CN112144895A - Transportation device for high-rise building and use method - Google Patents

Transportation device for high-rise building and use method Download PDF

Info

Publication number
CN112144895A
CN112144895A CN202011155938.2A CN202011155938A CN112144895A CN 112144895 A CN112144895 A CN 112144895A CN 202011155938 A CN202011155938 A CN 202011155938A CN 112144895 A CN112144895 A CN 112144895A
Authority
CN
China
Prior art keywords
fixedly connected
plate
rod
building
threaded rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202011155938.2A
Other languages
Chinese (zh)
Inventor
高文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202011155938.2A priority Critical patent/CN112144895A/en
Publication of CN112144895A publication Critical patent/CN112144895A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down

Abstract

The invention relates to the technical field of high-altitude operation, in particular to a conveying device for a high-rise building and a using method of the conveying device. The invention aims to solve the technical problems that the height of a building elevator is limited and long materials are inconvenient to transport. In order to solve the technical problem, the invention provides a transportation device for a high-rise building, which comprises two support frames, wherein the tops of the two support frames are fixedly connected with a baffle, one end between the two support frames is fixedly connected with a bottom plate, the middle part of the top of the baffle is fixedly connected with a first mounting block, the top of the first mounting block is fixedly connected with a first hanging ring, and an adjusting device is hung on the first hanging ring. According to the invention, one end of the support frame is fixed in the building through the expansion bolt, so that the other end of the support frame, the baffle plate and the bottom plate are positioned outside the building, and therefore, building materials which are inconvenient to transport by the building elevator can be transported and placed on the bottom plate through the tower crane, and the construction of high-rise buildings is facilitated.

Description

Transportation device for high-rise building and use method
The invention relates to a divisional application of a transportation device for a high-rise building, which has an application date of 2018, 26.04.78 and an application number of CN 201810387758.3.
Technical Field
The invention relates to the technical field of high-altitude operation, in particular to a conveying device for a high-rise building and a using method of the conveying device.
Background
In the existing high-rise construction of buildings, building elevators are often used for transporting building materials, the building materials such as PVC (polyvinyl chloride) line pipes, galvanized pipes and steel pipes are long, the heights of the building elevators are limited, and the transportation of the long materials is inconvenient.
Disclosure of Invention
Technical problem to be solved
Aiming at the defects of the prior art, the invention provides a transportation device for a high-rise building, which has the advantage of convenient use and solves the problems that the height of a building elevator is limited and the transportation of longer materials is inconvenient.
(II) technical scheme
In order to realize the technical problem, the invention provides a transportation device for a high-rise building, which comprises two support frames, wherein the tops of the two support frames are fixedly connected with a baffle, one end between the two support frames is fixedly connected with a bottom plate, the middle part of the top of the baffle is fixedly connected with a first installation block, the top of the first installation block is fixedly connected with a first hanging ring, an adjusting device is hung on the first hanging ring, the top of the adjusting device is provided with a stabilizing device, the top of the support frame, which is far away from one end of the bottom plate, is fixedly connected with a support device, the opposite surfaces of the two baffle plates are fixedly connected with transverse plates, the middle parts of the opposite surfaces of the two transverse plates are provided with jacks, the inner parts of the jacks are slidably connected with sliding strips, pulling plates are fixedly connected between the two sliding strips, the two sides of the sliding strips are provided with.
Preferably, adjusting device is including the alignment jig, the middle part of alignment jig one side is inlayed and is had the first screw thread lantern ring, the internal thread of the first screw thread lantern ring is pegged graft and is had first threaded rod, the first fixed block of one end fixedly connected with of first threaded rod, the first couple of one side fixedly connected with of first threaded rod is kept away from to first fixed block, the middle part of alignment jig opposite side is inlayed and is had the second screw thread lantern ring, the internal thread of the second screw thread lantern ring is pegged graft and is had the second threaded rod, the one end fixedly connected with second fixed block of second threaded rod, one side fixedly connected with second couple of second threaded rod is kept away from to the second fixed block, the second couple articulates on first link, the equal fixedly connected with stopper of one end opposite face of first threaded rod and second threaded rod, the first cover that rotates has.
Preferably, the stabilizing device comprises a pull rod, a second mounting block is fixedly connected to the bottom of the pull rod, a second hanging ring is fixedly connected to the bottom of the second mounting block, the first hook is hung on the second hanging ring, a third mounting block is fixedly connected to the top of the pull rod, and a mounting plate is fixedly connected to one side, away from the pull rod, of the third mounting block.
Preferably, the supporting device comprises a first clamping block, the bottom of the first clamping block is fixedly connected to the top of the supporting frame, a third threaded rod is fixedly connected to the top of the first clamping block, a threaded sleeve rod is sleeved on the outer surface of the third threaded rod, a second rotating sleeve is sleeved on the bottom of the outer surface of the threaded sleeve rod, an anti-slip sleeve is sleeved on the outer surface of the second rotating sleeve, a bearing seat is fixedly connected to the top of the threaded sleeve rod, a top fixedly connected with top plate of the bearing seat and a stabilizing plate are fixedly connected to the top of the top plate.
Preferably, fixing device is including seting up the activity chamber at the inside top of diaphragm, the spout has all been seted up to the both sides in activity chamber, the inside sliding connection of spout has the slider, fixedly connected with movable plate between two sliders, the middle part fixedly connected with locating lever of movable plate one side, the equal fixedly connected with extension spring in both ends of movable plate one side, the one end fixed connection at the inner wall in activity chamber of movable plate is kept away from to the extension spring, the one end that the movable plate was kept away from to the locating lever runs through the diaphragm and extends to the inside of locating hole, the top fixedly connected with poker rod of locating lever, the top of poker rod runs through.
Preferably, the middle part of the top of the pulling plate is fixedly connected with a handle.
(III) advantageous effects
Compared with the prior art, the invention provides a transportation device for a high-rise building, which has the following beneficial effects:
1. this conveyer for high-rise building uses through the cooperation of support frame, baffle and bottom plate, passes through expansion bolts with the one end of support frame and fixes in the inside of building for the other end, the baffle of support frame and bottom plate are located the outside of building, thereby can place the building material transportation of inconvenient building elevator transportation on the bottom plate through the tower crane, thereby make things convenient for the construction of high-rise building.
2. This conveyer for high-rise building thing through the setting of baffle, the baffle can play the effect of protection to the both sides of bottom plate, has avoided the material to drop from the bottom plate, and has protected construction personnel's personal safety, has improved the security.
3. This conveyer for high-rise building uses through the cooperation of stabilising arrangement and adjusting device, and mounting panel fixed connection on the stabilising arrangement is in the outside of building, and the first installation piece is fixed at the top of baffle on the adjusting device to play taut fixed effect to this conveyer for high-rise building, strengthened this conveyer for high-rise building's stability, avoided this conveyer for high-rise building to take place to rock when using.
4. This conveyer for high-rise building through adjusting device's setting, clockwise rotation alignment jig can make first threaded rod and second threaded rod move to the inboard to having played taut fixed effect to this conveyer for high-rise building, anticlockwise rotation alignment jig can make first threaded rod and second threaded rod move to the outside, has made things convenient for the outside with mounting panel fixed connection at the building.
5. This conveyer for high-rise building thing, through the setting of stopper, when anticlockwise rotation alignment jig made first threaded rod and second threaded rod to move to the outside, played spacing fixed effect to first threaded rod and second threaded rod, avoided first threaded rod and second threaded rod to break away from in the alignment jig.
6. This conveyer for high-rise building through strutting arrangement's setting, the clockwise rotation second rotates the cover and can makes roof rebound for roof and the inside top contact of building have played the fixed effect of support to the support frame, have further improved this conveyer for high-rise building's stability, and the anticlockwise rotation second rotates the cover and can make roof lapse, thereby has made things convenient for strutting arrangement's dismantlement.
7. This conveyer for high-rise building thing uses through the cooperation of jack, draw bar, arm-tie and handle, upwards stimulates the handle, can make the draw bar on the arm-tie upwards remove in the jack is inside for the arm-tie breaks away from with the diaphragm, has made things convenient for the tower crane to place the longer building material of length such as PVC spool, galvanized pipe and steel pipe at the top of bottom plate, has made things convenient for the transportation and the taking of the longer building material of length.
8. This conveyer for high-rise building thing through fixing device's setting, can make locating lever and locating hole separation to outside pulling poker rod to having made things convenient for pulling-up of arm-tie to make arm-tie and diaphragm break away from, loosening poker rod can make the locating lever insert to the inside of locating hole at the tensile effort of extension spring, thereby has played fixed effect to the arm-tie.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the adjusting device according to the present invention;
FIG. 3 is a schematic view of the supporting device of the present invention;
FIG. 4 is a top view of the structure of the present invention;
FIG. 5 is an enlarged view of a portion of FIG. 4 according to the present invention.
In the figure: 1 supporting frame, 2 baffle plates, 3 bottom plate, 4 first mounting blocks, 5 first hanging rings, 6 adjusting devices, 601 adjusting frames, 602 first threaded lantern rings, 603 first threaded rods, 604 first fixing blocks, 605 first hooks, 606 second threaded lantern rings, 607 second threaded rods, 608 second fixing blocks, 609 second hooks, 610 limiting blocks, 611 first rotating sleeves, 7 stabilizing devices, 701 pull rods, 702 second mounting blocks, 703 second hanging rings, 704 third mounting blocks, 705 mounting plates and 8 supporting devices, the device comprises a 801 first clamping block, an 802 third threaded rod, a 803 threaded sleeve rod, an 804 second rotating sleeve, a 805 anti-skidding sleeve, a 806 bearing seat, an 807 top plate, a 808 stabilizing plate, a 9 transverse plate, a 10 jack, an 11 slide bar, a 12 pulling plate, a 13 positioning hole, a 14 fixing device, a 1401 movable cavity, a 1402 sliding groove, a 1403 slide block, a 1404 moving plate, a 1405 positioning rod, a 1406 tension spring, a 1407 poking rod, a 15 mounting hole and a 16 handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, a transportation device for high-rise buildings comprises two support frames 1, wherein the tops of the two support frames 1 are fixedly connected with a baffle 2, the baffle 2 can play a role in protecting two sides of a bottom plate 3 through the arrangement of the baffle 2, so that materials are prevented from falling off the bottom plate 3, the personal safety of building personnel is protected, and the safety is improved, one end between the two support frames 1 is fixedly connected with the bottom plate 3, one end of the support frame 1 is fixed in the building through an expansion bolt through the matching use of the support frame 1, the baffle 2 and the bottom plate 3, so that the other end of the support frame 1, the baffle 2 and the bottom plate 3 are positioned outside the building, and therefore, building materials which are inconvenient to transport by a lifting elevator of a tower crane can be transported on the bottom plate 3, the construction of the high-rise buildings is facilitated, the middle part of the top of the baffle 2 is fixedly connected with a first installation, the first link 5 of top fixedly connected with of first installation piece 4, it has adjusting device 6 to articulate on first link 5, adjusting device 6's top is provided with stabilising arrangement 7, the top fixedly connected with strutting arrangement 8 of 3 one ends of bottom plate is kept away from to support frame 1, the equal fixedly connected with diaphragm 9 of the opposite face of two baffles 2, jack 10 has been seted up at the middle part of two diaphragm 9 opposite faces, the inside sliding connection of jack 10 has draw runner 11, fixedly connected with arm-tie 12 between two draw runners 11, locating hole 13 has all been seted up to the both sides of draw runner 11, the inside top of two diaphragm 9 is provided with fixing device 14, mounting hole 15 has been seted up at the top that 3 one ends of bottom plate were kept away from to support frame 1.
The adjusting device 6 comprises an adjusting frame 601, a first threaded collar 602 is embedded in the middle of one side of the adjusting frame 601, a first threaded rod 603 is inserted in the internal thread of the first threaded collar 602, a first fixed block 604 is fixedly connected to one end of the first threaded rod 603, a first hook 605 is fixedly connected to one side of the first fixed block 604 far away from the first threaded rod 603, a second threaded collar 606 is embedded in the middle of the other side of the adjusting frame 601, a second threaded rod 607 is inserted in the internal thread of the second threaded collar 606, a second fixed block 608 is fixedly connected to one end of the second threaded rod 607, a second hook 609 is fixedly connected to one side of the second fixed block 608 far away from the second threaded rod 607, the second hook 609 is hung on the first hanging ring 5, a limit block 610 is fixedly connected to one end of the opposite surfaces of the first threaded rod 603 and the second threaded rod 607, through the setting of the limit block 610, when the first threaded rod 603 and the second threaded rod 607 move outwards counterclockwise by, spacing fixed effect has been played to first threaded rod 603 and second threaded rod 607, avoided first threaded rod 603 and second threaded rod 607 to break away from alignment jig 601, the external surface of alignment jig 601 is fixed to cup joint first rotating sleeve 611, setting through adjusting device 6, clockwise rotation alignment jig 601 can make first threaded rod 603 and second threaded rod 607 move to the inboard, thereby having played taut fixed effect to this conveyer for the high-rise building, anticlockwise rotation alignment jig 601 can make first threaded rod 603 and second threaded rod 607 move to the outside, made things convenient for the outside with mounting panel 705 fixed connection at the building.
The stabilizing device 7 comprises a pull rod 701, a second mounting block 702 is fixedly connected to the bottom of the pull rod 701, a second hanging ring 703 is fixedly connected to the bottom of the second mounting block 702, a first hook 605 is hung on the second hanging ring 703, a third mounting block 704 is fixedly connected to the top of the pull rod 701, a mounting plate 705 is fixedly connected to one side, far away from the pull rod 701, of the third mounting block 704, the mounting plate 705 is fixedly connected to the outer side of the building through the cooperation of the stabilizing device 7 and the adjusting device 6, the mounting plate 705 on the stabilizing device 7 is fixedly connected to the outer side of the building, and a first mounting block 4 on the adjusting device 6 is fixed to the top of the baffle plate 2, so that the tensioning and fixing effects are achieved on the transporting device for the high-rise building, the stability of the transporting device for the high-rise building is enhanced, and the shaking of the transporting device for the high-.
The supporting device 8 comprises a first clamping block 801, the bottom of the first clamping block 801 is fixedly connected to the top of the supporting frame 1, the top of the first clamping block 801 is fixedly connected with a third threaded rod 802, a threaded sleeve rod 803 is sleeved on the outer surface of the third threaded rod 802 in a threaded manner, a second rotating sleeve 804 is fixedly sleeved on the bottom of the outer surface of the threaded sleeve rod 803, an anti-slip sleeve 805 is sleeved on the outer surface of the second rotating sleeve 804, a bearing seat 806 is fixedly connected to the top of the threaded sleeve rod 803, a top plate 807 is fixedly connected to the top of the bearing seat 806, a stabilizing plate 808 is fixedly connected to the top of the top plate 807, the top plate 807 can move upwards by rotating the second rotating sleeve 804 clockwise through the arrangement of the supporting device 8, so that the top plate 807 is in contact with the top inside of the building, the supporting and fixing effects are achieved on the supporting frame 1, and the stability of, rotating the second rotating sleeve 804 counterclockwise may cause the top plate 807 to move downward, thereby facilitating the removal of the support device 8.
The fixing device 14 comprises a movable cavity 1401 arranged at the top inside the transverse plate 9, sliding grooves 1402 are arranged on both sides of the movable cavity 1401, a sliding block 1403 is connected inside the sliding groove 1402 in a sliding manner, a moving plate 1404 is fixedly connected between the two sliding blocks 1403, a positioning rod 1405 is fixedly connected in the middle of one side of the moving plate 1404, tension springs 1406 are fixedly connected at both ends of one side of the moving plate 1404, one end, far away from the moving plate 1404, of each tension spring 1406 is fixedly connected to the inner wall of the movable cavity 1401, one end, far away from the moving plate 1404, of each positioning rod 1405 penetrates through the transverse plate 9 and extends into the positioning hole 13, a poking rod 1407 is fixedly connected to the top of each positioning rod 1405, the top of each poking rod 1407 penetrates through the transverse plate 9 and extends to the top of the transverse plate 9, and the positioning rods 1405 can be separated from the positioning holes 13 by, when the tap lever 1407 is released, the positioning rod 1405 is inserted into the positioning hole 13 by the tensile force of the tension spring 1406, thereby fixing the pulling plate 12.
Middle part fixedly connected with handle 16 at arm-tie 12 top uses through jack 10, draw bar 11, arm-tie 12 and handle 16's cooperation, upwards stimulates handle 16, can make draw bar 11 on the 12 inside rebound in jack 10 for arm-tie 12 breaks away from with diaphragm 9, has made things convenient for the tower crane to place the longer building material of length such as PVC spool, galvanized pipe and steel pipe at the top of bottom plate 3, has made things convenient for the longer building material's of length transportation and has taken.
The working principle is as follows: hoisting a high-rise building by using a conveying device through a tower crane, conveying the high-rise building to a required floor, fixing one end of a support frame 1 in the building through an expansion bolt, enabling the other end of the support frame 1, a baffle plate 2 and a bottom plate 3 to be positioned outside the building, fixing an installation plate 705 on a stabilizing device 7 on the outside of the building, rotating a first rotating sleeve 611 to adjust the length of an adjusting device 6, hanging a first hook 605 on the adjusting device 6 on a second hanging ring 703 on the stabilizing device 7, hanging a second hook 609 on the first hanging ring 5, rotating a second rotating sleeve 804 clockwise to enable a top plate 807 to move upwards, enabling the top plate 807 to be in contact with the top inside of the building, achieving the effect of supporting and fixing the support frame 1, and when a building material with a long length is required to be used in a high-rise building, pulling a poke rod 1407 outwards to enable a positioning rod 1405 to be separated from a positioning hole 13, pulling up handle 16 can make draw bar 11 on the arm-tie 12 upwards remove in jack 10 inside for arm-tie 12 breaks away from with diaphragm 9, and when normal use, inserts the inside of jack 10 with arm-tie 12, loosens poker rod 1407, and at the tensile effort of extension spring 1406, can make locating lever 1405 insert the inside to locating hole 13, thereby has played fixed effect to arm-tie 12.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (3)

1. The utility model provides a conveyer for high-rise building, includes two support frames (1), its characterized in that: the top parts of the two support frames (1) are fixedly connected with a baffle (2), one end between the two support frames (1) is fixedly connected with a bottom plate (3), the middle part of the top part of the baffle (2) is fixedly connected with a first mounting block (4), the top part of the first mounting block (4) is fixedly connected with a first hanging ring (5), an adjusting device (6) is hung on the first hanging ring (5), the top part of the adjusting device (6) is provided with a stabilizing device (7), the top part of one end of the support frame (1) far away from the bottom plate (3) is fixedly connected with a supporting device (8), the opposite surfaces of the two baffle plates (2) are fixedly connected with transverse plates (9), the middle parts of the opposite surfaces of the two transverse plates (9) are provided with jacks (10), the inner parts of the jacks (10) are slidably connected with sliding strips (11), and a pulling plate (12) is fixedly connected between the, positioning holes (13) are formed in the two sides of the sliding strip (11), fixing devices (14) are arranged at the tops of the inner parts of the two transverse plates (9), and mounting holes (15) are formed in the tops of the ends, far away from the bottom plate (3), of the supporting frames (1);
the fixing device (14) comprises a movable cavity (1401) arranged at the top inside the transverse plate (9), the two sides of the movable cavity (1401) are both provided with sliding grooves (1402), the sliding grooves (1402) are connected with sliding blocks (1403) in a sliding manner, a moving plate (1404) is fixedly connected between the two sliding blocks (1403), a positioning rod (1405) is fixedly connected to the middle part of one side of the moving plate (1404), both ends of one side of the moving plate (1404) are fixedly connected with tension springs (1406), one end of the tension spring (1406) far away from the moving plate (1404) is fixedly connected with the inner wall of the movable cavity (1401), one end of the positioning rod (1405) far away from the moving plate (1404) penetrates through the transverse plate (9) and extends into the positioning hole (13), the top of the positioning rod (1405) is fixedly connected with a poke rod (1407), and the top of the poke rod (1407) penetrates through the transverse plate (9) and extends to the top of the transverse plate (9); the middle part of the top of the pulling plate (12) is fixedly connected with a handle (16);
the adjusting device (6) comprises an adjusting frame (601), a first threaded sleeve ring (602) is embedded in the middle of one side of the adjusting frame (601), a first threaded rod (603) is inserted in the internal threads of the first threaded sleeve ring (602), a first fixed block (604) is fixedly connected to one end of the first threaded rod (603), a first hook (605) is fixedly connected to one side, away from the first threaded rod (603), of the first fixed block (604), a second threaded sleeve ring (606) is embedded in the middle of the other side of the adjusting frame (601), a second threaded rod (607) is inserted in the internal threads of the second threaded sleeve ring (606), a second fixed block (608) is fixedly connected to one end of the second threaded rod (607), a second hook (609) is fixedly connected to one side, away from the second threaded rod (607), of the second fixed block (608) is hung on the first hanging ring (5), one end of each of the opposite surfaces of the first threaded rod (603) and the second threaded rod (607) is fixedly connected with a limiting block (610), and the outer surface of the adjusting frame (601) is fixedly sleeved with a first rotating sleeve (611);
the stabilizing device (7) comprises a pull rod (701), a second mounting block (702) is fixedly connected to the bottom of the pull rod (701), a second hanging ring (703) is fixedly connected to the bottom of the second mounting block (702), a first hook (605) is hung on the second hanging ring (703), a third mounting block (704) is fixedly connected to the top of the pull rod (701), and a mounting plate (705) is fixedly connected to one side, far away from the pull rod (701), of the third mounting block (704).
2. The transportation apparatus for a high-rise building according to claim 1, wherein: the supporting device (8) comprises a first clamping block (801), the bottom of the first clamping block (801) is fixedly connected to the top of the supporting frame (1), a third threaded rod (802) is fixedly connected to the top of the first clamping block (801), a threaded sleeve rod (803) is sleeved on the outer surface of the third threaded rod (802), a second rotating sleeve (804) is fixedly sleeved on the bottom of the outer surface of the threaded sleeve rod (803), an anti-skidding sleeve (805) is sleeved on the outer surface of the second rotating sleeve (804), a bearing seat (806) is fixedly connected to the top of the threaded sleeve rod (803), a top plate (807) is fixedly connected to the top of the bearing seat (806), and a stabilizing plate (807) is fixedly connected to the top of the top plate (807).
3. A transportation device for high-rise buildings and a method of use thereof as claimed in any one of claims 1 to 2, wherein: the high-rise building is lifted by the conveying device through the tower crane and conveyed to a required floor, one end of the support frame (1) is fixed inside the building through an expansion bolt, the other end of the support frame (1), the baffle (2) and the bottom plate (3) are positioned outside the building, the mounting plate (705) on the stabilizing device (7) is fixed outside the building, the length of the adjusting device (6) can be adjusted by rotating the first rotating sleeve (611), the first hook (605) on the adjusting device (6) is hung on the second hanging ring (703) on the stabilizing device (7), the second hook (609) is hung on the first hanging ring (5), the top plate (807) can move upwards by rotating the second rotating sleeve (804) clockwise, so that the top plate (807) is contacted with the top inside of the building, and the support frame (1) is supported and fixed, when high-rise building needs to use the building material of longer length, outside pulling poker rod (1407) can make locating lever (1405) and locating hole (13) separate, pull handle (16) upwards, can make draw bar (11) on pulling plate (12) upwards remove in jack (10) inside, make pulling plate (12) break away from with diaphragm (9), when normal use, insert pulling plate (12) to the inside of jack (10), loosen poker rod (1407), at the tensile effort of extension spring (1406), can make locating lever (1405) insert to the inside of locating hole (13), thereby fixed effect has been played to pulling plate (12).
CN202011155938.2A 2018-04-26 2018-04-26 Transportation device for high-rise building and use method Withdrawn CN112144895A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011155938.2A CN112144895A (en) 2018-04-26 2018-04-26 Transportation device for high-rise building and use method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201810387758.3A CN108678392B (en) 2018-04-26 2018-04-26 Conveyer for high-rise building
CN202011155938.2A CN112144895A (en) 2018-04-26 2018-04-26 Transportation device for high-rise building and use method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201810387758.3A Division CN108678392B (en) 2018-04-26 2018-04-26 Conveyer for high-rise building

Publications (1)

Publication Number Publication Date
CN112144895A true CN112144895A (en) 2020-12-29

Family

ID=63801505

Family Applications (2)

Application Number Title Priority Date Filing Date
CN202011155938.2A Withdrawn CN112144895A (en) 2018-04-26 2018-04-26 Transportation device for high-rise building and use method
CN201810387758.3A Active CN108678392B (en) 2018-04-26 2018-04-26 Conveyer for high-rise building

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201810387758.3A Active CN108678392B (en) 2018-04-26 2018-04-26 Conveyer for high-rise building

Country Status (1)

Country Link
CN (2) CN112144895A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236672B (en) * 2020-01-16 2021-09-10 中铁二局集团有限公司 Ultra-high-rise concrete pouring movable protection device and construction method thereof
CN112158249B (en) * 2020-10-26 2022-09-23 中成进出口股份有限公司 Based on building conveyer for energy-saving material

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3035231B2 (en) * 1996-09-19 2000-04-24 高砂熱学工業株式会社 Vertical pipe lifting jig
CN103174303B (en) * 2011-12-23 2016-03-30 五冶集团上海有限公司 Movable overhanging unloading platform and making thereof and mounting method
CN203808534U (en) * 2014-04-28 2014-09-03 武汉一冶建筑安装工程有限责任公司 Tool type multifunctional discharging platform device
CN205857756U (en) * 2016-08-07 2017-01-04 史文锋 A kind of construction discharging platform
CN206144172U (en) * 2016-08-24 2017-05-03 通州建总集团有限公司 Equipment standard platform of unloading of encorbelmenting
CN207048348U (en) * 2017-07-03 2018-02-27 中国核工业第二二建设有限公司 A kind of tool-type, which is pressurized, supports discharging platform
CN107338965A (en) * 2017-08-28 2017-11-10 安徽宝业建工集团有限公司 The discharging of modularization ready-package and outer protection integrated system for assembled architecture
CN107514128B (en) * 2017-09-14 2020-04-10 山东华邦建设集团有限公司 Scaffold for building engineering

Also Published As

Publication number Publication date
CN108678392A (en) 2018-10-19
CN108678392B (en) 2020-12-15

Similar Documents

Publication Publication Date Title
CN108678392B (en) Conveyer for high-rise building
CN211486293U (en) High-altitude falling prevention device
CN206437772U (en) A kind of double special hanger of list
CN108639932A (en) Endoporus automatic decoupling suspender
CN201495028U (en) Horizontal hoisting tool for large-tonnage concrete segments of tunnel
CN216366372U (en) Safety suspension device for high-altitude operation
CN105460765A (en) Aluminum bar transferring hanging bracket
CN206654663U (en) A kind of balance sling for installing finishing mill taper box
CN210340016U (en) Building construction elevator cable limit structure
CN213923753U (en) Load-bearing device and bridge crane
CN208775713U (en) A kind of tool for replacing conveyor belt snub pulley
CN211078164U (en) Hoisting adjusting structure of crane
KR101472980B1 (en) Weight clamping type Gondola Hanger for Building facade maintenance
CN210177994U (en) Protection stores pylon of outer wall construction
CN207293933U (en) A kind of crane suspension hook to prolong the service life
CN207226806U (en) A kind of construction reinforcing bar boom hoisting
CN215666817U (en) Supporting device for replacing carrier roller of rubber belt conveyor
CN105060100B (en) Coke oven door suspention Special-purpose hanger clip tool
CN205472231U (en) Gallows is transported to aluminium bar
CN209350643U (en) A kind of fixation with steel wire mechanism of blank cutter
CN219546454U (en) Hoisting device for H steel production
CN116177377B (en) Argil jar hoist, turning device and transfer equipment
CN204784084U (en) Pre -buried nut
CN211945907U (en) Stable slag pot hoist of handling
CN211307641U (en) Corrugated paper conveyer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20201229

WW01 Invention patent application withdrawn after publication