CN112082193A - Floor heating pipe pipeline collection module structure and connecting and mounting method thereof - Google Patents

Floor heating pipe pipeline collection module structure and connecting and mounting method thereof Download PDF

Info

Publication number
CN112082193A
CN112082193A CN202011030685.6A CN202011030685A CN112082193A CN 112082193 A CN112082193 A CN 112082193A CN 202011030685 A CN202011030685 A CN 202011030685A CN 112082193 A CN112082193 A CN 112082193A
Authority
CN
China
Prior art keywords
pipeline
supporting
connecting plate
support
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011030685.6A
Other languages
Chinese (zh)
Other versions
CN112082193B (en
Inventor
丁欣欣
丁泽成
王文广
周东珊
许伟
武鹏
余文钊
王雨梦
张建平
张西亮
王晓杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yasha Decoration Co Ltd
Original Assignee
Zhejiang Yasha Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Yasha Decoration Co Ltd filed Critical Zhejiang Yasha Decoration Co Ltd
Priority to CN202011030685.6A priority Critical patent/CN112082193B/en
Publication of CN112082193A publication Critical patent/CN112082193A/en
Application granted granted Critical
Publication of CN112082193B publication Critical patent/CN112082193B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/141Tube mountings specially adapted therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/146Tubes specially adapted for underfloor heating
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Floor Finish (AREA)

Abstract

The invention provides a floor heating pipe pipeline collection module structure and a connecting and installing method thereof, and belongs to the technical field of floor heating pipe installation. The ground heating pipe pipeline collecting module structure and the connecting and installing method thereof comprise a pipeline supporting piece, an adjusting supporting piece, a heat insulation board, a ground heating pipe groove and a supporting plate. The adjusting support supports and can adjust the height of the pipeline support, so that the height of the pipeline support can be adjusted in real time, the height of the ground heating pipe can be adjusted, the periphery of one pipeline support is supported by the adjusting support respectively, one side end of the adjacent other pipeline support is arranged on the supporting plate positioned on one side end of the pipeline support, and the other side end of the adjacent other pipeline support is supported by the adjusting support, so that the installation of 2 adjacent pipeline supports can be realized, one set of adjusting support can be saved, the module is pipeline installation, the installation is simple and convenient, the construction is rapid, the labor hour is reduced, the construction period is shortened, and the field operation environment is green.

Description

Floor heating pipe pipeline collection module structure and connecting and mounting method thereof
Technical Field
The invention relates to the technical field of floor heating pipeline installation, in particular to a floor heating pipeline collection module structure and a connection installation method thereof.
Background
In built on stilts dry process underfloor heating system, every share of pipeline of ground heating coil generally chooses for use about 80m, and every share of water pipe need connect and divide the hydrophone, and current built on stilts ground heating scheme, every share of water pipe coil pipe accomplish the back, can follow and open a slot below built on stilts backup pad, wear out the water pipe and connect and divide the hydrophone. 1. During the installation, can not all accomplish the back at leveling support module installation and debugging, at dress ground heating coil, otherwise ground heating coil is when the overhead layer, and the installer can not see the overhead layer condition, and this kind of condition solution generally has two kinds:
1, installing an air conditioner module required by each floor heating pipe according to a deepening drawing, leveling after installation, performing water pipe coil pipe, connecting a water collecting and distributing device, and installing the following modules; the construction mode can cause the waste of workers and working hours, workers of the coil pipe and workers of the overhead leveling module can not coincide in time and need to carry out batch operation, and the water pipe running on the overhead layer can cause heat loss, thus being not beneficial to energy conservation;
2, after the overhead leveling module is completely installed, when the floor heating pipe coil is arranged, on-site grooving is carried out at the non-standard bent pipe, so that a plurality of notches appear, and the on-site efficiency and the operating environment are influenced; and warm up the business turn over water pipe and do not regard as warm up heating part, if adopt the modulus of bearing piece, water pipe interval 150mm has increaseed not heating area, is unfavorable for whole heating effect.
When the existing floor heating is installed, the overhead leveling modules need to be installed one by one, rapid installation cannot be realized through the matching of adjacent modules, and the traveling direction of the existing floor heating is single.
Disclosure of Invention
The invention aims to provide a structure of a floor heating pipe collecting module and a connecting and installing method thereof, aiming at the defects of the prior art.
The invention provides a floor heating pipe pipeline gathering module structure which comprises a plurality of pipeline supporting pieces, adjusting supporting pieces, heat insulation plates, floor heating pipe grooves and supporting plates, wherein the adjusting supporting pieces are used for supporting and adjusting the heights of the pipeline supporting pieces, the heat insulation plates are arranged on the pipeline supporting pieces, the floor heating pipe grooves are arranged on the heat insulation plates, the supporting plates are arranged on the adjusting supporting pieces, the periphery of one pipeline supporting piece is respectively supported by the adjusting supporting pieces, one side end of the adjacent other pipeline supporting piece is arranged on the supporting plate arranged at one side end of the one pipeline supporting piece, and the other side end of the adjacent other.
Furthermore, the pipeline supporting piece comprises a bearing plate, a supporting rib arranged on the bearing plate and a first mounting groove arranged on the supporting rib, and the top end of the adjusting supporting piece is screwed in the first mounting groove.
Furthermore, a plurality of supporting ribs are arranged on the bearing plate, the supporting ribs on one pipeline supporting piece are arranged in parallel, and the supporting ribs on one pipeline supporting piece are arranged at equal intervals.
Furthermore, the support rib comprises a first reinforcing rib integrally formed with the bearing plate, a second reinforcing rib fixed at the top end of the first reinforcing rib, and a third reinforcing rib fixed at the bottom end of the first reinforcing rib, the first mounting groove penetrates through the second reinforcing rib, the first reinforcing rib and the third reinforcing rib, the adjusting support piece comprises a threaded column screwed in the first mounting groove, a support base arranged at the bottom end of the threaded column, and a clamping seat used for supporting the third reinforcing rib, a second mounting groove is arranged in the middle of the clamping seat, and the threaded column is screwed in the second mounting groove.
Furthermore, the supporting plate comprises a first connecting plate, a second connecting plate connected to one end of the top of the first connecting plate, a third connecting plate connected to the other end of the top of the first connecting plate, a fourth connecting plate used for enabling the top ends of two adjacent pipeline supporting pieces to be kept flush when the supporting plate bears another adjacent pipeline supporting piece, a first fastening structure used for fixing the second connecting plate to one end of the second reinforcing rib, and a second fastening structure used for fixing the third connecting plate to the other end of the second reinforcing rib, wherein the fourth connecting plate is fixed to the bottom of the first connecting plate.
Furthermore, the first fastening structure comprises a first fixing hole arranged on the second connecting plate and a first screw used for penetrating through the first fixing hole at one end and connecting to one end of the second reinforcing rib, and the second fastening structure comprises a second fixing hole arranged on the third connecting plate and a second screw used for penetrating through the second fixing hole at one end and connecting to the other end of the second reinforcing rib.
Further, the support rib on one of the two adjacent bearing plates and the support rib on the other bearing plate are arranged in parallel or vertically.
Furthermore, the joint seat comprises a fifth connecting plate used for supporting the third reinforcing rib, a first stop plate used for limiting one end of the third reinforcing rib, and a second stop plate used for limiting the other end of the third reinforcing rib.
Furthermore, the second connecting plate and the third connecting plate are symmetrically arranged, the second connecting plate, the third connecting plate and the second reinforcing rib are perpendicular to the bearing plate, one end of the first screw penetrates through the first fixing hole and is connected to one end of the second reinforcing rib when the bottom end of the second connecting plate abuts against one end of the bearing plate, and one end of the second screw penetrates through the second fixing hole and is connected to the other end of the second reinforcing rib when the bottom end of the third connecting plate abuts against the other end of the bearing plate.
A method for installing a collecting module structure of a floor heating pipe pipeline comprises the following steps:
s1: installing a plurality of adjusting supporting pieces on one pipeline supporting piece, and rotating the adjusting supporting pieces to enable the whole pipeline supporting piece to be kept horizontal;
s2: mounting a support plate on an adjustment support on one side end of a pipeline support;
s3: placing one side end of another pipeline supporting piece on a supporting plate piece positioned at one side end of the pipeline supporting piece adjacent to the pipeline supporting piece;
s4: and installing an adjusting support member on the other side end of the other pipeline support member, and rotating the adjusting support member to enable the other pipeline support member to be kept horizontal integrally.
The invention discloses a floor heating pipe pipeline collection module structure and a connecting and installing method thereof, which have the following beneficial effects:
1. the heat insulation plate is supported by the pipeline supporting piece, the floor heating pipe is installed in the floor heating pipe groove, the installation is simple and convenient, the height of the pipeline supporting piece is supported and can be adjusted by the adjusting supporting piece, the height of the pipeline supporting piece can be adjusted in real time, the height of the floor heating pipe can be adjusted by the adjusting supporting piece on the periphery of one pipeline supporting piece, one side end of the adjacent other pipeline supporting piece is arranged on the supporting plate on one side end of the one pipeline supporting piece, the other side end of the adjacent other pipeline supporting piece is supported by the adjusting supporting piece, the installation of 2 adjacent pipeline supporting pieces can be realized, one set of adjusting supporting piece can be saved, the pipeline installation of a module is realized, the installation is simple and convenient, the construction is rapid;
2. support rib on the loading board in two adjacent and support rib on another loading board are parallel or perpendicular setting, then the trend of two adjacent ground heating coil is perpendicular or parallel, is applicable in the walking of the access pipeline arbitrary direction of warm up and collects to meet the less department of area that remains at last in the same mounting area and can pass through the direction that changes ground heating coil, thereby increase the heating area, improve the heating effect.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate embodiments of the invention and together with the description, serve to explain the principles of the invention. In the drawings, like reference numerals are used to indicate like elements. The drawings in the following description are directed to some, but not all embodiments of the invention. For a person skilled in the art, other figures can be derived from these figures without inventive effort.
Fig. 1 is a schematic structural diagram of a structure of a floor heating pipe collecting module and a connecting and installing method thereof according to an embodiment of the present invention;
fig. 2 is an enlarged view of a portion a of fig. 1 in a structure of a floor heating pipe collecting module and a connecting and installing method thereof according to an embodiment of the present invention;
fig. 3 is a partial structural schematic view of a structure of a floor heating pipe pipeline collecting module and a connecting and installing method thereof according to an embodiment of the present invention, when two adjacent pipeline supporting members are connected;
fig. 4 is a schematic structural view illustrating a pipe support member installed in a floor heating pipe collecting module structure and a connecting and installing method thereof according to an embodiment of the present invention;
fig. 5 is a schematic structural view illustrating a pipe support member installed at one end of fig. 4 near a wall in a structure of a floor heating pipe collecting module and a connection installation method thereof according to an embodiment of the present invention;
fig. 6 is a schematic structural view illustrating a pipe support member installed at one end of the pipe support member in fig. 5 according to an embodiment of the present invention;
fig. 7 is a schematic structural view of a ground heating pipe pipeline collection module structure and a connection installation method thereof according to an embodiment of the present invention, when an insulation board is installed on the pipeline supporting member in fig. 6 and a ground heating pipe is laid;
fig. 8 is a flow chart illustrating a structure of a floor heating pipe collecting module and a connecting and installing method thereof according to an embodiment of the present invention.
In the figure: the structure comprises the following components, by weight, 1-a bearing plate, 11-a support rib, 12-a first mounting groove, 2-an adjusting support piece, 21-a threaded column, 22-a support base, 231-a fifth connecting plate, 232-a first stop plate, 233-a second stop plate, 31-a fourth connecting plate, 32-a second connecting plate, 33-a third connecting plate, 34-a first fastening structure, 35-a second fastening structure, 4-a heat insulation plate and 41-a floor heating pipe groove.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention. It should be noted that the embodiments and features of the embodiments in the present application may be arbitrarily combined with each other without conflict.
Please refer to fig. 1 to 8. The ground heating pipe pipeline gathering module structure comprises a plurality of pipeline supporting pieces, an adjusting supporting piece 2 used for supporting and adjusting the height of the pipeline supporting pieces, a heat insulation board 4 arranged on the pipeline supporting pieces, a ground heating pipe groove 41 arranged on the heat insulation board 4 and a supporting plate piece arranged on the adjusting supporting piece 2, wherein the periphery of one pipeline supporting piece is respectively supported by the adjusting supporting piece 2, one side end of the adjacent other pipeline supporting piece is arranged on the supporting plate piece positioned on one side end of the one pipeline supporting piece, and the other side end of the adjacent other pipeline supporting piece is supported by the adjusting supporting piece 2.
Here, pipeline support piece supports heated board 4, the ground heating coil is installed in ground heating coil groove 41, simple installation, adjust support piece 2 and support and adjustable pipeline support piece's height, thereby can adjust pipeline support piece's height in real time and adjust the height of ground heating coil, a pipeline support piece supports through adjusting support piece 2 respectively all around, the support plate that is located a pipeline support piece one side end is arranged in to adjacent another pipeline support piece one side end, other sides of adjacent another pipeline support piece support through adjusting support piece 2, both can realize adjacent 2 pipeline support piece's installation, can save one set of regulation support piece 2 simultaneously, it is the piping erection to realize the module, simple installation, the construction is swift, reduce man-hour, the reduction of erection time, the on-the-site operation environment is greenization.
The pipeline supporting member may include a loading plate 1, a supporting rib 11 disposed on the loading plate 1, and a first mounting groove 12 disposed on the supporting rib 11, and the top end of the adjusting supporting member 2 is screwed to the first mounting groove 12. The ground heating coil is arranged above the bearing plate 1 to reduce heat loss.
The carrier plate 1 may be provided with a plurality of support ribs 11, the support ribs 11 on one pipeline support being arranged in parallel, the support ribs 11 on one pipeline support being arranged at equal intervals.
Support rib 11 can include the first stiffening rib with loading board 1 integrated into one piece, be fixed in the second stiffening rib on first stiffening rib top, be fixed in the third stiffening rib of first stiffening rib bottom, first mounting groove 12 runs through in the second stiffening rib, first stiffening rib, the third stiffening rib, adjust support piece 2 including the screw thread post 21 of spiro union in first mounting groove 12, set up in the support base 22 of screw thread post 21 bottom, a joint seat for supporting for the third stiffening rib, the joint seat middle part is equipped with the second mounting groove, screw thread post 21 spiro union in the second mounting groove.
The support plate may comprise a first connection plate, a second connection plate 32 connected to one end of the top of the first connection plate, a third connection plate 33 connected to the other end of the top of the first connection plate, a fourth connection plate 31 for keeping the top ends of two adjacent pipe supports level when they carry another adjacent pipe support, a first fastening structure 34 for fixing the second connection plate 32 to one end of the second reinforcing rib, a second fastening structure 35 for fixing the third connection plate 33 to the other end of the second reinforcing rib, the fourth connection plate 31 being fixed to the bottom of the first connection plate.
The first fastening structure 34 may include a first fixing hole disposed on the second connecting plate 32, a first screw for penetrating the first fixing hole at one end and connecting to one end of the second reinforcing rib, and the second fastening structure 35 includes a second fixing hole disposed on the third connecting plate 33, a second screw for penetrating the second fixing hole at one end and connecting to the other end of the second reinforcing rib.
Support rib 11 on one loading board 1 in two adjacent can with the support rib 11 on another loading board 1 parallel or perpendicular setting, then the trend of two adjacent ground heating coil is perpendicular or parallel, applicable in the ground any direction walking of access line way and collect of warming up to meet the less department of area that remains at last in the same installation area and can pass through the direction that changes ground heating coil, thereby increase the heating area, improve the heating effect.
The chuck may include a fifth connection plate 231 to support the third reinforcing rib, a first stopper plate 232 to limit one end of the third reinforcing rib, and a second stopper plate 233 to limit the other end of the third reinforcing rib.
The second connecting plate 32 and the third connecting plate 33 can be symmetrically arranged, the second connecting plate 32, the third connecting plate 33 and the second reinforcing rib are perpendicular to the bearing plate 1, one end of the first screw penetrates through the first fixing hole and is connected to one end of the second reinforcing rib when the bottom end of the second connecting plate 32 abuts against one end of the bearing plate 1, and one end of the second screw penetrates through the second fixing hole and is connected to the other end of the second reinforcing rib when the bottom end of the third connecting plate 33 abuts against the other end of the bearing plate 1.
The fourth connecting plate 31 is parallel to the carrier plate 1, so that it is ensured that one of the adjacent pipe supports placed on the fourth connecting plate 31 is parallel to the pipe support, and the top ends of the 2 pipe supports are kept flush.
Referring to fig. 1 to 8, a method for installing a pipe collecting module structure of a floor heating pipe includes the following steps:
s1: installing a plurality of adjusting support members 2 on one pipeline support member, and rotating the adjusting support members 2 to keep one pipeline support member horizontal as a whole;
s2: mounting a support plate on an adjusting support 2 located on one side end of one of the pipe supports;
s3: placing one side end of another pipeline supporting piece on a supporting plate piece positioned at one side end of the pipeline supporting piece adjacent to the pipeline supporting piece;
s4: the other side end of the other pipeline support member is provided with an adjusting support member 2, and the adjusting support member 2 is screwed to keep the other pipeline support member horizontal as a whole.
The bearing plate 1 can be a hollow stone plastic plate, the hollow stone plastic plate can play an effective heat preservation effect, the weight of the bearing plate is smaller, and the heat preservation plate 4 for installing the floor heating pipeline can reduce heat loss after being installed on the stone plastic plate, so that heat preservation on the ground is facilitated.
When the direction of the water pipe inlet and outlet pipeline is not consistent with that of the adjacent water pipe pipeline, a pipeline module needs to be installed; when the temperature difference is consistent, the adjusting support piece 2 is directly selected, the insulation board 4 is selected from a plane, and the groove is formed on the spot;
1, water pipes enter and exit pipelines along the wall, a support plate is arranged at the position of a support rib 11 of a bearing plate 1, each support rib 11 needs to be arranged, a pipeline support piece is lapped on the support plate, a threaded column 21 is arranged on the support rib 11 close to the wall, and the height of the threaded column is adjusted to be equal to that of an adjacent bearing module;
2 the water pipe inlet and outlet pipeline is arranged in the middle of a room, such as a middle corridor opposite to the room, and is generally a water pipe inlet and outlet pipeline collection position, supporting plate parts are arranged at the supporting ribs 11 of the adjusting and supporting parts 2 at the two sides of the supporting plate, the cut pipeline supporting parts are lapped on the supporting plate parts, adjusting pins in the supporting ribs 11 at the middle part of the adjusting and supporting parts 2 are adjusted, and the leveling height is ensured to be consistent;
3, installing an insulation board 4, placing the planar insulation board 4 above the supporting plate, and cutting the insulation board 4 on site according to the required space of the water pipe;
4, working the coil pipe of the floor heating water pipe, connecting the coil pipe to the water collecting and distributing device, and testing the water pressure for 24 hours;
5 paving a balance layer cover plate.
The above-described aspects may be implemented individually or in various combinations, and such variations are within the scope of the present invention.
It should be noted that, in the description of the present application, it should be noted that the terms "upper end", "lower end" and "bottom end" indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the drawings or the orientation or positional relationship which the product of the application is usually placed in when the product of the application is used, and are only for convenience of describing the present application and simplifying the description, but do not indicate or imply that the device referred to must have a specific orientation, be constructed in a specific orientation and be operated, and thus, should not be construed as limiting the present application. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
Finally, it should be noted that: the above examples are only for illustrating the technical solutions of the present invention, and are not limited thereto. Although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (10)

1. The utility model provides a ground heating coil pipe way collects modular structure which characterized in that: including a plurality of pipeline support piece, be used for supporting and adjustable pipeline support piece's height adjust support piece (2), set up heated board (4) on pipeline support piece, set up floor heating pipe groove (41) on heated board (4), set up the support plate on adjusting support piece (2), one pipeline support piece supports, adjacent another through adjusting support piece (2) respectively all around pipeline support piece one side is arranged in and is located one the support plate on pipeline support piece one side end, adjacent another other pipeline support piece's other sides are through adjusting support piece (2) support.
2. The floor heating pipe line collection modular structure of claim 1, wherein: the pipeline supporting piece comprises a bearing plate (1), a supporting rib (11) arranged on the bearing plate (1) and a first mounting groove (12) arranged on the supporting rib (11), and the top end of the adjusting supporting piece (2) is in threaded connection with the first mounting groove (12).
3. A floor heating pipe collection module structure as set forth in claim 2, wherein: the bearing plate (1) is provided with a plurality of supporting ribs (11), one supporting rib (11) on the pipeline supporting piece is arranged in parallel, and the other supporting rib (11) on the pipeline supporting piece is arranged at equal intervals.
4. A floor heating pipe collection module structure as claimed in claim 2 or 3, wherein: support rib (11) including with loading board (1) integrated into one piece's first stiffening rib, be fixed in the second stiffening rib on first stiffening rib top, be fixed in the third stiffening rib of first stiffening rib bottom, first mounting groove (12) run through in second stiffening rib, first stiffening rib, third stiffening rib, adjust support piece (2) including spiro union in screw thread post (21) of first mounting groove (12), set up in support base (22) of screw thread post (21) bottom, be used for carrying out the joint seat that supports for the third stiffening rib, joint seat middle part is equipped with the second mounting groove, screw thread post (21) spiro union in the second mounting groove.
5. The floor heating pipe line collection modular structure of claim 4, wherein: the supporting plate comprises a first connecting plate, a second connecting plate (32) connected to one end of the top of the first connecting plate, a third connecting plate (33) connected to the other end of the top of the first connecting plate, a fourth connecting plate (31) used for enabling the top ends of two adjacent pipeline supporting pieces to be kept flush when the supporting plate bears another adjacent pipeline supporting piece, a first fastening structure (34) used for fixing the second connecting plate (32) to one end of the second reinforcing rib, and a second fastening structure (35) used for fixing the third connecting plate (33) to the other end of the second reinforcing rib, wherein the fourth connecting plate (31) is fixed to the bottom of the first connecting plate.
6. The floor heating pipe line collection module structure of claim 5, wherein: the first fastening structure (34) comprises a first fixing hole arranged on the second connecting plate (32) and a first screw used for penetrating through the first fixing hole at one end and being connected to one end of the second reinforcing rib, and the second fastening structure (35) comprises a second fixing hole arranged on the third connecting plate (33) and a second screw used for penetrating through the second fixing hole at one end and being connected to the other end of the second reinforcing rib.
7. The floor heating pipe line collection modular structure of claim 6, wherein: the supporting ribs (11) on one bearing plate (1) and the supporting ribs (11) on the other bearing plate (1) in two adjacent bearing plates are arranged in parallel or vertically.
8. The floor heating pipe line collection modular structure of claim 4, wherein: the clamping seat comprises a fifth connecting plate (231) used for supporting the third reinforcing rib, a first stop plate (232) used for limiting one end of the third reinforcing rib, and a second stop plate (233) used for limiting the other end of the third reinforcing rib.
9. The floor heating pipe line collection modular structure of claim 6, wherein: the second connecting plate (32) and the third connecting plate (33) are symmetrically arranged, the second connecting plate (32), the third connecting plate (33) and the second reinforcing rib are perpendicular to the bearing plate (1), one end of each first screw penetrates through the first fixing hole and is connected to one end of the second reinforcing rib when the bottom end of the second connecting plate (32) abuts against one end of the bearing plate (1), and one end of each second screw penetrates through the second fixing hole and is connected to the other end of the second reinforcing rib when the bottom end of the third connecting plate (33) abuts against the other end of the bearing plate (1).
10. A method of installing a floor heating pipe collection module as claimed in any preceding claim, including the steps of:
s1: mounting a plurality of adjusting support members (2) on one pipeline support member, and rotating the adjusting support members (2) to keep one pipeline support member horizontal as a whole;
s2: mounting a support plate on an adjusting support (2) located on one side end of one of the pipeline supports;
s3: placing one side end of another pipeline supporting piece on a supporting plate piece positioned at one side end of the pipeline supporting piece adjacent to the pipeline supporting piece;
s4: and installing an adjusting support member (2) on the other side end of the other pipeline support member, and rotating the adjusting support member (2) to enable the other pipeline support member to be kept horizontal as a whole.
CN202011030685.6A 2020-09-27 2020-09-27 Floor heating pipe pipeline collecting module structure and connection installation method thereof Active CN112082193B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011030685.6A CN112082193B (en) 2020-09-27 2020-09-27 Floor heating pipe pipeline collecting module structure and connection installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011030685.6A CN112082193B (en) 2020-09-27 2020-09-27 Floor heating pipe pipeline collecting module structure and connection installation method thereof

Publications (2)

Publication Number Publication Date
CN112082193A true CN112082193A (en) 2020-12-15
CN112082193B CN112082193B (en) 2024-04-12

Family

ID=73738348

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011030685.6A Active CN112082193B (en) 2020-09-27 2020-09-27 Floor heating pipe pipeline collecting module structure and connection installation method thereof

Country Status (1)

Country Link
CN (1) CN112082193B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004030712A1 (en) * 2004-06-25 2006-01-19 Josef Blome Prefabricated bathroom wall hot and cold water supply installation kit with supply point
CN208252957U (en) * 2018-06-04 2018-12-18 中建八局第二建设有限公司 Floor heating branch pipe fixing device at a kind of water collecting and diversifying device
CN110242002A (en) * 2019-04-29 2019-09-17 浙江亚厦装饰股份有限公司 Floor heating assembly and installation method
CN110242003A (en) * 2019-04-29 2019-09-17 浙江亚厦装饰股份有限公司 Load-bearing floor heating assembly and installation method
CN210316369U (en) * 2019-07-05 2020-04-14 张剑辉 Novel floor overhead support
CN212585043U (en) * 2020-09-27 2021-02-23 浙江亚厦装饰股份有限公司 Floor heating pipe pipeline collection module structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004030712A1 (en) * 2004-06-25 2006-01-19 Josef Blome Prefabricated bathroom wall hot and cold water supply installation kit with supply point
CN208252957U (en) * 2018-06-04 2018-12-18 中建八局第二建设有限公司 Floor heating branch pipe fixing device at a kind of water collecting and diversifying device
CN110242002A (en) * 2019-04-29 2019-09-17 浙江亚厦装饰股份有限公司 Floor heating assembly and installation method
CN110242003A (en) * 2019-04-29 2019-09-17 浙江亚厦装饰股份有限公司 Load-bearing floor heating assembly and installation method
CN210316369U (en) * 2019-07-05 2020-04-14 张剑辉 Novel floor overhead support
CN212585043U (en) * 2020-09-27 2021-02-23 浙江亚厦装饰股份有限公司 Floor heating pipe pipeline collection module structure

Also Published As

Publication number Publication date
CN112082193B (en) 2024-04-12

Similar Documents

Publication Publication Date Title
CN212585043U (en) Floor heating pipe pipeline collection module structure
EP0036323A1 (en) Apparatus for use in a solar heating system
WO2018067700A1 (en) Integrated mechanical, electrical and plumbing appliance for a building
US20040035141A1 (en) Inertial energy storage device
CN112082193A (en) Floor heating pipe pipeline collection module structure and connecting and mounting method thereof
CN212457546U (en) Modular ice making integrated system
JPH09303803A (en) Floor heating device
CN210399121U (en) Geothermal building heating system
CN110260389A (en) A kind of overhead type ground heating system
CN215892505U (en) Bathroom floor heating structure
KR100467536B1 (en) A floor system of access-floor type with an iron sheet and a glass-ondol and the construction method of it
JP2010048313A (en) Equipment storage unit
KR20020062391A (en) A floor system of access-floor type using a glass-ondol and the construction method of it
CN112728217B (en) Water supply and drainage pipeline mounting structure
CN220931259U (en) Outdoor system and device of integrated air conditioner
WO2015179850A1 (en) Universal air handler unit
CN220689245U (en) Elevated warehouse temperature control system
JPH094787A (en) Piping wiring containing frame for outdoor machine and disposing work executing method therefor
CN113339870B (en) Bathroom floor heating structure and installation method thereof
CN209877071U (en) Ground heating water collecting and distributing device branch fixing support
CN211203281U (en) Anti-seismic bracket connecting piece convenient to install and firm in connection for building
CN214117355U (en) Overhead heating floor
CN215977965U (en) Energy-saving curtain wall for architectural decoration
CN220567336U (en) Ground radiation coil pipe device and radiation cooling and heating system
CN219140928U (en) Outdoor unit drainage assembly and air conditioner floor heating integrated outdoor unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant