CN112160342A - Construction method for buildings (structures) below roads - Google Patents

Construction method for buildings (structures) below roads Download PDF

Info

Publication number
CN112160342A
CN112160342A CN202011137236.1A CN202011137236A CN112160342A CN 112160342 A CN112160342 A CN 112160342A CN 202011137236 A CN202011137236 A CN 202011137236A CN 112160342 A CN112160342 A CN 112160342A
Authority
CN
China
Prior art keywords
road
fender
piles
construction method
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011137236.1A
Other languages
Chinese (zh)
Inventor
代为
张春浩
姜佑明
欧剑
文雪峰
韦露明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Co Ltd filed Critical China Railway 25th Bureau Group Co Ltd
Priority to CN202011137236.1A priority Critical patent/CN112160342A/en
Publication of CN112160342A publication Critical patent/CN112160342A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

A method for constructing the building under road includes such steps as enclosing one of the lanes to build the enclosure piles and top beams, laying steel structure on top beams for the vehicles to pass through, enclosing the other lanes one by one, and excavating the side edges of road to build the entrance and exit under road for later underground engineering and transportation of material. The construction method does not need to seal the road for a long time, the influence on the passage can be greatly reduced, and the road surface can still keep normal passing during the construction period of underground engineering, thereby effectively reducing the enclosing and shielding requirements of the road and ensuring the passing of the road surface; the fender pile can be used as a fender structure of an underground building (structure) at the same time, and the construction difficulty and the construction cost of subsequent engineering can be effectively reduced.

Description

Construction method for buildings (structures) below roads
Technical Field
The present invention relates to road construction, and more particularly, to a construction method for constructing a building or structure in the underground below a road.
Background
In the construction of the lower part of the existing road, such as the construction of a subway entrance, an underground tunnel, etc., it is necessary to enclose the road, and the enclosing time is usually several months to several years because the construction time is long. The road surface can not be used for any vehicle and pedestrian to pass during the surrounding and shielding period, the vehicle can only walk other automobile channels, the road passing is seriously influenced, and the blocking phenomenon is generated sometimes; if the traffic capacity needs to be ensured, a user needs to dismantle the building beside the enclosing and shielding passage to build a temporary lane and restore the temporary lane after the construction is finished, but the requirement on road conditions is high, the temporary lane is difficult to be applied to all road sections, the temporary lane cannot be applied to luxurious road sections with short land in cities, the building and the road surface are repeatedly built and dismantled, the cost is high, and the resource waste is easily caused.
Disclosure of Invention
The invention aims to provide a construction method of buildings or structures below a road, which can greatly reduce the need of road surface shielding, so as to reduce the influence of construction on road traffic and ensure the normal traffic capacity of the road.
The invention relates to a construction method of buildings (structures) below roads, which comprises the following steps:
constructing a row of transverse fender piles on two sides of a road, then constructing crown beams on the tops of the two rows of transverse fender piles, and connecting all fender piles in the same row into a whole;
constructing a row of longitudinal fender piles at two end parts of each transverse fender pile, constructing crown beams for connecting the longitudinal fender piles at the tops of the two rows of longitudinal fender piles, and connecting the crown beams at the tops of the longitudinal fender piles and the crown beams at the tops of the transverse fender piles into a whole;
after the concrete strength of the fender post and the crown beam reaches the design requirement, breaking the road surface along the direction of the construction road, and excavating the road surface until the top height of the crown beam is reached;
paving a pavement steel structure on the broken pavement;
and an access opening leading to the lower part of the pavement steel structure is formed at the side edge of the road.
The invention relates to a construction method of buildings (structures) below roads, which is characterized in that when a certain road needs to be constructed with the underground buildings or structures, such as subway stations, underground passages, subway ports and the like in subway engineering; firstly, building fender piles on two sides of a construction road, then building a crown beam on the top of the fender piles, and connecting all the fender piles into a whole by using the crown beam; then, sequentially building fender posts and crown beams between the end parts of the crown beams to form an annular maintenance structure; when the crown beam is constructed, the height difference between the top surface of the crown beam and the original pavement is consistent with the thickness of a pavement steel structure laid in the later period, so that the surface of the pavement steel structure is consistent with the elevation of the original pavement, the pavement steel structure can be smoothly connected with the pavement, and meanwhile, a steel plate, a bolt and the like used for connecting the pavement steel structure are embedded in the top surface of the crown beam; after the whole annular maintenance structure is built, the road surface is broken by using road surface breaking equipment, an excavator and the like, and the road surface is excavated downwards to the height of the top surface of the crown beam; then laying the prefabricated pavement steel structure on the crown beam, and welding and fixing the pavement steel structure with the embedded steel plate and the bolts on the crown beam by using equipment such as an electric welding machine and the like, so that the traffic capacity of the road can be recovered; meanwhile, an access opening which can be communicated to the lower part of the road, namely the lower part of the pavement steel structure, is built at the side edge of the road and is used as an access and conveying channel for subsequent underground engineering construction; thereafter, the steel structure of the road surface is used as a part of the road surface to maintain the traffic capacity, and the lower part of the steel structure of the road surface can pass through the entrance and exit to construct the building.
According to the construction method of the building (structure) below the road, the fender posts and the crown beams are simply constructed, the construction time is short, temporary road sealing and shielding measures can be taken on the periphery of the road in a low traffic flow period, such as a late night period, and then construction is carried out to avoid road blockage; meanwhile, the fender post and the crown beam can be built gradually as required, for example, the road is firstly sheltered and a plurality of fender posts are built in the first low traffic flow period (such as the night of the first day), the shelter is removed to recover the traffic before the low traffic flow period is ended, then the fender post is built in the second low traffic flow period (such as the night of the second day), so that the fender post is built in a sectionalized mode, and the crown beam is built in a one-time mode or a sectionalized mode according to the situation after all the fender posts are built, so that the influence on the traffic capacity of the road is reduced to the maximum extent. The construction of underground space can be carried out under the condition that the road surface is not influenced to pass, no matter the passing of people or the conveying of materials can be carried out through the access opening, the road surface part of the access opening needs to be continuously shielded, but the passing of the lane cannot be influenced on one hand, and on the other hand, the construction only needs a small area and cannot cause too much influence on the passing of pedestrians. By the construction method, the road traffic capacity can be effectively guaranteed, the road is prevented from being blocked for a long time, meanwhile, the fender post can be used as a fender structure of an underground building (structure), and the construction difficulty and the construction cost of subsequent engineering can be effectively reduced.
Detailed Description
A construction method of buildings (structures) below roads comprises the following steps:
constructing a row of transverse fender piles on two sides of a road, then constructing crown beams on the tops of the two rows of transverse fender piles, and connecting all fender piles in the same row into a whole;
constructing a row of longitudinal fender piles at two end parts of each transverse fender pile, constructing crown beams for connecting the longitudinal fender piles at the tops of the two rows of longitudinal fender piles, and connecting the crown beams at the tops of the longitudinal fender piles and the crown beams at the tops of the transverse fender piles into a whole;
after the concrete strength of the fender post and the crown beam reaches the design requirement, breaking the road surface along the direction of the construction road, and excavating the road surface until the top height of the crown beam is reached;
paving a pavement steel structure on the broken pavement;
and an access opening leading to the lower part of the pavement steel structure is formed at the side edge of the road.
In the construction method of the building (structure) below the road, if the construction road is a bidirectional lane, the lane in one direction can be firstly enclosed to build the enclosure piles and the crown beams, then the lane in the other direction is enclosed and the enclosure piles and the crown beams are built, then the enclosure piles and the crown beams are built along the transverse direction, and all the maintenance enclosure piles and the crown beams are connected into a whole; and then paving the steel structure of the pavement. In addition, if the width of the construction road is smaller, the fender posts and the crown beams can be built only on two sides of the road; if the width of the construction road is larger, the guard piles and the crown beams can be built in the middle of the construction road along the road direction so as to improve the supporting strength.
According to the construction method of the building (structure) below the road, in the process of constructing the fender posts and the crown beams, the fender posts and the crown beams on one side are constructed firstly, and then the fender posts and the crown beams on the other sides are constructed, so that the situation that multiple sides are constructed simultaneously to cause multiple fencing is avoided.
In the construction method of the building (structure) below the road, the height difference between the top surface of the crown beam and the original road surface is consistent with the thickness of the steel structure of the road surface, so that the elevation of the steel structure surface of the road surface is consistent with that of the original road surface, and the steel structure can be smoothly connected with the road surface; in addition, steel plates and bolts for connecting a pavement steel structure are pre-buried at the top surface of the crown beam during construction of the crown beam, so that the pavement steel structure is paved and fixed in a square manner; and after the crown beam is poured with concrete, the crown beam is backfilled to the height of the original pavement by using gravel or broken stones, and after the concrete strength of the guard piles and the crown beam reaches the design requirement, the backfilling part is broken and excavated again to lay a pavement steel structure, so that the road traffic capacity can be kept in the process of waiting for the concrete to solidify.
According to the construction method of the building (structure) below the road, the road surface steel structure can be prefabricated in a factory, and can also be manufactured in the construction process of the fender post and the crown beam, and then the road surface steel structure is transported to the construction road to be laid, so that the construction period and the construction complexity are reduced, and the manufacturing precision of the road surface steel structure is improved. The road surface steel structure may be a flat plate or a flat box-shaped steel plate box, and the structural strength is further improved by the structure of the steel plate box. In addition, the surface of the road surface steel structure can be provided with concave-convex patterns so as to improve the friction strength of the steel plate and improve the passing stability of the automobile on the steel plate.

Claims (9)

1. A construction method for buildings (structures) below roads is characterized by comprising the following steps:
constructing a row of transverse fender piles on two sides of a road, then constructing crown beams on the tops of the two rows of transverse fender piles, and connecting all fender piles in the same row into a whole;
constructing a row of longitudinal fender piles at two end parts of each transverse fender pile, constructing crown beams for connecting the longitudinal fender piles at the tops of the two rows of longitudinal fender piles, and connecting the crown beams at the tops of the longitudinal fender piles and the crown beams at the tops of the transverse fender piles into a whole;
after the concrete strength of the fender post and the crown beam reaches the design requirement, breaking the road surface along the direction of the construction road, and excavating the road surface until the top height of the crown beam is reached;
paving a pavement steel structure on the broken pavement;
and an access opening leading to the lower part of the pavement steel structure is formed at the side edge of the road.
2. The under-road building construction method according to claim 1, characterized in that: a row of fender piles and a crown beam which connects the fender piles into a whole are built in the middle of the road.
3. The under-road building construction method according to claim 1 or 2, characterized in that: and constructing each row of transverse fender piles in sequence, namely constructing one row of maintenance piles and constructing the top beams at the tops of the maintenance piles, and then constructing the other row of fender piles and the top beams.
4. The under-road building construction method according to claim 1 or 2, characterized in that: the height difference between the top surface of the crown beam and the original road surface is consistent with the thickness of the road surface steel structure.
5. The under-road building construction method according to claim 1 or 2, characterized in that: when the crown beam is built, steel plates and bolts for connecting a road steel structure are pre-buried at the top surface of the crown beam.
6. The under-road building construction method according to claim 1 or 2, characterized in that: and after the crown beam is poured with concrete, backfilling the crown beam by using gravel or broken stones until the height of the original pavement is marked.
7. The under-road building construction method according to claim 1, characterized in that: the road steel structure is manufactured in the process of building the fender post and the crown beam.
8. The under-road building construction method according to claim 1, characterized in that: the pavement steel structure is a flat box-shaped steel plate box.
9. The under-road building construction method according to claim 1 or 8, characterized in that: the surface of the road surface steel structure is provided with concave-convex patterns.
CN202011137236.1A 2020-10-22 2020-10-22 Construction method for buildings (structures) below roads Pending CN112160342A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011137236.1A CN112160342A (en) 2020-10-22 2020-10-22 Construction method for buildings (structures) below roads

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011137236.1A CN112160342A (en) 2020-10-22 2020-10-22 Construction method for buildings (structures) below roads

Publications (1)

Publication Number Publication Date
CN112160342A true CN112160342A (en) 2021-01-01

Family

ID=73864521

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011137236.1A Pending CN112160342A (en) 2020-10-22 2020-10-22 Construction method for buildings (structures) below roads

Country Status (1)

Country Link
CN (1) CN112160342A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202466338U (en) * 2012-02-24 2012-10-03 中铁十二局集团第二工程有限公司 Construction device for rapidly recovering metro station road
CN103696784A (en) * 2014-01-03 2014-04-02 沈阳铁道勘察设计院有限公司 Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN107558494A (en) * 2017-10-16 2018-01-09 西南交通大学 A kind of Underground Station structure and its method of construction
CN107794942A (en) * 2017-10-30 2018-03-13 中国冶集团有限公司 Riverbed comprehensive pipe gallery structure and its construction method are worn under one kind
CN110424988A (en) * 2019-08-16 2019-11-08 招商局重庆交通科研设计院有限公司 Tunnel waterproofing construction and tunnel waterproofing method
CN110486062A (en) * 2019-08-15 2019-11-22 中交铁道设计研究总院有限公司 A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202466338U (en) * 2012-02-24 2012-10-03 中铁十二局集团第二工程有限公司 Construction device for rapidly recovering metro station road
CN103696784A (en) * 2014-01-03 2014-04-02 沈阳铁道勘察设计院有限公司 Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN107558494A (en) * 2017-10-16 2018-01-09 西南交通大学 A kind of Underground Station structure and its method of construction
CN107794942A (en) * 2017-10-30 2018-03-13 中国冶集团有限公司 Riverbed comprehensive pipe gallery structure and its construction method are worn under one kind
CN110486062A (en) * 2019-08-15 2019-11-22 中交铁道设计研究总院有限公司 A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil
CN110424988A (en) * 2019-08-16 2019-11-08 招商局重庆交通科研设计院有限公司 Tunnel waterproofing construction and tunnel waterproofing method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴波: "《城市地下工程技术研究与实践》", 31 May 2008, 中国铁道出版社 *

Similar Documents

Publication Publication Date Title
CN111779027A (en) Construction method for constructing underground garage through cover-excavation top-down construction
CN110578339A (en) construction method of shaft type underground stereo garage
JP3586864B2 (en) Underground structure construction method and elevated traffic path
KR100546432B1 (en) A arch-shaped composite structure with the precast concrete pannel and the steel frame using the open trench tunnel method, and method for it
CN105256836A (en) Construction method for fast restoring road traffic in construction of underground project
JP4406577B2 (en) Digging road
JP6144726B2 (en) Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method
KR100510092B1 (en) A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it
US20100272509A1 (en) Traffic barrier section
CN112160342A (en) Construction method for buildings (structures) below roads
CN104895100B (en) Building close quarters builds underground space Caisson method
KR20210055980A (en) Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same
KR100592416B1 (en) How to secure the sidewalk and widen the roadway using concrete retaining wall blocks and truss-shaped pedestals on narrow roads
CN214614086U (en) Double-deck landing stage formula reverse construction method foundation ditch enclosure system
CN111663815A (en) Tunnel type stereo garage under road and construction method thereof
CN113215910A (en) Temporary pavement structure based on construction of limited-site subway station and application thereof
CN114109402A (en) Large-section construction method of underground excavated crossover line implemented by interval tunnel organization
CN113216249A (en) Method for constructing underground space under narrow road condition
JP2018021300A (en) Overhung sidewalk constituent body, and construction method of overhung sidewalk using the same
CN110804916A (en) Construction method for newly-built road to pass through existing road under traffic state
JP2003278479A (en) Method of constructing widening tunnel
CA2936215A1 (en) Construction methods and systems for grade separation structures
KR100252440B1 (en) Prefabrication type road crossing on different levels and method
US3385180A (en) Construction of roads and associated surfaces
CN110761188B (en) Overpass construction method at intersection of main road and local road

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210101

RJ01 Rejection of invention patent application after publication