CN111946352A - Deformation control method for mining roadway - Google Patents

Deformation control method for mining roadway Download PDF

Info

Publication number
CN111946352A
CN111946352A CN202010714153.8A CN202010714153A CN111946352A CN 111946352 A CN111946352 A CN 111946352A CN 202010714153 A CN202010714153 A CN 202010714153A CN 111946352 A CN111946352 A CN 111946352A
Authority
CN
China
Prior art keywords
blasting
roadway
working face
mining
lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010714153.8A
Other languages
Chinese (zh)
Other versions
CN111946352B (en
Inventor
杨仁树
李永亮
陈程
朱晔
方士正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN202010714153.8A priority Critical patent/CN111946352B/en
Publication of CN111946352A publication Critical patent/CN111946352A/en
Application granted granted Critical
Publication of CN111946352B publication Critical patent/CN111946352B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • F42D1/08Tamping methods; Methods for loading boreholes with explosives; Apparatus therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Abstract

The embodiment of the invention discloses a deformation control method for a mining roadway, relates to the technical field of coal mining, and can effectively control the deformation of the mining roadway. The method comprises the following steps: determining the blasting direction and the blasting depth of the directional blasting according to the engineering geological conditions of the transportation lane and the auxiliary transportation lane and the lane trend; the auxiliary conveying lane is provided with a second working face; the auxiliary conveying lane and the conveying lane are arranged at intervals and extend in parallel; and performing directional blasting on the top of the roadway of the haulage roadway at a first preset distance away from the mining front of the first working face according to the blasting direction and the blasting depth so as to break and connect the top rock stratum between the first working face and the second working face. The invention can be used in the field of coal mining.

Description

Deformation control method for mining roadway
Technical Field
The invention relates to the technical field of coal mining, in particular to a deformation control method for a mining roadway.
Background
With the increase of coal mining depth in China, the stress environment of surrounding rock of the roadway deteriorates, and the number of large-deformation roadways is gradually increased. At present, due to the shortage of mining continuation, the mining roadways of most mining areas adopt double-roadway tunneling, namely, the mining roadways of adjacent working faces are simultaneously excavated, and the formed main structure can comprise an upper working face transportation roadway, an auxiliary transportation roadway of the working face and a section coal pillar between the two working faces. The working face auxiliary conveying lane is influenced by mining operation of the adjacent working face conveying lane, so the working face auxiliary conveying lane is also called a mining lane.
The auxiliary transportation roadway is a typical deep mining roadway, not only bears stress concentration generated by deep self excavation, but also further superposes deep mining stress fields caused by mining of the previous working face, increases surrounding rock stress of the auxiliary transportation roadway, obviously increases deformation and increases supporting difficulty. For example, for a roadway with a deep part affected by mining, the supporting pressure of the roadway can be 2-5 times of the stress of the original rock, and the stress of the surrounding rock is larger. As shown in fig. 1, the overburden structure between two working faces is greatly asymmetric because the last working face is mined out, so that the mining roadway has remarkable large non-uniform deformation and strong bottom heave. At present, common supports such as anchor rods and anchor cables cannot effectively control the problems.
Disclosure of Invention
In view of this, the embodiment of the present invention provides a deformation control method for a mining roadway, which can effectively control deformation of the mining roadway.
The embodiment of the invention also provides a deformation control method of the mining roadway, which comprises the following steps: determining the blasting direction and the blasting depth of the directional blasting according to the engineering geological conditions of the transportation lane and the auxiliary transportation lane and the lane trend; the auxiliary conveying lane is provided with a second working face; the auxiliary conveying lane and the conveying lane are arranged at intervals and extend in parallel; and performing directional blasting on the top of the roadway of the haulage roadway at a first preset distance away from the mining front of the first working face according to the blasting direction and the blasting depth so as to break and connect the top rock stratum between the first working face and the second working face.
Optionally, before performing directional blasting on the top of the haulage roadway at a first preset distance from the mining front of the first working face according to the blasting direction and the blasting depth, the method further includes: and performing loosening blasting on the bottom of the auxiliary conveying roadway at a second preset distance from the mining front of the first working face, wherein the second preset distance is greater than the first preset distance.
Optionally, the method further includes: respectively determining the spacing between a plurality of directional blasting sites and the spacing between a plurality of loosening blasting sites according to the rock lithology of the transportation lane and the auxiliary transportation lane; loading explosives into each of the directional blasting sites and each of the loose blasting sites; and blasting each directional blasting site and each loose blasting site in sequence in the process that the first working face moves forward along with the excavation work.
Optionally, the second preset distance is 80-100 meters.
Optionally, the first preset distance is 50-80 meters.
Optionally, the method further includes: determining surrounding rock stress and deformation degree of the auxiliary conveying roadway according to mining conditions of the first working face and the second working face; and arranging a plurality of supporting devices in the surrounding rock of the auxiliary conveying roadway according to the stress and the deformation degree of the surrounding rock of the auxiliary conveying roadway.
Optionally, the haulage roadway and the auxiliary haulage roadway are separated by a section coal pillar; at least one part of the supporting device is arranged in the section coal pillar, and the supporting device in the section coal pillar is of an internal hollow structure; the method further comprises the following steps: and grouting and reinforcing the interior of the section coal pillar through the hollow structure.
Optionally, the support device comprises a bolt and/or an anchor cable.
According to the deformation control method of the mining roadway provided by the embodiment of the invention, a first working face is arranged in the transportation roadway; a second working face is arranged in the auxiliary conveying roadway; the auxiliary transportation lane and the transportation lane are arranged at intervals and extend in parallel; the roof of the haulage roadway is directionally blasted at a first predetermined distance from the front of mining at the first face to break the roof strata between the first face and the second face. Like this, when mining first working face in the haulage roadway, even the coal seam in the first working face is excavated, the stratum above the first working face falls, because the top stratum between first working face and the second working face has been broken the schizolysis by directional blasting and link to each other, thereby can not give the stratum above the second working face with the high stress conduction, also can not extrude the stratum above the second working face and produce huge lateral stress, thereby effectively avoided the country rock of supplementary haulage roadway to produce too big deformation and pucking because of the influence of mining.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic view of a prior art mining roadway deformed configuration;
fig. 2 is a flowchart of a deformation control method for a mining roadway according to an embodiment of the present invention;
fig. 3 is a schematic plan view of a roadway structure formed by the deformation control method for a mining roadway according to an embodiment of the present invention;
figure 4 is a schematic view of a distribution of support means in a mining roadway in an embodiment of the invention;
fig. 5 is a front view of blast hole arrangement in the deformation control method for a mining roadway according to the embodiment of the present invention;
fig. 6 is a schematic charging diagram of blast holes in the deformation control method for a mining roadway according to the embodiment of the invention;
fig. 7 is another schematic charging diagram of blast holes in the deformation control method for a mining roadway according to the embodiment of the invention.
Detailed Description
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
It should be understood that the described embodiments are only some embodiments of the invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 2, an embodiment of the present invention further provides a deformation control method for a mining roadway, including:
s51, determining the blasting direction and the blasting depth of the directional blasting according to the engineering geological conditions of the haulage roadway and the auxiliary haulage roadway and the roadway trend; the auxiliary conveying lane is provided with a second working face; the auxiliary conveying lane and the conveying lane are arranged at intervals and extend in parallel;
and S52, performing directional blasting on the top of the roadway of the haulage roadway at a first preset distance away from the mining front of the first working face according to the blasting direction and the blasting depth, so that the top rock stratum between the first working face and the second working face is broken and connected.
According to the deformation control method for the mining roadway, provided by the embodiment of the invention, the blasting direction and the blasting depth of directional blasting can be determined according to the engineering geological conditions of the transportation roadway and the auxiliary transportation roadway and the trend of the roadway, and the top of the roadway of the transportation roadway is subjected to directional blasting at a first preset distance away from the mining front of the first working face according to the blasting direction and the blasting depth, so that the top rock stratum between the first working face and the second working face is broken and connected. Like this, when mining first working face 11 in haulage way 1, even the colliery in first working face 11 is dug out, the stratum above the first working face falls, because the top stratum between first working face 11 and the second working face 21 has been broken the schizolysis by directional blasting and has been connected to can not give the stratum above the second working face 21 the high stress conduction, also can not extrude the stratum above the second working face 21 and produce huge lateral stress, thereby effectively avoided the country rock of auxiliary haulage way 2 to produce too big deformation and pucking because of the influence of mining.
In the method for controlling deformation of a mining roadway according to the embodiment of the present invention, the mining roadway refers to a roadway affected by mining, and specifically, the mining roadway refers to the auxiliary transport roadway 2 in the embodiment of the present invention.
For example, a roadway structure formed according to the deformation control method for a mining roadway shown in fig. 2 may be as shown in fig. 3. As shown in fig. 3, the tunnel structure may include:
the transportation system comprises a transportation lane 1, wherein a first working surface 11 is arranged in the transportation lane 1;
the auxiliary conveying lane 2 is provided with a second working surface 21; the auxiliary transportation lane 2 and the transportation lane 1 are arranged at intervals and extend in parallel;
the roof 13 of the haulage roadway is directionally blasted at a first predetermined distance from the mining front of the first face 11 to fracture the roof strata between the first face 11 and the second face 21.
Like this, when mining first working face 11 in haulage way 1, even the coal seam in first working face 11 is dug out, the stratum above the first working face falls, because the top stratum between first working face 11 and second working face 21 has been broken the schizolysis by the directional blasting and has been connected to can not give the stratum above second working face 21 high stress conduction, also can not extrude the stratum above second working face 21 and produce huge lateral stress, thereby effectively avoided the country rock of auxiliary haulage way 2 to produce too big deformation and pucking because of the influence of mining.
In particular implementation, in order to control the effect of the mining operation of the first face 11 on the secondary roadway 2 of the second face 21, and also in order not to affect the mining operation of the first face 11, the inventors have found in their research that directional blasting may be performed at a suitable distance before the mining operation of the first face 11. For example, in one embodiment of the present invention, directional blasting of the top strata of the haulage roadway 1 may be performed a first predetermined distance L1, e.g., 50-80 meters, ahead of the first face 11 to achieve better deformation control without affecting the mining operation of the first face 11.
In further studies, the inventor finds that as the first working face 11 is emptied and the rock formation at the top of the first working face 11 is gradually pressed downwards, the rock formation at the bottom of the haulage roadway 1 is subjected to huge stresses, and the stresses can be transmitted to the bottom of the auxiliary haulage roadway 2 of the second working face 21 through the rock formation at the bottom, so that the bottom of the auxiliary haulage roadway 2 is caused to bulge, and strong bottom heave is generated.
In order to solve the above problem, referring again to fig. 3, in an embodiment of the present invention, before the step S52, before directionally blasting the roadway roof of the haulage roadway at a first preset distance from the first face mining front according to the blasting direction and the blasting depth, the method further includes:
and performing loosening blasting on the bottom of the auxiliary conveying roadway at a second preset distance L2 from the mining front of the first working face, wherein the second preset distance is greater than the first preset distance L1, and for example, the second preset distance can be 80-100 meters. In this way, since the bottom of the auxiliary conveyor lane 2 is loosely blasted, even if the first face 11 generates a lateral compressive stress, the stress is absorbed by the crushed stones generated after the loose blasting of the bottom of the auxiliary conveyor lane 2, and the stress is not accumulated to generate a bottom heave.
It should be noted that as the first face mining operation progresses, the first face will gradually move forward. Referring to fig. 3, the arrow indicates a direction in which the coal mine in the first working face 11 is excavated, i.e., a direction in which the first working face 11 advances. With the forward movement of the first working face 11, it is also possible to perform more directional blasting and loosening blasting on the haulage drift 1 and the auxiliary haulage drift 2. The directional blasting site and the loose blasting site can be respectively shown as a string of small circles in the transportation lane 1 and a string of small circles in the auxiliary transportation lane 2 in fig. 3.
In a specific implementation, in an embodiment of the present invention, the method for controlling deformation of a mining roadway according to an embodiment of the present invention may further include:
respectively determining the spacing between a plurality of directional blasting sites and the spacing between a plurality of loosening blasting sites according to the rock lithology of the transportation lane and the auxiliary transportation lane;
loading explosives into each of the directional blasting sites and each of the loose blasting sites;
and blasting each directional blasting site and each loose blasting site in sequence in the process that the first working face moves forward along with the excavation work.
Further, in one embodiment of the invention, in order to control the deformation of the secondary roadway, in addition to trying to eliminate the effect of the mining operation of the adjacent first face 11, the supporting means of the secondary roadway may be modified.
Optionally, in an embodiment of the present invention, the method may further include:
determining surrounding rock stress and deformation degree of the auxiliary conveying roadway according to mining conditions of the first working face and the second working face;
and arranging a plurality of supporting devices in the surrounding rock of the auxiliary conveying roadway according to the stress and the deformation degree of the surrounding rock of the auxiliary conveying roadway.
For example, for the position where the deformation of the surrounding rock is large, the dense supporting device 3 can be arranged, and for the position where the deformation of the surrounding rock is small, the sparse supporting device 3 can be arranged, so that the surrounding rock of the auxiliary transportation roadway 2 can be effectively supported, and the severe deformation of the surrounding rock is prevented.
Alternatively, as shown in fig. 4, in one embodiment of the invention, the haulage roadway 1 and the secondary haulage roadway 2 are separated by section pillars 4; at least one part of the supporting device 3 is arranged in the section coal pillar, and the supporting device in the section coal pillar is of an internal hollow structure; the method further comprises the following steps: and grouting and reinforcing the interior of the section coal pillar through the hollow structure. Because both sides of the coal pillar of the section 4 are roadways, the roadway can bear larger stress, and the supporting device with a hollow structure is used for grouting into the coal pillar of the section 4, so that cracks in the coal pillar of the section 4 can be closed, and the coal pillar of the section 4 has higher strength.
Optionally, the supporting device may include various devices such as anchor rods and/or anchor cables, which are beneficial to enhance the supporting strength of the surrounding rock.
The following describes a method for controlling deformation of a mining roadway according to an embodiment of the present invention in detail by using a specific embodiment.
For example, in an embodiment of the present invention, the secondary transportation lane may be differentially supported, and then high stress may be transferred in the modes of bottom plate loosening blasting, advanced directional pre-splitting of the working face, and the like. The directional blasting and the loosening blasting may be performed as follows:
step one, determining the blasting direction and the blasting depth of directional blasting according to the engineering geological conditions of a transportation lane and an auxiliary transportation lane and the lane trend;
secondly, according to the blasting direction and the blasting depth, arranging a pre-splitting blast hole for loosening blasting in an auxiliary transportation lane 150 meters away from the mining front of the first working face, and arranging a pre-splitting blast hole for directional blasting in a transportation lane 100 meters away from the mining front of the first working face; as shown in fig. 5, the depths d1, d2 and the angles α, β of the two types of pre-split blastholes may be different according to geological conditions. A schematic of the charge configuration for directional blasting may be as shown in figure 6. A schematic of the charging of a loose blast may be as shown in figure 7.
Referring to fig. 6 and 7, the specific implementation of charging and sealing may include the following steps:
the reference numbers in fig. 6 and 7 are defined as follows: 71-booster, 72-lancing explosive charge, 73-detonator, 74-sealing stemming, 75-rock formation, 76-detonating cord, 81-booster, 82-explosive, 83-sealing stemming, 84-detonator, 85-rock formation, 86-detonating cord
1) Probe hole
In the step, a hole detecting pipe and a hole detecting head are needed, the hole detecting head needs to be the same as the blasting cartridge in size, the hole detecting head needs to be manufactured in advance, one set of hole detecting pipe and one set of hole detecting head need to be used for standby. In the exploratory hole, the gun rods are connected one by one, penetrate into the bottom of the hole to detect the depth of the gun hole, a specially-assigned person is required to record, and then the final charge and the length of the hole sealing are determined by comparing the recorded depth with the designed size of the drilled hole.
2) Manufacture of anti-skid devices
And (3) processing a small penetrating hole at the position of 100mm at the end of each section of the blasting cartridge, inserting an anti-skid device into the small penetrating hole, and adjusting the number of the anti-skid devices according to the number of the blasting cartridges.
3) Production of primary explosive
A section of blasting cartridge is taken, two holes with the size of about 4mm are drilled in the rear of the bottom end of the cartridge, the two holes are required to penetrate through a blasting bus, the bus respectively penetrates through each small hole, a wire head with the size of 100mm is reserved at the front end of the bus and is knotted to prevent the bus from sliding out of each small hole, the wire head of the bus is respectively connected with two coal mine allowable electric detonators, the joint of the wire heads is tightly wrapped by waterproof insulating tapes, the resistance of the coal mine allowable electric detonators is measured before connection to determine the conduction condition of the coal mine allowable electric detonators, the connected coal mine allowable electric detonators are placed into explosive, and the rear cover of the blasting cartridge is covered.
4) Sequential charge
A roll of blasting cartridges is pushed into the hole by the aid of the gun rods, the number of the blasting cartridges and the number of the gun rods which are fed into the hole at each time need to be recorded, and the blasting cartridges and the length of the exploratory hole are compared to determine whether the fed blasting cartridges are fed to a specified position. At most, no more than three blasting cartridges are pushed at one time, otherwise, the blasting cartridges are pushed by workers immovably and are easy to jam.
5) Plugging yellow mud
The hole sealing is carried out by adopting a compressed air medicine loading device and an antistatic flame-retardant plastic pipe to seal holes by compressed air and spraying mud. The hole sealing material is slightly tide loess, and the used yellow mud is sieved in advance. The wind pressure is 0.7MPa, and when the wind pressure is insufficient (less than 0.35MPa), hole sealing cannot be performed. And the rest blast holes are all plugged by yellow mud, the hole plugging pipe is slowly drawn out along with the continuous increase of the hole plugging distance in the plugging process, and a section of bus is exposed at the hole opening after the stemming is sealed, so that the blast holes can be conveniently connected and blasted.
If the exploratory hole is not smooth and is blocked, the high-pressure water pipe is firstly put down, rock slag in the hole is removed by high-pressure water, and then accumulated water in the hole is removed by compressed air. And (5) carrying out hole probing again, and then charging. If the through holes are not successfully tried for several times, collapse can occur inside the drilled hole, and the drilled hole is reasonably treated according to the actual situation on site.
It should be noted that the explosive types in the embodiments of the present invention are not limited, but need to meet the requirements related to "coal mine safety regulations", and may be gunpowder, gas, liquid, and the like. The various explosives can be assembled in different ways to form directional blasting or non-directional blasting.
Step three, performing loosening blasting in an auxiliary conveying roadway 100 meters away from the mining front of the first working face; bottom loose blasting-normal cartridge (non-directional blasting). The bottom plate loosens, explodes and transfers stress and static load.
And fourthly, performing directional blasting in the transportation lane 50 meters away from the mining front of the first working face. Directional presplitting blasting of the top plate-cutting of the cartridge. The directional pre-splitting of the top plate reduces the dynamic load and simultaneously reduces the bearing pressure.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. The term "comprising", without further limitation, means that the element so defined is not excluded from the group consisting of additional identical elements in the process, method, article, or apparatus that comprises the element.
All the embodiments in the present specification are described in a related manner, and the same and similar parts among the embodiments may be referred to each other, and each embodiment focuses on the differences from the other embodiments.
In particular, as for the apparatus embodiment, since it is substantially similar to the method embodiment, the description is relatively simple, and for the relevant points, reference may be made to the partial description of the method embodiment.
For convenience of description, the above devices are described separately in terms of functional division into various units/modules. Of course, the functionality of the units/modules may be implemented in one or more software and/or hardware implementations of the invention.
The above description is only for the specific embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope of the present invention are included in the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.

Claims (8)

1. A deformation control method for a mining roadway is characterized by comprising the following steps:
determining the blasting direction and the blasting depth of the directional blasting according to the engineering geological conditions of the transportation lane and the auxiliary transportation lane and the lane trend; the auxiliary conveying lane is provided with a second working face; the auxiliary conveying lane and the conveying lane are arranged at intervals and extend in parallel;
and performing directional blasting on the top of the roadway of the haulage roadway at a first preset distance away from the mining front of the first working face according to the blasting direction and the blasting depth so as to break and connect the top rock stratum between the first working face and the second working face.
2. The method of claim 1, wherein prior to directionally blasting the roof of the haulage roadway at a first predetermined distance from the first face front in mining according to the blast direction and the blast depth, the method further comprises:
and performing loosening blasting on the bottom of the auxiliary conveying roadway at a second preset distance from the mining front of the first working face, wherein the second preset distance is greater than the first preset distance.
3. The method of claim 2, further comprising:
respectively determining the spacing between a plurality of directional blasting sites and the spacing between a plurality of loosening blasting sites according to the rock lithology of the transportation lane and the auxiliary transportation lane;
loading explosives into each of the directional blasting sites and each of the loose blasting sites;
and blasting each directional blasting site and each loose blasting site in sequence in the process that the first working face moves forward along with the excavation work.
4. The method of claim 2, wherein the second predetermined distance is 80-100 meters.
5. The method of claim 1, wherein the first predetermined distance is 50-80 meters.
6. The method of claim 1, further comprising:
determining surrounding rock stress and deformation degree of the auxiliary conveying roadway according to mining conditions of the first working face and the second working face;
and arranging a plurality of supporting devices in the surrounding rock of the auxiliary conveying roadway according to the stress and the deformation degree of the surrounding rock of the auxiliary conveying roadway.
7. The method of claim 6, wherein the haulage roadway and the secondary haulage roadway are separated by section pillars; at least one part of the supporting device is arranged in the section coal pillar, and the supporting device in the section coal pillar is of an internal hollow structure; the method further comprises the following steps:
and grouting and reinforcing the interior of the section coal pillar through the hollow structure.
8. A method according to claim 6 or 7, characterised in that the support means comprise anchor rods and/or anchor lines.
CN202010714153.8A 2020-07-22 2020-07-22 Deformation control method for mining roadway Active CN111946352B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010714153.8A CN111946352B (en) 2020-07-22 2020-07-22 Deformation control method for mining roadway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010714153.8A CN111946352B (en) 2020-07-22 2020-07-22 Deformation control method for mining roadway

Publications (2)

Publication Number Publication Date
CN111946352A true CN111946352A (en) 2020-11-17
CN111946352B CN111946352B (en) 2023-03-24

Family

ID=73340824

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010714153.8A Active CN111946352B (en) 2020-07-22 2020-07-22 Deformation control method for mining roadway

Country Status (1)

Country Link
CN (1) CN111946352B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509395A (en) * 2009-03-16 2009-08-19 太原理工大学 The roof caving and tunnel protecting method
CN102778182A (en) * 2012-07-26 2012-11-14 山东科技大学 Beside-roadway escribing pressure relief method of roadway driving along gob of small coal pillar influenced by dynamic pressure
CN109209495A (en) * 2018-09-13 2019-01-15 天地科技股份有限公司 The stopping of a kind of fully-mechanized mining working cutting top unloading pressure protection method on the face of adopting
CN109763821A (en) * 2019-03-15 2019-05-17 山西潞安矿业(集团)有限责任公司 A kind of compound shield lane method of dynamic pressure exploiting field main entry
CN110067558A (en) * 2019-04-16 2019-07-30 中国矿业大学 A kind of severe inclined thick coal seam stope drift active workings joint release prevention and treatment impulsion pressure method
CN110685689A (en) * 2019-10-30 2020-01-14 中国矿业大学 Large-deformation roadway pressure relief method under influence of mining stress

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509395A (en) * 2009-03-16 2009-08-19 太原理工大学 The roof caving and tunnel protecting method
CN102778182A (en) * 2012-07-26 2012-11-14 山东科技大学 Beside-roadway escribing pressure relief method of roadway driving along gob of small coal pillar influenced by dynamic pressure
CN109209495A (en) * 2018-09-13 2019-01-15 天地科技股份有限公司 The stopping of a kind of fully-mechanized mining working cutting top unloading pressure protection method on the face of adopting
CN109763821A (en) * 2019-03-15 2019-05-17 山西潞安矿业(集团)有限责任公司 A kind of compound shield lane method of dynamic pressure exploiting field main entry
CN110067558A (en) * 2019-04-16 2019-07-30 中国矿业大学 A kind of severe inclined thick coal seam stope drift active workings joint release prevention and treatment impulsion pressure method
CN110685689A (en) * 2019-10-30 2020-01-14 中国矿业大学 Large-deformation roadway pressure relief method under influence of mining stress

Also Published As

Publication number Publication date
CN111946352B (en) 2023-03-24

Similar Documents

Publication Publication Date Title
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN102536239B (en) Long-wall working face coal pillar-free mining method
US8820847B2 (en) Block caving method
CN111878080B (en) Method for equipment withdrawal and self-lane-forming of withdrawal channel of fully mechanized coal mining face of coal mine
WO2011103620A1 (en) A method of reducing subsidence or windblast impacts from longwall mining
CN108518222A (en) Paste body filling combination top plate presplitting second mining super high seam stops the method for adopting line coal column
CN112832768B (en) Roadway protection method based on small coal pillars
CN109826628B (en) Coal pillar-free mining method for pre-splitting and arching under hard roof condition
CN112610218B (en) Thick coal seam fully-mechanized top-tunneling top-cutting pressure relief automatic roadway forming method
CN112377193B (en) Deep well small coal pillar gob-side entry retaining method based on top breaking and pressure relief of lower key layer of top plate
CN112647945A (en) Hard roof cutting method for protective layer mining
CN113107490A (en) Roof cutting and pressure relief method for high-ground-stress hard roof of coal mine
CN112282806B (en) Thick coal seam forced mining roadway blasting pressure relief and long anchor rod cooperative roof control method
Li et al. Trial of small gateroad pillar in top coal caving longwall mining of large mining height
CN106247876A (en) High working face cuts greatly a blasting method for fully-mechanized mining working tight roof overhead caving
CN110030013B (en) Gob-side entry retaining method for three-seam periodic roof cutting self-entry side of transition support area
CN113153295A (en) Mining method for extremely thick hard coal
Yang et al. Application cumulative tensile explosions for roof cutting in Chinese underground coal mines
RU2323337C2 (en) Method for underground thick ore body mining
CN111022050B (en) Fully-closed blasting pressure relief and self-retained roadway method for grouting reconstruction of composite roof
CN112922598A (en) Method for reducing gob-side entry driving roof pressure through roof cutting and pressure relief
CN102733851B (en) Control method for water-containing collapse columns in mining affected areas of combined reconstructed mines
CN109025999B (en) One-field three-purpose top coal weakening method
CN111946352B (en) Deformation control method for mining roadway
CN112780276A (en) Fully-closed blasting pressure relief structure for grouting reconstruction of composite roof and self-retained roadway method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant