CN111985801A - Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal - Google Patents

Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal Download PDF

Info

Publication number
CN111985801A
CN111985801A CN202010821981.1A CN202010821981A CN111985801A CN 111985801 A CN111985801 A CN 111985801A CN 202010821981 A CN202010821981 A CN 202010821981A CN 111985801 A CN111985801 A CN 111985801A
Authority
CN
China
Prior art keywords
information
processing
instruction
list
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010821981.1A
Other languages
Chinese (zh)
Inventor
陈乐宝
彭忠凯
汪永豪
刘小将
韩猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Huasheng Engineering Construction Technology Co Ltd
Original Assignee
Wuhan Huasheng Engineering Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Huasheng Engineering Construction Technology Co Ltd filed Critical Wuhan Huasheng Engineering Construction Technology Co Ltd
Priority to CN202010821981.1A priority Critical patent/CN111985801A/en
Publication of CN111985801A publication Critical patent/CN111985801A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/95Retrieval from the web
    • G06F16/953Querying, e.g. by the use of web search engines
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The application relates to the technical field of project supervision, and solves the problems of untimely management and processing in the traditional offline supervision mode and offline registration mode, and comprises the following steps of S10: a new request for question information is created, and the question information content of a requester is automatically collected; s20: generating a to-do list of corresponding problem information, generating a problem processing instruction and displaying a current instruction processing flow; s30: acquiring and identifying question reply information; s40: and detecting and comparing whether the current problem processing state is end or not. The application realizes the on-line recording and information circulation of construction problems and hidden dangers, reduces the use of paper materials, is more environment-friendly, simultaneously solves the defects existing in an off-line supervision mode and an off-line registration processing mode, improves the problem processing timeliness, and is quicker and more accurate in information transmission and improves the construction management efficiency.

Description

Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal
Technical Field
The invention relates to the technical field of project supervision, in particular to a method and a system for processing problems and hidden dangers of a construction project and an intelligent terminal.
Background
Project supervision refers to the entrustment of a supervision unit with related qualification by a party A, represents a professional service activity of monitoring the project construction of a party B by the party A according to project construction documents approved by the state, laws and regulations related to the project construction, project construction supervision contracts and other project construction contracts, and is of great importance to the construction of the whole building project in the project supervision activity, and supervisors need to ensure that the construction project meets the construction requirements to reduce the construction hidden danger.
Due to the fact that characteristics of each project are different, management and control key points of each project are different in the implementation process, and by means of a traditional offline supervision mode and an offline registration mode, the management and supervision mode has large uncertainty, careless mistakes are prone to occur in both management and supervision, transmission of upper management information and lower construction information is not in place, unnecessary contradictions in the supervision process of construction and supervision personnel are prone to being caused, and even the problem that construction has great hidden dangers is prone to being caused.
Disclosure of Invention
The invention aims to solve the defects of an offline supervision mode and an offline registration processing mode, improve the problem processing timeliness, enable information transmission to be faster and more accurate and improve the construction management efficiency.
The above object of the present invention is achieved by the following technical solutions:
the method for processing the problems and hidden dangers of the building engineering project comprises the following steps:
s10: a new problem information request is acquired through a preset data interface, and the problem information content of a requester is automatically acquired;
s20: storing the problem information content in a preset association database in an associated manner, generating a to-be-handled list of corresponding problem information, generating a problem processing instruction and displaying a current instruction processing flow;
s30: acquiring and identifying question reply information, searching and correspondingly generating a question processing state matched with the current processing step in the database;
s40: and detecting and comparing whether the current problem processing state is finished, if so, uploading the problem information content to a historical problem information base, displaying that the problem processing instruction is finished, and if not, transmitting the problem information content to a server corresponding to the next node.
By adopting the technical scheme, when a supervisor inspects the field condition, a problem list is newly built on line, information corresponding to a question is filled, the problem list is submitted to an information platform after the completion of the filling, if the problem is found continuously, the problem information can be further modified and supplemented by entering a problem processing page, the next node is submitted after the completion of the filling of the problem information is determined, a processing instruction of the problem is selected and submitted to a rectification responsible person, the rectification responsible person is in contact with a constructor for rectification, a rectification reply file is uploaded, the flow display is replied after the uploading, the supervisor can inspect the field again and further process the problem information, the application realizes the on-line recording and information of construction problems and circulation hidden dangers, reduces the use of paper materials, is more environment-friendly, and simultaneously solves the defects of an off-line supervision mode and an off-line registration processing mode, the problem processing timeliness is improved, information transmission is faster and more accurate, and the construction management efficiency is improved.
The present invention in a preferred example may be further configured to: in step S20, a question reprocessing instruction is also generated, the question reprocessing instruction including: reading/editing the modified question information, selecting the order deadline in the pop-up time selection box, saving the filled-in information, sending the instruction.
By adopting the technical scheme, the command can be conveniently modified, the fault tolerance rate is high, and the condition of command transmission errors is reduced.
The present invention in a preferred example may be further configured to: in step S30, the current question processing state is identified and matched to obtain matching information, and according to the matching information, the instruction processing flow automatically selects to keep the current question processing instruction page or jump to the corresponding next question processing instruction page.
By adopting the technical scheme, the problem information is processed more clearly and transparently, and the construction problem and the hidden danger are thoroughly solved.
The present invention in a preferred example may be further configured to: in step S40, a history instruction condition for displaying the current question information is also included.
By adopting the technical scheme, the supervision personnel can conveniently master the processing progress of the problem information in real time.
The invention also aims to provide a system for processing problems and hidden dangers of the construction project.
The second aim of the invention is realized by the following technical scheme:
building engineering project problem and hidden danger processing system includes:
the system comprises a problem list building module, a problem list building module and a problem list setting module, wherein the problem list building module is preset with a plurality of problem information pull-down frames, editing frames and photo uploading frames and is used for selecting and filling corresponding problem information and uploading related photos according to field framing, and the problem list building module is provided with a submitting module and is used for submitting and completing problem building;
the selection instruction setting module is preset with a plurality of processing instructions and is used for selecting and editing the next processing instruction of the problem information, and the edited flow is submitted to the next node;
the instruction reply confirmation module is used for receiving the instruction information submitted by the selection instruction setting module, presetting a reply file frame, uploading a reply file to the reply file frame, and automatically jumping to display the replied file after submitting the reply file;
and the question list module is used for displaying a plurality of question information lists and displaying the current processing state of the question information.
By adopting the technical scheme, when a supervisor inspects the field condition, a problem list is newly built on line, information corresponding to a question is filled, the problem list is submitted to an information platform after the completion of the filling, if the problem is found continuously, the problem information can be further modified and supplemented by entering a problem processing page, the next node is submitted after the completion of the filling of the problem information is determined, a processing instruction of the problem is selected and submitted to a rectification responsible person, the rectification responsible person is in contact with a constructor for rectification, a rectification reply file is uploaded, the flow display is replied after the uploading, the supervisor can inspect the field again and further process the problem information, the application realizes the on-line recording and information of construction problems and circulation hidden dangers, reduces the use of paper materials, is more environment-friendly, and simultaneously solves the defects of an off-line supervision mode and an off-line registration processing mode, the problem processing timeliness is improved, information transmission is faster and more accurate, and the construction management efficiency is improved.
The present invention in a preferred example may be further configured to: the system also comprises a patrol confirming module, a patrol status bar is preset, after the supervision personnel patrol the site situation, the patrol confirming module is used for displaying and processing patrol results, when the patrol status bar is selected to be patrol and completely changed, the process jumps to a process ending node, and when the patrol status bar is selected to be patrol and not completely changed, the process jumps to a selection instruction setting module.
By adopting the technical scheme, supervision personnel can monitor the construction problems and the hidden dangers more conveniently, so that the problem information can be processed more clearly and more transparently, and the construction problems and the hidden dangers can be thoroughly solved.
The present invention in a preferred example may be further configured to: the selection instruction setting module is a pop-up instruction selection box, and the corresponding instruction selection box comprises a verbal notice, a work contact list, a supervision engineer notice list, an engineering pause order, an engineering rework order and a supervision special report.
By adopting the technical scheme, the diversified function instructions are realized, and the processing flow is clearer and simpler.
The present invention in a preferred example may be further configured to: the problem list module is preset with detailed information, deleting, inquiring and other functions corresponding to the problem information.
By adopting the technical scheme, the detailed information of the problem information can be conveniently checked, and the problem information which is processed and finished can be deleted and inquired.
The invention aims to provide the intelligent terminal.
The third object of the invention is realized by the following technical scheme:
an intelligent terminal comprises a memory and a processor, wherein the memory is stored with a computer program which can be loaded by the processor and can execute a processing method of problems and hidden dangers of a construction project. The invention also provides a computer readable storage medium.
In summary, the invention includes at least one of the following beneficial technical effects:
1. the method has the advantages that the online recording and information transfer of construction problems and hidden dangers are realized, the supervision personnel, the rectification responsible personnel and the construction personnel can directly perform information transfer on line, the problem processing flow is simplified, the use of paper materials is reduced, the method is more environment-friendly, the defects existing in an offline supervision mode and an offline registration processing mode are overcome, the problem processing timeliness is improved, the information transfer is quicker and more accurate, and the construction management efficiency is improved;
2. the acceptance and treatment of the hidden danger of the construction problem can be realized by moving the end or the online platform, the site direct communication and direct rectification are convenient, the rapid recording of data is realized simultaneously by the site rectification, the same construction problem processing mode reference is realized in the later stage, and the construction problem processing efficiency is further improved.
Drawings
FIG. 1 is a schematic flow chart of a first embodiment of the present invention;
fig. 2 is a schematic structural diagram of a system according to a second embodiment of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In addition, the term "and/or" herein is only one kind of association relationship describing an associated object, and means that there may be three kinds of relationships, for example, a and/or B, which may mean: a exists alone, A and B exist simultaneously, and B exists alone. In addition, the character "/" herein generally indicates that the former and latter related objects are in an "or" relationship, unless otherwise specified.
The embodiments of the present invention will be described in further detail with reference to the drawings attached hereto.
Example one
The main flow of the method for processing the problems and hidden dangers of the constructional engineering project provided by the embodiment of the invention is described as follows.
As shown in fig. 1:
the method for processing the problems and hidden dangers of the building engineering project comprises the following steps:
s10: a new problem information request is acquired through a preset data interface, and the problem information content of a requester is automatically acquired;
the method comprises the steps that a supervisor newly builds a problem list, after a patrol site finds problems, pull-down selection is carried out according to a preset problem information option, corresponding problem information is selected and filled, related photos are uploaded according to actual site view finding of problems occurring in engineering projects, after detailed problem information content is filled, submission is selected to complete new construction of the problems, and the problem information comprises project names, problem names, positions, processes, construction units, problem types, creation time, instruction types and degrees, whether to reply or not, processing suggestions and rectification results, and a rectification leader.
S20: and storing the problem information content in a preset association database in an associated manner, generating a to-do list of the corresponding problem information, generating a problem processing instruction and displaying a current instruction processing flow. Problem reprocessing instructions are also generated, the problem reprocessing instructions including: reading/editing the modified question information, selecting the order deadline in the pop-up time selection box, saving the filled-in information, sending the instruction. The method is convenient for modifying the instruction again, has higher fault-tolerant rate and reduces the condition of instruction transmission errors.
S30: acquiring and identifying problem reply information, retrieving and correspondingly generating a problem processing state matched with the current processing step in a database, identifying and matching the current problem processing state to obtain matching information, automatically selecting and keeping a current problem processing instruction page or jumping to a corresponding next problem processing instruction page according to the matching information by an instruction processing flow, selecting a problem processing instruction, selecting a next processing instruction for the established problem, re-editing the instruction information and then sending the re-edited instruction to a rectification responsible person, wherein the re-editing of the instruction information comprises the following steps: directly reading/editing and modifying the problem information, selecting the deadline of the notice in a pop-up time selection box, saving the filled information, sending an instruction, and allowing a supervisor to check the instruction condition of the problem information history in an instruction history document. The method has the advantages of being convenient for modifying the instruction again, having higher fault-tolerant rate, reducing the condition of instruction transmission errors and being convenient for a supervisor to master the processing progress of problem information in real time.
The method comprises the steps that an instruction is replied and confirmed, a rectification responsible person checks a received instruction in a supervision notice sheet of a historical document of the rectification responsible person, a reply file is uploaded according to the actual reply condition of a project site construction unit for a problem instruction, after the reply file is uploaded, the flow automatically displays the reply, the reply file is received, a supervision person can go to the site to patrol the rectification condition of the construction unit, if the rectification is completed, the non-patrol state is switched to patrol and rectification in the historical document, and the problem processing flow is ended; if the correction is not completed, the non-inspection state of the history document is switched to inspection and non-correction, at this time, the system records the problem information, upgrades the instruction and repeats the loop from the step S30 until the problem is corrected or the supervision special item report instruction is reached.
And (4) problem list processing, namely checking, replying and deleting the problems displayed in the list according to whether the problems on site are solved or not.
S40: and detecting and comparing whether the current problem processing state is finished, if so, uploading the problem information content to a historical problem information base, displaying that the problem processing instruction is finished, and if not, transmitting the problem information content to a server corresponding to the next node.
The method also comprises the steps of displaying the historical instruction condition of the current problem information, entering a to-do list, directly checking the recorded problem information, returning to a main interface if selecting to return, directly modifying the information if selecting to modify, storing the modified information if selecting to store after modifying, selecting a scene photo, checking a corresponding scene picture, selecting to supplement and upload a related photo, selecting a scene and a content, directly reading the problem related information, manually editing and modifying, selecting an input box which requires to be cut to the right side of time, selecting a notice deadline in a popped time selection box, selecting to send, finishing the instruction editing and sending to a rectification responsible person, and checking the historical instruction condition of the problem in a historical document.
Example two
The system for processing problems and hidden dangers of the building engineering project, referring to fig. 2, comprises:
the system comprises a problem list building module, a plurality of problem information pull-down frames, editing frames and photo uploading frames, wherein the problem list building module is preset with the plurality of problem information pull-down frames, the editing frames and the photo uploading frames and is used for selecting and filling corresponding problem information and uploading related photos according to field framing, a submitting module is arranged and is used for submitting and completing problem building, and the problem list building module is also preset with functions of detailed information, deleting, inquiring and the like corresponding to the problem information, so that the detailed information checking of the problem information and the deleting and inquiring of the processed problem information are conveniently realized.
And the selection instruction setting module is a pop-up instruction selection box, the corresponding instruction selection box comprises a verbal notice, a work contact list, a supervision engineer notice list, an engineering pause order, an engineering rework order and a supervision special item report, the next step processing instruction is used for selecting and editing the problem information, and the flow is submitted to the next node after editing.
And the instruction reply confirmation module is used for receiving the instruction information submitted by the selection instruction setting module, presetting a reply file frame, uploading the reply file to the reply file frame, and automatically jumping to display the replied reply after submitting the reply file. And the question list module is used for displaying a plurality of question information lists and displaying the current processing state of the question information.
The system also comprises a patrol confirming module, a patrol status bar is preset, after the supervision personnel patrol the site situation, the patrol confirming module is used for displaying and processing patrol results, when the patrol status bar is selected to be patrol and completely changed, the process jumps to a process ending node, and when the patrol status bar is selected to be patrol and not completely changed, the process jumps to a selection instruction setting module. The supervision personnel of being convenient for more to the control of construction problem and hidden danger for the processing of problem information is more clear transparentization, guarantees the thorough solution of construction problem and hidden danger.
EXAMPLE III
An intelligent terminal comprises a memory and a processor, wherein the memory is stored with a computer program which can be loaded by the processor and can execute a processing method of problems and hidden dangers of a construction project. The invention also provides a computer readable storage medium.

Claims (10)

1. The method for processing the problems and hidden dangers of the building engineering project is characterized by comprising the following steps of:
s10: a new problem information request is acquired through a preset data interface, and the problem information content of a requester is automatically acquired;
s20: storing the problem information content in a preset association database in an associated manner, generating a to-be-handled list of corresponding problem information, generating a problem processing instruction and displaying a current instruction processing flow;
s30: acquiring and identifying question reply information, searching and correspondingly generating a question processing state matched with the current processing step in the database;
s40: and detecting and comparing whether the current problem processing state is finished, if so, uploading the problem information content to a historical problem information base, displaying that the problem processing instruction is finished, and if not, transmitting the problem information content to a server corresponding to the next node.
2. The method for handling the problems and hidden dangers in the constructional engineering project as recited in claim 1, wherein in step S20, a problem reprocessing instruction is further generated, wherein the problem reprocessing instruction comprises: reading/editing the modified question information, selecting the order deadline in the pop-up time selection box, saving the filled-in information, sending the instruction.
3. The method as claimed in claim 1, wherein in step S30, the current problem processing status is identified and matched to obtain matching information, and the instruction processing flow automatically selects to maintain the current problem processing instruction page or jump to the corresponding next problem processing instruction page according to the matching information.
4. The method as claimed in claim 1, wherein step S40 further includes displaying historical command status of current problem information.
5. Building engineering project problem and hidden danger processing system, its characterized in that includes:
the system comprises a problem list building module, a problem list building module and a problem list setting module, wherein the problem list building module is preset with a plurality of problem information pull-down frames, editing frames and photo uploading frames and is used for selecting and filling corresponding problem information and uploading related photos according to field framing, and the problem list building module is provided with a submitting module and is used for submitting and completing problem building;
the selection instruction setting module is preset with a plurality of processing instructions and is used for selecting and editing the next processing instruction of the problem information, and the edited flow is submitted to the next node;
the instruction reply confirmation module is used for receiving the instruction information submitted by the selection instruction setting module, presetting a reply file frame, uploading a reply file to the reply file frame and submitting the reply file, and automatically jumping to display a replied question processing state;
and the question list module is used for displaying a plurality of question information lists and displaying the current processing state of the question information.
6. The system for processing the problems and hidden dangers in the constructional engineering projects according to claim 5, further comprising a patrol confirming module for displaying and processing patrol results, wherein when the patrol status bar is selected to be patrolled and changed, the process jumps to a process ending node, and when the patrol status bar is selected to be patrolled and not changed, the process jumps to a selection instruction setting module.
7. The system for processing the problems and hidden dangers in the constructional engineering projects as recited in claim 6, further comprising a problem query module for acquiring the search keywords, receiving an input command for starting a search space button, comparing and identifying the acquired search keywords with the information in the history database, and obtaining and displaying a target identification result.
8. The system of claim 6, wherein the selection command setting module is a pop-up command selection box, and the corresponding command selection box comprises a verbal notification, a work contact list, a supervision engineer notification list, an engineering pause list, an engineering rework list, and a supervision project report.
9. The system for processing the problems and hidden dangers in the constructional engineering projects as recited in claim 6, wherein the problem list module is preset with functions of detailed information, deletion, query and the like corresponding to the problem information.
10. An intelligent terminal, characterized by comprising a memory and a processor, wherein the memory stores a computer program which can be loaded by the processor and execute the method for processing the problems and hidden dangers of the construction project according to any one of the claims 1 to 8.
CN202010821981.1A 2020-08-15 2020-08-15 Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal Pending CN111985801A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010821981.1A CN111985801A (en) 2020-08-15 2020-08-15 Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010821981.1A CN111985801A (en) 2020-08-15 2020-08-15 Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal

Publications (1)

Publication Number Publication Date
CN111985801A true CN111985801A (en) 2020-11-24

Family

ID=73434056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010821981.1A Pending CN111985801A (en) 2020-08-15 2020-08-15 Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal

Country Status (1)

Country Link
CN (1) CN111985801A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113627874A (en) * 2021-07-29 2021-11-09 福州交通信息投资运营有限公司 Engineering construction comprehensive management method and terminal

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108549988A (en) * 2018-04-17 2018-09-18 万翼科技有限公司 The treating method and apparatus of problem
CN109583771A (en) * 2018-12-04 2019-04-05 北京诺士诚国际工程项目管理有限公司 A kind of engineering supervisor method and device
CN109697547A (en) * 2017-10-24 2019-04-30 上海嘉实(集团)有限公司 The management method and management system of safe mass inspection

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109697547A (en) * 2017-10-24 2019-04-30 上海嘉实(集团)有限公司 The management method and management system of safe mass inspection
CN108549988A (en) * 2018-04-17 2018-09-18 万翼科技有限公司 The treating method and apparatus of problem
CN109583771A (en) * 2018-12-04 2019-04-05 北京诺士诚国际工程项目管理有限公司 A kind of engineering supervisor method and device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113627874A (en) * 2021-07-29 2021-11-09 福州交通信息投资运营有限公司 Engineering construction comprehensive management method and terminal

Similar Documents

Publication Publication Date Title
US8589257B2 (en) Method, system and apparatus for managing inventory
CN111985893A (en) Building engineering project material entry auditing method, intelligent terminal and storage medium
CN109697326B (en) Road disease processing method, device, computer equipment and storage medium
CN110706800A (en) Automatic management method and device for equipment maintenance, computer equipment and storage medium
CN112596476A (en) Formula switching method, equipment and system
CN110751298A (en) Equipment operation and maintenance system
CN114298343A (en) Management method and device for equipment inspection process, electronic equipment and storage medium
CN111985801A (en) Method and system for processing problems and hidden dangers of construction engineering project and intelligent terminal
CN115545676A (en) Method, system, equipment and medium for inspecting electric power assets
US11727351B2 (en) Systems and methods for automated information collection and processing
CN115760009B (en) Engineering progress management method, device, equipment and storage medium
CN117077976A (en) Workshop production management method, device and storage medium
CN115630902A (en) Warehousing management system based on digital twin technology
CN111144774B (en) Fixed asset management method and device, storage medium and computer equipment
CN113269499A (en) Warehouse management system and method
JP6540061B2 (en) INFORMATION PROCESSING APPARATUS, INFORMATION PROCESSING SYSTEM, INFORMATION PROCESSING METHOD, AND INFORMATION PROCESSING PROGRAM
CN112132300A (en) Transformer substation maintenance method, device and system
CN116923950A (en) Product in-box warehouse-in scheduling method, system and medium
CN110658778B (en) Online track scale unmanned metering system and method based on industrial Internet
CN112116295B (en) Three-dimensional warehouse inventory method, equipment and system
CN113177760B (en) Method, device and system for material object storage processing
CN114490785B (en) Multi-satellite model information detection method, device, equipment and storage medium
US20230315927A1 (en) Management system, management method, and management storage medium
CN116596246A (en) Flexible logistics system
CN110084514A (en) A kind of process automatic push method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination