CN112030925A - Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift - Google Patents

Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift Download PDF

Info

Publication number
CN112030925A
CN112030925A CN202010850792.7A CN202010850792A CN112030925A CN 112030925 A CN112030925 A CN 112030925A CN 202010850792 A CN202010850792 A CN 202010850792A CN 112030925 A CN112030925 A CN 112030925A
Authority
CN
China
Prior art keywords
suspender
connecting shaft
shaft
platform
disassembling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010850792.7A
Other languages
Chinese (zh)
Other versions
CN112030925B (en
Inventor
吴凡
蔡春华
程航
谢凯
李新宇
李伟雄
童强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Three Gorges Corp
Original Assignee
China Three Gorges Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Three Gorges Corp filed Critical China Three Gorges Corp
Priority to CN202010850792.7A priority Critical patent/CN112030925B/en
Publication of CN112030925A publication Critical patent/CN112030925A/en
Application granted granted Critical
Publication of CN112030925B publication Critical patent/CN112030925B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02CSHIP-LIFTING DEVICES OR MECHANISMS
    • E02C5/00Mechanisms for lifting ships vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a device and a method for efficiently disassembling and assembling suspenders of a vertical hydraulic hoist of a large-scale working gate of a vertical ship lift, which comprises an inter-suspender connecting shaft disassembling and assembling lower platform for disassembling a suspender connecting shaft between a first suspender and a second suspender, wherein an inter-suspender connecting shaft disassembling and assembling upper platform is fixed at the top of the inter-suspender connecting shaft disassembling and assembling lower platform, a jacking shaft tool is arranged on the inter-suspender connecting shaft disassembling and assembling upper platform, and a jack for ejecting and disassembling the suspender connecting shaft is arranged on the jacking shaft tool in a matched manner; the door connecting shaft dismounting platform is used for dismounting a door connecting shaft of a suspender between a second section of suspender and a working door, and the door connecting shaft dismounting platform is matched with a jack and a jacking shaft tool to realize the dismounting of the suspender door connecting shaft. The hanging rod of the vertical hydraulic hoist can overcome various technical difficulties faced by construction, and can efficiently assemble and disassemble the hanging rod of the vertical hydraulic hoist of the large work gate of the vertical ship lift with high quality.

Description

Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift
Technical Field
The invention relates to a device and a method for efficiently disassembling and assembling a suspender of a vertical hydraulic hoist of a large-scale working gate of a vertical ship lift, which are suitable for the efficient disassembling and assembling engineering of the suspender of the vertical hydraulic hoist of various vertical ship lifts and also provide beneficial reference for disassembling and assembling various large-scale multi-connecting-rod long-distance vertical hoist oil cylinder suspenders with similar structural characteristics in other engineering fields.
Background
The lower brake head working gate of the three gorge ship lift is a sinking type flat plate gate, the overall dimension is 28.84m multiplied by 19.75m multiplied by 4.72 m (width multiplied by height multiplied by thickness), the weight is about 670t, the gate lift is operated under pressure by 2 9000KN hydraulic hoist machines, the hoist oil cylinder hanging head of the hoist machine is connected with the lifting lug of the working gate through 2 sections of hanging rods, and the hanging rods are connected with the hanging head and the lifting lug through bearings. The lower gate head working gate door body downstream water stop surface is provided with a pressurizing water stop, and a hydraulic pump station, an inflating pump station, an electrical control system and equipment for operating and controlling the pressurizing water stop and the hydraulic machinery are arranged in the cavities at two sides of the door body. When needing to carry out door body structure and overhaul of the equipments, put the gate out the gate slot through the work of 2 9000KN hydraulic hoist and deposit on falling to 75m elevation maintenance locking roof beams. The hoist is continuous through 2 sections jibs between the headstock gear and the door body, need demolish 2 jibs structure when putting out the gate slot to lock the lock position, because jib structure arranges in the gate slot within range, it demolishs the in-process and is in high face empty state, receives jib structure design and installation characteristics influence simultaneously, leads to the jib to face the dismouting in-process and is difficult, construction is difficult, the big three difficult points of safe risk. Therefore, a proper suspender disassembly and assembly technology must be innovatively developed to overcome various difficulties and realize smooth construction of engineering.
Disclosure of Invention
The invention aims to provide a device and a method for efficiently disassembling and assembling a suspender of a vertical hydraulic hoist of a large work gate of a vertical ship lift, which can overcome various technical difficulties faced by construction, efficiently and excellently complete the efficient disassembly and assembly of the suspender of the vertical hydraulic hoist of the large work gate of the vertical ship lift, and realize the purpose of rapidly lifting a large plane gate and discharging the gate out of a groove.
In order to achieve the technical features, the invention is realized as follows: the efficient disassembling and assembling device for the booms of the vertical hydraulic hoist of the large-scale work gate of the vertical ship lift comprises an inter-boom connecting shaft disassembling and assembling lower platform for disassembling a boom connecting shaft between a first section of boom and a second section of boom, wherein an inter-boom connecting shaft disassembling and assembling upper platform is fixed at the top of the inter-boom connecting shaft disassembling and assembling lower platform, a jacking shaft tool is arranged on the inter-boom connecting shaft disassembling and assembling upper platform, and a jack for ejecting and disassembling the boom connecting shaft is installed on the jacking shaft tool in a matched manner;
the door connecting shaft dismounting platform is used for dismounting a door connecting shaft of a suspender between a second section of suspender and a working door, and the door connecting shaft dismounting platform is matched with a jack and a jacking shaft tool to realize the dismounting of the suspender door connecting shaft.
The jack is connected with a hydraulic pump station, and a balancing weight is fixed at one end of the lower platform of the connecting shaft dismounting between the booms.
A boom bracket is also included for supporting the boom.
The method for disassembling and assembling the suspender of the vertical ship lift large-scale working gate vertical hydraulic hoist suspender efficient disassembling and assembling device comprises the following steps:
the method comprises the following steps: according to the characteristics of the connecting shaft structures and the construction part structures between the hanging heads of the hanging rods and the hoist, between the hanging rods and the lifting lugs of the door body, and the special shape of the construction process, a connecting shaft dismounting lower platform between the hanging rods, a connecting shaft dismounting upper platform between the hanging rods, a hanging rod bracket and a jacking shaft tool are designed and manufactured;
step two: lifting the working gate to a first boom within the working limit range to be locked by opening and closing an oil cylinder of the hydraulic hoist according to the operating rule of the hydraulic hoist for the working gate;
step three: arranging a lower platform for connecting shaft disassembly and assembly between the suspenders and an upper platform for connecting shaft disassembly and assembly between the suspenders, wherein the platform for connecting shaft disassembly and assembly between the suspenders is a detachable double-layer platform, and the upper and lower layers of platforms are combined into a whole in advance;
step four: a jacking shaft tool is arranged on an upper platform for connecting shaft dismounting between the suspenders; arranging a jack on the jacking shaft tool; arranging a suspender bracket;
step five: starting the jack to perform shaft dismounting construction on the connecting shaft of the suspender;
step six: after a suspender connecting shaft between the first suspender and the second suspender is removed, the first suspender is placed in a horizontal state by utilizing the auxiliary cooperation of a crane, a hydraulic hoist is started, and the lower part of the first suspender is placed on a well-arranged suspender bracket through an oil cylinder of the hydraulic hoist;
step seven: dismantling construction of a connecting shaft between hanging heads of a first section of hanging rod and a hydraulic hoist oil cylinder is carried out, the dismantling operation is the same as the dismantling operation of the connecting shaft of the hanging rod, and the first section of hanging rod is hung and rotated to a side vacant position for storage after the dismantling operation of the connecting shaft between the hanging heads is finished, so that the dismantling of the first section of hanging rod is finished;
step eight: after the first section of hanger rod is removed, the hydraulic hoist cylinder descends to the second section of hanger rod, the hoist cylinder hanging head and the second section of hanger rod are connected in a shaft penetrating mode, and the shaft penetrating mode and the shaft removing mode are opposite in program; then removing the inter-suspender connecting shaft disassembling and assembling lower platform, the inter-suspender connecting shaft disassembling and assembling upper platform, the jack, the hydraulic pump station and the balancing weight;
step nine: starting a hydraulic hoist, lifting the working gate to a second section of suspender working limit range to be locked by starting and stopping a hydraulic hoist oil cylinder;
step ten: finishing the arrangement of a connecting door shaft dismounting platform, a jacking shaft tool, a jack and a hydraulic pump station;
step eleven: after the arrangement is in place, removing the baffles at two ends of the door body lifting lug plate connecting shaft, starting the hydraulic pump station and the jack, and performing shaft removal construction of the lifting rod connecting shaft;
step twelve: carrying out second section suspender dismantling construction, wherein the construction process is the same as the first section suspender dismantling process;
step thirteen: connecting a hydraulic hoist oil cylinder hanging head with a working gate lifting lug plate by using a shaft, wherein the construction method is the same as the shaft connecting mode between the hoist oil cylinder hanging head and the second section of lifting rod;
fourteen steps: through the steps, the efficient disassembly and assembly of the suspender of the vertical hydraulic hoist of the large-scale work gate of the vertical ship lift are smoothly realized.
In the manufacturing process of the design in the first step, the steel structure strength and the structure size of the device must be ensured to meet the construction requirements, and the construction obstruction caused by insufficient structure strength or size deviation of the auxiliary device is avoided;
in the third step, as the connecting shaft dismounting platform between the suspenders adopts a detachable double-layer platform structure, the upper and lower layers of platforms need to be combined into a whole in advance, and the platform is hoisted integrally after being carefully checked, and the hoisting in-place working condition of the platform is determined according to the suspender holes reserved between the suspenders and the platform.
When the jacking shaft tool device is arranged in the fourth step, shaft end baffles on two sides of the hanger rod are removed before arrangement, so that the jacking shaft tool is ensured to be aligned to bolt holes of end plates of the jacking shaft tool and fastening bolt holes of the shaft end baffles, the jacking shaft tool is ensured to be in a horizontal state, and the connecting bolts are firmly fastened;
when arranging a hydraulic pump station and a jack, ensuring that the jack is horizontally arranged at the bottom of the jacking shaft tool, arranging the hydraulic pump station in a space area outside a construction range, installing the hydraulic pump station and a high-pressure oil pipe of a jack part to meet design requirements, and arranging oil absorption cotton at the bottom of the hydraulic pump station and the jack;
when arranging the suspender bracket, the suspender bracket is ensured to be arranged at a site designated position, the bottom of the suspender bracket is ensured to be tightly contacted with the ground, and the bracket is stable and does not shake.
In the fifth step, four-point technical control elements are noticed in the shaft dismounting process: the first point is that in the jacking process of the jack, the pressure change of a hydraulic pump station needs to be concerned constantly, and whether the jacking process is smooth or not is determined through the pressure change; secondly, when the jamming condition of the connecting shaft is determined through the pressure change value of the hydraulic pump station, after the pressure is relieved by the hydraulic jack, the position of the suspender is finely adjusted by the aid of the mechanical jack in an auxiliary matching mode, and the jamming is eliminated; a third point suspender connecting shaft and a shaft sleeve are in clearance fit, the working condition of the jack for fixing the shaft due to the fact that the shaft and the shaft sleeve are just in friction bonding possibly exists at the initial stage of shaft dismounting, and at the moment, a manual knocking mode is needed for auxiliary construction; the fourth point is that in the jack shaft jacking process, the front and back directions of the jack are not allowed to be stayed by constructors, so that safety accidents caused by existing accidents are avoided.
In the sixth step, after the connecting shaft between the first section of the suspender and the second section of the suspender is removed, a crane is used for hanging a steel wire rope to hang a hanging head at the lower part of the suspender, the first section of the suspender swings downstream to a vacant position along the water flow direction, then the suspender rotates by 90 degrees to be placed outside the door slot, and the first section of the suspender is placed in a horizontal state by using the downward auxiliary cooperation of a hydraulic hoist and is placed on the arranged bracket;
the lower hanging head of the first section of suspender is hung by using a crane hanging steel wire rope, and then the first section of suspender swings to swing towards the downstream, and the structure of the connecting shaft dismounting upper platform between the suspenders needs to be unlocked and dismounted because the first section of suspender swings and the connecting shaft dismounting upper platform between the suspenders interfere;
before shaft penetration in the step eight, a hydraulic hoist is used for opening and closing to adjust the matching precision between the oil cylinder hanging head and the second section of hanger rod hanging head in the height direction, and a high-precision horizontal angle square is used for detecting the levelness of the inner wall of a shaft penetrating hole, so that the condition that no blockage exists in the shaft connecting penetrating process is met is ensured; after the shaft penetrating is finished, the lower platform, the upper platform, the jack and the hydraulic pump station are disassembled and assembled by the connecting shaft between the booms; the device is prevented from being in the operation range of the door body and being spatially interfered with the next working procedure.
In the step ten, the door connecting shaft dismounting platform consists of two parts, the platform close to the upstream side takes the effect of a safety channel into consideration, and the platform needs to be temporarily and firmly connected with the door body after being arranged in place.
The invention has the following beneficial effects:
1. a method and a device for efficiently dismounting and mounting a suspender of a vertical hydraulic hoist of a large work gate of a vertical ship lift are characterized in that the suspender of the vertical hydraulic hoist of the large work gate of the vertical ship lift is efficiently dismounted and mounted smoothly through a strict and reasonable operation flow by means of special auxiliary platform and tool auxiliary construction.
2. The invention has the outstanding characteristics of high technical content, simple structure, quick and convenient use, cyclic use, satisfying of installation requirements, solving of various construction difficulties, economy, high quality, high efficiency and the like, and can overcome various construction technical difficulties in construction.
3. The invention is suitable for the efficient disassembly and assembly engineering of the suspender of the vertical hydraulic hoist of various vertical ship lifts, and also provides a useful reference for the disassembly and assembly of various large gates and metal structures with similar structural characteristics in other engineering fields.
Drawings
The invention is further illustrated by the following figures and examples.
FIG. 1 is a front view of the platform for assembling and disassembling a coupling between booms according to the present invention.
Fig. 2 is a front view of the jacking shaft tool of the invention.
Fig. 3 is a top view of the jacking shaft tool of the present invention.
Fig. 4 is a schematic view of the support structure of the first section of hanger bar during disassembly of the present invention.
FIG. 5 is a front view of the coupling shaft dismounting platform between the hanger rod and the gate lifting lug of the present invention.
FIG. 6 is a left side view of the coupling shaft dismounting platform between the hanger rod and the gate lifting lug of the present invention.
In the figure: the lifting device comprises a first section of lifting rod 1, a lifting rod connecting shaft 2, a second section of lifting rod 3, an upper connecting shaft dismounting platform 4 between the lifting rods, a jacking shaft tool 5, a lower connecting shaft dismounting platform 6 between the lifting rods, a jack 7, a balancing weight 8, a hydraulic pump station 9, a hydraulic hoist oil cylinder 10, a lifting rod bracket 11, a lifting rod connecting door shaft 12, a working door 13 and a connecting door shaft dismounting platform 14.
Detailed Description
Embodiments of the present invention will be further described with reference to the accompanying drawings.
Example 1:
referring to fig. 1-6, the efficient disassembling and assembling device for the booms of the vertical hydraulic hoist of the large work gate of the vertical ship lift comprises an inter-boom connecting shaft disassembling and assembling lower platform 6 for disassembling a boom connecting shaft 2 between a first section of boom 1 and a second section of boom 3, an inter-boom connecting shaft disassembling and assembling upper platform 4 is fixed at the top of the inter-boom connecting shaft disassembling and assembling lower platform 6, a jacking shaft tool 5 is arranged on the inter-boom connecting shaft disassembling and assembling upper platform 4, and a jack 7 for ejecting and disassembling the boom connecting shaft 2 is arranged on the jacking shaft tool 5 in a matching manner; the door connecting shaft dismounting platform comprises a door connecting shaft dismounting platform 14 used for dismounting a door connecting shaft 12 between a second section of suspender 3 and a working door 13, wherein the door connecting shaft dismounting platform 14 is matched with a jack 7 and a jacking shaft tool 5 to realize the dismounting of the door connecting shaft 12.
Furthermore, the jack 7 is connected with a hydraulic pump station 9, and a balancing weight 8 is fixed at one end of the lower platform 6 for connecting and disassembling the shafts between the booms.
Further, a boom bracket 11 for supporting the boom is included.
Example 2:
the method for disassembling and assembling the suspender of the vertical ship lift large-scale working gate vertical hydraulic hoist suspender efficient disassembling and assembling device comprises the following steps:
the method comprises the following steps: according to the characteristics of the connecting shaft structures and the construction part structures between the hanging heads of the hanging rods and the hoist, between the hanging rods and the lifting lugs of the door body, and the special shape of the construction process, the lower platform 6 for connecting shaft disassembly between the hanging rods, the upper platform 4 for connecting shaft disassembly between the hanging rods, the hanging rod bracket 11 and the jacking shaft tool 5 are designed and manufactured;
step two: lifting a working gate 13 to a first section of suspender 1 to be locked within the working limit range by opening and closing an oil cylinder 10 of a hydraulic hoist according to the operating rule of the hydraulic hoist for the working gate;
step three: arranging a lower platform 6 for connecting shaft disassembly and assembly between the suspenders and an upper platform 4 for connecting shaft disassembly and assembly between the suspenders, wherein the platform for connecting shaft disassembly and assembly between the suspenders is a detachable double-layer platform, and combining the upper and lower layers of platforms into a whole in advance;
step four: a jacking shaft tool 5 is arranged on the upper platform 4 for connecting and disassembling the shafts between the suspenders; a jack 7 is arranged on the jacking shaft tool 5; arranging a suspender bracket 11;
step five: starting the jack 7 to perform shaft dismounting construction on the suspender connecting shaft 2;
step six: after a suspender connecting shaft 2 between a first suspender 1 and a second suspender 3 is removed, the first suspender 1 is placed in a horizontal state by using the auxiliary cooperation of a crane, a hydraulic hoist is started, and the lower part of the first suspender 1 is placed on a well-arranged suspender bracket 11 through an oil cylinder 10 of the hydraulic hoist;
step seven: dismantling construction of a connecting shaft between hanging heads of the first section of hanging rod 1 and the oil cylinder 10 of the hydraulic hoist is carried out, the dismantling operation is the same as that of the hanging rod connecting shaft 2, and after the dismantling of the connecting shaft between the hanging heads is finished, the first section of hanging rod is hung and rotated to a side vacant position for storage, so that the dismantling of the first section of hanging rod is finished;
step eight: after the first section of hanger rod is removed, the hydraulic hoist cylinder 10 descends to the second section of hanger rod 3, the hoist cylinder hanging head and the second section of hanger rod 3 are connected in a shaft penetrating mode, and the shaft penetrating mode and the shaft removing mode are opposite in program; then removing the inter-boom connecting shaft dismounting lower platform 6, the inter-boom connecting shaft dismounting upper platform 4, the jack 7, the hydraulic pump station 9 and the counterweight block 8;
step nine: starting the hydraulic hoist, lifting the working gate 13 to the working limit range of the second boom to be locked by opening and closing the oil cylinder of the hydraulic hoist;
step ten: finishing the arrangement of the connecting door shaft dismounting platform 14, the jacking shaft tool 5, the jack 7 and the hydraulic pump station 9;
step eleven: after the arrangement is in place, removing the baffles at the two ends of the door body lifting lug plate connecting shaft, starting the hydraulic pump station and the jack, and performing shaft removal construction on the lifting rod connecting shaft 12;
step twelve: dismantling construction of the second section of the suspender 3 is carried out, and the construction process is the same as the dismantling process of the first section of the suspender 1;
step thirteen: connecting a hydraulic hoist oil cylinder hanging head with a working gate lifting lug plate by using a shaft, wherein the construction method is the same as the shaft connecting mode between the hoist oil cylinder hanging head and the second section of lifting rod;
fourteen steps: through the steps, the efficient disassembly and assembly of the suspender of the vertical hydraulic hoist of the large-scale work gate of the vertical ship lift are smoothly realized.
Furthermore, in the manufacturing process of the design in the first step, the steel structure strength and the structure size of the device must be ensured to meet the construction requirements, and the construction obstruction caused by insufficient structure strength or size deviation of the auxiliary device is avoided;
furthermore, in the third step, as the connecting shaft dismounting platform between the suspenders adopts a detachable double-layer platform structure, the upper and lower layers of platforms need to be combined into a whole in advance, and the platform needs to be hoisted integrally after careful inspection, and the hoisting in-place working condition of the platform needs to be determined according to the suspender hole reserved between the suspenders and the platform.
Further, when the jacking shaft tool device is arranged in the fourth step, shaft end baffles on two sides of the hanger rod are removed before arrangement, so that an end plate bolt hole of the jacking shaft tool 5 is aligned with a shaft end baffle fastening bolt hole, the jacking shaft tool 5 is ensured to be in a horizontal state, and a connecting bolt is fastened firmly;
when arranging a hydraulic pump station and a jack, ensuring that the jack is horizontally arranged at the bottom of the jacking shaft tool 5, arranging the hydraulic pump station in a space area outside a construction range, installing the hydraulic pump station and a high-pressure oil pipe of a jack part to meet design requirements, and arranging oil absorption cotton at the bottom of the hydraulic pump station and the jack;
when arranging the suspender bracket, the suspender bracket is ensured to be arranged at a site designated position, the bottom of the suspender bracket is ensured to be tightly contacted with the ground, and the bracket is stable and does not shake.
Furthermore, in the fifth step, four-point technical control elements are noted in the shaft dismounting process: the first point is that in the jacking process of the jack, the pressure change of a hydraulic pump station needs to be concerned constantly, and whether the jacking process is smooth or not is determined through the pressure change; secondly, when the jamming condition of the connecting shaft is determined through the pressure change value of the hydraulic pump station, after the pressure is relieved by the hydraulic jack, the position of the suspender is finely adjusted by the aid of the mechanical jack in an auxiliary matching mode, and the jamming is eliminated; a third point suspender connecting shaft and a shaft sleeve are in clearance fit, the working condition of the jack for fixing the shaft due to the fact that the shaft and the shaft sleeve are just in friction bonding possibly exists at the initial stage of shaft dismounting, and at the moment, a manual knocking mode is needed for auxiliary construction; the fourth point is that in the jack shaft jacking process, the front and back directions of the jack are not allowed to be stayed by constructors, so that safety accidents caused by existing accidents are avoided.
Furthermore, in the sixth step, after the connecting shaft between the first section of the suspender and the second section of the suspender is removed, a crane is used for hanging a steel wire rope to hang a hanging head at the lower part of the suspender, the first section of the suspender swings downstream to a vacant position along the water flow direction, the suspender rotates by 90 degrees to be placed outside the door slot, and the first section of the suspender is placed in a horizontal state by using the downward auxiliary cooperation of a hydraulic hoist and is placed on the arranged bracket;
the lower hanging head of the first section of suspender is hung by using a crane hanging steel wire rope, and then the first section of suspender swings to swing towards the downstream, and the structure of the upper platform 4 for connecting shaft assembling and disassembling between suspenders needs to be unlocked and disassembled because the swinging area of the first section of suspender and the upper platform 4 for connecting shaft assembling and disassembling between suspenders interfere with each other;
furthermore, before shaft penetration in the eighth step, a hydraulic hoist is used for opening and closing to adjust the matching precision between the oil cylinder hanging head and the second section of hanging rod hanging head in the height direction, and a high-precision horizontal angle square is used for detecting the levelness of the inner wall of the shaft penetrating hole, so that the shaft connecting penetrating process is ensured to be free of blocking; after the shaft penetrating is finished, the inter-suspender connecting shaft dismounting lower platform 6, the inter-suspender connecting shaft dismounting upper platform 4, the jack 7 and the hydraulic pump station 9 need to be removed; the device is prevented from being in the operation range of the door body and being spatially interfered with the next working procedure.
Furthermore, in the step ten, the door connecting shaft dismounting platform 14 is formed by two parts, the function of a safety channel is considered when the platform is close to the upstream side, and the platform is firmly connected with the door body temporarily after being arranged in place.

Claims (10)

1. High-efficient dismouting device of vertical ship lift large-scale work gate vertical type hydraulic hoist jib, its characterized in that: the lifting device comprises an inter-suspender connecting shaft disassembling and assembling lower platform (6) used for disassembling a suspender connecting shaft (2) between a first suspender (1) and a second suspender (3), wherein an inter-suspender connecting shaft disassembling and assembling upper platform (4) is fixed at the top of the inter-suspender connecting shaft disassembling and assembling lower platform (6), a jacking shaft tool (5) is arranged on the inter-suspender connecting shaft disassembling and assembling upper platform (4), and a jack (7) used for jacking and disassembling the suspender connecting shaft (2) is installed on the jacking shaft tool (5) in a matching manner;
the disassembly and assembly platform comprises a door connecting shaft disassembly and assembly platform (14) which is used for disassembling a door connecting shaft (12) of a suspender between a second section of suspender (3) and a working door (13), wherein the door connecting shaft disassembly and assembly platform (14) is matched with a jack (7) and a jacking shaft tool (5), so that the disassembly of the door connecting shaft (12) of the suspender is realized.
2. The efficient disassembling and assembling device for the suspender of the vertical ship lift large-sized working gate vertical hydraulic hoist as claimed in claim 1, wherein: the jack (7) is connected with a hydraulic pump station (9), and a balancing weight (8) is fixed at one end of the lower platform (6) for connecting and disassembling the shafts between the booms.
3. The efficient disassembling and assembling device for the suspender of the vertical ship lift large-sized working gate vertical hydraulic hoist as claimed in claim 1, wherein: also included is a boom bracket (11) for supporting the boom.
4. The method for disassembling and assembling the suspender of the vertical ship lift by using the efficient suspender disassembling and assembling device of the vertical hydraulic hoist for the large-scale work gate of the vertical ship lift as claimed in any one of claims 1 to 3 is characterized by comprising the following steps:
the method comprises the following steps: according to the characteristics of the connecting shaft structure and the construction position structure between the hanger rods and the hoist heads of the hoist, between the hanger rods and the hanger lugs of the door body, and the special shape of the construction process, a connecting shaft dismounting lower platform (6) between the hanger rods, a connecting shaft dismounting upper platform (4) between the hanger rods, a hanger rod bracket (11) and a jacking shaft tool (5) are designed and manufactured;
step two: lifting the working gate (13) to a first section of hanger rod (1) within the working limit range to be locked by opening and closing an oil cylinder (10) of a hydraulic hoist according to the operating rule of the hydraulic hoist for the working gate;
step three: arranging a lower platform (6) for connecting shaft disassembly and assembly between the booms and an upper platform (4) for connecting shaft disassembly and assembly between the booms, wherein the connecting shaft disassembly and assembly platform between the booms is a detachable double-layer platform, and the upper and lower layers of platforms are combined into a whole in advance;
step four: a jacking shaft tool (5) is arranged on the upper platform (4) for connecting and disassembling the shafts between the suspenders; a jack (7) is arranged on the jacking shaft tool (5); arranging a boom bracket (11);
step five: starting the jack (7) to perform shaft dismounting construction on the suspender connecting shaft (2);
step six: after a suspender connecting shaft (2) between a first suspender (1) and a second suspender (3) is detached, the first suspender (1) is placed in a horizontal state by utilizing the auxiliary cooperation of a crane, a hydraulic hoist is started, and the lower part of the first suspender (1) is placed on a well-arranged suspender bracket (11) through an oil cylinder (10) of the hydraulic hoist;
step seven: dismantling construction of a connecting shaft between hanging heads of a first section of hanging rod (1) and a hydraulic hoist oil cylinder (10), wherein the dismantling operation is the same as that of the hanging rod connecting shaft (2), and after the dismantling of the connecting shaft between the hanging heads is finished, the first section of hanging rod is hung to a side vacant position for storage, so that the dismantling of the first section of hanging rod is finished;
step eight: after the first section of hanger rod is removed, the hydraulic hoist cylinder (10) descends to the second section of hanger rod (3), the hoist cylinder hanging head and the second section of hanger rod (3) are connected in a shaft penetrating mode, and the shaft penetrating mode and the shaft removing mode are opposite in program; then removing the inter-boom connecting shaft dismounting lower platform (6), the inter-boom connecting shaft dismounting upper platform (4), the jack (7), the hydraulic pump station (9) and the counterweight block (8);
step nine: starting the hydraulic hoist, lifting the working gate (13) to the working limit range of the second section of suspender to be locked by opening and closing the oil cylinder of the hydraulic hoist;
step ten: the arrangement of the door connecting shaft dismounting platform (14), the jacking shaft tool (5), the jack (7) and the hydraulic pump station (9) is completed;
step eleven: after the arrangement is in place, removing the baffles at two ends of the door body lifting lug plate connecting shaft, starting a hydraulic pump station and a jack, and performing shaft removal construction on the lifting rod connecting shaft (12);
step twelve: dismantling construction of the second section of the suspender (3) is carried out, and the construction process is the same as the dismantling process of the first section of the suspender (1);
step thirteen: connecting a hydraulic hoist oil cylinder hanging head with a working gate lifting lug plate by using a shaft, wherein the construction method is the same as the shaft connecting mode between the hoist oil cylinder hanging head and the second section of lifting rod;
fourteen steps: through the steps, the efficient disassembly and assembly of the suspender of the vertical hydraulic hoist of the large-scale work gate of the vertical ship lift are smoothly realized.
