CN112031397A - Fixed template structure of pouring frame for construction engineering construction - Google Patents

Fixed template structure of pouring frame for construction engineering construction Download PDF

Info

Publication number
CN112031397A
CN112031397A CN202010937914.6A CN202010937914A CN112031397A CN 112031397 A CN112031397 A CN 112031397A CN 202010937914 A CN202010937914 A CN 202010937914A CN 112031397 A CN112031397 A CN 112031397A
Authority
CN
China
Prior art keywords
template
plate
construction
support column
telescopic rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010937914.6A
Other languages
Chinese (zh)
Inventor
高洪锋
张�荣
汪浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN202010937914.6A priority Critical patent/CN112031397A/en
Publication of CN112031397A publication Critical patent/CN112031397A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/02Forming boards or similar elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6801Fillings therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a fixed template structure of a pouring frame for construction engineering construction, and relates to the technical field of building template structures. This fixed template structure of frame of pouring of building engineering construction usefulness is through setting up support column one and support column two, and support column one can be as an organic whole two adjacent templates one, and support column two can be with two adjacent template two are as an organic whole, and then can reduce half engineering volume when the installation, the installation of being convenient for simultaneously, installation labour saving and time saving, improve device practicality and work efficiency, through setting up bead, recess and joint strip, when the installation, the bead can insert in the recess, joint strip seals it simultaneously, guarantees not have the clearance between the two, and then can not take place the overflow and leak at the slip casting in-process, not only can not cause the waste to the thick liquid, and guarantee that the product can not produce the overflow limit, improve device functionality in addition.

Description

Fixed template structure of pouring frame for construction engineering construction
Technical Field
The invention relates to the technical field of building template structures, in particular to a fixed template structure of a pouring frame for construction engineering construction.
Background
The building formwork is a temporary supporting structure, which is made according to the design requirement, so that the concrete structure and the components are formed according to the specified position and geometric dimension, the correct position is kept, the self weight of the building formwork and the external load acting on the building formwork are borne, the aim of formwork engineering is fulfilled, the quality and the construction safety of the concrete engineering are ensured, the construction progress is accelerated, and the engineering cost is reduced.
However, when the fixed template structure of the existing pouring frame for construction engineering construction is installed, four templates need to be assembled, so that the installation work amount is large, the time and labor are wasted in the installation process, the practicability and the installation efficiency of the device are reduced, secondly, the fixed template structure of the pouring frame for the existing construction engineering construction has certain gaps at the joints between the templates in the using process, furthermore, the slurry can generate overflow leakage in the grouting process, which not only wastes the slurry, but also affects the appearance of the product and reduces the functionality of the device, and in addition, the slurry can form certain pressure on the inner wall of the template in the grouting process of the fixed template structure of the pouring frame for the existing construction engineering construction, further, the formwork and the product are deformed, and the working effect of the device is reduced, so that a pouring frame fixed formwork structure for construction engineering construction is urgently needed to solve the existing problems.
Disclosure of Invention
The present invention has been made to solve the above problems, and an object of the present invention is to provide a fixed formwork structure for a casting frame used in construction work.
The invention realizes the purpose through the following technical scheme:
a fixed template structure of a pouring frame for construction of building engineering comprises a bottom plate, a support, a mold cover plate and a mold base, and comprises a first support column, a second support column, a first template and a second template, wherein the first template is arranged on two side walls of the first support column, the second template is arranged on one side of the first template, the second support column is arranged on one side of the second template, a cavity is formed between the first template and the second template, a convex edge is arranged on one side wall of the first template, a groove is arranged on one side wall of the second template, sealing rubber strips are arranged on inner walls on two sides of the groove, connecting plates are arranged on the first template and the side wall on one upper end of the second template, connecting holes are arranged on the connecting plates, right-angle locking plates are arranged at the joints of the first template and the second template, and locking bolts are arranged, the fixing device is characterized in that a locking hole is formed in one side wall of the first template and one side wall of the second template bottom, a turnover plate is arranged on one side wall of the first template and one side wall of the second template bottom, a mounting seat is arranged at the upper end of the turnover plate, a rotating shaft is arranged between the inner walls of the mounting seat, a telescopic rod is arranged on one side wall of the rotating shaft, one end of the telescopic rod is provided with a fastening plate, a fastening hole is formed in the fastening plate, a button is arranged on one side wall of a sliding part of the telescopic rod, a through hole is formed in one side wall of a fixing part of the telescopic rod, positioning bolts are arranged on two sides of the mounting seat, a fixing plate is arranged on one side wall of the first support column and.
Furthermore, the first template is rotationally connected with the first support column, and the second template is rotationally connected with the second support column.
Through the technical scheme, the first support column can be used for placing the first template into a whole, the second support column can be used for placing the second template into a whole, so that half of engineering quantity can be reduced during installation, installation is facilitated, time and labor are saved during installation, and practicability and working efficiency of the device are improved.
Furthermore, the convex edge is welded with the first template, the groove is formed in the second template, and the sealing rubber strip is connected with the groove through a screw.
Through the technical scheme, when the grouting device is installed, because the convex edge corresponds to the specification of the groove, the convex edge can be inserted into the groove, meanwhile, the sealing rubber strip can seal the groove, no gap exists between the convex edge and the groove, overflow and leakage cannot occur in the grouting process, waste of slurry cannot be caused, overflow of products cannot be generated, and the functionality of the grouting device is improved.
Furthermore, the connecting plate is welded with the first template and the second template, and the connecting holes are formed in the connecting plate.
Through the technical scheme, the connecting holes are combined with the connecting plate and can be convenient for the device to be assembled.
Furthermore, the locking bolt penetrates through the right-angle locking plate, the locking holes are formed in the first template and the second template, and the locking bolt is connected with the locking holes through threads.
Through the technical scheme, the locking bolt is combined with the locking hole to fix the joint of the first template and the second template.
Furthermore, the turnover plate is hinged to the first template and the second template, the mounting seat is connected with the turnover plate through screws, and the rotating shaft is rotatably connected with the mounting seat.
Through the technical scheme, the turnover plate can fix the mounting seat, and the rotating shaft can rotate in the mounting seat so as to drive the telescopic rod to rotate.
Furthermore, the telescopic rod is connected with the rotating shaft through a screw, the fastening plate is connected with the telescopic rod through a bolt, and the fastening hole is formed in the fastening plate.
Through the technical scheme, the telescopic rod can freely stretch out and draw back, so that the height of the fastening plate can be adjusted, the periphery of the first template and the periphery of the second template can be supported and fixed through the fastening holes, deformation of the first template and the second template due to too large pressure in the grouting process is prevented, deformation of products is prevented, and the mold building effect of the device is improved.
Furthermore, the button with the telescopic link passes through spring coupling, the through-hole shaping in on the telescopic link.
Through the technical scheme, the button is combined with the through hole to enable the adjusting height of the telescopic rod to be fixed.
Further, the positioning bolt penetrates through the turnover plate.
Through the technical scheme, the positioning bolt can fix the turnover plate.
Further, the fixed plate is welded with the first support column and the second support column, the fixed hole is formed in the fixed plate, and the fixed bolt is connected with the fixed hole through threads.
Through the technical scheme, the fixing bolt is combined with the fixing hole, so that the first support column and the second support column can be fixed.
The specific working principle is as follows: when in use, the first support column and the second support column are fixed through the fixing bolt and the fixing hole, after the first support column and the second support column are fixed, the first template and the second template are rotated to enable the convex edge to be inserted into the groove, meanwhile, the sealing rubber strip can seal the convex edge, no gap exists between the first template and the second template, further, no overflow leakage occurs in the grouting process, not only is the slurry not wasted, but also the product is prevented from overflowing, the functionality of the device is improved, then, the locking bolt and the locking hole are used for fixing the joint of the first template and the second template, the turnover plate is turned over to be tiled and fixed through positioning, then, the telescopic rod is rotated and can be freely stretched, so that the height of the fastening plate is adjusted, and then, the fastening hole is used for supporting and fixing the peripheries of the first template and the second template, the template I and the template II are prevented from deforming due to overlarge pressure in the grouting process, so that the product is prevented from deforming, the mold building effect of the device is improved, grouting can be performed in the cavity after the template I and the template II are fixed, and in addition, the device can be heightened and assembled through the connecting plate and the connecting holes according to actual conditions.
The invention has the beneficial effects that:
1. by arranging the first support column and the second support column, the first support column can integrate two adjacent templates, and the second support column can integrate two adjacent templates, so that half of the engineering amount can be reduced during installation, the installation is convenient, the time and labor are saved during the installation process, and the practicability and the working efficiency of the device are improved;
2. by arranging the convex edge, the groove and the sealing rubber strip, when the grouting device is installed, the convex edge can be inserted into the groove, and the sealing rubber strip seals the groove, so that no gap exists between the convex edge and the groove, no overflow leakage occurs in the grouting process, the slurry is not wasted, no overflow edge is generated on a product, and the functionality of the grouting device is improved;
3. through setting up pivot, telescopic link, mounting plate and fastening hole, the pivot can drive the telescopic link and rotate, and the telescopic link can freely stretch out and draw back simultaneously, and then adjusts the support height of mounting plate, can support fixedly to the periphery of template one and template two through the fastening hole, prevents to take place deformation because of the too big pressure that receives at slip casting in-process template one and template two, and then guarantees that the product can not take place deformation, improves building of device mould effect.
Drawings
FIG. 1 is a front view of a fixed formwork structure of a pouring frame for construction of constructional engineering according to the present invention;
FIG. 2 is a cross-sectional view of a fixed plate in a fixed formwork structure of a pouring frame for construction of constructional engineering according to the present invention;
FIG. 3 is a front view of a first form in a fixed form structure of a pouring frame for construction of a construction project according to the present invention;
FIG. 4 is a front view of a second form in the fixed form structure of the pouring frame for construction of the constructional engineering of the present invention;
fig. 5 is a cross-sectional view of a telescopic rod in a fixed formwork structure of a pouring frame for construction work according to the present invention.
The reference numerals are explained below:
1. a first template; 2. connecting holes; 3. a connecting plate; 4. a first supporting column; 5. a fastening plate; 6. a telescopic rod; 7. a fixing plate; 8. fixing the bolt; 9. a turnover plate; 10. positioning the bolt; 11. a rotating shaft; 12. a mounting seat; 13. a fastening hole; 14. locking the bolt; 15. a right angle locking plate; 16. a second template; 17. a second supporting column; 18. a cavity; 19. a fixing hole; 20. a locking hole; 21. a rib; 22. a groove; 23. sealing rubber strips; 24. a button; 25. and a through hole.
Detailed Description
The invention will be further described with reference to the accompanying drawings in which:
as shown in fig. 1-5, a fixed formwork structure of a pouring frame for construction of building engineering comprises a first support pillar 4, a second support pillar 17, a first formwork 1 and a second formwork 16, wherein both side walls of the first support pillar 4 are provided with the first formwork 1, one side of the first formwork 1 is provided with the second formwork 16, one side of the second formwork 16 is provided with the second support pillar 17, a cavity 18 is formed between the first formwork 1 and the second formwork 16, one side wall of the first formwork 1 is provided with a convex rib 21, one side wall of the second formwork 16 is provided with a groove 22, both inner walls of both sides of the groove 22 are provided with sealing rubber strips 23, both side walls of the upper ends of the first formwork 1 and the second formwork 16 are provided with connecting plates 3, the connecting plates 3 are provided with connecting holes 2, and a right-angle locking plate 15 is arranged at the joint of the first formwork 1 and the second formwork 16, the locking device is characterized in that a locking bolt 14 is arranged on the right-angle locking plate 15, locking holes 20 are respectively arranged on the side walls of the first template 1 and the second template 16, a turnover plate 9 is respectively arranged on the side walls of the bottom ends of the first template 1 and the second template 16, an installation seat 12 is arranged at the upper end of the turnover plate 9, a rotating shaft 11 is arranged between the inner walls of the installation seat 12, a telescopic rod 6 is arranged on one side wall of the rotating shaft 11, a fastening plate 5 is arranged at one end of the telescopic rod 6, a fastening hole 13 is arranged on the fastening plate 5, a button 24 is arranged on one side wall of the sliding part of the telescopic rod 6, a through hole 25 is arranged on one side wall of the fixing part of the telescopic rod 6, positioning bolts 10 are respectively arranged on two sides of the installation seat 12, a fixing plate 7 is arranged on the side walls of the bottom ends of, the fixing hole 19 is internally provided with a fixing bolt 8.
In this embodiment, template one 1 with support column one 4 rotates to be connected, template two 16 with support column two 17 rotates to be connected, support column one 4 can be with two adjacent template one 1 as an organic whole, support column two 17 can be with two adjacent template two 16 as an organic whole, and then can reduce half engineering volume when the installation, the installation of being convenient for simultaneously, installation labour saving and time saving improves device practicality and work efficiency.
In this embodiment, the rib 21 with the welding of template one 1, recess 22 is formed in on the template two 16, joint strip 23 with recess 22 passes through the screw connection, when the installation, because the rib 21 with the specification of recess 22 is corresponding, and then can with the rib 21 inserts in the recess 22, simultaneously joint strip 23 can seal it, guarantees not to have the clearance between the two, and then can not take place the overflow and leak at the slip casting in-process, not only can not cause the waste to the thick liquid, guarantees moreover that the product can not produce the excessive limit, improves device functionality.
In this embodiment, the connecting plate 3 is welded to the first template 1 and the second template 16, the connecting hole 2 is formed in the connecting plate 3, and the connecting hole 2 is combined with the connecting plate 3 and can facilitate assembly of the device.
In this embodiment, the locking bolt 14 penetrates through the right-angle locking plate 15, the locking holes 20 are formed in the first template 1 and the second template 16, the locking bolt 14 is connected with the locking holes 20 through threads, and the locking bolt 14 is combined with the locking holes 20 to fix the joint of the first template 1 and the second template 16.
In this embodiment, the turning plate 9 is hinged to the first template 1 and the second template 16, the mounting seat 12 is connected to the turning plate 9 through screws, the rotating shaft 11 is rotatably connected to the mounting seat 12, the turning plate 9 can fix the mounting seat 12, and the rotating shaft 11 can rotate in the mounting seat 12 to drive the telescopic rod 6 to rotate.
In this embodiment, the telescopic rod 6 is connected with the rotating shaft 11 through a screw, the fastening plate 5 is connected with the telescopic rod 6 through a bolt, the fastening hole 13 is formed in the fastening plate 5, the telescopic rod 6 can freely stretch and retract, so that the height of the fastening plate 5 is adjusted, and meanwhile, the peripheries of the first template 1 and the second template 16 can be supported and fixed through the fastening hole 13, so that the first template 1 and the second template 16 are prevented from being deformed due to too large pressure in a grouting process, deformation of a product is further prevented, and a mold building effect of the device is improved.
In this embodiment, the button 24 is connected to the telescopic rod 6 through a spring, the through hole 25 is formed in the telescopic rod 6, and the button 24 and the through hole 25 are combined to fix the height of the telescopic rod 6.
In this embodiment, the positioning bolt 10 penetrates through the turning plate 9, and the positioning bolt 10 can fix the turning plate 9.
In this embodiment, the fixing plate 7 is welded to the first support pillar 4 and the second support pillar 17, the fixing hole 19 is formed in the fixing plate 7, the fixing bolt 8 is connected to the fixing hole 19 through a thread, and the fixing bolt 8 is combined with the fixing hole 19, so that the first support pillar 4 and the second support pillar 17 can be fixed.
The specific working principle is as follows: when in use, the first support column 4 and the second support column 17 are fixed through the fixing bolt 8 and the fixing hole 19, after the fixing is completed, the first template 1 and the second template 16 are rotated to enable the convex edge 21 to be inserted into the groove 22, meanwhile, the sealing rubber strip 23 can seal the convex edge, no gap exists between the first template 1 and the second template 16, further no overflow leakage occurs in the grouting process, not only no slurry is wasted, but also no overflow edge is generated on a product, the functionality of the device is improved, then the connecting part of the first template 1 and the second template 16 is fixed through the locking bolt 14 and the locking hole 20, the turnover plate 9 is turned over to be tiled and then is fixed through positioning, then the telescopic rod 6 is rotated, and meanwhile, the telescopic rod 6 can freely stretch out and draw back, so that the height of the fastening plate 5 is adjusted, and then the peripheries of the first template 1 and the second template 16 are supported and fixed through the fastening holes 13, so that the first template 1 and the second template 16 are prevented from being deformed due to overlarge pressure applied to the templates in the grouting process, the deformation of products is further avoided, the mold building effect of the device is improved, grouting can be performed into the cavity 18 after the fixing is completed, and in addition, the device can be heightened and assembled through the connecting plates 3 and the connecting holes 2 according to actual conditions.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. The utility model provides a frame fixed template structure pours that building engineering construction used which characterized in that: the die comprises a first support column (4), a second support column (17), a first die plate (1) and a second die plate (16), wherein the first die plate (1) is arranged on two side walls of the first support column (4), the second die plate (16) is arranged on one side of the first die plate (1), the second support column (17) is arranged on one side of the second die plate (16), a cavity (18) is formed between the first die plate (1) and the second die plate (16), a convex rib (21) is arranged on one side wall of the first die plate (1), a groove (22) is arranged on one side wall of the second die plate (16), sealing rubber strips (23) are arranged on inner walls of two sides of the groove (22), a connecting plate (3) is arranged on each of the first die plate (1) and the side wall of the upper end of the second die plate (16), a connecting hole (2) is arranged on each connecting plate (3), and a right-angle locking plate (15) is arranged at the joint of the, the locking device is characterized in that a locking bolt (14) is arranged on the right-angle locking plate (15), locking holes (20) are formed in the side walls of the first template (1) and the second template (16), a turnover plate (9) is arranged on the side walls of the bottom ends of the first template (1) and the second template (16), a mounting seat (12) is arranged at the upper end of the turnover plate (9), a rotating shaft (11) is arranged between the inner walls of the mounting seat (12), a telescopic rod (6) is arranged on one side wall of the rotating shaft (11), a fastening plate (5) is arranged at one end of the telescopic rod (6), a fastening hole (13) is formed in the fastening plate (5), a button (24) is arranged on one side wall of the sliding part of the telescopic rod (6), a through hole (25) is formed in one side wall of the fixing part of the telescopic rod (6), and positioning bolts (10), the support column I (4) and the support column II (17) are both provided with a fixing plate (7) on one side wall of the bottom end, a fixing hole (19) is formed in the fixing plate (7), and a fixing bolt (8) is arranged in the fixing hole (19).
2. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the first template (1) is rotationally connected with the first support column (4), and the second template (16) is rotationally connected with the second support column (17).
3. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the rib (21) is welded with the first template (1), the groove (22) is formed in the second template (16), and the sealing rubber strip (23) is connected with the groove (22) through screws.
4. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the connecting plate (3) is welded with the first template (1) and the second template (16), and the connecting holes (2) are formed in the connecting plate (3).
5. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the locking bolt (14) runs through the right-angle locking plate (15), the locking holes (20) are formed in the first template (1) and the second template (16), and the locking bolt (14) is connected with the locking holes (20) through threads.
6. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the turnover plate (9) is hinged to the first template (1) and the second template (16), the installation seat (12) is connected with the turnover plate (9) through screws, and the rotating shaft (11) is rotatably connected with the installation seat (12).
7. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the telescopic rod (6) is connected with the rotating shaft (11) through screws, the fastening plate (5) is connected with the telescopic rod (6) through bolts, and the fastening holes (13) are formed in the fastening plate (5).
8. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the button (24) is connected with the telescopic rod (6) through a spring, and the through hole (25) is formed in the telescopic rod (6).
9. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the positioning bolt (10) penetrates through the turnover plate (9).
10. The fixed formwork structure of the pouring frame for the construction of the building engineering according to the claim 1, characterized in that: the fixing plate (7) is welded with the first supporting column (4) and the second supporting column (17), the fixing hole (19) is formed in the fixing plate (7), and the fixing bolt (8) is connected with the fixing hole (19) through threads.
CN202010937914.6A 2020-09-09 2020-09-09 Fixed template structure of pouring frame for construction engineering construction Pending CN112031397A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010937914.6A CN112031397A (en) 2020-09-09 2020-09-09 Fixed template structure of pouring frame for construction engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010937914.6A CN112031397A (en) 2020-09-09 2020-09-09 Fixed template structure of pouring frame for construction engineering construction

Publications (1)

Publication Number Publication Date
CN112031397A true CN112031397A (en) 2020-12-04

Family

ID=73584304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010937914.6A Pending CN112031397A (en) 2020-09-09 2020-09-09 Fixed template structure of pouring frame for construction engineering construction

Country Status (1)

Country Link
CN (1) CN112031397A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685026A (en) * 2021-08-13 2021-11-23 蒋建敏 High-strength building template for supporting
CN115573561A (en) * 2022-01-12 2023-01-06 佳木斯大学 Building template connecting frame for civil engineering containing fixed plate

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1727149A (en) * 2004-07-28 2006-02-01 邱则有 Cylindrical die in use for molding component of concrete filled double thin wall
CN1991072A (en) * 2003-12-09 2007-07-04 邱则有 Cavity form component for concrete filling
CN110453915A (en) * 2019-09-05 2019-11-15 三一筑工科技有限公司 The template tooling and its application method of superposed column Cast-in-Situ Segment
CN209990142U (en) * 2019-04-01 2020-01-24 中国建筑第二工程局有限公司 Prevent leaking concrete construction template
CN110778111A (en) * 2019-11-07 2020-02-11 张永祥 Fixed template structure of pouring frame for civil construction engineering construction
CN210316549U (en) * 2019-05-22 2020-04-14 深圳市佰邦建筑设计顾问有限公司 Formwork system of L type infilled wall constructional column
CN210369924U (en) * 2019-05-27 2020-04-21 滕州建工建设集团有限公司 Template for building
CN211074047U (en) * 2019-11-05 2020-07-24 李志华 Building engineering template fixing device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1991072A (en) * 2003-12-09 2007-07-04 邱则有 Cavity form component for concrete filling
CN1727149A (en) * 2004-07-28 2006-02-01 邱则有 Cylindrical die in use for molding component of concrete filled double thin wall
CN209990142U (en) * 2019-04-01 2020-01-24 中国建筑第二工程局有限公司 Prevent leaking concrete construction template
CN210316549U (en) * 2019-05-22 2020-04-14 深圳市佰邦建筑设计顾问有限公司 Formwork system of L type infilled wall constructional column
CN210369924U (en) * 2019-05-27 2020-04-21 滕州建工建设集团有限公司 Template for building
CN110453915A (en) * 2019-09-05 2019-11-15 三一筑工科技有限公司 The template tooling and its application method of superposed column Cast-in-Situ Segment
CN211074047U (en) * 2019-11-05 2020-07-24 李志华 Building engineering template fixing device
CN110778111A (en) * 2019-11-07 2020-02-11 张永祥 Fixed template structure of pouring frame for civil construction engineering construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113685026A (en) * 2021-08-13 2021-11-23 蒋建敏 High-strength building template for supporting
CN115573561A (en) * 2022-01-12 2023-01-06 佳木斯大学 Building template connecting frame for civil engineering containing fixed plate

Similar Documents

Publication Publication Date Title
CN112031397A (en) Fixed template structure of pouring frame for construction engineering construction
CN103334564B (en) The method of wall brick mounting structure and installation wall brick
CN108000689B (en) Combined template for concrete member with window frame, pouring method of combined template and concrete member
CN110561596A (en) Precast beam mold and working method thereof
CN110424731B (en) Cast-in-place end post template combined type reinforcing device with assembly type structure and implementation method
CN210714298U (en) Cast iron square gate connection structure
CN204877022U (en) Energy -conservation attaches frame system
CN112627570A (en) Repairing tool for repairing large gap of door opening and construction method thereof
CN108331333B (en) Aluminum alloy formwork inner wall column root plug seam optimization device and construction method thereof
CN112900855A (en) Template device for sealing and plugging outer wall hole at edge of floor slab and construction method thereof
CN221052685U (en) Basement outer wall post-cast strip seals construction structures
CN218715142U (en) Fixed template structure of pouring frame
CN206170290U (en) C type cement template convenient to form removal
CN216732323U (en) Stair mould capable of preventing slurry leakage
CN213774489U (en) A aluminium template structure for cast-in-place stair
CN210918209U (en) Integrally assembled and finalized large template
CN218439392U (en) Rotary plug template of tunnel secondary lining trolley
CN219855138U (en) Precast pile shaping groove
CN219587225U (en) Aluminum alloy template bottom leakage blocking device
CN214831978U (en) Pier template special-shaped structure
CN214981985U (en) Prevent prefabricated case roof beam template of centre form come-up
CN114809606B (en) Method for installing adjustable assembly type prefabricated primary and secondary beam support-free mold sealing device
CN212744022U (en) Loose joint type annular soft lap joint combination device of tunnel secondary lining trolley
CN211446443U (en) New and old concrete joint grout blocking device
CN218623297U (en) Device for adjusting deviation of internal and external angles between templates

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201204

RJ01 Rejection of invention patent application after publication