CN112081153B - Lifting method of raft foundation high-rise building - Google Patents

Lifting method of raft foundation high-rise building Download PDF

Info

Publication number
CN112081153B
CN112081153B CN201910517279.3A CN201910517279A CN112081153B CN 112081153 B CN112081153 B CN 112081153B CN 201910517279 A CN201910517279 A CN 201910517279A CN 112081153 B CN112081153 B CN 112081153B
Authority
CN
China
Prior art keywords
lifting
building
grouting
raft foundation
holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910517279.3A
Other languages
Chinese (zh)
Other versions
CN112081153A (en
Inventor
崔学栋
吴继光
崔腾跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Hengxiang Hongye Foundation Reinforcement Technology Co Ltd
Original Assignee
Beijing Hengxiang Hongye Foundation Reinforcement Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Hengxiang Hongye Foundation Reinforcement Technology Co Ltd filed Critical Beijing Hengxiang Hongye Foundation Reinforcement Technology Co Ltd
Priority to CN201910517279.3A priority Critical patent/CN112081153B/en
Publication of CN112081153A publication Critical patent/CN112081153A/en
Application granted granted Critical
Publication of CN112081153B publication Critical patent/CN112081153B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种筏板基础高层建筑物的抬升方法,包括以下步骤:布测点:围绕着建筑物的外轮廓间隔布设多个测点,根据测点的标高确定出建筑物的抬升侧;形成加固体:在筏板基础的范围内间隔布设有多个垂直于筏板基础的加固注浆孔,加固注浆孔内采用压力注浆在筏板基础下方形成加固体;布设抬升孔:在靠近建筑物抬升侧的两端于筏板基础的外侧布设倾斜向下的抬升孔,孔底延伸至承重墙正下方;抬升:抬升孔内同时压力注浆,对建筑物抬升侧进行抬升,控制抬升侧建筑物两个拐角的抬升速度,使两个拐角的标高最终同时抬升至与建筑物非抬升侧对应拐角的标高相同的高度。本发明具有整体稳固性好,可操作性强,安全可控以及对建筑物破坏小的优点。

Figure 201910517279

The invention relates to a lifting method for a high-rise building with a raft foundation, comprising the following steps: arranging measuring points: arranging a plurality of measuring points around the outer contour of the building at intervals, and determining the lifting side of the building according to the elevation of the measuring points; Formation of reinforcements: a plurality of reinforcement grouting holes perpendicular to the raft foundation are arranged at intervals within the range of the raft foundation, and pressure grouting is used in the reinforcement grouting holes to form reinforcements under the raft foundation; At the two ends of the lifting side of the building, inclined downward lifting holes are arranged on the outside of the raft foundation, and the bottom of the hole extends to just below the bearing wall; lifting: pressure grouting is carried out in the lifting hole at the same time, and the lifting side of the building is lifted and controlled. The lifting speed of the two corners of the building on the lifting side, so that the elevations of the two corners are finally raised to the same height as the elevation of the corresponding corners on the non-lifting side of the building at the same time. The invention has the advantages of good overall stability, strong operability, safety and controllability and little damage to buildings.

Figure 201910517279

Description

一种筏板基础高层建筑物的抬升方法A kind of lifting method of raft foundation high-rise building

技术领域technical field

本发明涉及建筑抬升的技术领域,尤其是涉及一种筏板基础高层建筑物的抬升方法。The invention relates to the technical field of building lifting, in particular to a lifting method of a high-rise building with a raft foundation.

背景技术Background technique

筏板基础由底板、梁等整体组成。建筑物荷载较大,地基承载力较弱,常采用砼底板筏板承受建筑物荷载,形成筏基,其整体性好。由于建筑勘察、设计、施工或恶劣天气等原因,建成的建筑物因地基强度不够会出现下沉现象。如果建筑物倾斜值超过允许倾斜值,就会影响正常使用,甚至开裂、破损,对建筑物的结构安全构成威胁,这时需要进行抬升纠偏处理。The raft foundation is composed of a base plate, beams, etc. as a whole. The building load is large and the bearing capacity of the foundation is weak. The concrete floor raft is often used to bear the load of the building to form a raft foundation, which has good integrity. Due to architectural survey, design, construction or bad weather, the built buildings may sink due to insufficient foundation strength. If the inclination value of the building exceeds the allowable inclination value, it will affect the normal use, and even crack and damage, posing a threat to the structural safety of the building.

目前,现有的抬升方法一般采用聚氨酯注浆进行抬升。聚氨酯注浆法是通过向地基中注射聚氨酯泡沫反应原料,通过聚氨酯泡沫反应产生的巨大膨胀压力和胶结作用对加固土体进行充填、渗透、挤密、置换和加固,同时对已发生不均匀沉降的建构筑物进行纠偏。但是由于聚氨酯泡沫产生的膨胀力大小不均匀,所以抬升的高度和速度不易控制,抬升过程容易对建筑物造成二次破坏。所以需要研究一套抬升方法,既能实现筏板基础高层建筑物的抬升,又能减少对建筑物的二次破坏。At present, the existing lifting methods generally use polyurethane grouting for lifting. The polyurethane grouting method is to fill, infiltrate, compact, replace and reinforce the reinforced soil through the huge expansion pressure and cementation generated by the polyurethane foam reaction by injecting the polyurethane foam reaction raw materials into the foundation, and at the same time, the uneven settlement has occurred. rectification of buildings. However, due to the uneven size of the expansion force generated by the polyurethane foam, the height and speed of the lifting are not easy to control, and the lifting process is likely to cause secondary damage to the building. Therefore, it is necessary to study a set of lifting methods, which can not only realize the lifting of high-rise buildings with raft foundation, but also reduce the secondary damage to the buildings.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种筏板基础高层建筑物的抬升方法,解决了筏板基础高层建筑物沉降抬升的问题,具有整体稳固性好,抬升速度和高度可控以及减少对建筑物二次破坏的优点。The purpose of the present invention is to provide a lifting method for a high-rise building with a raft foundation, which solves the problem of settlement and lifting of a high-rise building on a raft foundation, has good overall stability, controllable lifting speed and height, and reduces secondary damage to the building. The advantages of destruction.

本发明的上述发明目的是通过以下技术方案得以实现的:The above-mentioned purpose of the present invention is achieved through the following technical solutions:

一种筏板基础高层建筑物的抬升方法,包括以下步骤:A method for lifting a high-rise building based on a raft, comprising the following steps:

S1、布测点:建筑物底部包括筏板基础,围绕着建筑物的外墙间隔布设多个测点,根据测点的标高确定出建筑物四个拐角中沉降量大的两点所在的一侧为抬升侧;S1. Measuring points: the bottom of the building includes a raft foundation, and a plurality of measuring points are arranged around the outer wall of the building at intervals. According to the elevation of the measuring points, determine the one where the two points with the largest settlement in the four corners of the building are located. The side is the raised side;

S2、形成加固体:在筏板基础的范围内间隔布设有多个垂直于筏板基础的加固注浆孔,加固注浆孔内进行压力注浆,在筏板基础下方形成大于筏板厚度的连续完整的加固体;S2. Formation of reinforcement: A plurality of reinforcement grouting holes perpendicular to the raft foundation are arranged at intervals within the range of the raft foundation, and pressure grouting is carried out in the reinforcement grouting holes, and under the raft foundation, a grouting hole larger than the thickness of the raft plate is formed. Continuous and complete solidification;

S3、布设抬升孔:在建筑物抬升侧的靠近承重墙两端的位置,在筏板基础上紧贴承重墙布设竖向抬升孔,竖向抬升孔穿透筏板基础,孔底延伸至靠近加固体底部位置;或在筏板基础的外侧布设倾斜向下的抬升孔,孔底延伸至靠近加固体底部位置,并位于承重墙正下方;S3. Lay up lifting holes: at the position on the lifting side of the building near the two ends of the load-bearing wall, lay vertical lifting holes on the raft foundation close to the load-bearing wall, the vertical lifting holes penetrate the raft foundation, and the bottom of the hole extends to close to the load-bearing wall. The position of the solid bottom; or the inclined downward lifting hole is arranged on the outer side of the raft foundation, and the bottom of the hole extends to the position near the bottom of the reinforced solid, and is located directly under the load-bearing wall;

S4、抬升:抬升孔内同时进行压力注浆,对建筑物的抬升侧进行抬升,抬升时,控制抬升侧建筑物两个拐角的抬升速度,使两个拐角的标高最终同时抬升至与建筑物非抬升侧对应拐角的标高相同的高度。S4. Lifting: pressure grouting is carried out in the lifting hole at the same time, and the lifting side of the building is lifted. When lifting, the lifting speed of the two corners of the building on the lifting side is controlled, so that the elevations of the two corners are finally lifted to the same level as the building. The non-raised side corresponds to the same height as the elevation of the corner.

通过采用上述技术方案,首先通过在筏板底部注浆形成加固体,防止建筑物继续沉降;然后在抬升侧承重墙下方的加固体底部位置进行压力注浆,将建筑物进行速度可控的抬升;加固体作为受力缓冲结构,保护了建筑物在抬升过程中不受二次破坏;抬升侧的两端同时抬升、同时停止,避免了非抬升侧被连带抬起现象,进一步减小了抬升过程对建筑结构的破坏;抬升时注入的浆液与填充土体空隙,进一步加固了承重墙底部土层,有效避免了二次沉降的发生;本方案集抬升加固于一体,具有整体稳固性好,可操作性强,安全可控以及对建筑物破坏小的优点。By adopting the above technical scheme, firstly, the reinforcement is formed by grouting at the bottom of the raft to prevent the building from continuing to settle; then pressure grouting is carried out at the bottom of the reinforcement under the bearing wall of the lifting side to lift the building at a controllable speed. ; Reinforcement body acts as a force buffer structure to protect the building from secondary damage during the lifting process; both ends of the lifting side are lifted and stopped at the same time, avoiding the phenomenon that the non-lifting side is jointly lifted and further reducing the lifting The damage to the building structure during the process; the injected slurry and the filling soil voids during the lifting further strengthen the soil layer at the bottom of the load-bearing wall and effectively avoid the occurrence of secondary settlement; this scheme integrates lifting and reinforcement, and has good overall stability. It has the advantages of strong operability, safety and controllability and little damage to buildings.

本发明进一步设置为:在抬升侧沿墙体长度方向、既有抬升孔之间间隔布设有若干个加密抬升孔;所有抬升孔内同时进行压力注浆,对建筑物抬升侧进行抬升,抬升时,控制各抬升点处建筑物承重墙的抬升速度,使建筑物 抬升侧的各点逐渐趋于相同的标高,并同时抬升至建筑物非抬升侧的对应位置的标高相同的高度。The present invention is further set up as follows: on the lifting side along the length direction of the wall, a number of dense lifting holes are arranged at intervals between the existing lifting holes; pressure grouting is carried out in all the lifting holes at the same time, and the lifting side of the building is lifted. , control the lifting speed of the load-bearing wall of the building at each lifting point, so that each point on the lifting side of the building gradually tends to the same elevation, and at the same time, it is lifted to the same height as the elevation of the corresponding position on the non-lifting side of the building.

通过采用上述技术方案,解决了抬升侧两端抬升孔之间的筏板基础底部悬空造成的建筑结构的破坏,保证了抬升过程中及抬升结束后建筑物结构的稳固性。By adopting the above technical solution, the damage to the building structure caused by the suspension of the bottom of the raft foundation between the lifting holes at both ends of the lifting side is solved, and the stability of the building structure during the lifting process and after the lifting is guaranteed.

本发明进一步设置为:填充补强:在阀板基础的中间位置布设补强孔,补强孔的孔底延伸至阀板基础与加固体的结合面处,向补强孔的底端注浆,将所有阀板基础底面与加固体顶面之间的空隙填充密实。The present invention is further provided as follows: filling and reinforcement: a reinforcement hole is arranged in the middle position of the valve plate foundation, the bottom of the reinforcement hole extends to the joint surface of the valve plate foundation and the reinforcement body, and the bottom end of the reinforcement hole is grouted , and fill the gaps between the bottom surface of the base of all valve plates and the top surface of the reinforcement body.

通过采用上述技术方案,在注浆抬升完成之后,向加固孔内注浆补强,防止建筑物在抬升后,因底部不密实发生二次沉降,对建筑物造成二次破坏。By adopting the above technical solution, after the grouting lifting is completed, grouting reinforcement is carried out into the reinforcement hole to prevent secondary settlement of the building due to the uncompacted bottom after the building is lifted, causing secondary damage to the building.

本发明进一步设置为:抬升孔布设在筏板基础的外侧,抬升侧的每个建筑物拐角对应布设两个抬升孔,两个抬升孔分别位于筏板基础相互垂直的两条外轮廓线的外侧;两个抬升孔的孔底分别延伸至相互垂直的两堵承重墙的正下方。The present invention is further arranged as follows: the lifting holes are arranged on the outer side of the raft foundation, and two lifting holes are correspondingly arranged at the corners of each building on the lifting side, and the two lifting holes are respectively located on the outer sides of the two perpendicular outer contour lines of the raft foundation. ; The hole bottoms of the two lifting holes respectively extend to just below the two mutually perpendicular load-bearing walls.

通过采用上述技术方案,一是拐角处均设置有结构柱,作为抬升受力处,抬升更加可控,对建筑结构的破坏更小,也方便抬升的过程控制;二是通过两个倾斜的抬升孔,使得注入的浆液不断向建筑筏板中间部位堆积,使得抬升效率更高、节约材料;四是两个抬升孔分别延伸至在相互垂直的承重墙的正下方,使得建筑拐角的两面墙同时受力,更好的保护了建筑物结构的内部受力,减小损害。By adopting the above technical solutions, firstly, the corners are provided with structural columns, which serve as the lifting force, the lifting is more controllable, the damage to the building structure is smaller, and the lifting process control is also convenient; The injected slurry continuously accumulates in the middle of the building raft, which makes the lifting more efficient and saves materials. Fourth, the two lifting holes extend directly below the mutually perpendicular load-bearing walls, so that the two walls at the corner of the building are simultaneously It can better protect the internal force of the building structure and reduce damage.

本发明进一步设置为:抬升侧的每个建筑物拐角对应布设两个抬升孔,两个抬升孔分别设置在建筑物拐角的不同边上;一个抬升孔布设在筏板基础的外侧,另一个抬升孔设置在承重墙的内侧。The present invention is further arranged as follows: each building corner on the lifting side is correspondingly arranged with two lifting holes, and the two lifting holes are respectively arranged on different sides of the corner of the building; one lifting hole is arranged on the outer side of the raft foundation, and the other is lifted The holes are provided on the inside of the load-bearing wall.

通过采用上述技术方案,解决了遇到两座单元楼房相互紧挨,相邻单元之前只留有十几公分的沉降缝,无法在沉降缝处布设抬升孔的问题。By adopting the above technical solution, the problem that two unit buildings are close to each other, and there are only ten centimeters of settlement joints before the adjacent units, can not be arranged at the settlement joints.

本发明进一步设置为:抬升时采用间歇式注浆抬升,先注浆抬升一定高度,暂停一段时间注浆,然后再注浆抬升一定高度。The present invention is further configured as follows: during the lifting, intermittent grouting is used to lift, firstly, grouting is raised to a certain height, grouting is suspended for a period of time, and then the grouting is raised to a certain height.

通过采用上述技术方案,间歇式注浆抬升,先对建筑物进行抬升,然后暂停,使建筑物内的受力重分布,在建筑物适应抬升后的受力后,再注浆抬升一段高度,避免在抬升时对建筑物造成二次破坏,保证建筑物的结构稳定性。By adopting the above technical scheme, intermittent grouting lifts, first lifts the building, and then pauses to redistribute the force in the building. Avoid secondary damage to the building during lifting, and ensure the structural stability of the building.

本发明进一步设置为:注浆抬升时对建筑物各个测点进行实时监控。The present invention is further configured to: monitor each measuring point of the building in real time when the grouting is lifted.

通过采用上述技术方案,一方面控制抬升侧建筑物两个拐角的抬升速度,使两个拐角最终同时抬升至与建筑物非抬升侧的对应拐角标高相同的高度;另一方面对非抬升侧进行监控,观测到异常情况时,能够采取调整抬升速度或停止注浆等措施,确保抬升时建筑物的稳定性。By adopting the above technical solution, on the one hand, the lifting speed of the two corners of the building on the lifting side is controlled, so that the two corners are finally lifted to the same height as the corresponding corner elevation on the non-lifting side of the building; Monitoring, when abnormal conditions are observed, measures such as adjusting the lifting speed or stopping grouting can be taken to ensure the stability of the building during lifting.

本发明进一步设置为:抬升孔的深度为筏板基础厚度的5-10倍。The present invention is further set as follows: the depth of the lifting hole is 5-10 times of the thickness of the raft foundation.

通过采用上述技术方案,确保出浆口与筏板基础底部有足够的缓冲带,避免对筏板基础造成破坏;同时又能兼顾注浆抬升效果且能避免材料浪费。By adopting the above technical scheme, it is ensured that there is sufficient buffer zone between the grouting outlet and the bottom of the raft foundation, so as to avoid damage to the raft foundation; at the same time, the grouting lifting effect can be taken into account and material waste can be avoided.

本发明进一步设置为:步骤S2中采用钻注一体机逐段分层进行注浆。The present invention is further provided as follows: in step S2, a drilling-grouting integrated machine is used to perform grouting step by step and layer by layer.

通过采用上述技术方案,注浆一段,即凝固一段,逐层施工,能够降低对地基土层的扰动。By adopting the above technical scheme, the first stage of grouting, that is, the first stage of solidification, is constructed layer by layer, which can reduce the disturbance to the foundation soil layer.

本发明进一步设置为:所述压力注浆采用的浆液为双组分浆液,不同组分的浆液在注浆管或钻杆底部的出浆口压入土体并汇合发生反应并凝固,初凝时间为5-60s。The present invention is further configured as follows: the slurry used in the pressure grouting is a two-component slurry, and the slurries of different components are pressed into the soil at the slurry outlet at the bottom of the grouting pipe or the drill pipe and merged to react and solidify. The time is 5-60s.

通过采用上述技术方案,加固注浆时,快速凝固的浆液能够及时起到支撑作用,不会因注浆干扰原状土层造成建筑的二次沉降;抬升注浆时,浆液不断从出浆口喷出,快速凝固后的体积不断增大,从而将顶部的结构均匀提升,通过调节注浆压力可以调整抬升速度,抬升安全可控;注浆停止时,抬升即停止,注浆后,土体进行了加强,能够有效防止建筑物二次沉降。By adopting the above technical solutions, the rapidly solidified grout can play a supporting role in time during reinforcement grouting, and the secondary settlement of the building will not be caused by the grouting disturbing the original soil layer; when the grouting is lifted, the grout is continuously sprayed from the grouting outlet. After grouting, the volume after rapid solidification continues to increase, so that the top structure is evenly lifted. The lifting speed can be adjusted by adjusting the grouting pressure, and the lifting is safe and controllable; when the grouting stops, the lifting stops immediately. It can effectively prevent the secondary settlement of the building.

综上所述,本发明的有益技术效果为:To sum up, the beneficial technical effects of the present invention are:

1.首先通过在筏板底部注浆形成加固体,防止建筑物继续沉降;然后在抬升侧承重墙下方的加固体底部位置进行压力注浆,将建筑物进行速度可控的抬升;加固体作为受力缓冲结构,保护了建筑物在抬升过程中不受二次破坏;抬升侧的两端同时抬升、同时停止,避免了非抬升侧被连带抬起现象,进一步减小了抬升过程对建筑结构的破坏;抬升时注入的浆液与填充土体空隙,进一步加固了承重墙底部土层,有效避免了二次沉降的发生;本方案集抬升加固于一体,具有整体稳固性好,可操作性强,安全可控以及对建筑物破坏小的优点;1. First, the reinforcement is formed by grouting at the bottom of the raft to prevent the building from continuing to settle; then pressure grouting is performed at the bottom of the reinforcement under the bearing wall of the raised side to lift the building at a controllable speed; The force-bearing buffer structure protects the building from secondary damage during the lifting process; both ends of the lifting side are lifted and stopped at the same time, avoiding the phenomenon that the non-lifting side is jointly lifted, and further reducing the impact of the lifting process on the building structure. The injected slurry and filling soil voids during lifting further strengthen the soil layer at the bottom of the load-bearing wall and effectively avoid the occurrence of secondary settlement; this scheme integrates lifting and reinforcement, and has good overall stability and strong operability. , safe and controllable and the advantages of less damage to buildings;

2.抬升孔位置的不同设置方式既保证了建筑物的抬升加固,而且能够适用于多种不同施工环境,提高了该工艺的适用范围;2. The different setting methods of the position of the lifting hole not only ensure the lifting and reinforcement of the building, but also can be applied to a variety of different construction environments, which improves the scope of application of the process;

3.通过抬升时采用间歇抬升工艺,先对建筑物进行抬升,然后暂停,使建筑物内的受力重分布,在建筑物适应抬升后的受力后,再注浆抬升一段高度,避免在抬升时对建筑物造成二次破坏,保证建筑物的结构稳定性;3. By adopting the intermittent lifting process during lifting, the building is first lifted, and then paused to redistribute the force in the building. After the building is adapted to the force after the lifting, grouting is carried out to lift a certain height, so as to avoid It will cause secondary damage to the building when it is lifted to ensure the structural stability of the building;

4.通过对抬升过程中各个测点进行实时监控,能够及时的掌握抬升侧的抬升高度和速度,以及非抬升侧在抬升时的状态,保证在抬升过程中建筑物的稳定性;4. Through real-time monitoring of each measuring point during the lifting process, the lifting height and speed of the lifting side can be grasped in time, as well as the state of the non-lifting side during lifting, so as to ensure the stability of the building during the lifting process;

5.补强孔的设置进一步防止了建筑物二次沉降的发生。5. The setting of reinforcement holes further prevents the occurrence of secondary settlement of the building.

附图说明Description of drawings

图1是本发明突出加固体的立面示意图;Fig. 1 is the elevational schematic diagram of protruding reinforcement of the present invention;

图2是本发明突出加固注浆孔布置位置的俯视示意图;Fig. 2 is the top view schematic diagram of the arrangement position of protruding reinforcement grouting hole of the present invention;

图3是本发明突出实施例一中抬升孔布置位置的俯视示意图;3 is a schematic top view of the arrangement position of the lifting holes in the first embodiment of the present invention;

图4是本发明突出实施例一中抬升孔的立面示意图;4 is a schematic elevational view of the lifting hole in the first embodiment of the present invention;

图5是实施例一中说明抬升原理的拐角编号示意图;Fig. 5 is the corner numbering schematic diagram illustrating the lifting principle in the first embodiment;

图6是突出显示补强孔对筏板基础底部进行填充注浆的立面示意图;Figure 6 is a schematic elevational view showing that the reinforcement holes are filled with grouting at the bottom of the raft foundation;

图7是本发明实施例二中抬升孔的布置位置的俯视示意图;7 is a schematic top view of the arrangement position of the lifting holes in the second embodiment of the present invention;

图8是本发明实施例三中两撞建筑物紧挨时抬升孔布置位置的俯视示意图。FIG. 8 is a schematic top view of the arrangement position of the lifting holes when the two striking buildings are close to each other in the third embodiment of the present invention.

图中,1、筏板基础;2、承重墙;3、加固体;31、加固注浆孔;4、抬升孔;41、加密抬升孔;5、补强孔;11-14、四个拐角点。In the figure, 1. Raft foundation; 2. Load-bearing wall; 3. Reinforced body; 31. Reinforced grouting hole; 4. Lifting hole; 41. Encrypted lifting hole; 5. Reinforcing hole; point.

具体实施方式Detailed ways

以下结合附图对本发明作进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings.

本发明公开的一种筏板基础高层建筑物的抬升方法,包括以下步骤:A method for lifting a high-rise building with a raft foundation disclosed in the present invention comprises the following steps:

S1、布测点:围绕着建筑物的外轮廓间隔均匀布设多个测点,利用水准仪测量出每个测点的标高,根据测点的标高确定出建筑物四个拐角中沉降量大的两点所在的一侧为抬升侧。S1. Deploying measuring points: Arrange multiple measuring points evenly spaced around the outer contour of the building, measure the elevation of each measuring point with a level gauge, and determine two of the four corners of the building with the largest settlement according to the elevation of the measuring points. The side where the point is located is the raised side.

S2、形成加固体3:参照图1和图2,根据地质情况和水文情况,确定加固区,如果建筑物筏板基础1底部均为填方等软弱地层,则全部进行加固,如果筏板基础1以下有一部分为硬质岩层或承载力较高的原状土层,则仅在填方区域进行加固。该实施例以全部进行加固的情况进行介绍。S2. Form reinforcement 3: Referring to Figure 1 and Figure 2, determine the reinforcement area according to the geological and hydrological conditions. If the bottom of the raft foundation 1 of the building is filled with soft strata such as fill, all of them should be reinforced. A part below 1 is a hard rock layer or undisturbed soil layer with high bearing capacity, so it is only reinforced in the filling area. This embodiment is described in the case of all reinforcement.

如图2所示,在筏板基础12底部的加固的范围内间隔梅花状布设有多个垂直于筏板基础12的加固注浆孔31。首先在加固注浆孔31处破除筏板基础11表面的钢筋保护层,露出筏板钢筋,然后用钻机(可以是水钻)穿过钢筋间隙、在筏板基础11上钻出加固注浆孔31。本实施例中,加固注浆孔31直径为42mm,采用梅花形布置,相邻加固注浆孔31之间的间距为3-6m,当加固注浆孔31与墙体位置冲突时,适当调整加固注浆孔31间距。As shown in FIG. 2 , a plurality of reinforcement grouting holes 31 perpendicular to the raft foundation 12 are arranged at intervals within the reinforced range of the bottom of the raft foundation 12 . First, break the protective layer of the reinforcement on the surface of the raft foundation 11 at the reinforcement grouting hole 31 to expose the reinforcement of the raft. . In this embodiment, the diameter of the reinforcement grouting holes 31 is 42 mm, which is arranged in a plum blossom shape, and the distance between the adjacent reinforcement grouting holes 31 is 3-6 m. When the reinforcement grouting holes 31 conflict with the position of the wall, adjust them appropriately Reinforce the spacing between the grouting holes 31 .

回看图1,向加固注浆孔31内进行压力注浆,在筏板基础1下方形成大于筏板厚度的连续完整的加固体3。具体地,注浆时采用钻注一体机进行钻孔及注浆,钻杆直径为42mm,采用双重芯管,内芯直径为12mm,注浆钻头为双浆液混合器。采取后退式注浆工艺,钻杆从加固注浆孔31钻入地下,深度大于筏板基础1的厚度,优选地,钻入至下部地基承载力更大的地层内,本实施例中钻入至筏板基础1底部以下16m。然后开始注浆,注浆使用的注浆液采用双组分复合浆液,两种浆液分别从钻杆的不同通道到达注浆管的出浆口,在出浆口处压入周围土体,在土体中汇合后发生化学反应,在5-60内完成初凝。Referring back to FIG. 1 , pressure grouting is performed into the reinforcement grouting hole 31 to form a continuous and complete reinforcement body 3 greater than the thickness of the raft under the raft foundation 1 . Specifically, the drilling and grouting machine was used for drilling and grouting. The diameter of the drill pipe was 42 mm, the double core pipe was used, and the inner core diameter was 12 mm. The grouting drill bit was a double slurry mixer. The backward grouting process is adopted, and the drill pipe is drilled into the ground from the reinforcement grouting hole 31 to a depth greater than the thickness of the raft foundation 1. Preferably, it is drilled into the stratum with greater bearing capacity of the lower foundation. In this embodiment, the drill pipe is drilled into the ground. 16m below the bottom of raft foundation 1. Then start grouting. The grouting liquid used for grouting adopts two-component composite grout. The two kinds of grout reach the grouting outlet of the grouting pipe from different channels of the drill pipe respectively, and press into the surrounding soil at the grouting outlet. After the confluence in the soil, a chemical reaction occurs, and the initial setting is completed within 5-60.

接着进行分段抬升注浆,注浆压力为0.8-1.5Mpa,每抬升一段,注浆一段,每次抬升0.3-0.5m,直至阀板基础底部。然后采用跳孔法进行注浆,所有加固注浆孔31全部注浆后,在阀板基础底部形成的连续完整的加固体3。Then carry out grouting by subsection lifting, the grouting pressure is 0.8-1.5Mpa, and each section is lifted, and one section is grouted, and each lift is 0.3-0.5m until the bottom of the valve plate foundation. Then, grouting is carried out by using the skip hole method. After all the reinforcing grouting holes 31 are all grouted, a continuous and complete reinforcement body 3 is formed at the bottom of the valve plate foundation.

S3、布设抬升孔4:参照图3和图4,在靠近建筑物抬升侧靠近承重墙2两端的位置分别布设抬升孔4,在筏板基础1的外侧布设倾斜向下的抬升孔4,抬升侧的每个建筑物拐角对应布设两个抬升孔4,两个抬升孔4分别位于筏板基础1相互垂直的两条外轮廓线的外侧;分别延伸至相互垂直的两堵承重墙2的正下方。抬升孔4钻进前,根据筏板的埋深、厚度及抬升孔4孔底等深度参数计算出开孔位置及倾斜角度,保证抬升孔4不穿过筏板基础1,而是紧贴筏板基础1边沿钻入至承重墙2底部。钻孔时采用钻注一体机的钻杆直接钻进即可。S3, laying lifting holes 4: referring to Figure 3 and Figure 4, lay lifting holes 4 at positions close to the lifting side of the building and near both ends of the load-bearing wall 2, and lay the lifting holes 4 inclined downward on the outside of the raft foundation 1 to lift Two lifting holes 4 are correspondingly arranged at the corners of each building on the side, and the two lifting holes 4 are respectively located on the outer sides of the two mutually perpendicular outer contour lines of the raft foundation 1; below. Before the lifting hole 4 is drilled, the opening position and inclination angle are calculated according to the buried depth and thickness of the raft and the depth parameters of the hole bottom of the lifting hole 4, so as to ensure that the lifting hole 4 does not pass through the raft foundation 1, but is close to the raft. The edge of the slab foundation 1 is drilled to the bottom of the load-bearing wall 2. When drilling, the drill pipe of the drilling and injecting machine can be used to drill directly.

抬升孔4的深度应为筏板基础1厚度的5-10倍,确保出浆口与筏板基础1底部有足够的缓冲带,避免对筏板基础1造成破坏;同时又能兼顾注浆抬升效果且能避免材料浪费。由于筏板基础1的厚度与建筑物的高度具有一定线性关系,建筑物越高,筏板基础1厚度就越厚,同样的建筑物越高,抬升时所需要的力就越大,缓冲带的厚度也需要更大,所以选用筏板基础1的厚度作为抬升孔4深度设定的基本参数。The depth of the lifting hole 4 should be 5-10 times the thickness of the raft foundation 1 to ensure that there is enough buffer zone between the grouting outlet and the bottom of the raft foundation 1 to avoid damage to the raft foundation 1; effect and avoid material waste. Since the thickness of the raft foundation 1 has a certain linear relationship with the height of the building, the higher the building, the thicker the thickness of the raft foundation 1, the higher the same building, the greater the force required to lift, the buffer zone The thickness of the raft also needs to be larger, so the thickness of the raft foundation 1 is selected as the basic parameter for setting the depth of the lifting hole 4 .

S4、抬升:经多次现场抬升经验得出,在实际建筑抬升的过程中,如果在抬升时只抬升建筑物其中一个拐角点,会造成建筑物非抬升侧连带抬起。如图5所示,建筑拐角编号为11、12、13、14。沉降量大的点为11和12,当仅注浆抬升12时,非抬升侧的13会连带被抬升,特别是12和13所在的边为短边时,更容易产生连带抬升现象,且会发生11号点加速下沉的现象。如果11号点和12号点同时进行注浆抬升操作,则可以避免13号点的连带抬升现象。所以注浆抬升工作必须在抬升侧的两个拐角同时进行。S4. Lifting: After many times of on-site lifting experience, it is concluded that in the process of actual building lifting, if only one of the corner points of the building is lifted during lifting, the non-lifting side of the building will be lifted together. As shown in Figure 5, the building corners are numbered 11, 12, 13, and 14. The points with large settlement are 11 and 12. When only 12 is raised by grouting, the 13 on the non-lifting side will be lifted together, especially when the sides 12 and 13 are short sides, it is more likely to cause joint lifting, and will The phenomenon of accelerated sinking at point 11 occurred. If point 11 and point 12 are grouted and lifted at the same time, the associated lifting phenomenon of point 13 can be avoided. Therefore, the grouting lifting work must be carried out at the two corners of the lifting side at the same time.

抬升时,向控制建筑物抬升侧的抬升孔4内同时压力注浆,压力注浆采用的浆液为双组分浆液,不同组分的浆液在注浆管或钻杆底部的出浆口压入土体并汇合发生反应并凝固,初凝时间为5-60s,注浆压力为1.2-2Mpa。此时抬升侧以非抬升侧为转轴,对建筑物抬升侧进行缓慢抬升,避免非抬升侧被连带抬升。抬升时,采用水准仪采集建筑物各个测点的标高数据,进行实时监控,通过调整注浆压力和浆液的浓度,以控制抬升侧建筑物两个拐角的抬升速度,使两个拐角匀速提升,最终同时抬升至与建筑物非抬升侧对应拐角的标高相同的高度。注浆过程中控制抬升速度,使两个拐角同时达到最终标高,此项技术措施防止了一个拐角停止后,另一个仍继续注浆时,非抬升侧的拐角被连带抬升的发生。When lifting, press grouting into the lifting hole 4 on the lifting side of the control building at the same time. The grout used for pressure grouting is two-component grout. The grout of different components is pressed into the grout outlet at the bottom of the grouting pipe or drill pipe. The soil mass reacts and solidifies after confluence, the initial setting time is 5-60s, and the grouting pressure is 1.2-2Mpa. At this time, the lifting side takes the non-lifting side as the rotation axis, and slowly lifts the lifting side of the building to avoid the non-lifting side being jointly lifted. When lifting, use a level to collect the elevation data of each measuring point of the building for real-time monitoring. By adjusting the grouting pressure and the concentration of the slurry, the lifting speed of the two corners of the building on the lifting side is controlled, so that the two corners are lifted at a uniform speed. At the same time, it is raised to the same height as the elevation of the corresponding corner on the non-raised side of the building. During the grouting process, the lifting speed is controlled so that the two corners reach the final elevation at the same time. This technical measure prevents the occurrence of the non-lifting side corners being jointly lifted when the other corner continues to be grouted after one corner stops.

进一步地,在注浆抬升时采用间歇式注浆抬升,先注浆抬升一段高度,暂停一段时间注浆,然后再注浆抬升一段高度,每次抬升一般为1cm,暂停时间一般为12-24h。间歇式注浆抬升,先对建筑物进行抬升,然后暂停,使建筑物内的受力重分布,在建筑物适应抬升后的受力后,再注浆抬升一段高度,避免在抬升时对建筑物造成二次破坏,保证建筑物的结构稳定性。Further, intermittent grouting lifting is adopted during grouting lifting. First grouting is lifted for a certain height, grouting is suspended for a period of time, and then grouting is lifted for a certain height. Each lifting is generally 1cm, and the pause time is generally 12-24h. . Intermittent grouting lift, first lift the building, and then pause to redistribute the force in the building. After the building adapts to the force after the lift, grouting lifts a certain height to avoid the impact on the building during lifting. It can cause secondary damage and ensure the structural stability of the building.

回看图3,当抬升侧为建筑物的长边时,两个端头抬升点之间的距离一般都会超过10米,这种情况下,筏板基础1中部悬空,对筏板基础1的结构不利。所以,优选地,在抬升侧沿墙体长度方向、原有抬升孔4之间间隔布设若干个加密抬升孔41。优选地,加密的抬升孔4的孔底延伸至结构柱的正下方。所有抬升孔4内同时进行压力注浆,对建筑物抬升侧进行抬升,抬升时,控制各抬升点处建筑物承重墙2的抬升速度,使建筑物抬升侧的各抬升点均速抬升,最终同时抬升至与建筑物非抬升侧的对应位置的标高相同的高度。Looking back at Figure 3, when the lifting side is the long side of the building, the distance between the lifting points of the two ends is generally more than 10 meters. In this case, the middle of the raft foundation 1 is suspended, and the Unfavorable structure. Therefore, preferably, several encrypted lifting holes 41 are arranged at intervals between the original lifting holes 4 on the lifting side along the length direction of the wall. Preferably, the hole bottom of the densified lifting hole 4 extends to just below the structural column. Pressure grouting is carried out in all the lifting holes 4 at the same time, and the lifting side of the building is lifted. During the lifting, the lifting speed of the building bearing wall 2 at each lifting point is controlled, so that each lifting point on the lifting side of the building is lifted at an average speed, and finally At the same time, it is raised to the same height as the elevation of the corresponding position on the non-raised side of the building.

抬升完成后,建筑物的拐角11和拐角14标高相同,拐角12和拐角13的标高相同。此时,如果拐角11和拐角13的标高相差不大,例如小于2cm,则可以不再做抬升处理;如果二者标高相差较大,例如大于5cm,则可以根据实际情况确定是否再次抬升。如果要继续抬升,则定义拐角12、拐角13所在的边为抬升侧,然后重复步骤S3和S4,最终将四个拐角点标高(即筏板基础1的所有标高)抬升至统一标高,达到完全水平。After the lifting is completed, the elevations of the corners 11 and 14 of the building are the same, and the elevations of the corners 12 and 13 are the same. At this time, if the difference between the elevations of the corners 11 and 13 is not large, for example, less than 2cm, the lifting process can no longer be performed; if the difference between the two elevations is relatively large, such as greater than 5cm, it can be determined according to the actual situation whether to lift again. If you want to continue to lift, define the side where the corners 12 and 13 are located as the lifting side, and then repeat steps S3 and S4, and finally lift the four corner point elevations (that is, all the elevations of the raft foundation 1) to a unified elevation, to achieve complete Level.

S5、补强:结合图3与图6,在阀板基础的中间位置布设补强孔5,补强孔5可以利用原有的加固注浆孔31,补强孔5的孔底延伸至阀板基础与加固体3的结合面处,向补强孔5的底端注浆,将所有阀板基础底面与加固体3顶面之间的空隙填充密实,以防止在注浆抬升完成之后建筑物发生再次沉降。补强孔5内注入的浆液一般采用水泥浆即可。当阀板面积较大时,可以间隔设置多个补强孔5。进行补强孔5注浆时,在靠近建筑外墙处选定几个原有加固注浆孔31作为排气孔,其它注浆加固孔进行封孔处理。当这些排气孔里返出浆液时,证明空隙已经填充密实。S5. Reinforcement: Combined with Figure 3 and Figure 6, a reinforcement hole 5 is arranged in the middle of the valve plate foundation. The reinforcement hole 5 can use the original reinforcement grouting hole 31, and the bottom of the reinforcement hole 5 extends to the valve plate. At the joint surface of the plate foundation and the reinforcement body 3, grouting is carried out to the bottom end of the reinforcement hole 5, and the gaps between the bottom surface of the valve plate foundation and the top surface of the reinforcement body 3 are filled and compacted, so as to prevent the building after the grouting is completed. Substance occurs again. The slurry injected into the reinforcement hole 5 can generally be cement slurry. When the area of the valve plate is large, a plurality of reinforcing holes 5 can be arranged at intervals. When grouting the reinforcement holes 5, several original reinforcement grouting holes 31 are selected as exhaust holes near the outer wall of the building, and other grouting reinforcement holes are sealed. When the slurry returned from these vent holes, it proved that the voids had been filled densely.

S6、封孔:注浆完成后,拔出钻杆并同步注浆填充孔洞,然后将筏板基础1上的所有钻孔以及凿除的保护层采用相对筏板基础11同一标号或高一标号的水泥砂浆封堵抹平。S6. Hole sealing: After the grouting is completed, pull out the drill pipe and fill the holes with grouting synchronously, and then use the same label or one higher than the raft foundation 11 for all the drilled holes on the raft foundation 1 and the protective layer to be removed. cement mortar for plugging and troweling.

实施例二:Embodiment 2:

实施例一中抬升孔4设置在筏板基础1的外侧,避开了对筏板基础1的钻孔,保护了筏板基础1不被破坏,且钻进时不需采用水钻等专用工具,提高了工作效率。但是有时建筑物外围没有足够的操作空间,此时,如图7所示,抬升孔4需要设置在建筑物内部,在建筑物抬升侧,紧贴承重墙2布设竖向抬升孔4,竖向抬升孔4穿透筏板基础1,孔底延伸至靠近加固体3底部位置。In the first embodiment, the lifting hole 4 is arranged on the outer side of the raft foundation 1, which avoids the drilling of the raft foundation 1, protects the raft foundation 1 from being damaged, and does not need to use special tools such as a water drill when drilling. Improved work efficiency. But sometimes there is not enough operating space on the periphery of the building. At this time, as shown in Figure 7, the lifting hole 4 needs to be arranged inside the building. The lifting hole 4 penetrates the raft foundation 1 , and the bottom of the hole extends to a position close to the bottom of the reinforcement body 3 .

在抬升孔4处破除筏板基础11表面的钢筋保护层,露出筏板钢筋,用水钻在筏板基础11的钢筋间隙之间向下钻进,形成加固注浆孔31。At the lifting hole 4, the protective layer of the steel bar on the surface of the raft foundation 11 is broken to expose the steel bar of the raft.

该方案采用竖向钻孔,有两方面原因,一是由于筏板基础1内靠近上下表面处均设置有钢筋网,倾斜钻孔时,钻到钢筋上的概率很高,多次更换位置钻孔严重影响施工进度,而且对筏板基础1结构造成破坏。而破除保护层后,能够精准地找到钢筋间隙,加之由于筏板基础1的上下层钢筋网片的间隙位置相对,所以竖直钻进后基本都可以从下层钢筋间隙通过,从而大大提升施工效率,并将结构破坏减小到最低。There are two reasons for this scheme to use vertical drilling. One is that the raft foundation 1 is provided with steel mesh near the upper and lower surfaces. When the drilling is inclined, the probability of drilling on the steel is very high. The holes seriously affect the construction progress and cause damage to the raft foundation 1 structure. After the protective layer is removed, the gap between the reinforcing bars can be accurately found. In addition, because the gaps between the upper and lower reinforcing meshes of the raft foundation 1 are opposite, the vertical drilling can basically pass through the gaps between the reinforcing bars on the lower layer, thereby greatly improving the construction efficiency. , and minimize structural damage.

二是由于倾斜钻孔后,虽然抬升孔4的孔底伸入至承重墙2正下方的,对注浆抬升有利,但是由于与实施例一中的倾斜布孔相比,抬升孔4的倾斜方向一个是朝向建筑物中心方向,一个是朝向建筑物外围,经现场实际操作,同等条件下,倾斜朝外的抬升孔4所用的材料超出向内倾斜抬升孔4的30%以上。实施例中紧贴承重墙2竖向布孔的方案,比倾斜朝外的抬升孔4方案节约材料15%以上。Second, after the inclined drilling, although the bottom of the lifting hole 4 extends directly below the load-bearing wall 2, which is beneficial to the grouting lifting, but compared with the inclined hole arrangement in the first embodiment, the inclination of the lifting hole 4 One of the directions is towards the center of the building, and the other is towards the periphery of the building. After the actual operation on site, under the same conditions, the material used for the upwardly inclined lifting hole 4 exceeds the inwardly inclined lifting hole 4 by more than 30%. In the embodiment, the scheme of vertically arranging holes close to the load-bearing wall 2 saves more than 15% of materials compared with the scheme of lifting holes 4 inclined outward.

较佳地,可以提前将一些加固注浆孔31布设在抬升侧的承重墙2的内侧,并紧贴承重墙2设置,抬升注浆操作时,可以选定部分加固抬升孔4作为抬升加固孔。Preferably, some reinforcement grouting holes 31 can be arranged on the inner side of the bearing wall 2 on the lifting side in advance, and are set close to the bearing wall 2. During the lifting and grouting operation, some reinforcement lifting holes 4 can be selected as lifting reinforcement holes. .

实施例三:Embodiment three:

参照图8,在实际的建筑中,有时会遇到两座单元楼房相互紧挨,相邻单元之前只留有10cm左右的的沉降缝,此时在建筑物紧挨侧布设抬升孔4显然是不合适的,又因一个抬升孔4不足以将建筑物均匀的向上抬起,所以此时设置两个抬升孔4,一个抬升孔4同以上设置,倾斜设置在建筑物的外侧,另一个抬升孔4靠近建筑物墙体竖直设置在建筑物的内侧,两个抬升孔4分别设置在建筑物拐角的不同边上,在抬升时,同时注浆抬升。Referring to Figure 8, in actual construction, sometimes two unit buildings are adjacent to each other, and only about 10cm of settlement joints are left before the adjacent units. Inappropriate, and because one lifting hole 4 is not enough to lift the building up evenly, two lifting holes 4 are set up at this time, one lifting hole 4 is set as above, and is inclined to the outside of the building, and the other is lifted. The hole 4 is vertically arranged on the inner side of the building close to the building wall, and the two lifting holes 4 are respectively arranged on different sides of the corner of the building.

以上实施例中提到的加固注浆和抬升注浆使用的注浆液采用双组分复合浆液,为方便表述,命名为A浆液和B浆液,两种浆液分别从钻杆的不同通道到达注浆管的出浆口,在出浆口处压入周围土体,在土体中汇合后发生化学反应,在短时间内完成初凝。The grouting liquid used in reinforcement grouting and lifting grouting mentioned in the above embodiments adopts two-component composite grouting, which is named as A grout and B grout for convenience. The slurry outlet of the slurry pipe is pressed into the surrounding soil at the slurry outlet, and a chemical reaction occurs after confluence in the soil, and the initial setting is completed in a short time.

注浆液只要能满足初凝时间要求并有较好的渗透性即可,可以是现有技术中的任意一种。The grouting liquid can be any one in the prior art as long as it can meet the requirements of the initial setting time and has good permeability.

以下一种注浆液配方可供采用:A浆液由如下重量份的原料组成:金属氧化物和/或金属氢氧化物70-90份,复合缓凝剂0.5-1.2份,减水剂0.5-0.7,酸碱缓冲剂0.7-1.5,复合稳定剂3-5,复合表面活性剂0.5-1.5。其中氧化金属物可以是氧化镁、氧化铝、磷酸镁等任意两种的组合;复合缓凝剂为尿素、硼砂和三聚磷酸钠中的至少两种;减水剂可以是聚羧酸减水剂或萘减水剂;酸碱缓冲剂为碳酸镁或氢氧化钾;复合稳定剂为羟甲基纤维素、正烷基十六醇、淀粉醚和纤维素醚中的至少两种;复合表面活性剂为烷基聚氧乙烯醚、苄基酚聚氧乙烯醚和烷基磺酸盐中的至少两种。以上各单独组分中要使用两种及两种以上的不同材料时,可以按等数量级进行配制,两种的设置主要是为了防止其中一种失效,以便使整体复合浆液效果更加稳定。The following grouting liquid formula can be used: A slurry is composed of the following raw materials by weight: 70-90 parts of metal oxides and/or metal hydroxides, 0.5-1.2 parts of composite retarder, 0.5-1.2 parts of water reducing agent 0.7, acid-base buffer 0.7-1.5, compound stabilizer 3-5, compound surfactant 0.5-1.5. Wherein the metal oxide can be any combination of magnesium oxide, aluminum oxide, magnesium phosphate, etc.; the composite retarder is at least two kinds of urea, borax and sodium tripolyphosphate; the water reducing agent can be polycarboxylate water reducing agent agent or naphthalene water reducing agent; acid-base buffer is magnesium carbonate or potassium hydroxide; composite stabilizer is at least two kinds of hydroxymethyl cellulose, n-alkylhexadecanol, starch ether and cellulose ether; composite surface The active agent is at least two of alkyl polyoxyethylene ether, benzylphenol polyoxyethylene ether and alkyl sulfonate. When two or more different materials are to be used in the above individual components, they can be prepared in the same order of magnitude. The two settings are mainly to prevent one of them from failing, so as to make the overall composite slurry effect more stable.

B浆液由如下重量份的原料组成:磷酸盐30~40份,消泡剂0.2~1份。其中,磷酸盐可以是磷酸氢二铵或磷酸二氢钾;消泡剂可以是有机硅消泡剂或聚醚消泡剂。The B slurry is composed of the following raw materials in parts by weight: 30-40 parts of phosphate and 0.2-1 part of defoamer. Among them, the phosphate can be diammonium hydrogen phosphate or potassium dihydrogen phosphate; the defoamer can be a silicone defoamer or a polyether defoamer.

A浆液和B浆液分别与水按重量比100:40~50混合搅拌成浆液,经不同管路压入注浆管,至出浆口汇合反应并在土体中固化。Slurry A and Slurry B are mixed with water at a weight ratio of 100:40 to 50, respectively, and stirred to form a slurry, which is pressed into the grouting pipe through different pipelines, and reacts at the slurry outlet and solidifies in the soil.

复合浆液初凝时间的不同主要通过调节复合缓凝剂的比重大小实现。The difference in the initial setting time of the composite slurry is mainly realized by adjusting the specific gravity of the composite retarder.

本具体实施方式的实施例均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The embodiments of this specific embodiment are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore: all equivalent changes made according to the structure, shape and principle of the present invention should be covered in within the protection scope of the present invention.

Claims (7)

1.一种筏板基础高层建筑物的抬升方法,其特征在于,包括以下步骤:1. a lifting method of a raft foundation high-rise building, is characterized in that, comprises the following steps: S1、布测点:建筑物底部包括筏板基础(1),围绕着建筑物的外墙间隔布设多个测点,根据测点的标高确定出建筑物四个拐角中沉降量大的两个拐角所在的一侧为抬升侧;S1. Layout of measuring points: the bottom of the building includes a raft foundation (1), a plurality of measuring points are arranged around the outer wall of the building at intervals, and two of the four corners of the building with the largest settlement are determined according to the elevations of the measuring points. The side where the corner is located is the raised side; S2、形成加固体(3):在筏板基础(1)的范围内间隔梅花状布设有多个垂直于筏板基础(1)的加固注浆孔(31),加固注浆孔(31)内进行压力注浆,在筏板基础(1)下方形成大于筏板厚度的连续完整的加固体(3),注浆采用后退式分段注浆方式,注浆压力为0.8-1.5Mpa,每段长度0.3-0.5m,直至与筏板基础(1)连接;S2. Forming a reinforcement (3): a plurality of reinforcement grouting holes (31) perpendicular to the raft foundation (1) are arranged in the range of the raft foundation (1) at intervals of plum blossoms, and the reinforcement grouting holes (31) Pressure grouting is carried out inside to form continuous and complete reinforcements (3) larger than the thickness of the raft under the raft foundation (1). The length of the segment is 0.3-0.5m until it is connected to the raft foundation (1); S3、布设抬升孔(4):在建筑物抬升侧的靠近承重墙(2)长度方向两端的位置,在筏板基础(1)上紧贴承重墙(2)的位置布设竖向抬升孔(4),竖向抬升孔(4)穿透筏板基础(1),孔底延伸至靠近加固体(3)底部位置;或在筏板基础(1)的外侧布设倾斜向下的抬升孔(4),孔底延伸至靠近加固体(3)底部位置,并位于承重墙(2)正下方,抬升侧的每个建筑物拐角对应布设两个抬升孔(4),两个抬升孔(4)分别设置在建筑物拐角的不同边上,抬升孔(4)的深度为筏板基础(1)厚度的5-10倍;S3. Lay the lifting holes (4): at the position on the lifting side of the building near the two ends in the length direction of the bearing wall (2), on the raft foundation (1), lay the vertical lifting holes ( 4), the vertical lifting hole (4) penetrates the raft foundation (1), and the bottom of the hole extends to a position close to the bottom of the reinforcement (3); or an inclined downward lifting hole ( 4), the bottom of the hole extends to the position close to the bottom of the reinforcement body (3), and is located directly below the load-bearing wall (2). ) are respectively arranged on different sides of the corner of the building, and the depth of the lifting hole (4) is 5-10 times the thickness of the raft foundation (1); S4、抬升:抬升孔(4)内同时进行压力注浆,对建筑物的抬升侧进行抬升,抬升侧与承重墙(2)平行,抬升时,抬升侧的两个拐角同时进行抬升,控制抬升侧建筑物两个拐角的抬升速度,使两个拐角的标高最终同时抬升至与建筑物非抬升侧对应拐角的标高相同的高度;抬升时采用间歇式注浆抬升,先注浆抬升一定高度,暂停一段时间注浆,然后再注浆抬升一定高度,比较与抬升侧垂直的两相对的非抬升侧的标高,当存在大于要求的标高差时,将其中标高低的非抬升侧作为新的抬升侧重复步骤S3和S4;S4. Lifting: pressure grouting is carried out in the lifting hole (4) at the same time, and the lifting side of the building is lifted. The lifting side is parallel to the bearing wall (2). When lifting, the two corners of the lifting side are lifted at the same time to control the lifting. The lifting speed of the two corners of the side building, so that the elevations of the two corners are finally raised to the same height as that of the corresponding corners on the non-raised side of the building; Pause grouting for a period of time, and then grouting to raise a certain height, compare the elevations of the two opposite non-raised sides perpendicular to the raised side, when there is a difference greater than the required elevation difference, take the non-raised side with the lower elevation as the new raised side Repeat steps S3 and S4 on the side; 在抬升侧沿墙体长度方向、原有抬升孔(4)之间间隔布设有若干个加密抬升孔(41);所有抬升孔(4)和所有加密抬升孔(41)内同时进行压力注浆,对建筑物抬升侧进行抬升,抬升时,控制各抬升点处建筑物承重墙(2)的抬升速度,使建筑物抬升侧的各点均匀抬升,最终同时抬升至与建筑物非抬升侧对应位置的标高相同的高度;Several intensified lifting holes (41) are arranged at intervals along the length of the wall and between the original lifting holes (4) on the lifting side; pressure grouting is carried out simultaneously in all the lifting holes (4) and all the intensified lifting holes (41). , the lifting side of the building is lifted. When lifting, the lifting speed of the building load-bearing wall (2) at each lifting point is controlled, so that each point on the lifting side of the building is lifted evenly, and finally at the same time, it is lifted to the corresponding non-lifting side of the building. The elevation of the location is the same height; S5、填充补强:在筏板基础(1)的中间位置布设补强孔(5),补强孔(5)的孔底延伸至筏板基础(1)与加固体(3)的结合面处,向补强孔(5)的底端注浆,将所有筏板基础(1)底面与加固体(3)顶面之间的空隙填充密实。S5. Filling and reinforcement: A reinforcement hole (5) is arranged in the middle of the raft foundation (1), and the bottom of the reinforcement hole (5) extends to the joint surface of the raft foundation (1) and the reinforcement (3). At the bottom of the reinforcement hole (5), grouting is performed to fill the gaps between the bottom surface of all the raft foundations (1) and the top surface of the reinforcement body (3). 2.根据权利要求1所述的一种筏板基础高层建筑物的抬升方法,其特征在于:步骤S5中,选取部分加固注浆孔(31)作为排气孔,封闭剩余加固注浆孔(31),当排气孔出现返浆时,停止补强孔(5)注浆。2. The lifting method of a high-rise building with a raft foundation according to claim 1, wherein in step S5, some reinforcement grouting holes (31) are selected as exhaust holes, and the remaining reinforcement grouting holes (31) are closed. 31), when the grouting occurs in the vent hole, stop the grouting of the reinforcing hole (5). 3.根据权利要求1所述的一种筏板基础高层建筑物的抬升方法,其特征在于:步骤S3中抬升孔(4)布设在筏板基础(1)的外侧,拐角处设置的两个抬升孔(4)分别位于筏板基础(1)相互垂直的两条外轮廓线的外侧;两个抬升孔(4)的孔底分别延伸至相互垂直的两堵承重墙(2)的正下方。3. the lifting method of a kind of raft foundation high-rise building according to claim 1, is characterized in that: in step S3, the lifting hole (4) is arranged on the outside of the raft foundation (1), and the two corners are arranged The lifting holes (4) are respectively located on the outer sides of the two mutually perpendicular outer contour lines of the raft foundation (1); the hole bottoms of the two lifting holes (4) respectively extend to directly below the two mutually perpendicular load-bearing walls (2) . 4.根据权利要求1所述的一种筏板基础高层建筑物的抬升方法,其特征在于:步骤S3中拐角的两个抬升孔(4)其中一个抬升孔(4)布设在筏板基础(1)的外侧,另一个抬升孔(4)设置在承重墙(2)的内侧。4. The lifting method of a high-rise building with a raft foundation according to claim 1, characterized in that: in step S3, one of the lifting holes (4) of the two lifting holes (4) at the corners is arranged on the raft foundation (4). 1), another lifting hole (4) is arranged on the inner side of the load-bearing wall (2). 5.根据权利要求1-4任一所述的一种筏板基础高层建筑物的抬升方法,其特征在于:步骤S4中注浆抬升时对建筑物各个测点进行实时监控。5. The lifting method of a raft foundation high-rise building according to any one of claims 1-4, wherein in step S4, each measuring point of the building is monitored in real time during grouting lifting. 6.根据权利要求1-4任一所述的一种筏板基础高层建筑物的抬升方法,其特征在于:步骤S2中采用钻注一体机逐段分层进行注浆。6 . The lifting method for a high-rise building with a raft foundation according to any one of claims 1 to 4 , wherein in step S2 , a drilling-grouting integrated machine is used to perform grouting section by section and layer by section. 7 . 7.根据权利要求1所述的一种筏板基础高层建筑物的抬升方法,其特征在于:所述压力注浆采用的浆液为双组分浆液,不同组分的浆液在注浆管或钻杆底部的出浆口压入土体并汇合发生反应并凝固,初凝时间为5-60s,抬升孔(4)内的注浆压力为1.2-2.0Mpa。7. The lifting method of a raft foundation high-rise building according to claim 1, wherein the slurry used in the pressure grouting is a two-component slurry, and the slurry of different components is placed in a grouting pipe or a drill. The grouting outlet at the bottom of the rod is pressed into the soil and merged to react and solidify. The initial setting time is 5-60s, and the grouting pressure in the lifting hole (4) is 1.2-2.0Mpa.
CN201910517279.3A 2019-06-14 2019-06-14 Lifting method of raft foundation high-rise building Active CN112081153B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910517279.3A CN112081153B (en) 2019-06-14 2019-06-14 Lifting method of raft foundation high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910517279.3A CN112081153B (en) 2019-06-14 2019-06-14 Lifting method of raft foundation high-rise building

Publications (2)

Publication Number Publication Date
CN112081153A CN112081153A (en) 2020-12-15
CN112081153B true CN112081153B (en) 2022-08-23

Family

ID=73734085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910517279.3A Active CN112081153B (en) 2019-06-14 2019-06-14 Lifting method of raft foundation high-rise building

Country Status (1)

Country Link
CN (1) CN112081153B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343078B (en) * 2019-08-09 2022-07-08 北京恒祥宏业基础加固技术有限公司 A precision lifting method for the foundation of plant equipment
CN112343106A (en) * 2019-08-09 2021-02-09 北京恒祥宏业基础加固技术有限公司 Construction method for settlement reinforcement, lifting and deviation correction of high-rise building
CN111894055B (en) * 2020-07-31 2022-01-04 江苏省地质矿产局第三地质大队 Construction method for correcting deviation and reducing settlement of building by using EPS light soil
CN116815837B (en) * 2023-08-29 2023-11-17 上海建工一建集团有限公司 Pre-lifting construction method for soft soil geological super-high-rise piled raft foundation

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017013014A1 (en) * 2015-07-17 2017-01-26 Thur S.R.L. Method for improving the mechanical and hydraulic characteristics of foundation grounds of existing built structures
CN107435346A (en) * 2017-08-18 2017-12-05 北京恒祥宏业基础加固技术有限公司 A kind of grouting and reinforcing method for correcting error suitable for high building structure
CN108842840A (en) * 2018-07-04 2018-11-20 湖南大学 Perforating causes the weak intercalated layer slip-casting lifting method of building settlement under a kind of compensation subway tunnel

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10487473B2 (en) * 2017-06-20 2019-11-26 Charles L. Asplin Wall lifting methods

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2017013014A1 (en) * 2015-07-17 2017-01-26 Thur S.R.L. Method for improving the mechanical and hydraulic characteristics of foundation grounds of existing built structures
CN107435346A (en) * 2017-08-18 2017-12-05 北京恒祥宏业基础加固技术有限公司 A kind of grouting and reinforcing method for correcting error suitable for high building structure
CN108842840A (en) * 2018-07-04 2018-11-20 湖南大学 Perforating causes the weak intercalated layer slip-casting lifting method of building settlement under a kind of compensation subway tunnel

Also Published As

Publication number Publication date
CN112081153A (en) 2020-12-15

Similar Documents

Publication Publication Date Title
US11453992B2 (en) Pile foundation bearing platform settlement, reinforcement, lift-up and leveling structure, and construction method thereof
CN112081153B (en) Lifting method of raft foundation high-rise building
US11840820B2 (en) Method for strengthening and lifting high-rise building having raft foundation
WO2021027025A1 (en) High-rise building settling reinforcing and lifting correcting construction method
CN103195085B (en) Downward story-adding basement and construction method thereof
CN112663694B (en) Construction method for lifting and rectifying building on silt geology
CN112942455A (en) Reinforcing and lifting method for karst foundation high-rise building
WO2023155851A1 (en) Engineering method for settlement reinforcement and lifting of residential building foundation
CN112081155B (en) Reinforcing and lifting method for bar-shaped or box-shaped foundation building
CN112343078B (en) A precision lifting method for the foundation of plant equipment
CN106894420B (en) Basement construction method for supporting
CN112081157B (en) Construction method for forming reinforced composite pile foundation by high-rise building retreating type grouting
CN112081158B (en) Construction method for forming reinforced composite pile foundation by advanced grouting of high-rise building
CN112575794A (en) Deep silt geological foundation pit support structure and construction method thereof
CN108532624B (en) A kind of chemical tank raft foundation reinforcement structure
CN214423369U (en) Deep silt geology foundation ditch retaining structure
CN110863496B (en) Method for replacing, supporting, excavating and constructing arch center foundation by concrete supporting in stone-filled island building area
CN203034465U (en) Core soil reserved double-buttress inclined inner support foundation pit supporting and protecting device
CN114382487B (en) Non-excavation reverse disassembly method for ultra-deep vertical shaft
CN221919358U (en) Premixed flow state solidification geotechnical pile
CN211036970U (en) CFG pile composite foundation structure
CN103498476A (en) Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method
Lu et al. The Key Technology of Integral lifting-up Protection Project of Yuhuang Pavilion—A Review
CN118835638A (en) Underground diaphragm wall composite anchorage foundation and construction method thereof
CN118548065A (en) Sedimentation control construction method and structure for underpass existing frame structure group

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant