CN112127228A - Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway - Google Patents

Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway Download PDF

Info

Publication number
CN112127228A
CN112127228A CN202010973874.0A CN202010973874A CN112127228A CN 112127228 A CN112127228 A CN 112127228A CN 202010973874 A CN202010973874 A CN 202010973874A CN 112127228 A CN112127228 A CN 112127228A
Authority
CN
China
Prior art keywords
pile
concrete
concrete layer
rib
pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010973874.0A
Other languages
Chinese (zh)
Other versions
CN112127228B (en
Inventor
谢金钊
谢飞帆
陶林辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hengyang Jinming Environmental Technology Co ltd
Original Assignee
Hengyang Jinming Environmental Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hengyang Jinming Environmental Technology Co ltd filed Critical Hengyang Jinming Environmental Technology Co ltd
Priority to CN202010973874.0A priority Critical patent/CN112127228B/en
Publication of CN112127228A publication Critical patent/CN112127228A/en
Application granted granted Critical
Publication of CN112127228B publication Critical patent/CN112127228B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/06Pavings made of prefabricated single units made of units with cement or like binders
    • E01C5/08Reinforced units with steel frames
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/50Removable forms or shutterings for road-building purposes; Devices or arrangements for forming individual paving elements, e.g. kerbs, in situ
    • E01C19/502Removable forms or shutterings, e.g. side forms; Removable supporting or anchoring means therefor, e.g. stakes

Abstract

The pile-carrying plate-shaped member comprises a plate-shaped member body, a pile head is arranged below the member body, the pile head is connected with the member body above the pile head into a whole, a pile tip is formed at the bottom end of the pile head, and a holding part which is convenient for being held by hands to lift the pile-carrying plate-shaped member and a treading part which is convenient for being treaded by feet to insert the pile head downwards are arranged on the member body. The pile-bearing plate-shaped component can replace the existing steel mould to be used as a template for pouring a concrete layer, is simple to mold and operate, is flexible to construct, can save the mold removal time, shortens the road laying period, can form a smoother road turning radian, and is favorable for improving the road attractiveness.

Description

Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway
Technical Field
The invention relates to the technical field of highway engineering, in particular to a slab-shaped member with piles, a highway concrete layer pouring construction method and a highway.
Background
As shown in fig. 1, when a concrete layer a of a road is laid, in most of the existing methods, a road surface is divided into two halves by taking a road surface center line as a boundary, one half of the road surface is laid first, and after the concrete is solidified to reach a certain strength, the other half of the road surface is laid. Before concreting, need install steel mould B earlier, still need demolish steel mould B after the concrete setting reaches design strength, because the cohesion between the concrete after the solidification and steel mould B interface is great, overlap joint reinforcing bar C also wears out in the hole of wearing the muscle of inboard steel mould B (being by the steel mould of half that one side that does not pour promptly), need to pry with the help of the drill rod very much and just can pull down steel mould B, the in-process of steel mould B is hindered easily to the drill rod sled down, lead to the concrete face to appear colobomely, and the road shoulder filling construction also must just can go on after steel mould B demolishs, the time limit for a project is difficult to shorten. In addition, most of the existing steel moulds B are made of straight steel materials, and the turning radian of the laid road body is not smooth and the attractiveness is not high on some sharp-curved road sections.
At present, most of the improvement means aiming at the problems are focused on changing the connecting and fixing structure of the steel die B, so that the assembling operation of the steel die B is simpler (namely how to quickly assemble the die), but a satisfactory scheme is not provided in the aspects of how to make the die removal easier, how to make the radian of the die assembly of the curve smoother and how to shorten the construction period.
Disclosure of Invention
The invention aims to provide a sheet-shaped component with piles for pouring construction of a concrete layer of a road, which can replace the existing steel mould.
In order to achieve the purpose, the invention adopts the following technical scheme: the utility model provides a take stake platelike component, is including wholly being platelike component body the below of component body is equipped with the pile head, the pile head links into an integrated entity with the component body of top the bottom of pile head forms the stake point be equipped with the portion of holding of being convenient for the staff to hold in order to mention this take stake platelike component and the portion of stepping on of being convenient for the people's foot to trample in order to down insert the pile head on the component body.
Wherein the grip is disposed at a top of the member body.
Wherein the pedal part is arranged at the bottom of the component body.
Further, a first rib extending transversely is arranged at the top of the component body, and the first rib protrudes outwards compared with the front surface of the component body, so that a grip part is formed at the joint of the front surface of the component body and the first rib.
Furthermore, a second rib extending transversely is arranged at the bottom of the component body, and the second rib protrudes outwards compared with the front surface of the component body, so that a pedal part is formed at the joint of the front surface of the component body and the second rib.
Preferably, the front surface of the component body is provided with a plurality of rib penetrating holes at intervals, the rib penetrating holes are blind holes and extend from the front surface to the back surface of the component body, and the hole bottoms of the rib penetrating holes are thin walls which can be penetrated through by reinforcing steel bars.
Further, both ends all are equipped with along the floor of vertical extension about the component body, the floor is compared in the positive of component body and is protruding outward, the top and the first rib of floor link to each other, the bottom and the second rib of floor link to each other, floor, first rib, second rib and component body and pile head are by concrete integrated casting shaping.
On the basis of the sheet-shaped component with the pile, the invention also provides a pouring construction method of a road concrete layer, which takes the sheet-shaped component with the pile as a template and comprises the following steps:
die filling: inserting pile-carrying plate-shaped members at two sides of a concrete layer to be poured, splicing all the pile-carrying plate-shaped members side by side along the extending direction of a road and inserting pile heads of the pile-carrying plate-shaped members into a cushion layer or roadbed soil below the pile-carrying plate-shaped members so that all the pile-carrying plate-shaped members are vertically fixed;
pouring concrete: pouring concrete into a concrete pouring area between the two rows of the pile plate-shaped members, and forming a concrete layer after the poured concrete is solidified;
and finishing the pouring construction of the road concrete layer.
Or dividing the concrete layer into a left part and a right part by taking the central line of the road as a boundary, pouring the concrete layer of the left half part, and pouring the concrete layer of the right half part;
inserting pile-bearing plate-shaped components at two sides of a left half concrete layer, inserting the pile-bearing plate-shaped components inserted at the junction of the left half concrete layer and a right half concrete layer into pile-bearing plate-shaped components with reinforcing holes, inserting the reinforcing holes through the pile-bearing plate-shaped components before inserting, placing reinforcing steel bars in concrete pouring areas corresponding to the left half concrete layer before pouring the left half concrete layer, enabling lap-joint reinforcing steel bars needing to be anchored in the right half concrete layer to penetrate through the reinforcing holes, pouring concrete after the placement of the reinforcing steel bars is finished, and obtaining the left half concrete layer after the concrete is solidified;
inserting a row of sheet-shaped members with piles at one side of the concrete layer of the right half part close to the road shoulder, thereby forming a concrete pouring area corresponding to the concrete layer of the right half part, pouring concrete after placing reinforcing steel bars in the concrete pouring area corresponding to the concrete layer of the right half part, and obtaining the concrete layer of the right half part after the concrete is solidified;
and finishing the pouring construction of the road concrete layer.
Finally, the invention also relates to a highway, which comprises a concrete layer, wherein the concrete layer is poured by adopting the method, and the left side, the right side and the middle of the concrete layer are inserted with the pile plate-shaped components.
The pile-carrying plate-shaped member provided by the invention has a very simple integral structure, the gripping part and the pedal part are arranged on the member body, and the pile head with the pile tip is arranged below the member body, so that in field construction, a worker can grip the gripping part with hands to lift the member to a position needing insertion, then the pedal part is stepped downwards with feet, and the pile head is inserted into soil or a cushion layer to enable the member to be vertically fixed (if the soil is soft, the member can be reinforced and fixed by proper amount of concrete), the pile-carrying plate-shaped member is spliced side by side along the road extension direction to replace the existing steel mould, the mould assembly operation is easier and simpler, the pile-carrying plate-shaped member does not need to be disassembled after the concrete is solidified, the mould disassembly time is saved, and the condition that the concrete layer is damaged due to the mould disassembly of the steel drill is avoided. In addition, as the pile-bearing plate-shaped member does not need to be demolded after the pile-bearing plate-shaped member is adopted, the outer side of the pile-bearing plate-shaped member can be immediately covered with soil and compacted to form a road shoulder after concrete pouring is finished, and the road laying period can be greatly shortened. Finally, the pile-bearing plate-shaped member provided by the invention has smaller size (can be manually held and lifted), and can form smoother road turning radian by using the pile-bearing plate-shaped member for die-filling, so that the construction is more flexible, and the road appearance is better.
Drawings
Fig. 1 a-e are schematic diagrams illustrating a construction process of a road concrete layer in the prior art.
Fig. 2 is a schematic front view of a sheet-like member with piles in the embodiment.
Fig. 3 is a back structure diagram of a sheet-like member with piles in the embodiment.
Fig. 4 a-c are schematic views illustrating a construction process for molding and pouring a concrete base layer of a road by using the sheet member with piles shown in fig. 2 and 3.
In the figure:
1-component body 2-pile head 3-first rib
4-second rib 5-rib plate 1 a-grip
1 b-tread part 1 c-through-rib hole A-concrete layer
B-steel mould C-lapping steel bar D-cushion layer
A1 left half concrete layer A2 right half concrete layer.
Detailed Description
It should be noted that, unless otherwise explicitly stated or limited, the terms "mounted," "connected," "fixed," and the like are used broadly in the present invention, and may be, for example, fixedly connected, detachably connected, or integrally connected; they may be directly connected or indirectly connected through an intermediate, and those skilled in the art can understand the specific meaning of the above terms in the present invention according to specific situations.
Furthermore, in the present invention, the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the referred device or element must have a specific orientation, be configured in a specific orientation, and operate, and thus, should not be construed as limiting the present invention.
Referring to fig. 2 and 3, the sheet member with pile used in the embodiment of the present invention includes a member body 1 having a plate shape as a whole, pile heads 2 are disposed below the member body 1, the pile heads 2 are integrally connected to the member body 1 above the pile heads, a pile tip is formed at a bottom end of the pile heads 2, and a grip portion 1a for being gripped by a human hand to lift the sheet member with pile and a stepping portion 1b for being stepped by a human foot to insert the pile heads 2 downward are disposed on the member body 1. Wherein the grip part 1a is arranged on the top of the member body 1, and the pedal part 1b is arranged on the bottom of the member body 1. It should be noted that the above-mentioned grip part 1a and step part 1b are not limited to be provided on the top and bottom of the member body 1, and may be provided on other parts, and the shape thereof is not particularly limited as long as a position convenient for the hand to grip and the foot to step down can be provided.
As an alternative arrangement, a first rib 3 extending in the transverse direction is provided on the top of the member body 1, and the first rib 3 protrudes outward from the front surface of the member body 1, so that a grip portion 1a is formed at the junction of the front surface of the member body 1 and the first rib 3. Meanwhile, a second rib 4 extending transversely is arranged at the bottom of the member body 1, and the second rib 4 protrudes outwards compared with the front surface of the member body 1, so that a pedal part 1b is formed at the joint of the front surface of the member body 1 and the second rib 4. The number of pile heads 2 is preferably plural and the whole of the pile heads 2 is tapered from top to bottom, and the pile heads 2 are provided below the member body 1 at intervals in the lateral direction.
In addition, in order to reduce the weight of the sheet-shaped component with the pile, the thickness of the component body 1 can be made as thin as possible, in order to avoid the situation that the thinned component body 1 is collided to cause corner defects in the transportation process, rib plates 5 extending along the vertical direction can be arranged at the left end and the right end of the component body 1 to strengthen the strength of the edges of the component body 1, the rib plates 5 are preferably protruded outwards compared with the front surface of the component body 1 (namely the rib plates 5 are preferably arranged on the front surface of the component body 1), the top ends of the rib plates 5 are connected with the first ribs 3, and the bottom ends of the rib plates 5 are connected with the second ribs 4. In the factory production, the member body 1, the pile head 2, the rib plate 5, the first rib 3, and the second rib 4 may be integrally cast with concrete.
As a preferable structure, as shown in fig. 2, a plurality of rib penetrating holes 1c are further provided at intervals on the front surface of the member body 1, the rib penetrating holes 1c are blind holes and extend from the front surface to the back surface of the member body 1, and the bottom of the rib penetrating hole 1c is a thin wall which can be penetrated by a steel bar.
Fig. 4 shows a construction process for laying a concrete base layer a of a road using the above-described pilated plate-like member instead of a steel form. Similar to the construction process of the existing steel mould B, when the steel mould B is replaced by the pile-carrying plate-shaped member to lay the concrete base layer A, the concrete layer A is divided into a left part and a right part by taking the center line of the road as a boundary, the left half part of the concrete layer A1 is poured firstly, and then the right half part of the concrete layer A2 is poured.
As shown in a in fig. 4, firstly, a sheet-like component with piles is inserted into two sides of a left half concrete layer a1 to be poured, the sheet-like component with piles inserted into the junction of the left half concrete layer a1 and the right half concrete layer a2 adopts a sheet-like component with piles provided with reinforcement holes 1c, and before insertion, the thin wall at the bottom of each reinforcement hole 1c is inserted through by using a steel bar. Before pouring concrete, firstly placing reinforcing steel bars in a concrete pouring area corresponding to the left half concrete layer A1, enabling the overlap reinforcing steel bars C needing to be anchored in the right half concrete layer A2 to penetrate through the penetrating reinforcing steel bar holes 1C, pouring concrete after the placement of the reinforcing steel bars is finished, and obtaining the left half concrete layer A1 after the concrete is solidified, wherein the step b is shown in figure 4.
As shown in c in fig. 4, a row of sheet-like elements with piles is inserted on the side, close to the shoulder, of the right concrete half a2 to be poured, so that concrete pouring areas corresponding to the right concrete half a2 are formed, after reinforcing steel bars are placed in the concrete pouring areas corresponding to the right concrete half a2, concrete is poured, and the right concrete half a2 is obtained after the concrete is solidified. And finishing the pouring construction of the road concrete layer.
It should be noted that, when inserting the above-mentioned sheet-like pile member, the worker may first grasp the grip portion 1a with his/her hand to lift the sheet-like pile member to the position where the formwork is inserted in the mat D, which has been previously lined, and then press the tread portion 1b downward with his/her foot to insert the pile head 2 into the mat D so that the member is vertically fixed (if the mat D is soft, the member may be further fixed with a proper amount of concrete). And after the concrete layer A is poured, covering soil on the outer side of the pile-bearing plate-shaped component and compacting to form a road shoulder, and paving a road surface layer on the concrete base layer A. The obvious difference between the road paved by the method and the existing road is that the left side, the right side and the middle of the concrete layer A are all inserted with the plate-shaped members with piles.
If the application occasion of the sheet-shaped member with the pile in the embodiment is a road with a narrow width (for example, a single-lane rural road), since the concrete layer a of the whole road is formed by one-time casting without overlapping steel bars, it is not necessary to provide the reinforcement penetrating hole 1c on the member body 1, the construction mode of the concrete layer a is much simpler than the construction mode of separately casting the concrete layer a into the left part and the right part, and the construction process is as follows: firstly, inserting sheet-shaped components with piles into two sides of a concrete layer A to be poured, splicing all the sheet-shaped components with piles side by side along the extending direction of a road, and inserting pile heads 2 into a cushion layer D or roadbed soil below the sheet-shaped components with piles, so that all the sheet-shaped components with piles are vertically fixed; and then pouring concrete into the concrete pouring area between the two rows of the pile plate-shaped members, and forming a concrete layer A after the poured concrete is solidified.
As can be seen from fig. 2 and 3, the overall construction of the staked plate-like members used in the above embodiments is very simple. Because the grasping part 1a and the treading part 1b are arranged on the member body 1, and the pile head 2 with the pile tip is arranged below the member body 1, during on-site construction, a sheet-shaped member with the pile can be manually inserted by workers to replace the existing steel mould. In addition, as the pile-bearing plate-shaped member does not need to be demolded after the pile-bearing plate-shaped member is adopted, the outer side of the pile-bearing plate-shaped member can be immediately covered with soil and compacted to form a road shoulder after concrete pouring is finished, and the road laying period can be greatly shortened. Finally, because the pile-carrying plate-shaped component has smaller size (can be manually held and lifted), the pile-carrying plate-shaped component can be used for moulding to form smoother road turning radian, the construction is more flexible, and the road appearance is better.
The above embodiments are preferred implementations of the present invention, and the present invention can be implemented in other ways without departing from the spirit of the present invention.
Some of the drawings and descriptions of the present invention have been simplified to facilitate the understanding of the improvements over the prior art by those skilled in the art, and some other elements have been omitted from this document for the sake of clarity, and it should be appreciated by those skilled in the art that such omitted elements may also constitute the subject matter of the present invention.

Claims (10)

1. Take stake platelike component is platelike component body (1) including whole, its characterized in that: the pile structure is characterized in that a pile head (2) is arranged below the component body (1), the pile head (2) and the component body (1) above the pile head (2) are integrally cast and molded through concrete, a pile tip is formed at the bottom end of the pile head (2), and a holding part (1 a) which is convenient for a hand to hold to lift the pile plate-shaped component and a treading part (1 b) which is convenient for a foot to tread to insert the pile head (2) downwards are arranged on the component body (1).
2. The staked plate-like member of claim 1, wherein: the grip portion (1 a) is provided on the top of the member body (1).
3. The staked plate-like member of claim 1, wherein: the pedal part (1 b) is arranged at the bottom of the component body (1).
4. The staked plate-like member of claim 2, wherein: a first rib (3) extending transversely is arranged at the top of the component body (1), and the first rib (3) protrudes outwards compared with the front surface of the component body (1), so that a holding part (1 a) is formed at the joint of the front surface of the component body (1) and the first rib (3).
5. The staked plate-like member of claim 4, wherein: and a second rib (4) extending transversely is arranged at the bottom of the component body (1), and the second rib (4) protrudes outwards compared with the front surface of the component body (1), so that a pedal part (1 b) is formed at the joint of the front surface of the component body (1) and the second rib (4).
6. The staked plate-like member of any one of claims 1-5, wherein: the front of the component body (1) is provided with a plurality of rib penetrating holes (1 c) at intervals, the rib penetrating holes (1 c) are blind holes and extend from the front to the back of the component body (1), and the hole bottom of the rib penetrating holes (1 c) is a thin wall which can be penetrated through by a steel bar.
7. The staked plate-like member of claim 5, wherein: both ends all are equipped with along vertical extension's floor (5) about component body (1), floor (5) are compared in the front of component body (1) and are outwards protruding, the top and first rib (3) of floor (5) link to each other, the bottom and the second rib (4) of floor (5) link to each other, floor (5), first rib (3), second rib (4) and component body (1) and pile head (2) are by the integrative casting shaping of concrete.
8. The road concrete layer pouring construction method is characterized in that the sheet-shaped component with the piles, which is disclosed by any one of claims 1 to 8, is used as a template, and the method comprises the following steps:
die filling: inserting pile-carrying plate-shaped members at two sides of a concrete layer (A) to be poured, splicing all the pile-carrying plate-shaped members side by side along the extending direction of a road and inserting pile heads (2) into a cushion layer (D) or roadbed soil below the pile-carrying plate-shaped members so that all the pile-carrying plate-shaped members are vertically fixed;
pouring concrete: pouring concrete into a concrete pouring area between the two rows of the pile plate-shaped members, and forming a concrete layer (A) after the poured concrete is solidified;
and finishing the pouring construction of the road concrete layer.
9. The road concrete layer pouring construction method according to claim 8, characterized in that: dividing the concrete layer (A) into a left part and a right part by taking the center line of the road as a boundary, pouring the left half part of the concrete layer (A1) firstly, and then pouring the right half part of the concrete layer (A2);
inserting pile-carrying plate-shaped components on two sides of a left half concrete layer (A1) to be poured, inserting the pile-carrying plate-shaped components inserted at the junction of the left half concrete layer (A1) and a right half concrete layer (A2) into the pile-carrying plate-shaped components of claim 6, poking through the reinforcement through holes (1C) of the pile-carrying plate-shaped components, placing reinforcing steel bars in concrete pouring areas corresponding to the left half concrete layer (A1) before pouring concrete, enabling lap-joint reinforcing steel bars (C) to be anchored in the right half concrete layer (A2) to penetrate through the reinforcement through holes (1C), pouring concrete after the placement of the reinforcing steel bars is finished, and obtaining the left half concrete layer (A1) after the concrete is solidified;
then inserting a row of sheet-like components with piles at one side, close to a road shoulder, of the right half concrete layer (A2) to be poured, so that a concrete pouring area corresponding to the right half concrete layer (A2) is formed, pouring concrete after placing steel bars in the concrete pouring area corresponding to the right half concrete layer (A2), and obtaining the right half concrete layer (A2) after the concrete is solidified;
and finishing the pouring construction of the road concrete layer.
10. A highway, includes concrete layer, its characterized in that: the concrete layer (a) is cast by the method of claim 9, and the pile-plate-shaped members are inserted into the left side, the right side and the middle of the concrete layer (a).
CN202010973874.0A 2020-09-16 2020-09-16 Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway Active CN112127228B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010973874.0A CN112127228B (en) 2020-09-16 2020-09-16 Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010973874.0A CN112127228B (en) 2020-09-16 2020-09-16 Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway

Publications (2)

Publication Number Publication Date
CN112127228A true CN112127228A (en) 2020-12-25
CN112127228B CN112127228B (en) 2022-04-08

Family

ID=73846846

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010973874.0A Active CN112127228B (en) 2020-09-16 2020-09-16 Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway

Country Status (1)

Country Link
CN (1) CN112127228B (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4712764A (en) * 1986-05-23 1987-12-15 Lee Roy White Flexible forms
KR20100092609A (en) * 2009-02-13 2010-08-23 신상원 Precast form structure for gutter and construction method using the same
US20120155960A1 (en) * 2010-12-17 2012-06-21 Dale Lowery Curb forming system
CN104350206A (en) * 2013-03-21 2015-02-11 朴海永 Prefabricated mold for construction of concrete pavement
CN106906726A (en) * 2017-03-13 2017-06-30 王本勋 A kind of cement concrete pavement steel form
WO2018055323A1 (en) * 2016-09-20 2018-03-29 Fast-Form Systems Ltd Road form work
CN207392014U (en) * 2017-10-24 2018-05-22 中国水利水电第十二工程局有限公司 Build highway template switching clamp device
CN110158424A (en) * 2019-06-12 2019-08-23 刘凌晓 Concrete-pouring template
CN209989835U (en) * 2019-04-24 2020-01-24 武汉中科岩土工程有限责任公司 Along river curb prestressed anchorage cable sheet-pile wall
CN110886176A (en) * 2019-12-17 2020-03-17 山东汇通建设集团有限公司 Multifunctional assembled road fender foundation roadbed concrete side mold
CN210856872U (en) * 2019-08-09 2020-06-26 郴州市鸿业建筑工程有限公司 Concrete road surface is laid and is used moulding structure
CN210975464U (en) * 2019-10-23 2020-07-10 甘肃省小陇山林业实验局基建管理中心 Concrete road foundation construction device

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4712764A (en) * 1986-05-23 1987-12-15 Lee Roy White Flexible forms
KR20100092609A (en) * 2009-02-13 2010-08-23 신상원 Precast form structure for gutter and construction method using the same
US20120155960A1 (en) * 2010-12-17 2012-06-21 Dale Lowery Curb forming system
CN104350206A (en) * 2013-03-21 2015-02-11 朴海永 Prefabricated mold for construction of concrete pavement
WO2018055323A1 (en) * 2016-09-20 2018-03-29 Fast-Form Systems Ltd Road form work
CN106906726A (en) * 2017-03-13 2017-06-30 王本勋 A kind of cement concrete pavement steel form
CN207392014U (en) * 2017-10-24 2018-05-22 中国水利水电第十二工程局有限公司 Build highway template switching clamp device
CN209989835U (en) * 2019-04-24 2020-01-24 武汉中科岩土工程有限责任公司 Along river curb prestressed anchorage cable sheet-pile wall
CN110158424A (en) * 2019-06-12 2019-08-23 刘凌晓 Concrete-pouring template
CN210856872U (en) * 2019-08-09 2020-06-26 郴州市鸿业建筑工程有限公司 Concrete road surface is laid and is used moulding structure
CN210975464U (en) * 2019-10-23 2020-07-10 甘肃省小陇山林业实验局基建管理中心 Concrete road foundation construction device
CN110886176A (en) * 2019-12-17 2020-03-17 山东汇通建设集团有限公司 Multifunctional assembled road fender foundation roadbed concrete side mold

Also Published As

Publication number Publication date
CN112127228B (en) 2022-04-08

Similar Documents

Publication Publication Date Title
CN104153493B (en) The concrete shear wall structure printed based on 3D and construction method thereof
CN114102811A (en) Method for manufacturing H-shaped concrete pile by adopting mould
CN107097331A (en) Sectional die, casting method and precast wall body structure for pouring precast wall body
CN101327613A (en) Method for manufacturing pre-fabricated reinforced concrete plate with rib
CN112127228B (en) Slab-shaped member with pile, pouring construction method for concrete layer of highway and highway
CN106393399A (en) Prefabricated stairway formwork
CN109252434A (en) A kind of asphalt pavement structure and its construction method
CN209703708U (en) It is a kind of for the pre-buried positioning device for hanging nail of prefabricated components
CN111335355A (en) Special-shaped block post-pouring type light retaining wall supporting structure and construction method thereof
CN101327614A (en) Method for manufacturing pre-fabricated reinforced concrete plate with rib
CN213358250U (en) Multipurpose sheet-like member with pile
CN109763458A (en) Dam body seepage wall trolley, walling mechanism, dam body seepage wall construction method
CN209812671U (en) Prefabricated square steel marking die
CN210798044U (en) Wallboard in prefabricated of assembly type structure
CN209686711U (en) Prefabricated laminated superposed column, reinforced column and assembled architecture body
CN110593075A (en) Arch bridge stone arch coupon fixing structure and construction method thereof
JP2586921B2 (en) Concrete stairs and construction method
CN205928989U (en) A non - design, can all rotary die plate bodys system for bench is prefabricated
CN206170283U (en) Prefabricated staircase mould
CN217759486U (en) Prefabricated plate structure and coincide floor
CN217424917U (en) Model test tunnel lining mould convenient to drawing of patterns
CN110145120A (en) A kind of constructional column cover die and the construction method with its pre-buried concrete-constituted pile reinforcing bar
CN213143868U (en) Hole construction tool is reserved to railing basis
KR20110051567A (en) Precast concrete road boundary part, method of forming the road boundary part using the same, and apparatus of forming the same
CN112065049A (en) Construction method of embedded flower bed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant