CN112064799A - Rapid construction method for sintering engineering batching chamber - Google Patents

Rapid construction method for sintering engineering batching chamber Download PDF

Info

Publication number
CN112064799A
CN112064799A CN202010842707.2A CN202010842707A CN112064799A CN 112064799 A CN112064799 A CN 112064799A CN 202010842707 A CN202010842707 A CN 202010842707A CN 112064799 A CN112064799 A CN 112064799A
Authority
CN
China
Prior art keywords
storage bin
civil engineering
bin
hoisting
subsection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010842707.2A
Other languages
Chinese (zh)
Inventor
韦宁
卫海鹏
陈林栋
蒲璞
阳代茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN202010842707.2A priority Critical patent/CN112064799A/en
Publication of CN112064799A publication Critical patent/CN112064799A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3522Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by raising a structure and then adding structural elements under it

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacture And Refinement Of Metals (AREA)

Abstract

The invention relates to a rapid construction method for a sintering engineering batching chamber, which comprises the following steps: dividing a storage bin into an upper section and a lower section, processing and manufacturing each part, pre-assembling each part, and installing a horizontal beam and a sliding support; after the civil engineering storage bin layer is constructed, removing the scaffold below the civil engineering storage bin layer, and hoisting the upper section of the storage bin; building an inner scaffold and an outer scaffold above a civil engineering material bin layer; installing a fixed sliding rack, and installing a sliding rail on the fixed sliding rack; and hoisting the lower section of the storage bin to the sliding rack integrally or sectionally in sequence, sliding the lower section of the storage bin to a position right below the upper section of the storage bin, and splicing and fixing the lower section of the storage bin with the upper section after the lower section of the storage bin is in place by adopting an inverted hoisting method. The invention can realize the effective combination and the simultaneous promotion of the civil engineering main body construction and the steel material bin construction of the batching chamber of the sintering engineering, and improve the construction efficiency of the batching chamber area of the sintering engineering.

Description

Rapid construction method for sintering engineering batching chamber
Technical Field
The invention belongs to the technical field of engineering construction, and particularly relates to a rapid construction method for a sintering engineering batching chamber.
Background
In the traditional construction process of a sintering engineering batching chamber, because the batching chamber construction relates to civil engineering major structure, steel silo construction and subsequent equipment installation, especially the cross construction of the civil engineering major structure and the steel silo construction continuously exists, the traditional construction method mainly comprises the following two types: (1) after all the construction of the civil engineering main structure is completed, assembling the bulk material bins on site, and then adopting an inverted hanging method to carry out construction of the steel bins, and further carrying out equipment installation construction on the next step; (2) when the civil engineering main structure is constructed to the steel material bin, the construction of the civil engineering main structure is temporarily slowed, the construction of the upper civil engineering main structure is continued after the upper subsection of the steel material bin is integrally hoisted in place, after the construction of the upper main structure is completed and the construction of an external scaffold is completed, the lower subsection of the steel material bin is assembled on site and then is constructed by adopting an inverted hoisting method, and further the equipment installation construction on the next step is further carried out. As the batching room has more equipment and higher requirements, the whole equipment is longer in installation and debugging period, and the batching room engineering adopts the two traditional construction methods, the requirement of quick construction of the batching room in the sintering engineering can not be effectively met.
Disclosure of Invention
The invention aims to solve the technical problem of providing a rapid construction method for a sintering engineering batching chamber, which realizes the effective combination and the simultaneous promotion of the civil engineering main body construction and the steel material bin construction of the sintering engineering batching chamber and improves the construction efficiency of the area of the sintering engineering batching chamber.
The technical scheme adopted by the invention for solving the technical problem is to provide a rapid construction method for a sintering engineering batching chamber, which comprises the following steps:
(1) dividing the stock bin into an upper section and a lower section according to the position of the stock bin mounted on a civil engineering stock bin layer, then according to site construction conditions and the selected hoisting mechanical working condition, carrying out non-segmentation or segmentation on the upper section or segmentation on the lower section, processing and manufacturing each part and carrying out pre-assembly, mounting a horizontal beam in a top bin body of the upper section of the stock bin, and arranging a sliding support on the lower section of the stock bin;
(2) after the civil engineering storage bin layer structure of the civil engineering main body of the batching chamber is constructed, the inner scaffold and the outer scaffold below the civil engineering storage bin layer are removed, and a crane is used for hoisting the upper section of the storage bin;
(3) after the upper part of the stock bin is installed in a segmented mode, an inner scaffold and an outer scaffold above a civil engineering stock bin layer are erected, the horizontal projection part of the inner scaffold in the stock bin is erected upwards by a horizontal cross beam, the outer scaffold is erected upwards by cantilever type steel, and the cantilever type steel is installed on the civil engineering stock bin layer;
(4) installing a fixed sliding rack, wherein the fixed sliding rack extends from the exterior of the civil engineering main body of the batching chamber to the lower part of the civil engineering bunker layer, and installing a sliding rail on the fixed sliding rack;
(5) and hoisting the lower section of the storage bin to the sliding rack integrally or sectionally in sequence, sliding the lower section of the storage bin to a position right below the upper section of the storage bin, and splicing and fixing the lower section of the storage bin with the upper section after the lower section of the storage bin is in place by adopting an inverted hoisting method.
The sliding supports are arranged on the outer side of the funnel section of the lower part section of the storage bin and are arranged oppositely.
And (5) installing more than three hoisting devices on the segmented inner wall of the upper part of the stock bin at uniform intervals along the circumferential direction, correspondingly arranging hoisting points on the inner wall of the lower segment of the stock bin along the circumferential direction, and connecting the hoisting devices with the hoisting points of the lower segment of the stock bin and then performing reverse-pulling hoisting.
And (5) in the construction processes of the steps (4) to (5), synchronously constructing the civil engineering main body above the civil engineering material bin layer.
Advantageous effects
The invention can realize the simultaneous construction of the civil engineering main structure at the upper part of the steel material bin layer of the batching chamber and the lower section of the steel material bin of the material bin, compared with the traditional batching chamber construction, the continuity of the civil engineering main structure and the steel material bin construction is ensured by closely combining the civil engineering construction technology and the steel material bin construction technology and mutually supporting, thereby promoting the rapid construction of the batching chamber and being beneficial to improving the construction efficiency of the batching chamber of the sintering engineering.
Drawings
Fig. 1 is a schematic structural diagram of a bunker segment according to an embodiment of the present invention.
Fig. 2 is a schematic diagram of hoisting construction of an upper section of a storage bin.
Fig. 3 is a schematic diagram of scaffold erection construction above a civil engineering silo layer.
Fig. 4 is a schematic diagram of the slipping process of the lower section of the storage bin in position.
Fig. 5 is a schematic diagram of the process of reversely hanging the lower part of the storage bin in position.
Detailed Description
The invention will be further illustrated with reference to the following specific examples. It should be understood that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Further, it should be understood that various changes or modifications of the present invention may be made by those skilled in the art after reading the teaching of the present invention, and such equivalents may fall within the scope of the present invention as defined in the appended claims.
A rapid construction method for a sintering engineering batching room comprises the following steps:
(1) the method comprises the steps of dividing a storage bin into an upper section 1 and a lower section 2 according to the position of the storage bin mounted on a civil engineering storage bin layer 5, dividing the upper section 1 into three subsections shown in figure 1 according to site construction conditions and the working condition of a selected hoisting machine, and dividing the lower section 2 into two subsections shown in figure 1. The sub-sections are respectively processed and manufactured and are pre-assembled, a horizontal beam 3 is installed in a top sub-section cabin body of the upper section 1 of the storage bin, a sliding support 4 is installed on the outer side of a funnel section of the lower section 2 of the storage bin, and the sliding supports 4 are oppositely arranged.
(2) After the civil engineering material storehouse layer 5 structure construction of batching room civil engineering main part is accomplished, demolish the inside and outside scaffold of part below civil engineering material storehouse layer 5, use hoist 6 to hoist upper portion subsection 1 of feed bin.
(3) After the installation of the upper portion subsection 1 of feed bin is accomplished, begin to set up civil engineering feed bin layer 5 above inside, outer scaffold, interior scaffold is upwards set up by horizontal beam 3 at the inside horizontal projection part of feed bin, and outer scaffold is upwards set up the scaffold of encorbelmenting by encorbelmenting shaped steel 7, and the shaped steel 7 of encorbelmenting is installed on civil engineering feed bin layer 5.
(4) And a fixed sliding rack 8 is installed, the fixed sliding rack 8 extends to the lower part of the civil engineering material storehouse layer 5 from the exterior of the civil engineering main body of the batching room, and a sliding rail 9 is installed on the fixed sliding rack 8.
(5) And sequentially hoisting the sections of the lower section 2 of the storage bin to the sliding rack 8, so that the sliding support 4 and the sliding rail 9 form sliding fit, and the sections sequentially slide to positions right below the section 1 on the upper part of the storage bin, are positioned by adopting an inverted hoisting method, and are assembled, welded and fixed with the section 1 on the upper part. Three hoisting apparatus 10 are installed on the inner wall of the upper section 1 of the storage bin at uniform intervals along the circumferential direction, hoisting points are correspondingly arranged on the inner wall of the lower section 2 of the storage bin along the circumferential direction, the hoisting apparatus 10 is connected with the hoisting points of the lower section 2 of the storage bin and then is hoisted by pulling backwards, and the hoisting apparatus 10 adopts an electric hoist.
In the construction process of the steps (4) - (5), the construction of the civil engineering main body above the civil engineering material storehouse layer 5 is synchronously carried out, so that the simultaneous construction of the civil engineering main body structure at the upper part of the steel material storehouse layer of the proportioning room and the subsection steel material storehouse under the material storehouse is realized, the continuity of the civil engineering main body construction and the steel material storehouse construction is ensured by closely combining the civil engineering construction technology and the steel material storehouse construction technology and mutually supporting, the rapid construction of the proportioning room is promoted, and the construction efficiency of the proportioning room of the sintering engineering is favorably improved.

Claims (4)

1. A rapid construction method for a sintering engineering batching room comprises the following steps:
(1) dividing the stock bin into an upper subsection (1) and a lower subsection (2) according to the position of the stock bin mounted on a civil engineering stock bin layer (5), then according to the site construction condition and the selected hoisting mechanical working condition, not segmenting the upper subsection (1) or dividing the upper subsection into a plurality of subsections, not segmenting the lower subsection (2) or dividing the lower subsection into a plurality of subsections, processing and manufacturing each part and pre-assembling the parts, mounting a horizontal cross beam (3) in a top bin body of the upper subsection (1) of the stock bin, and arranging a sliding support (4) on the lower subsection (2) of the stock bin;
(2) after the civil engineering material bin layer (5) structure of the civil engineering main body of the batching room is constructed, the inner scaffold and the outer scaffold below the civil engineering material bin layer (5) are removed, and a crane (6) is used for hoisting the upper section (1) of the material bin;
(3) after the upper section (1) of the storage bin is installed, an inner scaffold and an outer scaffold above a civil engineering storage bin layer (5) are erected, the horizontal projection part of the inner scaffold inside the storage bin is erected upwards by a horizontal cross beam (3), the outer scaffold is erected upwards by cantilever type steel (7), and the cantilever type steel (7) is installed on the civil engineering storage bin layer (5);
(4) installing a fixed sliding rack (8), wherein the fixed sliding rack (8) extends from the exterior of the civil engineering main body of the batching room to the lower part of the civil engineering bunker layer (5), and installing a sliding rail (9) on the fixed sliding rack (8);
(5) the lower subsection (2) of the storage bin is integrally or sectionally hung on the sliding rack (8) in sequence and slides to the position right below the upper subsection (1) of the storage bin, and is spliced and fixed with the upper subsection (1) after being in place by adopting an inverted hanging method.
2. The rapid construction method of the sintering engineering batching room according to claim 1 is characterized in that: the sliding supports (4) are arranged on the outer side of the funnel section of the lower part section (2) of the storage bin and are arranged oppositely.
3. The rapid construction method of the sintering engineering batching room according to claim 1 is characterized in that: in the step (5), more than three hoisting devices (10) are uniformly installed on the inner wall of the upper section (1) of the storage bin at intervals along the circumferential direction, hoisting points are correspondingly arranged on the inner wall of the lower section (2) of the storage bin along the circumferential direction, and the hoisting devices (10) are connected with the hoisting points of the lower section (2) of the storage bin and then are pulled backwards for hoisting.
4. The rapid construction method of the sintering engineering batching room according to claim 1 is characterized in that: and (5) in the construction processes of the steps (4) to (5), synchronously constructing the civil engineering main body above the civil engineering material storehouse layer (5).
CN202010842707.2A 2020-08-20 2020-08-20 Rapid construction method for sintering engineering batching chamber Pending CN112064799A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010842707.2A CN112064799A (en) 2020-08-20 2020-08-20 Rapid construction method for sintering engineering batching chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010842707.2A CN112064799A (en) 2020-08-20 2020-08-20 Rapid construction method for sintering engineering batching chamber

Publications (1)

Publication Number Publication Date
CN112064799A true CN112064799A (en) 2020-12-11

Family

ID=73662326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010842707.2A Pending CN112064799A (en) 2020-08-20 2020-08-20 Rapid construction method for sintering engineering batching chamber

Country Status (1)

Country Link
CN (1) CN112064799A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114434101A (en) * 2022-01-21 2022-05-06 广东科能工程管理有限公司 Split welding method for steel cone hopper of charging bin

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202023348U (en) * 2011-01-17 2011-11-02 中国建筑第四工程局有限公司 Hanging-opening type scaffold
CN104764327A (en) * 2015-03-26 2015-07-08 中国五冶集团有限公司 Indoor smoke channel mounting process of sintering engineering
CN106121248A (en) * 2016-06-21 2016-11-16 北京首钢建设集团有限公司 The installation method of sintering large flue in a kind of restricted area
CN107227814A (en) * 2017-06-19 2017-10-03 中国建筑第二工程局有限公司 Sectional construction method for large cantilever concrete structure
CN108033415A (en) * 2017-11-21 2018-05-15 中冶天工集团天津有限公司 A kind of installation method in sintered material storehouse
JP2019072960A (en) * 2017-10-18 2019-05-16 株式会社ミスミ特殊 Core bit, inverter control core drill, and method of dry-drilling concrete
US20190185383A1 (en) * 2012-04-16 2019-06-20 Schott Corporation Polycrystalline chalcogenide ceramic material
CN110127520A (en) * 2019-05-10 2019-08-16 上海二十冶建设有限公司 The small lattice funnel of large-type sinterer and dust-fall pipe installation method
CN110319707A (en) * 2019-06-28 2019-10-11 五冶集团上海有限公司 Large-scale environmental protection sintering flue gas vortex mixer installation method
CN110725597A (en) * 2019-10-23 2020-01-24 中国十九冶集团有限公司 Construction platform erection structure and method for ring beam at top of concrete silo
CN112719802A (en) * 2020-12-21 2021-04-30 上海二十冶建设有限公司 Method for accurately positioning and installing converter backing ring and converter shell

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202023348U (en) * 2011-01-17 2011-11-02 中国建筑第四工程局有限公司 Hanging-opening type scaffold
US20190185383A1 (en) * 2012-04-16 2019-06-20 Schott Corporation Polycrystalline chalcogenide ceramic material
CN104764327A (en) * 2015-03-26 2015-07-08 中国五冶集团有限公司 Indoor smoke channel mounting process of sintering engineering
CN106121248A (en) * 2016-06-21 2016-11-16 北京首钢建设集团有限公司 The installation method of sintering large flue in a kind of restricted area
CN107227814A (en) * 2017-06-19 2017-10-03 中国建筑第二工程局有限公司 Sectional construction method for large cantilever concrete structure
JP2019072960A (en) * 2017-10-18 2019-05-16 株式会社ミスミ特殊 Core bit, inverter control core drill, and method of dry-drilling concrete
CN108033415A (en) * 2017-11-21 2018-05-15 中冶天工集团天津有限公司 A kind of installation method in sintered material storehouse
CN110127520A (en) * 2019-05-10 2019-08-16 上海二十冶建设有限公司 The small lattice funnel of large-type sinterer and dust-fall pipe installation method
CN110319707A (en) * 2019-06-28 2019-10-11 五冶集团上海有限公司 Large-scale environmental protection sintering flue gas vortex mixer installation method
CN110725597A (en) * 2019-10-23 2020-01-24 中国十九冶集团有限公司 Construction platform erection structure and method for ring beam at top of concrete silo
CN112719802A (en) * 2020-12-21 2021-04-30 上海二十冶建设有限公司 Method for accurately positioning and installing converter backing ring and converter shell

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114434101A (en) * 2022-01-21 2022-05-06 广东科能工程管理有限公司 Split welding method for steel cone hopper of charging bin
CN114434101B (en) * 2022-01-21 2022-11-29 广东科能工程管理有限公司 Split welding method for steel cone bucket of charging barrel bin

Similar Documents

Publication Publication Date Title
CN108019076B (en) Construction method of large-diameter reinforced concrete silo and device for conical shell construction
CN105507652A (en) Hydraulic lifting and upside-down construction method for internal steel tube of chimney
CN109184189B (en) Construction method for conical shell silo top structure of large-diameter silo
CN107447997A (en) Wall-building machine
CN109081247A (en) A kind of hanging method of vestibule large-span steel girder
CN112064799A (en) Rapid construction method for sintering engineering batching chamber
CN104531931B (en) Method for installing dust removal pipeline at lower part of blast furnace casting house
CN1974792A (en) Self-hoisting construction method and furnace top crane for general overhaul of blast furnace
CN109055637B (en) Hydraulic lifting process for mounting furnace shell in blast furnace overhaul
CN202417519U (en) Synchronous trolley
CN110185458B (en) Bidirectional shield launching method
CN110562387A (en) construction method of floating oil storage platform pipe bundle unit
CN104060841A (en) Large-span steel girder installation construction method
CN209760872U (en) Diagonal draw bar for supporting-free formwork
CN101956372B (en) Quick construction method for No. 0 section of prestressed concrete beam type bridge
CN210530883U (en) Construction system for horizontal splicing, vertical rotation and combination of circular strip steel lining tunnel
CN101858165B (en) Tower mast structural segmented sheathing and piercing drawout integral installation technology
CN112431465A (en) Rapid construction method for large-diameter steel bin placed in limited space
CN209975714U (en) Assembled prefabricated component
CN209493033U (en) Belt plow
CN108868098B (en) Support frame used outside hoistway and mounting method thereof
CN206860218U (en) A kind of shield machine integrally originates the interim station support frame in space
CN204510925U (en) A kind of homogenization warehouse factory building structure
CN110593906A (en) Horizontal splicing vertical rotation combined construction system and method for circular strip steel lining tunnel
CN213806661U (en) Construction is with platform of unloading

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201211

RJ01 Rejection of invention patent application after publication