required for the joining work It becomes difficult. In such a case, a construction method such as installing an intermediate fulcrum such as a deep foundation pile or using a large construction material can be considered, but this construction method also increases the number of construction days or construction costs. There was a problem that increased.

そこで、本発明は、どのような橋梁形式であっても、また、橋台前がどのような地形であっても、張出し架設工法における施工効率の向上を図り工期を短縮できる、PC橋の閉合方法を提供することを目的とする。   Therefore, the present invention provides a PC bridge closing method capable of improving the construction efficiency in the overhanging construction method and shortening the construction period regardless of the type of bridge and the topography of the abutment. The purpose is to provide.

本発明に係る第一のPC橋の閉合方法では、既に張出し施工された桁部における上下床版の温度差を小さくし、張出し端部におけるたわみを調整し、閉合部に、該ウェブを、床版コンクリートの施工を行う前に架設固定する。   In the first method for closing a PC bridge according to the present invention, the temperature difference between the upper and lower floor slabs in the already-extended girder portion is reduced, the deflection at the overhang end is adjusted, and the web is placed on the closing portion. Install and fix the plate concrete before construction.

本発明において、上下床版の温度差は、自然の気温変化によることなく人為的に制御する。例えば、既に施工された主桁部における上床版の表面に散水をすることにより、温度差を制御することができる。   In the present invention, the temperature difference between the upper and lower floor slabs is artificially controlled without being caused by a natural temperature change. For example, the temperature difference can be controlled by watering the surface of the upper floor slab in the already installed main girder.

張出し端部とは、橋脚から張出し架設された桁部の自由端を意味する。閉合部は、張出し端部同士の間の他、張出し端部と端支点部または橋脚頭部の間も含まれる。端支点部とは、ブロックの張り出しが行われていない橋台に、橋脚から張出し架設された桁部の自由端を接合するために設けられた部分を意味する。また、橋脚頭部とは、橋脚の上部に設けられた、ブロック張り出し用の部位を意味する。   The overhang end means the free end of the girder extending over the bridge pier. The closing portion includes not only between the overhanging end portions but also between the overhanging end portion and the end fulcrum portion or the pier head portion. The end fulcrum portion means a portion provided for joining a free end of a girder portion extending from the pier to an abutment where no block is extended. Further, the pier head means a block overhanging portion provided at the upper part of the pier.

ウェブとは、ブロックにおいて鉛直方向を支持する部材であり、波形鋼板が好適である。架設固定とは、ウェブが、施工段階にある橋梁の構造材をなす程度まで、接合することを意味する。従来、ウェブは、上下床版コンクリートが打設施工された段階で橋梁の構造材となっていたが、本発明においては、床版コンクリートが打設施工される前に、橋梁の構造材をなすことになる。ウェブの構成材として波形鋼板を使用する場合、そのの接合は、ウェブの溶接やボルト締め等の方法で行うことができる。また、複数のブロックにわたって架設する場合には、添接板により連続化させてもよい。   The web is a member that supports the vertical direction in the block, and a corrugated steel plate is preferable. The erection and fixing means that the web is joined to the extent that it forms the structural material of the bridge in the construction stage. Conventionally, the web has become a structural material for the bridge when the upper and lower floor slab concrete has been cast. However, in the present invention, before the floor slab concrete is cast, the web is made of the structural material for the bridge. It will be. When a corrugated steel plate is used as a web component, the joining can be performed by a method such as web welding or bolting. Moreover, when installing over several blocks, you may make it continuous by an attachment board.

また、ウェブを構成する波形鋼板には、その上下に補剛材(フランジ)を備えておくことが好ましい。   Moreover, it is preferable to provide the corrugated steel plate which comprises a web with the stiffener (flange) on the upper and lower sides.

更にまた、該閉合部に架設固定された該ウェブを使用して吊支保工を設置してもよい。   Furthermore, you may install a suspension support using this web erected and fixed to this closing part.

本発明に係る第二のPC橋の閉合方法では、閉合部に、床版コンクリートを施工する前に架設固定し、該ウェブの上方に、該閉合部を挟んで対向する部位に密接する補助部材を設置する。   In the second PC bridge closing method according to the present invention, the auxiliary member is installed and fixed to the closing portion before the floor slab concrete is constructed, and is in close contact with the portion facing the closing portion sandwiched above the web. Is installed.

本発明に係る第一のPC橋の閉合方法によれば、ウェブを構造材として利用することにより、張出し施工長が短い橋脚を有する橋梁形式の場合や、橋台前の地形が急峻な場合であっても、橋梁架設作業全体の施工効率を向上させ、工期短縮を図ることができる。   According to the first PC bridge closing method according to the present invention, the web is used as a structural material, and the bridge type has a short pier with a short overhang construction length or the topography in front of the abutment is steep. However, it is possible to improve the construction efficiency of the entire bridge construction work and shorten the construction period.

より具体的には、例えば、橋台前の地形が急峻な場合は、梁側から見て橋台の手前に設けられた橋脚(手前橋脚という)から張出し施工した桁部の張出し端部と、橋台に設けられた端支点部の間の閉合部に、ウェブを、床版コンクリートの施工を行う前に架設固定する。すると、架設固定されたウェブを使用してそこから型枠支保工を直接吊った状態で、上下床版コンクリートの施工を行うことができる。従って、張出し端部と端支点部との間に必要とされる大がかりな梁材やガーダーが不要となり、橋台の前が急峻な場合であっても、工期短縮を図ることができる。   More specifically, for example, when the terrain in front of the abutment is steep, the overhanging end of the girder that is overhanging from the pier (in front of the abutment) provided in front of the abutment as viewed from the beam side, and the abutment The web is installed and fixed to the closing part between the provided end fulcrum parts before the floor slab concrete is constructed. Then, it is possible to construct the upper and lower floor slab concrete in a state where the formwork supporting work is directly suspended from the erected and fixed web. Accordingly, a large beam material or girder required between the overhanging end portion and the end fulcrum portion is unnecessary, and the construction period can be shortened even when the front of the abutment is steep.

なお、一般的な橋梁の桁は、寒暖差により鉛直方向と水平方向(橋軸方向)に変形するが、張出し端部と端支点部の間(側径間)や張出し端部の間(中央閉合部)などで、波形鋼板などを架設固定するための仮接合を行うと、桁の変位は拘束され仮接合部分に力が伝わり応力を発生させる。そして、その応力が許容応力を超えると、仮接合部分は壊れることになる。そのため、ウェブを架設固定する作業を安全に完了させるためには、仮接合から本接合完了までの間、仮接合部分に発生する2次力を如何に発生させないか、或いは発生させる量を少なくするかが重要となる。   General bridge girders are deformed in the vertical and horizontal directions (bridge axis direction) due to differences in temperature, but between the overhang end and the end fulcrum (between the side diameters) and between the overhang ends (center When temporary joining for erection and fixing of corrugated steel sheets or the like is performed at a closing portion), the displacement of the girders is restrained, and force is transmitted to the temporary joining portion to generate stress. And if the stress exceeds allowable stress, a temporary joined part will be broken. Therefore, in order to safely complete the work of erection and fixing the web, the secondary force generated in the temporary joining portion is not generated or the amount generated is reduced from the temporary joining to the completion of the main joining. Is important.

通常、張出し架設の段階では、引張り力の付与された鋼線が上床版に配置されるため、たわみの発生した桁は上方に反り上がることから、閉合部の施工において主桁のたわみや応力の改善を図る場合、一般には張出し先端にカウンターウェイト等を配置し、桁を強制的に昇降させる必要がある。しかしながら、カウンターウェイト等を設置するための設備は大がかりとなり、また、そのための荷役設備等も別途必要になるという問題があった。この点に関し、本発明に係るPC橋の閉合方法では、外気温(日気温変化)と主桁変位に着目し、上下面の温度差と変位の関係を利用して、桁のたわみや応力の改善を図ることができる。より具体的には、以下の通りである。   Normally, at the stage of overhanging construction, the steel wire to which tensile force is applied is placed on the upper floor slab. For improvement, it is generally necessary to place a counterweight or the like at the tip of the overhang to forcibly raise or lower the beam. However, there is a problem that equipment for installing a counterweight or the like becomes a large scale, and cargo handling equipment or the like for that purpose is required separately. With regard to this point, the PC bridge closing method according to the present invention focuses on the outside air temperature (daily air temperature change) and the main girder displacement, and uses the relationship between the temperature difference between the upper and lower surfaces and the displacement so that the deflection of the girder and the stress are reduced. Improvements can be made. More specifically, it is as follows.

張出架設された桁部は、日中太陽光を浴びると上下面の温度差により変形を起こし、夕方に最大となり、日没と共に桁部に生じた温度差が解消されその変形が縮小することは、経験として認識されている。従って、ウェブの仮接合は温度差が生じない時間帯、すなわち朝方に行えば良いことになる。しかしながら、外気の低下と下面の温度差の減少は同時には進行せず、夕刻に最大となったたわみが収束するまでには時間を要する。太陽光を浴びて、蓄熱するコンクリートの性状により、外気の変動とコンクリート温度の変動には時間差が生じるためである。一方、現場で閉合部の仮接合を行う際、作業の進捗により、桁部の変形が少ない時間帯内だけで作業が終了するとは限らない。そして、その場合は、仮接合が安全な状態まで作業が進むとは限らない事を意味している。そこで、上下床版の温度差を人為的に小さくし、たわみの収束時間を短縮させることにより、仮接合作業を含めたウェブの架設固定に必要な作業時間を確保することができる。   The overhanging girder is deformed due to the temperature difference between the upper and lower surfaces when exposed to sunlight during the day, and is maximized in the evening. The temperature difference generated in the girder with sunset is eliminated and the deformation is reduced. Is recognized as an experience. Therefore, the temporary joining of the web may be performed in a time zone where there is no temperature difference, that is, in the morning. However, the decrease in the outside air and the decrease in the temperature difference on the lower surface do not proceed at the same time, and it takes time until the maximum deflection in the evening converges. This is because there is a time difference between the fluctuation of the outside air and the fluctuation of the concrete temperature due to the properties of the concrete that receives sunlight and stores heat. On the other hand, when temporary joining of the closing part is performed at the site, the work is not necessarily completed only within a time zone in which the deformation of the girder part is small due to the progress of the work. And in that case, it means that work does not necessarily advance to the state where temporary joining is safe. Therefore, by manually reducing the temperature difference between the upper and lower floor slabs and shortening the deflection convergence time, it is possible to secure the work time required for erection and fixing of the web including the temporary joining work.

上下床版の温度差を人為的に小さくする方法としては、例えば、橋面散水が有効である。作為的に床版上面(上スラブコンクリート)に散水を行い、水の蒸発時に起こる冷却効果により、上下面の温度差を低減でき、変位量も同時に低減できる。更に、同時に、コンクリートの蓄熱量を定量的にコントロールできる。また、養生マットに水を蓄積することによっても同様の効果を得ることができる。   As a method for artificially reducing the temperature difference between the upper and lower floor slabs, for example, bridge surface watering is effective. Water is sprayed on the upper surface of the slab (upper slab concrete), and the cooling effect that occurs when the water evaporates can reduce the temperature difference between the upper and lower surfaces, and the amount of displacement can be reduced at the same time. At the same time, the amount of heat stored in the concrete can be controlled quantitatively. Moreover, the same effect can be acquired also by accumulating water in a curing mat.

ただし、本発明に係るPC橋の閉合方法の特徴である上記温度管理手法には、桁部上下面温度差と変位の関係を定量的に把握しておく必要がある。例えば、桁部上下面温度差の低減に橋面散水や養生マットを利用する場合、散水の程度、或いは蓄積水量による変形との関係把握には、温度差値のパラメーターが必要となり、温度差計測を伴わない桁部の変形測定のみでは、散水事象や水の蓄積の結果による変形しか把握出来ないことになる。どの程度の散水量や散水時間が必要となるか、或いは、養生マットにどれ位の水を蓄積する必要があるか、などの定量的評価は、温度差計測と変位の測定を同時に行うことによってのみ可能となる。そして、そのような定量的評価により、桁の変形が生じない閉合部仮接合の作業時間を定量的に造りだすことが、はじめて可能となる。   However, the temperature management method, which is a feature of the PC bridge closing method according to the present invention, needs to quantitatively grasp the relationship between the girder upper and lower surface temperature difference and the displacement. For example, when using bridge surface watering or curing mats to reduce the temperature difference between the upper and lower surfaces of the girder, the temperature difference parameter is required to understand the relationship between the degree of watering and the deformation due to the amount of accumulated water. Only deformation due to watering events and water accumulation can be grasped only by measuring deformation of the girder part without accompanying. Quantitative evaluations such as how much water is sprayed, how much time is needed, or how much water needs to be accumulated in the curing mat can be done by simultaneously measuring the temperature difference and measuring the displacement. Only possible. And, by such quantitative evaluation, it becomes possible for the first time to quantitatively create the working time of the closed joint temporary joining in which no deformation of the girder occurs.

既述のように、桁部のたわみは朝方に発生しはじめ、上下温度差が大きくなる夕刻に大きくなる。従って、架設固定作業が完了する時間帯により、閉合部のウェブに発生する断面力(応力)は違ってくる。例えば、日中に橋面散水を行う場合、温度差が大きく桁が下向きに変形した状態で閉合部のウェブ接合を行えば、閉合部のウェブには、温度差が無くなった状態において、上縁(フランジを有する場合は上フランジ)に引張力、下縁(フランジを有する場合は下フランジ)に圧縮力が発生する。また、温度差が無い状態で閉合部のウェブ接合を行えば、変形の発生する日中、閉合部のウェブの上縁に圧縮応力が、下縁に引張応力が働くことになる。   As described above, the deflection of the girder part begins to occur in the morning and increases in the evening when the temperature difference between the upper and lower sides becomes large. Accordingly, the cross-sectional force (stress) generated in the web of the closing portion varies depending on the time period in which the installation and fixing work is completed. For example, when watering a bridge surface during the day, if the web of the closing portion is joined with the temperature difference being large and the girder being deformed downward, the upper edge of the closing portion web is removed in the state where the temperature difference is eliminated. A tensile force is generated on the upper flange if the flange is provided, and a compressive force is generated on the lower edge if the flange is provided. Further, if the closed portion is joined to the web in a state where there is no temperature difference, during the day when deformation occurs, compressive stress acts on the upper edge of the closed portion web and tensile stress acts on the lower edge.

一方、本発明に係るPC橋の閉合方法では、閉合部にウェブを架設固定し構造材として使用しているため、閉合部のコンクリート打設を行うと、コンクリート荷重によりウェブ上縁には圧縮力、下縁には引張力が働くことになる。従って、桁部の変形が下向きに起こっている状態でウェブを接合すると、コンクリート荷重によりウェブに発生する応力を低減することができる。すなわち、橋梁が完成した段階において、下床版には圧縮力が、上床版には引張力が働くと、橋梁にかかる死荷重、活荷重に対して反対方向の力となるため、鉄筋やPC鋼材等の構造部材の省略を期待できる。   On the other hand, in the PC bridge closing method according to the present invention, since the web is installed and fixed to the closing portion and used as a structural material, when concrete is placed in the closing portion, the compressive force is applied to the upper edge of the web due to the concrete load. A tensile force acts on the lower edge. Therefore, when the web is joined in a state where the girder is deformed downward, the stress generated in the web due to the concrete load can be reduced. In other words, when the bridge is completed, if a compressive force is applied to the lower floor slab and a tensile force is applied to the upper floor slab, the force is in the opposite direction to the dead load and live load applied to the bridge. Omission of structural members such as steel can be expected.

なお、桁部の変形は日照により温度差が発生し始めると同時に変形を始めるが、夕刻日照が終了してもコンクリートの蓄熱効果により、変形の復元速度は遅くなることは既述の通りである。そこで、桁部の変形が下向きに起こっている時間帯を利用してウェブ接合を行う場合、既設ウェブと高さを合致させる必要がある。温度差計測と変位測定データ、更に散水による制御を組合せることにより、ウェブ接合高さを合致させつつ、ウェブに有利な接合を作為的に造れることが可能となる。   It should be noted that the deformation of the girder starts to deform at the same time as the temperature difference begins to occur due to sunlight, but the deformation recovery speed is slowed down due to the heat storage effect of the concrete even after the evening sunlight is finished, as described above. . Therefore, when performing web joining using a time zone in which the deformation of the girder occurs downward, it is necessary to match the height with the existing web. By combining the temperature difference measurement, the displacement measurement data, and the control by watering, it becomes possible to make a web-friendly joint while making the web joint height match.

ウェブの構成材としては波形鋼板が好適であるが、その波形鋼板の上下に補剛材(フランジ)を備えておくことが更に好ましい。この場合、この波形鋼板で構成されたウエブは隣接する桁部同士の力を伝達できるものとなるため、コンクリート打設を行う際に、補強材としての機能を有することになる。   A corrugated steel sheet is suitable as a constituent material of the web, but it is more preferable to provide stiffeners (flanges) above and below the corrugated steel sheet. In this case, since the web comprised with this corrugated steel plate can transmit the force of adjacent girder parts, it will have a function as a reinforcing material when placing concrete.

本発明に係る第二のPC橋の閉合方法によれば、閉合部において、架設固定されたウェブの上方に、閉合部を挟んで対向する部位に密接する補助部材を設置するため、寒暖差による変形に起因する軸力と回転を拘束し、床版コンクリート施工時の閉合部の変形を抑えるとともに、支保工の構造を簡素化し、あるいは、ウェブ鋼板を薄いものにすることができる。しかも、閉合部を挟んで対向する部位に密接させる簡易な構造であるため、工期に影響を与えることもない。   According to the second PC bridge closing method according to the present invention, in the closing portion, the auxiliary member that is in close contact with the opposite portion across the closing portion is installed above the erected and fixed web. The axial force and rotation resulting from the deformation are restrained, the deformation of the closing portion at the time of floor slab concrete construction is suppressed, the structure of the support work is simplified, or the web steel plate can be made thin. And since it is a simple structure made close to the part which opposes on both sides of a closing part, it does not affect a construction period.

図1〜図3を参照しながら、本発明に係るPC橋の閉合方法の実施例を説明する。図1は、同工法における張出し端部と端支点部の間の閉合部を施工する際の概略工程を示し、(a)は閉合部にウェブが架設される前の状態の側面図、(b)は閉合部にウェブが架設され吊支保工が設置された状態の側面図、(c)は閉合部の下床版コンクリートが打設された状態の側面図、(d)は閉合部の上床版コンクリートが打設された状態の側面図である。図2は、同工法が実施される橋脚の一部概観を示す側面図である。図3は、橋脚からの張出し施工の概略工程を示し、(a)は施工対象領域に下床版コンクリートが打設され移動作業車が次領域のウェブ上に移動された状態の斜視図、(b)は施工対象領域にプレキャストリブを仮設した状態の斜視図、(c)は施工対象領域に上床版コンクリートが打設された状態の斜視図である。   An embodiment of a PC bridge closing method according to the present invention will be described with reference to FIGS. FIG. 1: shows the general | schematic process at the time of constructing the closing part between the overhang | projection edge part and an end fulcrum part in the construction method, (a) is a side view of the state before a web is constructed in a closing part, (b) ) Is a side view of a state where a web is erected in the closed part and a suspension support is installed, (c) is a side view of a state where the lower floor slab concrete is placed in the closed part, and (d) is an upper floor of the closed part. It is a side view in the state where slab concrete was laid. FIG. 2 is a side view showing a partial overview of the pier in which the construction method is implemented. FIG. 3 shows a schematic process of overhang construction from a bridge pier, and (a) is a perspective view in a state where a lower floor slab concrete is placed in a construction target area and a moving work vehicle is moved onto a web in the next area. b) is a perspective view in a state in which precast ribs are temporarily installed in a construction target area, and (c) is a perspective view in a state in which upper floor slab concrete is placed in the construction target area.

このPC橋の閉合方法が実施される橋梁の橋台3の前は、急峻で場所打ち支保工の施工が困難な地形となっている。そこで、深礎杭などによる中間支点を設置したり、或いは大型架設材を使用する等といった工期を長期化させる施工方法を採ることなく、以下の工程を実施することにより、工期の短縮化が図られている。なお、以下に説明する工程は、本発明に係る第1及び第2のPC橋の閉合方法の双方を同時に施工した場合であるが、これらの方法をそれぞれ分けて行うことも可能である。   In front of the bridge abutment 3 where this PC bridge closing method is implemented, the terrain is steep and difficult to perform in-situ support. Therefore, the construction period can be shortened by implementing the following processes without adopting a construction method that prolongs the construction period, such as installing an intermediate fulcrum such as a deep foundation pile or using a large construction material. It has been. In addition, although the process demonstrated below is the case where both the closing method of the 1st and 2nd PC bridge which concerns on this invention is constructed simultaneously, it is also possible to perform these methods separately, respectively.

まず、梁側から見て橋台3の手前に設けられた橋脚4a(以後、手前橋脚4aという)から、橋台3に向かって桁部2を張出し施工する。この張出し施工の工程では、図3に示すように、まず、施工対象領域nに、ウェブ1を架設し、下床版コンクリートを打設し、下床版22を構築する。なお、以下の工程も含め、この実施例におけるウェブ1の構成には、波形鋼板を使用している。続いて、次の施工領域n+1にウェブ1を架設し、移動作業車5を次の施工領域に移動させ、図3(a)に示す状態とする。そして、施工対象領域nに、プレキャストリブ24を仮設して図3(b)に示す状態とした後、上床版コンクリートを打設し、上床版21を構築し、ブロックを形成する(図3(c)に示す状態)。以降、次の施工領域n+1においても同様の施工を行うことにより、順次ブロックを形成することができる。ただし、上下床版コンクリートの打設はどちらが先行してもよく、桁長に応じて上下床版を同時に施工してもよい。また、波形鋼板1は、幾つかの施工領域について一時に架設してもよい。   First, the girder 2 is extended from the bridge pier 4a (hereinafter referred to as the front pier 4a) provided in front of the abutment 3 as viewed from the beam side toward the abutment 3. In this overhang construction process, as shown in FIG. 3, first, the web 1 is erected in the construction target region n, and the lower floor slab concrete is placed to construct the lower floor slab 22. In addition, the corrugated steel plate is used for the structure of the web 1 in this Example including the following processes. Subsequently, the web 1 is installed in the next construction area n + 1, and the mobile work vehicle 5 is moved to the next construction area, so that the state shown in FIG. Then, after precast ribs 24 are temporarily installed in the construction target region n to obtain the state shown in FIG. 3B, the upper floor slab concrete is placed, the upper floor slab 21 is constructed, and a block is formed (FIG. 3 ( c)). Thereafter, the blocks can be sequentially formed by performing the same construction in the next construction area n + 1. However, either the upper or lower floor slab concrete may be placed first, and the upper and lower floor slabs may be simultaneously applied according to the girder length. Further, the corrugated steel sheet 1 may be constructed at a time for several construction areas.

手前橋脚4aから張出施工した桁部2の端部23(本発明の張出し端部に相当)が、橋台3に予め設けられた端支点部31にある程度近づき、図1(a)に示す状態となったら、その端部23と端支点部31との間の閉合部6に、ウェブ1を架設固定する。ウェブ1の架設には、クレーンなどを使用してもよい。   The end 23 (corresponding to the overhang end of the present invention) of the girder 2 overhanging from the front bridge pier 4a approaches the end fulcrum 31 provided in advance on the abutment 3 to some extent, and is in the state shown in FIG. Then, the web 1 is constructed and fixed to the closing portion 6 between the end portion 23 and the end fulcrum portion 31. A crane or the like may be used to construct the web 1.

手前橋脚4aから張出し施工した桁部2は、寒暖差により鉛直方向と水平方向(橋軸方向)に変形するため、閉合部6にウェブ1を架設固定する際、仮接合を行うと、桁の変位は拘束され仮接合部分に力が伝わり応力を発生させる。そして、その応力が許容応力を超えると、仮接合部分は壊れることになる。そこで、この架設固定作業は、桁部2の変形によるたわみが最も小さくなる朝方に行うものとする。また、十分な作業時間を確保するため、作業前日からの橋面散水により上下床版21、22の温度差を人為的に小さくし、たわみの収束時間を短縮させておく。   Since the girder part 2 that is extended from the front pier 4a is deformed in the vertical direction and the horizontal direction (bridge axis direction) due to the difference in temperature, when the web 1 is erected and fixed to the closing part 6, The displacement is constrained and a force is transmitted to the temporarily joined portion to generate a stress. And if the stress exceeds allowable stress, a temporary joined part will be broken. Therefore, this erection and fixing work is performed in the morning where the deflection due to the deformation of the girder 2 is minimized. Further, in order to secure a sufficient work time, the temperature difference between the upper and lower floor slabs 21 and 22 is artificially reduced by watering the bridge surface from the day before the work, and the convergence time of the deflection is shortened.

架設固定作業が終了したら、次に、架設固定されたウェブ1の上方に、閉合部6を挟んで対向する部位に密接する補助部材23を設置し、ウェブ1よりなる既施工の桁から型枠支保工7を直接吊り下げ、図1(b)に示す状態とする。そして、この状態で下床版コンクリートを打設し、下床版22の閉合を行い、図1(c)に示す状態とする。次に、下床版22にプレストレスを与えウェブ1と一体にした断面を形成した後に、上床版コンクリートを打設し、プレストレスを導入し、上床版21の閉合を行い、閉合作業が終了となる。ただし、上下床版21、22の施工は、手前橋脚4aからの張出し施工と同様、どちらが先行してもよく、閉合長に応じて上下床版21、22を同時に施工してもよい。また、移動作業車5を直接ウェブ1上へ移動、設置し支保工として用いてもよい。   When the erection and fixing work is finished, next, an auxiliary member 23 is installed above the erected and fixed web 1 so as to be in close contact with the part facing the closing part 6. The support work 7 is directly hung to a state shown in FIG. Then, in this state, the lower floor slab concrete is placed, the lower floor slab 22 is closed, and the state shown in FIG. Next, after prestressing the lower floor slab 22 to form a cross section integrated with the web 1, the upper floor slab concrete is placed, prestress is introduced, the upper floor slab 21 is closed, and the closing operation is completed. It becomes. However, the construction of the upper and lower floor slabs 21 and 22 may be preceded in the same manner as the overhang construction from the near bridge pier 4a, and the upper and lower floor slabs 21 and 22 may be simultaneously constructed according to the closing length. Alternatively, the mobile work vehicle 5 may be moved and installed directly on the web 1 and used as a support work.

補助部材23には、通常のH形鋼が用いられている。このH形鋼の一端と、閉合部を挟んで対向する既設上床版21の一方との間には図示しないジャッキが介装されており、このジャッキの長さを調整することにより、閉合部を挟んで対向する既設上床版21に密着させた状態としている。ただし、補助部材23の材質や設置方法に制限はなく、寒暖差による変形に起因する軸力と回転を、床版コンクリート施工時まで拘束できるものであれば、その他のものを適宜使用してもよい。   For the auxiliary member 23, a normal H-section steel is used. A jack (not shown) is interposed between one end of the H-shaped steel and one of the existing upper floor slabs 21 facing each other with the closing portion interposed therebetween. By adjusting the length of the jack, the closing portion is It is set as the state made to contact | adhere to the existing upper floor slab 21 which opposes on both sides. However, there is no limitation on the material and installation method of the auxiliary member 23, and other materials may be used as appropriate as long as the axial force and rotation caused by deformation due to temperature difference can be restrained until the floor slab concrete construction. Good.

なお、図1〜図3に示す実施例は、張出し端部と橋台に設けられた端支点部の間の閉合部におけるものであるが、本発明のPC橋の閉合方法は、張出し端部23同士、或いは張出し端部23と橋脚頭部41の間の閉合部において実施することも可能である。   In addition, although the Example shown in FIGS. 1-3 is in the closing part between the overhanging end part and the end fulcrum part provided in the abutment, the closing method of the PC bridge of the present invention is the overhanging end part 23. It is also possible to implement in the closed part between each other or the overhanging end part 23 and the pier head part 41.

第二東名高速道路の赤淵川橋下り線の構築に際し、本発明に係るPC橋の併合方法を実施した。対象となった橋梁では、橋台へ架設される、手前橋脚から張出し施工した桁部が長く、上下床版の温度差による変異の大きいことが事前の計測でわかった。そこで、前日からの橋面散水を実施し、たわみ収束時間の短縮を図った。図4〜図6に、上下床版の温度差とたわみの推移を示す。上下床版の温度差の計測にはデータローガーと熱電対を使用し、熱電対は、図7に示すように、上床版の波形鋼板上方位置の2箇所(91、92)、下床版の幅方向中央位置の1箇所(93)、ブロック内の1箇所(94)、及びブロック外の1箇所(95)に設置した。なお、図4〜図6において、丸印は、目視結果を示している。また、図6において時間軸と交差する破線は、橋面散水の開始時刻である8時30分と終了時刻である16時を示している。更に、図7において、図1〜3に示す実施例と実質的に同じ場所には同符号を付した。   In constructing the Akabanegawa Bridge down line of the Second Tomei Expressway, the PC bridge merge method according to the present invention was implemented. In the target bridge, it was found from prior measurements that the girder that was built on the abutment and extended from the front pier was long and that the variation due to the temperature difference between the upper and lower decks was large. Therefore, the bridge surface watering from the previous day was carried out to shorten the deflection convergence time. 4 to 6 show changes in temperature difference and deflection between the upper and lower floor slabs. A data logger and a thermocouple are used to measure the temperature difference between the upper and lower floor slabs. As shown in FIG. 7, the thermocouple is located at two locations (91, 92) above the corrugated steel plate of the upper floor slab, the lower floor slab. Were installed at one location (93) in the center in the width direction, 1 location (94) inside the block, and 1 location (95) outside the block. In addition, in FIGS. 4-6, the circle mark has shown the visual result. Moreover, the broken line which cross | intersects the time axis in FIG. 6 has shown 8:30 which is the start time of bridge surface watering, and 16:00 which is an end time. Further, in FIG. 7, the same reference numerals are given to substantially the same places as in the embodiment shown in FIGS.

図4〜図6に示すように、床版温度差によるたわみは晴天時に大きくなり、その場合のたわみは朝8時頃に発生することがわかった。また、橋面散水を実施した場合、上下床版の温度差を制御することによりたわみ収束時間を短縮できることがわかった。そこで、前日から橋面散水を実施してたわみ収束時間を短縮し、朝8時までに閉合作業を終了させるための作業時間を確保した。この結果、閉合作業時のたわみ差は5mm程度に抑えられ、上下フラン時に発生する2次応力も大幅に低減させることができた。   As shown in FIG. 4 to FIG. 6, it was found that the deflection due to the floor slab temperature difference became large during fine weather, and the deflection in that case occurred around 8 o'clock in the morning. In addition, it was found that the deflection convergence time can be shortened by controlling the temperature difference between the upper and lower floor slabs when watering the bridge surface. Therefore, the bridge surface watering was carried out from the previous day to shorten the deflection convergence time, and ensured the work time to finish the closing work by 8:00 am. As a result, the difference in deflection during the closing operation was suppressed to about 5 mm, and the secondary stress generated during the upper and lower flank could be greatly reduced.

本発明に係るPC橋の閉合方法の実施例における張出し端部と端支点部の間の閉合部を施工する際の概略工程を示し、(a)は閉合部にウェブが架設される前の状態の側面図、(b)は閉合部にウェブが架設され吊支保工が設置された状態の側面図、(c)は閉合部の下床版コンクリートが打設された状態の側面図、(d)は閉合部の上床版コンクリートが打設された状態の側面図である。The rough process at the time of constructing the closing part between the overhang | projection edge part and an end fulcrum part in the Example of the closing method of the PC bridge which concerns on this invention is shown, (a) is the state before a web is constructed in a closing part (B) is a side view of a state in which a web is installed in a closed portion and a suspension support is installed, (c) is a side view of a state in which lower floor slab concrete is placed in the closed portion, (d ) Is a side view of a state in which the upper floor slab concrete of the closing portion is placed. 同PC橋の閉合方法が実施される橋脚の一部概観を示す側面図である。It is a side view which shows the one part outline of the pier in which the closing method of the PC bridge is implemented. 橋脚から張出される桁の施工工法の概略工程を示し、(a)は施工対象領域に下床版コンクリートが打設され移動作業車が次領域のウェブ上に移動された状態の斜視図、(b)は施工対象領域にプレキャストリブを仮設した状態の斜視図、(c)は施工対象領域に上床版コンクリートが打設された状態の斜視図である。(A) is a perspective view of a state where a lower floor slab concrete is placed in a construction target area and a moving work vehicle is moved on a web in the next area. b) is a perspective view in a state in which precast ribs are temporarily installed in a construction target area, and (c) is a perspective view in a state in which upper floor slab concrete is placed in the construction target area. 晴天時における上下床版の温度差とたわみの時間推移を示し、(a)は上下床版の温度差の推移グラフ、(b)はたわみの推移グラフである。The temperature difference between the upper and lower floor slabs and the time transition of the deflection in fine weather are shown, (a) is the transition graph of the temperature difference between the upper and lower floor slabs, and (b) is the transition graph of the deflection. 雨天時における上下床版の温度差とたわみの時間推移を示し、(a)は上下床版の温度差の推移グラフ、(b)はたわみの推移グラフである。The temperature difference between the upper and lower floor slabs and the time transition of deflection during rainy weather are shown. (A) is a transition graph of the temperature difference between the upper and lower floor slabs, and (b) is a transition graph of the deflection. 晴天時において橋面散水を実施した場合の上下床版の温度差とたわみの推移を示し、(a)は上下床版の温度差の推移グラフ、(b)はたわみの推移グラフである。The transition of the temperature difference and deflection of the upper and lower floor slabs when the bridge surface watering is performed in fine weather, (a) is a transition graph of the temperature difference of the upper and lower floor slabs, (b) is a transition graph of the deflection. 熱電対の設置場所を示す、ブロックの概略横断面図である。It is a schematic cross-sectional view of a block showing the installation location of a thermocouple.

符号の説明Explanation of symbols

1 ウェブ
2 桁部
3 橋台
6 閉合部
7 吊支保工
21 上床版
22 下床版
23 補助部材
31 端支点部
41 橋脚頭部
DESCRIPTION OF SYMBOLS 1 Web 2 Girder part 3 Abutment 6 Closure part 7 Suspension support work 21 Upper floor slab 22 Lower floor slab 23 Auxiliary member 31 End fulcrum part 41 Pier head

Claims (3)

既に張出し施工された桁部(2)における上下床版(21,22)の温度差を小さくし、張出し端部(23)におけるたわみを調整し、閉合部(6)にウェブ(1)を、床版コンクリートの施工を行う前に架設固定することを特徴とするPC橋の閉合方法。   Reduce the temperature difference between the upper and lower floor slabs (21, 22) in the already stretched girder (2), adjust the deflection at the stretched end (23), and place the web (1) in the closing part (6), A method of closing a PC bridge, characterized in that it is erected and fixed before construction of floor slab concrete. 該閉合部(6)に架設固定された該ウェブ(1)を使用して吊支保工(7)を設置する請求項1に記載のPC橋の閉合方法。   The method for closing a PC bridge according to claim 1, wherein the suspension support (7) is installed using the web (1) erected and fixed to the closing portion (6). 閉合部(6)に、ウェブ(1)を、床版コンクリートの施工を行う前に架設固定し、該ウェブ(1)の上方に、該閉合部(6)を挟んで対向する部位に密接する補助部材(23)を設置することを特徴とするPC橋の閉合方法。   Prior to construction of floor slab concrete, the web (1) is erected and fixed to the closing part (6), and is closely above the web (1) to the opposite part across the closing part (6). A method for closing a PC bridge, characterized by installing an auxiliary member (23).
JP2007322649A 2007-12-13 2007-12-13 Pc bridge closure method Pending JP2009144410A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007322649A JP2009144410A (en) 2007-12-13 2007-12-13 Pc bridge closure method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007322649A JP2009144410A (en) 2007-12-13 2007-12-13 Pc bridge closure method

Publications (1)

Publication Number Publication Date
JP2009144410A true JP2009144410A (en) 2009-07-02

Family

ID=40915332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007322649A Pending JP2009144410A (en) 2007-12-13 2007-12-13 Pc bridge closure method

Country Status (1)

Country Link
JP (1) JP2009144410A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864735A (en) * 2010-07-16 2010-10-20 中铁二局股份有限公司 Construction method of stayed-cable
CN102011369A (en) * 2010-11-12 2011-04-13 中铁十二局集团第二工程有限公司 Construction method of steel shells of bridge closure segments striding over various roads
JP2014005685A (en) * 2012-06-26 2014-01-16 Sumitomo Mitsui Construction Co Ltd Method for constructing box girder bridge
JP2016003475A (en) * 2014-06-16 2016-01-12 前田建設工業株式会社 Correction method for upward shift amount, and correction method and program for upward shift amount
CN107558376A (en) * 2017-09-12 2018-01-09 中铁四局集团市政工程有限公司 A kind of installation method of closure section Wavelike steel webplate
CN112227204A (en) * 2020-08-07 2021-01-15 中交二公局第二工程有限公司 Side span pushing closure construction method for cable-stayed bridge
CN112391950A (en) * 2020-10-14 2021-02-23 华南理工大学 Device and method for adjusting center line deviation of closure opening of high-tower and low-tower cable-stayed bridge
CN113255039A (en) * 2021-05-26 2021-08-13 中铁大桥勘测设计院集团有限公司 Method for determining main beam closure opening of steel truss girder cable-stayed suspension cable cooperation system bridge
CN115094775A (en) * 2022-07-22 2022-09-23 武汉理工大学 Large-span PC continuous rigid frame bridge non-counterweight closure construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03293407A (en) * 1990-04-12 1991-12-25 P S Co Ltd Construction of bridge employing stay cable

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03293407A (en) * 1990-04-12 1991-12-25 P S Co Ltd Construction of bridge employing stay cable

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JPN6012012325; 伊藤篤、外3名: '波形鋼板ウェブ橋の温度変化による影響と施工-第二東名高速道路赤淵川橋下り線-' 第16回プレストレストコンクリートの発展に関するシンポジウム論文集 , 20070918, 第311-314頁, 社団法人プレストレストコンクリート技術協会 *
JPN6012012326; 萩原直樹、外3名: '波形鋼板ウェブを架設材として利用した張出し架設-第二東名高速道路 赤淵川橋下り線-' 第16回プレストレストコンクリートの発展に関するシンポジウム論文集 , 20070918, 第319-322頁, 社団法人プレストレストコンクリート技術協会 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864735A (en) * 2010-07-16 2010-10-20 中铁二局股份有限公司 Construction method of stayed-cable
CN102011369A (en) * 2010-11-12 2011-04-13 中铁十二局集团第二工程有限公司 Construction method of steel shells of bridge closure segments striding over various roads
CN102011369B (en) * 2010-11-12 2013-01-23 中铁十二局集团第二工程有限公司 Construction method of steel shells of bridge closure segments striding over various roads
JP2014005685A (en) * 2012-06-26 2014-01-16 Sumitomo Mitsui Construction Co Ltd Method for constructing box girder bridge
JP2016003475A (en) * 2014-06-16 2016-01-12 前田建設工業株式会社 Correction method for upward shift amount, and correction method and program for upward shift amount
CN107558376B (en) * 2017-09-12 2019-07-19 中铁四局集团市政工程有限公司 A kind of installation method of closure section Wavelike steel webplate
CN107558376A (en) * 2017-09-12 2018-01-09 中铁四局集团市政工程有限公司 A kind of installation method of closure section Wavelike steel webplate
CN112227204A (en) * 2020-08-07 2021-01-15 中交二公局第二工程有限公司 Side span pushing closure construction method for cable-stayed bridge
CN112391950A (en) * 2020-10-14 2021-02-23 华南理工大学 Device and method for adjusting center line deviation of closure opening of high-tower and low-tower cable-stayed bridge
CN112391950B (en) * 2020-10-14 2021-10-26 华南理工大学 Device and method for adjusting center line deviation of closure opening of high-tower and low-tower cable-stayed bridge
CN113255039A (en) * 2021-05-26 2021-08-13 中铁大桥勘测设计院集团有限公司 Method for determining main beam closure opening of steel truss girder cable-stayed suspension cable cooperation system bridge
CN113255039B (en) * 2021-05-26 2022-04-29 中铁大桥勘测设计院集团有限公司 Method for determining main beam closure opening of steel truss girder cable-stayed suspension cable cooperation system bridge
CN115094775A (en) * 2022-07-22 2022-09-23 武汉理工大学 Large-span PC continuous rigid frame bridge non-counterweight closure construction method

Similar Documents

Publication Publication Date Title
JP2009144410A (en) Pc bridge closure method
JP5373979B2 (en) Construction Method of Steel Composite Girder Bridge {ConstructionMethod SteelCompositeGirderBridge}
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
US9657494B2 (en) Method for producing a tower construction from reinforced concrete
CN107245951B (en) Mid-span and double-side simultaneous closure construction method for cable-stayed bridge
CN104264592A (en) Construction method of continuous beam
JP2014009461A (en) Spc bridge erection method
CN102808383A (en) Construction process for back-sloping and jacking curved bridge
CN110512530A (en) A kind of combination beam binodal section Cantilever Construction Method
JP2008274586A (en) Pillar head construction method
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
Reddy et al. Simulation of construction of cable-stayed bridges
CN102797223A (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN111914458B (en) Method for controlling line shape of arch ring of reinforced concrete arch bridge
CN109853964A (en) A kind of construction method for steel construction armored concrete mixed structure
KR100631029B1 (en) Precasted concrete plate assembly and the construction method using thereof
JP4033871B2 (en) How to build a bridge girder
JP2967876B1 (en) Method of forming concrete slab and method of constructing upper road suspension bridge
JP6509096B2 (en) Extension method
JP6280145B2 (en) Repair and reinforcement structure for reinforced concrete structures
Byle et al. Time-dependent deformation behavior of prestressed high performance concrete bridge beams
JP2010101072A (en) Structure of composite beam, and construction method for composite beam
CN108316120A (en) It can rapidly-assembled precast bridge and its construction method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
KR101011443B1 (en) Structure with integrated slab beam bridge and method of manufacturing thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20101124

A977 Report on retrieval

Effective date: 20120217

Free format text: JAPANESE INTERMEDIATE CODE: A971007

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120313

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120511

A131 Notification of reasons for refusal

Effective date: 20120725

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120913

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20121016