5. The method for disassembling and assembling the suspender of the vertical ship lift large-sized work gate vertical hydraulic hoist according to claim 4, which comprises the following steps: in the manufacturing process of the design in the first step, the steel structure strength and the structure size of the device must be ensured to meet the construction requirements, and the construction obstruction caused by insufficient structure strength or size deviation of the auxiliary device is avoided;
in the third step, as the connecting shaft dismounting platform between the suspenders adopts a detachable double-layer platform structure, the upper and lower layers of platforms need to be combined into a whole in advance, and the platform is hoisted integrally after being carefully checked, and the hoisting in-place working condition of the platform is determined according to the suspender holes reserved between the suspenders and the platform.
6. The method for disassembling and assembling the suspender of the vertical ship lift large-sized work gate vertical hydraulic hoist according to claim 4, which comprises the following steps: when the jacking shaft tool device is arranged in the fourth step, shaft end baffles on two sides of the hanger rod are removed before arrangement, so that the alignment of an end plate bolt hole of the jacking shaft tool (5) and a shaft end baffle fastening bolt hole is ensured, the jacking shaft tool (5) is ensured to be in a horizontal state, and a connecting bolt is firmly fastened;
when arranging a hydraulic pump station and a jack, ensuring that the jack is horizontally arranged at the bottom of a jacking shaft tool (5), arranging the hydraulic pump station in a space area outside a construction range, installing the hydraulic pump station and a high-pressure oil pipe of a jack part to meet design requirements, and arranging oil absorption cotton at the bottom of the hydraulic pump station and the jack;
when arranging the suspender bracket, the suspender bracket is ensured to be arranged at a site designated position, the bottom of the suspender bracket is ensured to be tightly contacted with the ground, and the bracket is stable and does not shake.
7. The method for disassembling and assembling the suspender of the vertical ship lift large-sized work gate vertical hydraulic hoist according to claim 4, which comprises the following steps: in the fifth step, four-point technical control elements are noticed in the shaft dismounting process: the first point is that in the jacking process of the jack, the pressure change of a hydraulic pump station needs to be concerned constantly, and whether the jacking process is smooth or not is determined through the pressure change; secondly, when the jamming condition of the connecting shaft is determined through the pressure change value of the hydraulic pump station, after the pressure is relieved by the hydraulic jack, the position of the suspender is finely adjusted by the aid of the mechanical jack in an auxiliary matching mode, and the jamming is eliminated; a third point suspender connecting shaft and a shaft sleeve are in clearance fit, the working condition of the jack for fixing the shaft due to the fact that the shaft and the shaft sleeve are just in friction bonding possibly exists at the initial stage of shaft dismounting, and at the moment, a manual knocking mode is needed for auxiliary construction; the fourth point is that in the jack shaft jacking process, the front and back directions of the jack are not allowed to be stayed by constructors, so that safety accidents caused by existing accidents are avoided.
8. The method for disassembling and assembling the suspender of the vertical ship lift large-sized work gate vertical hydraulic hoist according to claim 4, which comprises the following steps: in the sixth step, after the connecting shaft between the first section of the suspender and the second section of the suspender is removed, a crane is used for hanging a steel wire rope to hang a hanging head at the lower part of the suspender, the first section of the suspender swings downstream to a vacant position along the water flow direction, then the suspender rotates by 90 degrees to be placed outside the door slot, and the first section of the suspender is placed in a horizontal state by using the downward auxiliary cooperation of a hydraulic hoist and is placed on the arranged bracket;
before the lower hanging head of the first section of suspender is hung by using a crane hanging steel wire rope and swings to the downstream, the structure of the connecting shaft dismounting upper platform (4) between the suspenders needs to be unlocked and dismounted because the swinging area of the first section of suspender and the connecting shaft dismounting upper platform (4) between the suspenders have interference.
9. The method for disassembling and assembling the suspender of the vertical ship lift large-sized work gate vertical hydraulic hoist according to claim 4, which comprises the following steps: before shaft penetration in the step eight, a hydraulic hoist is used for opening and closing to adjust the matching precision between the oil cylinder hanging head and the second section of hanger rod hanging head in the height direction, and a high-precision horizontal angle square is used for detecting the levelness of the inner wall of a shaft penetrating hole, so that the condition that no blockage exists in the shaft connecting penetrating process is met is ensured; after the shaft penetrating is finished, a connecting shaft between the booms is removed to disassemble and assemble the lower platform (6), a connecting shaft between the booms is removed to disassemble and assemble the upper platform (4), a jack (7) and a hydraulic pump station (9); the device is prevented from being in the operation range of the door body and being spatially interfered with the next working procedure.
10. The method for disassembling and assembling the suspender of the vertical ship lift large-sized work gate vertical hydraulic hoist according to claim 4, which comprises the following steps: in the step ten, the door connecting shaft dismounting platform (14) is composed of two parts, the function of a safety channel is considered when the platform is close to the upstream side, and the platform is firmly connected with the door body temporarily after being arranged in place.
CN202010850792.7A 2020-08-21 2020-08-21 Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift Active CN112030925B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010850792.7A CN112030925B (en) 2020-08-21 2020-08-21 Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010850792.7A CN112030925B (en) 2020-08-21 2020-08-21 Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift

Publications (2)

Publication Number Publication Date
CN112030925A true CN112030925A (en) 2020-12-04
CN112030925B CN112030925B (en) 2022-03-11

Family

ID=73580468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010850792.7A Active CN112030925B (en) 2020-08-21 2020-08-21 Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift

Country Status (1)

Country Link
CN (1) CN112030925B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457774A (en) * 2021-12-14 2022-05-10 长江三峡通航管理局 Tool and method for disassembling hydraulic cylinder of horizontal gate of working gate of ship lift lock head

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000302369A (en) * 1999-04-21 2000-10-31 Hitachi Plant Eng & Constr Co Ltd Pipe suspension device
CN204621510U (en) * 2015-05-25 2015-09-09 中国长江电力股份有限公司 Hydraulic steel gate detaching device for pin shaft
CN108677908A (en) * 2018-07-24 2018-10-19 中国葛洲坝集团机电建设有限公司 Large-scale headstock gear sunpender pitman shaft, which is worn, moves back axis method and device
CN208744093U (en) * 2018-09-06 2019-04-16 中国长江三峡集团有限公司 Axis tooling is torn in a kind of ship lock ogee gate sunpender joint open

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000302369A (en) * 1999-04-21 2000-10-31 Hitachi Plant Eng & Constr Co Ltd Pipe suspension device
CN204621510U (en) * 2015-05-25 2015-09-09 中国长江电力股份有限公司 Hydraulic steel gate detaching device for pin shaft
CN108677908A (en) * 2018-07-24 2018-10-19 中国葛洲坝集团机电建设有限公司 Large-scale headstock gear sunpender pitman shaft, which is worn, moves back axis method and device
CN208744093U (en) * 2018-09-06 2019-04-16 中国长江三峡集团有限公司 Axis tooling is torn in a kind of ship lock ogee gate sunpender joint open

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114457774A (en) * 2021-12-14 2022-05-10 长江三峡通航管理局 Tool and method for disassembling hydraulic cylinder of horizontal gate of working gate of ship lift lock head
CN114457774B (en) * 2021-12-14 2024-04-19 宜昌三峡通航工程技术有限公司 Tool and method for disassembling and assembling hydraulic cylinder of lock head working gate of ship lift

Also Published As

Publication number Publication date
CN112030925B (en) 2022-03-11

Similar Documents

Publication Publication Date Title
CN108190757B (en) Barrel frame supporting type steel platform and tower crane integral jacking device and jacking method thereof
CN102650261A (en) Segmental lifting method for impeller of high-power wind driven generator
CN105692470A (en) Internal climbing tower crane and operating method thereof
CN107142954B (en) Steel hanging box lifting system for integral lifting and lifting method thereof
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN114955887B (en) Method for installing portal crane on ship
CN112030925B (en) Efficient disassembly and assembly device and method for suspender of vertical hydraulic hoist of large-sized working gate of vertical ship lift
CN111236077B (en) Unloading construction method for steel box girder
CN110273039B (en) Blast furnace surrounding pipe hoisting structure and installation method thereof
CN112045626B (en) Efficient maintenance device and method for large horizontal plane gate hinge bearing of vertical ship lift
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN203878979U (en) Bolt opposite-pulling type track sliding formwork
CN203486787U (en) Integral lifting device for cabinet top of Wiggins coal gas cabinet
CN111350523A (en) Construction method and device for dismantling negative ring in limited space
CN112456348B (en) Heat absorber hoisting method
CN111485887B (en) Construction method of novel working well
CN102345280A (en) Field installation process of large-span high-water-head hydraulic driving type steel dam gate
CN111392616A (en) Internal climbing arm type tower crane jacking device and construction method
CN112249915A (en) Large bridge crane hoisting method for closed occasions of factory buildings
CN107304030B (en) Special hoisting device for replacing heat exchange tube of transverse tube cooler and application method thereof
CN218560840U (en) Lifting appliance for dismounting large-scale rolling mill housing
CN218434602U (en) Novel aerial working platform
CN110885000B (en) Disassembling process of tyre crane
CN219386680U (en) High-speed railway station room quick column-beam connection node structure based on BIM
CN114457774B (en) Tool and method for disassembling and assembling hydraulic cylinder of lock head working gate of ship lift

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant