CN1120917C - 用于加固边坡的预应力抗滑桩及其施工方法 - Google Patents

用于加固边坡的预应力抗滑桩及其施工方法 Download PDF

Info

Publication number
CN1120917C
CN1120917C CN 00132690 CN00132690A CN1120917C CN 1120917 C CN1120917 C CN 1120917C CN 00132690 CN00132690 CN 00132690 CN 00132690 A CN00132690 A CN 00132690A CN 1120917 C CN1120917 C CN 1120917C
Authority
CN
China
Prior art keywords
pile
prestressed
side slope
slip
resisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 00132690
Other languages
English (en)
Other versions
CN1292448A (zh
Inventor
祝介旺
杨志法
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Institute of Geology and Geophysics of CAS
Original Assignee
Institute of Geology and Geophysics of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Institute of Geology and Geophysics of CAS filed Critical Institute of Geology and Geophysics of CAS
Priority to CN 00132690 priority Critical patent/CN1120917C/zh
Publication of CN1292448A publication Critical patent/CN1292448A/zh
Application granted granted Critical
Publication of CN1120917C publication Critical patent/CN1120917C/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

本发明公开了一种用于加固边坡的预应力抗滑桩及其方法,包括箍筋、钢筋和测斜管,箍筋圆周内分布有钢筋,在靠近滑动面对应的抗滑桩位置上设有预应力柱体。用混凝土浇注的抗滑桩具有中空部分。预应力柱为通长布设或局部布设。它克服了现有抗滑桩的缺点与不足,具有高效和重点的加固性能,提高检测效果,使抗滑桩更安全、更可靠,其抗滑效果更好。

Description

用于加固边坡的预应力抗滑桩及其施工方法
技术领域
本发明涉及用于加固边坡的预应力抗滑桩及其方法,尤其是一种具有高效和重点加固性能的预应力抗滑桩及其方法。
背景技术
为了加固岩体边坡,人们常常在坡面和坡趾前放入抗滑桩。目前现有的用于加固岩体边坡的抗滑桩主要做法是:
一.在滑体前挖大直径的适当深的桩孔;
二.在孔内放入事先做好的有主钢筋和箍筋且带有钢筋应力计的钢筋笼;
三.用混凝土浇筑形成桩;
四.将多根桩用横梁连接起来;
五.将桩间的缝隙用钢筋混凝土连接起来;
六.作桩间排水孔。
如图1、2所示,现有的用于加固岩体边坡的抗滑桩的主要结构为:在箍筋内均匀分布粗钢筋,箍筋内为实心的混凝土,箍筋外有适当厚度的混凝土保护层,有些抗滑桩在其混凝土内还设有测倾管。其工作原理是滑动体的推力作用于桩,桩体受弯,通过桩体内的钢筋受拉来承担滑体的推力,通过埋设在抗滑桩内的测倾管监测桩体的变形。
根据理论分析和现场应用实践,上述抗滑桩存在着以下不足:一、没有针对潜在的滑动面进行设计,桩内钢筋作等量通长布设,往往会造成潜在的滑动面部位的不安全和非滑动部位的浪费;二、抗滑桩内发挥主要作用的抗拉钢筋和发挥辅助作用的抗压钢筋不作区别,一律按等量设置,造成不必要的浪费;三、现有的抗滑桩通常都很粗大,有的桩体的横截面尺寸可达数米,所以混凝土用量很多。对于主要起抗滑作用的抗滑桩来说,中性面附近的混凝土所起作用很小,是一种浪费。
发明内容
本发明的目的是提供一种用于加固边坡的预应力抗滑桩及其方法,它克服了现有抗滑桩的缺点与不足,具有高效和重点的加固性能,提高检测效果,使抗滑桩更安全、更可靠,其抗滑效果更好。
本发明的目的是这样实现的:一种用于加固边坡的预应力抗滑桩,包括箍筋、主筋和测斜管,箍筋圆周内分布有主筋,在抗滑桩内受拉一侧位置上设有预应力柱体。
预应力柱为通长布设或局部布设。
用混凝土浇筑的抗滑桩具有中空部分。
抗滑桩的测斜管贴靠在中空部分的内壁上。
在中空部分再设置使之重新加固起来的钢筋混凝土或预应力柱。
数根抗滑桩用连接梁连结起来,所述抗滑桩之间为混凝土,在其间留设有排水孔。
在抗滑桩内的受拉一侧设有适当长度的预应力柱,其长度短于从坡面到稳定面之间的长度。
箍筋为圆形或螺旋形状。
一种用预应力抗滑桩加固边坡的方法,包括以下步骤:
一.在滑体前挖大直径的桩孔;
二.在工厂做好预应力柱,在柱周边埋设预埋件;
三.利用桩孔开挖过程进行工程地质分析,确定滑体的滑动面或潜在的滑动面;
四.将工厂做好的预应力柱作为受拉钢筋,将设置在抗滑桩内受拉一侧的预应力柱与其它抗滑桩主筋通过箍筋连接起来,安放在滑动面或潜在的滑动面处,作局部或作通长布设;
五.放置中空模板;
六.用混凝土浇筑形成中空的抗滑桩;
七.在中空部分的内侧安放测斜管;
八.作桩间排水孔。
上述方法还可在作桩间排水孔之前,包括以下步骤:
一.将多根桩用连接梁连接起来;
二.将桩间的缝隙用钢筋混凝土连接起来。
本发明具有以下优点:一、高效的加固性能:抗滑桩在滑体的作用下,主要是受弯和受剪,由于采用了预应力柱作为受拉钢筋,这就使抗滑桩的抗弯能力大大增强;二、重点加固效能:可利用挖桩孔过程准确地确定潜在滑动面的位置和产状,在这种情况下,可以针对滑动面作重点加固,即利用预应力柱加固,而对其他一般部位作通常粗钢筋加固;三、节约混凝土:将较粗大的抗滑桩作成中空的,从而节约了混凝土用量;四、补充加固性能:如果发现抗滑桩在使用过程中,变形过大,则可以将抗滑桩中空部分用钢筋混凝土或预应力柱重新加固起来;五、检测设备便于安装:由于抗滑桩做成中空的,因此非常有利于安装检测设备和对桩体破坏情况进行观察,必要时还可进入作业。
附图说明
图1为现行抗滑桩正立面结构示意图;
图2为图1的A-A截面图;
图3为本发明滑体—抗滑桩体系侧视图;
图4为本发明预应力抗滑桩的结构图;
图5为图4的B-B截面图;
图6为本发明部分预应力抗滑桩的结构图;
具体实施方式
下面结合附图详细说明依据本发明提出的用于加固边坡的预应力抗滑桩及其方法的具体结构和工作原理。
如图3、4、5、6所示,本发明预应力抗滑桩的主要做法是:
一.在滑体前挖大直径的适当深的桩孔;
二.在工厂做好预应力柱12,在柱周边埋设预埋件;
三.利用桩孔开挖过程进行工程地质分析,确定和估计滑体的滑动面或潜在的滑动面;
四.将工厂做好的预应力柱12作为受拉钢筋7,将预应力柱12与受压钢筋9通过箍筋8连接起来,安放在滑动面或潜在的滑动面处,作局部或作通长布设;
五.放置中空模板;
六.用混凝土浇筑形成中空的抗滑桩4;
七.在中空部分的内侧安放测斜管10;
八.将多根桩用连接横梁6连接起来;
七.将桩间的缝隙用钢筋混凝土连接起来;
八.作桩间排水孔5。
由图中可以看出,每一抗滑桩4包括箍筋8、主钢筋7和9、预应力柱12和测斜管,箍筋8可以为圆形或螺旋形状,它依桩体形状的不同而不同,箍筋8圆周内均匀分布主钢筋7和9,在靠近潜在滑动面2对应的抗滑桩4内受拉一侧位置上设有预应力柱12。
用于加固(岩体)边坡的预应力抗滑桩4具有中空部分14,将测斜管10从中空部分装入,贴靠在其内壁上,使其安装更为方便。
预应力抗滑桩4的中空部分14可以根据需要,在中空部分再设置钢筋混凝土或预应力柱,使之重新加固起来。
抗滑桩4设在坡面1和坡趾11间,在潜在滑动面2对应的抗滑桩4位置上设有适当长度的预应力柱12’,其长度短于从坡面1到稳定面3之间的长度,也就是说预应力柱12不是通长设置的,如图6所示,这样既可起到加强的作用,又可节省预应力柱。
数根抗滑桩4用连接梁连结起来,所述抗滑桩之间为混凝土,在其间留设有排水孔5。

Claims (10)

1.一种用于加固边坡的预应力抗滑桩,包括箍筋、主筋和测斜管,其特征在于:箍筋圆周内分布有主筋,在抗滑桩内受拉一侧位置上设有预应力柱体。
2.如权利要求1所述的用于加固边坡的预应力抗滑桩,其特征在于:预应力柱为通长布设或局部布设。
3.如权利要求1所述的用于加固边坡的预应力抗滑桩,其特征在于:用混凝土浇筑的抗滑桩具有中空部分。
4.如权利要求3所述的用于加固边坡的预应力抗滑桩,其特征在于:抗滑桩的测斜管贴靠在中空部分的内壁上。
5.如权利要求3所述的用于加固边坡的预应力抗滑桩,其特征在于:在中空部分再设置使之重新加固起来的钢筋混凝土或预应力柱。
6.如权利要求1所述的用于加固边坡的预应力抗滑桩,其特征在于:数根抗滑桩用连接梁连结起来,所述抗滑桩之间为混凝土,在其间留设有排水孔。
7.如权利要求1所述的用于加固边坡的预应力抗滑桩,其特征在于:在抗滑桩内的受拉一侧设有适当长度的预应力柱,其长度短于从坡面到稳定面之间的长度。
8.如权利要求1所述的用于加固边坡的预应力抗滑桩,其特征在于:箍筋为圆形或螺旋形状。
9.一种用预应力抗滑桩加固边坡的方法,其特征在于:包括以下步骤:
一.在滑体前挖大直径的桩孔;
二.在工厂做好预应力柱,在柱周边埋设预埋件;
三.利用桩孔开挖过程进行工程地质分析,确定滑体的滑动面或潜在的滑动面;
四.将工厂做好的预应力柱作为受拉钢筋,将设置在抗滑桩内受拉一侧的预应力柱与其它抗滑桩主筋通过箍筋连接起来,安放在滑动面或潜在的滑动面处,作局部或作通长布设;
五.放置中空模板;
六.用混凝土浇筑形成中空的抗滑桩;
七.在中空部分的内侧安放测斜管;
八.作桩间排水孔。
10.如权利要求9所述的用预应力抗滑桩加固边坡的方法,其特征在于:在作桩间排水孔之前,还包括以下步骤:
一.将多根桩用连接梁连接起来;
二.将桩间的缝隙用钢筋混凝土连接起来。
CN 00132690 2000-11-17 2000-11-17 用于加固边坡的预应力抗滑桩及其施工方法 Expired - Fee Related CN1120917C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00132690 CN1120917C (zh) 2000-11-17 2000-11-17 用于加固边坡的预应力抗滑桩及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00132690 CN1120917C (zh) 2000-11-17 2000-11-17 用于加固边坡的预应力抗滑桩及其施工方法

Publications (2)

Publication Number Publication Date
CN1292448A CN1292448A (zh) 2001-04-25
CN1120917C true CN1120917C (zh) 2003-09-10

Family

ID=4595326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00132690 Expired - Fee Related CN1120917C (zh) 2000-11-17 2000-11-17 用于加固边坡的预应力抗滑桩及其施工方法

Country Status (1)

Country Link
CN (1) CN1120917C (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1313681C (zh) * 2005-02-28 2007-05-02 王凯 捆绑式抗滑桩结构及施工方法
CN100497844C (zh) * 2007-02-14 2009-06-10 中铁西北科学研究院有限公司 适用于多层滑面及深层滑面的多锚点抗滑桩的设置方法

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1298938C (zh) * 2004-12-08 2007-02-07 重庆交通科研设计院 后张法桩身预应力抗滑桩及施工方法
CN101845819B (zh) * 2010-05-25 2012-02-22 武汉大学 一种深厚土质边坡的加固支护方法
CN101881025B (zh) * 2010-07-01 2012-01-18 中国水电顾问集团华东勘测设计研究院 用于深厚覆盖层边坡支护的浅埋式柔性抗滑桩的设计方法
CN102140800B (zh) * 2011-01-24 2012-10-03 中铁西北科学研究院有限公司 一种快速安全环保的非开挖式抗滑桩施工方法
CN102493436A (zh) * 2011-11-25 2012-06-13 中冶集团武汉勘察研究院有限公司 矩形抗滑桩人工掘进新工法
CN102660956B (zh) * 2012-05-25 2015-04-01 薛忠群 混凝土胎模结构及浇筑方法
CN104018496B (zh) * 2014-05-13 2017-01-04 中冶集团武汉勘察研究院有限公司 一种桩身设置水平加腋梁的圆形截面抗滑桩及其施工方法
CN105544565A (zh) * 2016-01-14 2016-05-04 广西大学 一种边坡抗滑支挡结构
CN109235465A (zh) * 2018-09-20 2019-01-18 中铁二院工程集团有限责任公司 打入预应力超强混凝土管桩护壁式小型组合抗滑桩结构

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1313681C (zh) * 2005-02-28 2007-05-02 王凯 捆绑式抗滑桩结构及施工方法
CN100497844C (zh) * 2007-02-14 2009-06-10 中铁西北科学研究院有限公司 适用于多层滑面及深层滑面的多锚点抗滑桩的设置方法

Also Published As

Publication number Publication date
CN1292448A (zh) 2001-04-25

Similar Documents

Publication Publication Date Title
CN1120917C (zh) 用于加固边坡的预应力抗滑桩及其施工方法
CN200964593Y (zh) 可回收式预应力锚索
US7033116B1 (en) Post-tensioned rammed earth construction
CN1064424C (zh) 一种具有防水、挡土和承重功能的地下连续墙的施工方法
CN1776105A (zh) 预制预应力钢筋混凝土底板、具有其的桥梁及其施工方法
CN1112484C (zh) 施加预应力的地下连续墙
CN111364364A (zh) 现浇筑预应力混凝土连续箱梁施工方法
Giongo et al. On-site testing of masonry shear walls strengthened with timber panels
CN1313681C (zh) 捆绑式抗滑桩结构及施工方法
CN1619063A (zh) 后张法桩身预应力抗滑桩及施工方法
CN101029488A (zh) 部分粘接预应力抗拔抗浮桩及其施工方法
CN1051129C (zh) 预应力锚索无腰梁护壁桩锚固工法
CN2469046Y (zh) 挖孔桩预制钢筋砼护壁
CN211006396U (zh) 混凝土原桥的加固结构
CN1278573A (zh) 用于加固岩石边坡的预应力锚梁
Zumrawi et al. A study on Strengthening of Building foundation for Storey Extension
CN2809391Y (zh) 超大截面向心应力抗变形涵管
CN111058368A (zh) 一种利用高强灌浆料的波纹钢加强拱及其搭建方法
CN1037286C (zh) 一种基坑支护结构及其施工方法
CN2679263Y (zh) 半预铸梁柱接头
CN2787965Y (zh) 大截面圆心应力抗震涵管
CN2760113Y (zh) 预置劲芯夯实水泥土桩
CN217810309U (zh) 一种基于预应力混凝土的道路桥梁裂缝加固结构
CN215630017U (zh) 一种应用于基坑中的植筋水泥土支护结构
De Rose et al. The rehabilitation of a concrete structure using fibre reinforced plastics

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: INST OF GEOLOGY AND GEOPHYSICS, CHINESE ACADEMY OF

Free format text: FORMER NAME: INSTITUTE OF GEOLOGY, CHINESE ACADEMY OF SCIENCES

CP03 Change of name, title or address

Address after: Beijing City, Qi Jia Huo Zi Chinese Academy of Sciences Institute of Geology

Patentee after: Institute of Geology and Geophysics, Chinese Academy of Sciences

Address before: Beijing City, Qi Jia Huo Zi Chinese Academy of Sciences Institute of Geology

Patentee before: Inst. of Geology, Chinese Academy of Sciences

EE01 Entry into force of recordation of patent licensing contract

Assignee: China Railway Construction Engineering Bureau No.16 Group Corp., Ltd.

Assignor: Inst. of Geology, Chinese Academy of Sciences

Contract fulfillment period: 2009.4.28 to 2014.4.30 contract change

Contract record no.: 2009990000545

Denomination of invention: Prestressed slip-resisting pile for reinforcing side slope and its method

Granted publication date: 20030910

License type: Exclusive license

Record date: 2009.5.22

LIC Patent licence contract for exploitation submitted for record

Free format text: EXCLUSIVE LICENSE; TIME LIMIT OF IMPLEMENTING CONTACT: 2009.4.28 TO 2014.4.30; CHANGE OF CONTRACT

Name of requester: CHINA RAILWAY 16 BUREAU GROUP CO., LTD.

Effective date: 20090522

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20030910

Termination date: 20101117