CN111851301A - a bridge erecting machine - Google Patents

a bridge erecting machine Download PDF

Info

Publication number
CN111851301A
CN111851301A CN202010656983.XA CN202010656983A CN111851301A CN 111851301 A CN111851301 A CN 111851301A CN 202010656983 A CN202010656983 A CN 202010656983A CN 111851301 A CN111851301 A CN 111851301A
Authority
CN
China
Prior art keywords
bridge
erecting machine
longitudinal main
cantilever
cantilever beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010656983.XA
Other languages
Chinese (zh)
Inventor
孙西濛
曹艳辉
马瑞
陈雅南
张建恪
李晓罡
徐晨光
侯巨伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Road and Bridge Co Ltd
Original Assignee
Beijing Municipal Road and Bridge Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Road and Bridge Co Ltd filed Critical Beijing Municipal Road and Bridge Co Ltd
Priority to CN202010656983.XA priority Critical patent/CN111851301A/en
Publication of CN111851301A publication Critical patent/CN111851301A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种架桥机,主要包括:纵向主梁、连接横梁、悬臂横梁、起重天车、行走小车、前支腿、后支腿、配重块。纵向主梁间采用连接横梁连接,纵向主梁上方安装有悬臂横梁,悬臂横梁上方铺设有滑轨,使得起重天车可以在悬臂横梁上方自由滑动,纵向主梁前端设置有前支腿,纵向主梁后端设置有后支腿。通过在纵向主梁上方设置悬臂横梁,可以实现桥侧提梁;悬臂横梁上安装有配重块,用以保障提梁作业时架桥机稳定性。本发明构造简明、机理明确、便于加工,能够有效提升拆梁和架梁效率。

Figure 202010656983

The invention discloses a bridge erecting machine, which mainly comprises: a longitudinal main beam, a connecting beam, a cantilever beam, a hoisting crane, a walking trolley, a front outrigger, a rear outrigger and a counterweight. The longitudinal main beams are connected by connecting beams, the cantilever beams are installed above the longitudinal main beams, and the slide rails are laid above the cantilever beams, so that the crane can slide freely above the cantilever beams. The rear end of the main beam is provided with a rear support leg. By setting the cantilever beam above the longitudinal main beam, the bridge side beam can be lifted; the cantilever beam is installed with a counterweight to ensure the stability of the bridge erection machine during the beam lifting operation. The invention has simple structure, clear mechanism, convenient processing, and can effectively improve the efficiency of beam dismantling and beam erection.

Figure 202010656983

Description

一种架桥机a bridge erecting machine

技术领域technical field

本发明属于架桥机设备技术领域,具体涉及一种新型架桥机。The invention belongs to the technical field of bridge erecting machine equipment, and particularly relates to a novel bridge erecting machine.

背景技术Background technique

随着国家经济实力的提升,车流量在逐年增长,行车荷载已经远超当年的设计荷载。同时车流量的急速增长也使得城市桥梁的通行能力愈发的捉襟见肘,城市桥梁已经越来越拥堵,城市桥梁的更新显得十分的重要和紧迫。主梁更换是桥梁提升改造的主要形式,目前急需更换的城市桥梁大部分集中在城市中心繁华地段,建筑物密集、道路繁忙,操作空间有限,同时长时间的中断交通对于城市交通压力重大,因此采用先进特殊的设备对桥梁改造快速施工来说意义重大。With the improvement of the country's economic strength, the traffic flow is increasing year by year, and the traffic load has far exceeded the design load of the year. At the same time, the rapid growth of traffic flow has also made the traffic capacity of urban bridges increasingly stretched, and urban bridges have become more and more congested. The renewal of urban bridges is very important and urgent. The replacement of the main beam is the main form of bridge upgrading and reconstruction. At present, most of the urban bridges in urgent need of replacement are concentrated in the prosperous areas of the city center. The buildings are dense, the roads are busy, and the operating space is limited. The use of advanced and special equipment is of great significance to the rapid construction of bridge reconstruction.

传统的架桥机设备为了施工标准化、结构通用性、整体稳定性等因素考虑,通常将架桥机设置成为纵向对称型的形式,在两纵向主梁间实现架梁和拆梁作业,操作方法一般是固定化的,施工操作过程也较为复杂,施工速度缓慢,无法满足在城区提升改造工程进行快速施工的要求。尤其是当梁侧有作业空间的大规模提升改造工程,工期会较长,传统的架桥机设备不够经济。针对特殊的施工环境,进行设备的改进可以使架桥机设备适用性更强。In order to consider factors such as construction standardization, structural versatility, and overall stability, the traditional bridge erecting machine equipment is usually set in a longitudinally symmetrical form, and the beam erection and dismantling operations are realized between the two longitudinal main beams. The operation method It is generally fixed, the construction operation process is also relatively complex, and the construction speed is slow, which cannot meet the requirements of rapid construction in urban upgrading and renovation projects. Especially when there is a large-scale upgrading and reconstruction project with working space on the beam side, the construction period will be longer, and the traditional bridge erecting machine equipment is not economical enough. According to the special construction environment, the improvement of the equipment can make the bridge erection equipment more applicable.

发明内容SUMMARY OF THE INVENTION

本发明主要是解决上述现有技术存在的问题,提供了一种新型稳定、可侧面提梁的架桥机。本发明主要适用于梁侧有作业空间的施工环境,与传统架桥机相比,本发明突出优势在于架桥机结构形式更加简单,在梁侧有作业空间的场景下施工更加方便快捷,悬臂横梁的悬臂长度通过在悬臂横梁下方设置滑动设备即可调整,同时根据施工环境需要调整配重块重量即可保证结构稳定性需要。The present invention mainly solves the problems existing in the above-mentioned prior art, and provides a new type of bridge erecting machine that is stable and can lift beams on the side. The invention is mainly suitable for the construction environment with working space on the beam side. Compared with the traditional bridge erecting machine, the outstanding advantage of the present invention is that the structure of the bridge erecting machine is simpler, the construction is more convenient and quicker in the scene where there is working space on the girder side, and the cantilever cantilever The cantilever length of the beam can be adjusted by setting a sliding device under the cantilever beam, and the weight of the counterweight can be adjusted according to the needs of the construction environment to ensure the structural stability.

为实现上述目的,本发明提供了一种新型架桥机构造,主要包括纵向主梁、连接横梁、悬臂横梁、起重天车、行走小车、前支腿、后支腿和配重块。所述纵向主梁之间通过连接横梁机械连接在一起;所述纵向主梁上方安装有悬臂横梁,所述悬臂横梁的上方铺设有滑轨,所述起重天车能够沿滑轨在悬臂横梁上方自由滑动;所述纵向主梁的前端设置有前支腿,所述纵向主梁的后端设置有后支腿,悬臂横梁上安装有配重块,所述纵向主梁的下方安装有行走小车。In order to achieve the above purpose, the present invention provides a new type of bridge erecting machine structure, which mainly includes a longitudinal main beam, a connecting beam, a cantilever beam, a crane, a traveling trolley, a front outrigger, a rear outrigger and a counterweight. The longitudinal main beams are mechanically connected together by connecting beams; a cantilever beam is installed above the longitudinal main beam, a sliding rail is laid above the cantilever beam, and the crane can move on the cantilever beam along the sliding rail. The upper part slides freely; the front end of the longitudinal main beam is provided with a front leg, the rear end of the longitudinal main beam is provided with a rear leg, a counterweight is installed on the cantilever beam, and a walking beam is installed below the longitudinal main beam trolley.

作为优选,所述悬臂横梁伸出纵向主梁外侧,悬臂横梁伸出长度根据设计要求确定,所述悬臂横梁能够实现桥侧外提梁作业。Preferably, the cantilever beam extends out of the longitudinal main beam, and the extension length of the cantilever beam is determined according to the design requirements, and the cantilever beam can realize the operation of lifting the beam outside the bridge side.

作为优选,所述配重块采用机械连接安装在悬臂横梁一侧,用于平衡架桥机整体稳定性,所述配重块的重量和安装位置根据设计要求确定,提梁作业时架桥机需进行抗倾覆验算。Preferably, the counterweight is installed on one side of the cantilever beam by mechanical connection to balance the overall stability of the bridge erecting machine. The weight and installation position of the counterweight are determined according to design requirements. Perform an anti-overturning check.

作为优选,所述行走小车安装在纵向主梁的中部下方,能够实现架桥机在作业桥面上行走。Preferably, the traveling trolley is installed under the middle of the longitudinal main beam, so that the bridge erecting machine can travel on the working bridge deck.

作为优选,所述架桥机适用于15~30m小跨径预制箱梁、T梁、空心板梁提梁作业。Preferably, the bridge erecting machine is suitable for the lifting operation of prefabricated box girder, T girder and hollow slab girder with a small span of 15-30 m.

作为优选,纵向主梁由不同长度的箱型梁组成,各箱型梁之间采用高强螺栓进行连接。Preferably, the longitudinal main beam is composed of box beams of different lengths, and high-strength bolts are used to connect the box beams.

作为优选,所述的悬臂横梁采用三角桁架结构,三角桁架结构由型钢焊接组成,三角桁架结构能够在纵向主梁上前后行走;每个悬臂横梁上方设置一台起重天车,起重天车能够在悬臂横梁上左右移动,起重天车上设有卷扬机、滚筒和钢丝绳。Preferably, the cantilever beam adopts a triangular truss structure, the triangular truss structure is composed of welded section steel, and the triangular truss structure can walk forward and backward on the longitudinal main beam; a crane crane is installed above each cantilever beam, and the crane crane It can move left and right on the cantilever beam, and the hoisting crane is equipped with a hoist, a roller and a steel wire rope.

作为优选,所述前支腿和后支腿均为伸缩式结构,确保架桥机在前后移动和过孔的过程中能够进行上下伸缩,同时前支腿上还设计有行走系统。Preferably, the front outriggers and the rear outriggers are both telescopic structures to ensure that the bridge erecting machine can be extended up and down in the process of moving back and forth and passing through holes, and a walking system is also designed on the front outriggers.

与现有技术相比较,本发明通过设置悬臂式横梁,实现了桥侧提梁作业,在特殊的工况下施工更加高效;安装有机械连接的配重块,可按照设计要求进行配重,可保障架桥机整体稳定性;构造结构形式简单,受力机理明确,便于加工和安装。Compared with the prior art, the present invention realizes the lifting operation of the bridge side beam by setting the cantilever beam, and the construction is more efficient under special working conditions; Ensure the overall stability of the bridge erecting machine; the structure is simple in form, the force mechanism is clear, and it is easy to process and install.

附图说明Description of drawings

图1为一种新型架桥机的正截面图;Fig. 1 is a front sectional view of a new type of bridge erecting machine;

图2为一种新型架桥机的侧视图;Fig. 2 is a side view of a new type of bridge erecting machine;

图3为一种新型架桥机的俯视图;Fig. 3 is a top view of a new type of bridge erecting machine;

图4为纵向主梁横截面图;Figure 4 is a cross-sectional view of a longitudinal main beam;

图5为纵向主梁节段示意图;Figure 5 is a schematic diagram of a longitudinal main beam segment;

图6为悬臂横梁示意图;6 is a schematic diagram of a cantilever beam;

图7为一种新型架桥机拆梁过程示意图;Fig. 7 is a kind of schematic diagram of the dismantling process of the new bridge erecting machine;

图8为一种新型架桥机过孔过程示意图。Fig. 8 is a schematic diagram of a new type of bridge erecting machine via process.

图中:1—纵向主梁;2—连接横梁;3—悬臂横梁;4—行走小车;5—滑轮;6—起重天车;7—配重块;8—前支腿;9—后支腿。In the figure: 1—longitudinal main beam; 2—connecting beam; 3—cantilever beam; 4—travel trolley; 5—pulley; 6—hoisting crane; 7—counterweight block; 8—front outrigger; 9—rear outriggers.

具体实施方式Detailed ways

下面通过实施例,并结合附图,对本发明的技术方案作进一步的具体说明,本发明的特点将更加清楚。需要说明的是,附图均采用非常简化的形式且均使用非精确的比例,仅用以方便、明晰地辅助说明本发明目的。The technical solutions of the present invention will be further described in detail below through the embodiments and in conjunction with the accompanying drawings, and the characteristics of the present invention will be made clearer. It should be noted that the accompanying drawings are all in a very simplified form and in imprecise scales, and are only used to assist in explaining the purpose of the present invention conveniently and clearly.

实施例:一种新型架桥机构造,如图1-图3所示,包括纵向主梁1、连接横梁2、悬臂横梁3、起重天车4、行走小车5、滑轮6、配重块7、前支腿8、后支腿9。所述纵向主梁1与连接横梁2机械连接,所述纵向主梁1上方安装有悬臂横梁3,所述悬臂横梁3上方铺设有滑轨,所述起重天车6可以在悬臂横梁3上方自由滑动,所述纵向主梁1前端设置有前支腿8,所述纵向主梁1后端设置有后支腿9,悬臂横梁3上安装有配重块4,所述纵向主梁1下方安装有行走小车5。Example: A new type of bridge erecting machine structure, as shown in Figures 1-3, includes a longitudinal main beam 1, a connecting beam 2, a cantilever beam 3, a crane 4, a walking trolley 5, a pulley 6, and a counterweight block 7. Front outrigger 8, rear outrigger 9. The longitudinal main beam 1 is mechanically connected with the connecting beam 2, a cantilever beam 3 is installed above the longitudinal main beam 1, a slide rail is laid above the cantilever beam 3, and the crane 6 can be above the cantilever beam 3 Free sliding, the front end of the longitudinal main beam 1 is provided with a front leg 8, the rear end of the longitudinal main beam 1 is provided with a rear leg 9, and a counterweight 4 is installed on the cantilever beam 3, below the longitudinal main beam 1 A walking trolley 5 is installed.

所述悬臂横梁3伸出纵向主梁1外侧,其长度根据设计要求确定,所述悬臂横梁3能够实现桥侧外提梁作业。所述配重块7采用机械连接安装在悬臂横梁3一侧,用于平衡架桥机整体稳定性,所述配重块7重量和安装位置根据设计要求确定,提梁作业时架桥机需进行抗倾覆验算。所述行走小车5安装在纵向主梁中部下方,能够实现架桥机在作业桥面上行走。所述一种新型架桥机适用于15~30m小跨径预制箱梁、T梁、空心板梁提梁作业。The cantilever beam 3 protrudes from the outside of the longitudinal main beam 1, and its length is determined according to the design requirements, and the cantilever beam 3 can realize the operation of lifting the beam outside the bridge side. The counterweight 7 is installed on one side of the cantilever beam 3 by mechanical connection, and is used to balance the overall stability of the bridge erecting machine. The weight and installation position of the counterweight 7 are determined according to the design requirements. Anti-overturning check. The walking trolley 5 is installed under the middle of the longitudinal main beam, so that the bridge erecting machine can walk on the working bridge deck. The new type of bridge erecting machine is suitable for beam lifting operations of 15-30m small-span prefabricated box girder, T girder and hollow slab girder.

如图4-图5所示,纵向主梁1由不同长度的箱型梁组成,各节段采用高强螺栓连接。As shown in Figures 4-5, the longitudinal main beam 1 is composed of box beams of different lengths, and each segment is connected by high-strength bolts.

如图6所示,所述的悬臂横梁3采用三角桁架,三角桁架由型钢焊接组成,三角桁架可在纵向主梁上前后行走,每个悬臂横梁3上方设置一台起重天车6,起重天车6可在悬臂横梁3上左右移动,起重天车6上设有卷扬机、滚筒、钢丝绳,用于起重作业。As shown in FIG. 6 , the cantilever beam 3 adopts a triangular truss, and the triangular truss is composed of welded steel sections. The triangular truss can travel forward and backward on the longitudinal main beam. A crane 6 is set above each cantilever beam 3 to lift The crane 6 can move left and right on the cantilever beam 3, and the crane 6 is provided with a winch, a roller, and a wire rope for lifting operations.

此外,所述前支腿8和后支腿9均设计为伸缩式,确保架桥机在前后移动和过孔的过程中可以上下伸缩,同时前支腿8还设计有行走系统,用于架桥机过孔。In addition, the front outriggers 8 and the rear outriggers 9 are designed to be telescopic to ensure that the bridge erecting machine can be retracted up and down during the process of moving back and forth and passing through holes. At the same time, the front outriggers 8 are also designed with a walking system for the Bridge machine vias.

为解决上述问题,本发明还提供了一种新型架桥机提梁方法和过孔方法,所述方法包括采用本架桥机设备,还包括如下步骤,如图7-图8所示。In order to solve the above problems, the present invention also provides a new method for lifting beams and a method for passing a hole.

架桥机提梁方法描述如下:The lifting method of the bridge erection machine is described as follows:

S1:两台起重天车6分别停靠在悬臂横梁3设定位置,挂钩于待拆梁板的端部,提起两片梁板至设定高度,设定位置和设定高度按照作业要求确定;S1: The two cranes 6 are respectively parked at the set position of the cantilever beam 3, hooked to the end of the beam plate to be dismantled, and the two beam plates are lifted to the set height. The set position and set height are determined according to the operation requirements. ;

S2:起重天车6沿悬臂横梁3横移设定距离,使待拆梁板移出桥跨位置,设定距离根据作业要求确定;S2: The hoisting crane 6 traverses the set distance along the cantilever beam 3, so that the beam plate to be removed moves out of the bridge span position, and the set distance is determined according to the operation requirements;

S3:起重天车6下放待拆梁板。S3: The crane 6 lowers the beam plate to be dismantled.

架桥机过孔方法描述如下:The via method of the bridge erection machine is described as follows:

S1:架桥机的2组悬臂横梁3均行走并停靠与纵向主梁1的前端。S1: The two sets of cantilever beams 3 of the bridge erecting machine all travel and stop with the front end of the longitudinal main beam 1.

S2:后支腿9回缩一个节段;S2: The rear outrigger 9 is retracted by one segment;

S3:架桥机通过前支腿8下的行走系统在未拆除的梁板上向前行走至下一段拆除梁板的位置上。S3: The bridge erecting machine walks forward on the unremoved beam plate through the walking system under the front outrigger 8 to the position where the beam plate is removed in the next section.

S4:后支腿8伸出,支撑于盖梁上。S4: The rear outriggers 8 are extended and supported on the cover beam.

S5:主横梁向后移动至待拆除梁板的上方,准备下一孔梁板的拆除。S5: Move the main beam backward to the top of the beam plate to be removed, and prepare for the removal of the next hole beam plate.

综上所述,在本实施例提供的一种新型架桥机构造中,通过设置悬臂式横梁,实现了桥侧提梁作业,扩大了架桥机适用范围;安装有机械连接的配重块,可按照设计要求进行配重,可保障架桥机整体稳定性;构造结构形式简单,受力机理明确,便于加工和安装;还能够降低成本,提高施工效率。To sum up, in the structure of a new type of bridge erecting machine provided in this embodiment, by setting the cantilever beam, the side beam lifting operation of the bridge is realized, and the applicable scope of the bridge erecting machine is expanded; The counterweight can be carried out according to the design requirements, which can ensure the overall stability of the bridge erecting machine; the structural form is simple, the force mechanism is clear, and it is easy to process and install; it can also reduce costs and improve construction efficiency.

上述描述仅是对本发明较佳实施例的描述,并非对本发明范围的任何限定,本发明领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求书的保护范围。The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes and modifications made by those of ordinary skill in the field of the present invention based on the above disclosure all belong to the protection scope of the claims.

Claims (10)

1.一种架桥机,其特征在于:包括纵向主梁、连接横梁、悬臂横梁、起重天车、行走小车、前支腿、后支腿和配重块;纵向主梁之间通过连接横梁机械连接在一起;所述纵向主梁上方安装有悬臂横梁;悬臂横梁的上方铺设有滑轨,起重天车能够沿滑轨在悬臂横梁上方自由滑动;纵向主梁的前端设置有前支腿,所述纵向主梁的后端设置有后支腿,悬臂横梁上安装有配重块,纵向主梁的下方安装有行走小车。1. a bridge erecting machine is characterized in that: comprise longitudinal main beam, connecting beam, cantilever beam, crane crane, traveling trolley, front outrigger, rear outrigger and counterweight; The beams are mechanically connected together; a cantilever beam is installed above the longitudinal main beam; a sliding rail is laid above the cantilever beam, and the crane can slide freely along the sliding rail above the cantilever beam; the front end of the longitudinal main beam is provided with a front support The rear end of the longitudinal main beam is provided with a rear support leg, a counterweight is installed on the cantilever beam, and a walking trolley is installed under the longitudinal main beam. 2.根据权利要求1所述的一种架桥机,其特征在于:所述悬臂横梁伸出纵向主梁外侧,悬臂横梁伸出长度根据设计要求确定,所述悬臂横梁能够实现桥侧外提梁作业。2. A bridge erecting machine according to claim 1, characterized in that: the cantilever beam extends out of the longitudinal main beam, and the extension length of the cantilever beam is determined according to design requirements, and the cantilever beam can realize the lifting beam on the side of the bridge Operation. 3.根据权利要求1所述的一种架桥机,其特征在于:所述配重块采用机械连接安装在悬臂横梁一侧,用于平衡架桥机整体稳定性,所述配重块的重量和安装位置根据设计要求确定,提梁作业时架桥机需进行抗倾覆验算。3. A bridge erecting machine according to claim 1, characterized in that: the counterweight is installed on one side of the cantilever beam by mechanical connection to balance the overall stability of the bridge erecting machine. The weight and installation position are determined according to the design requirements, and the bridge erection machine needs to be checked for anti-overturning during the beam lifting operation. 4.根据权利要求1所述的一种架桥机,其特征在于:所述行走小车安装在纵向主梁的中部下方,实现架桥机在作业桥面上行走。4 . The bridge erecting machine according to claim 1 , wherein the traveling trolley is installed under the middle of the longitudinal main girder, so that the bridge erecting machine can walk on the working bridge deck. 5 . 5.根据权利要求1所述的一种架桥机,其特征在于:所述架桥机适用于15~30m小跨径预制箱梁、T梁、空心板梁提梁作业。5 . The bridge erecting machine according to claim 1 , wherein the bridge erecting machine is suitable for the lifting operation of prefabricated box girder, T girder and hollow slab girder with a small span of 15-30 m. 6 . 6.根据权利要求1所述的一种架桥机,其特征在于:纵向主梁由不同长度的箱型梁组成,各箱型梁之间采用高强螺栓进行连接。6 . The bridge erecting machine according to claim 1 , wherein the longitudinal main beam is composed of box-shaped beams of different lengths, and high-strength bolts are used to connect the box-shaped beams. 7 . 7.根据权利要求1所述的一种架桥机,其特征在于:所述的悬臂横梁采用三角桁架结构,三角桁架结构由型钢焊接组成,三角桁架结构能够在纵向主梁上前后行走;每个悬臂横梁上方设置一台起重天车,起重天车能够在悬臂横梁上左右移动,起重天车上设有卷扬机、滚筒和钢丝绳。7. A bridge erecting machine according to claim 1, characterized in that: the cantilever beam adopts a triangular truss structure, the triangular truss structure is formed by welding section steel, and the triangular truss structure can travel back and forth on the longitudinal main beam; A hoisting crane is arranged above each cantilever beam, the hoisting crane can move left and right on the cantilever beam, and the hoisting crane is provided with a hoist, a roller and a wire rope. 8.根据权利要求1所述的一种架桥机,其特征在于:所述前支腿和后支腿均为伸缩式结构,确保架桥机在前后移动和过孔的过程中能够进行上下伸缩,同时前支腿上还设计有行走系统。8. A bridge erecting machine according to claim 1, characterized in that: the front outriggers and the rear outriggers are both telescopic structures to ensure that the bridge erecting machine can move up and down during the process of moving back and forth and passing through holes. Telescopic, and a walking system is also designed on the front outriggers. 9.根据权利要求1所述的一种架桥机,其特征在于:该架桥机的提梁方法实施如下,9. A kind of bridge erection machine according to claim 1, is characterized in that: the beam lifting method of this bridge erection machine is implemented as follows, S1:两台起重天车分别停靠在悬臂横梁设定位置,挂钩于待拆梁板的端部,提起两片梁板至设定高度,设定位置和设定高度按照作业要求确定;S1: The two cranes are respectively parked at the set position of the cantilever beam, hooked to the end of the beam plate to be dismantled, and the two beam plates are lifted to the set height. The set position and set height are determined according to the operation requirements; S2:起重天车沿悬臂横梁横移设定距离,使待拆梁板移出桥跨位置,设定距离根据作业要求确定;S2: The hoisting crane traverses the set distance along the cantilever beam, so that the beam plate to be removed moves out of the bridge span position, and the set distance is determined according to the operation requirements; S3:起重天车下放待拆梁板。S3: The beam plate to be dismantled is placed under the crane. 10.根据权利要求1所述的一种架桥机,其特征在于:该架桥机的过孔方法如下:10. A kind of bridge erection machine according to claim 1, is characterized in that: the through hole method of this bridge erection machine is as follows: S1:架桥机的2组悬臂横梁均行走并停靠与纵向主梁的前端;S1: The 2 sets of cantilever beams of the bridge erecting machine all walk and stop with the front end of the longitudinal main beam; S2:后支腿回缩一个节段;S2: The rear outrigger is retracted by one segment; S3:架桥机通过前支腿下的行走系统在未拆除的梁板上向前行走至下一段拆除梁板的位置上;S3: The bridge erecting machine walks forward on the unremoved girder slab through the walking system under the front outrigger to the position where the girder slab is removed in the next section; S4:后支腿伸出,支撑于盖梁上;S4: The rear outrigger is extended and supported on the cover beam; S5:主横梁向后移动至待拆除梁板的上方,准备下一孔梁板的拆除。S5: Move the main beam backward to the top of the beam plate to be removed, and prepare for the removal of the next hole beam plate.
CN202010656983.XA 2020-07-09 2020-07-09 a bridge erecting machine Pending CN111851301A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010656983.XA CN111851301A (en) 2020-07-09 2020-07-09 a bridge erecting machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010656983.XA CN111851301A (en) 2020-07-09 2020-07-09 a bridge erecting machine

Publications (1)

Publication Number Publication Date
CN111851301A true CN111851301A (en) 2020-10-30

Family

ID=73152834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010656983.XA Pending CN111851301A (en) 2020-07-09 2020-07-09 a bridge erecting machine

Country Status (1)

Country Link
CN (1) CN111851301A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114635362A (en) * 2022-03-23 2022-06-17 保利长大工程有限公司 Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge
CN116201033A (en) * 2023-03-27 2023-06-02 安徽省公路桥梁工程有限公司 Large cantilever flange steel box girder pre-splicing and hoisting construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09256323A (en) * 1996-03-22 1997-09-30 Mitsui Miike Mach Co Ltd Bridge girder erection device
CN201809075U (en) * 2010-07-31 2011-04-27 卫华集团有限公司 Bridge crane for loading and unloading of continental river dock
CN104894979A (en) * 2015-06-02 2015-09-09 中铁二十三局集团有限公司 Side-fed bridge girder erection machine and girder erection method thereof
CN109750605A (en) * 2019-03-05 2019-05-14 冯丛 A kind of compound main beam of civil engineering bridge construction
CN208884365U (en) * 2018-08-24 2019-05-21 浙江中建路桥设备有限公司 It is a kind of can side bale handle Bridge Erector
CN212688727U (en) * 2020-07-09 2021-03-12 北京市政路桥股份有限公司 Bridge erecting machine

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09256323A (en) * 1996-03-22 1997-09-30 Mitsui Miike Mach Co Ltd Bridge girder erection device
CN201809075U (en) * 2010-07-31 2011-04-27 卫华集团有限公司 Bridge crane for loading and unloading of continental river dock
CN104894979A (en) * 2015-06-02 2015-09-09 中铁二十三局集团有限公司 Side-fed bridge girder erection machine and girder erection method thereof
CN208884365U (en) * 2018-08-24 2019-05-21 浙江中建路桥设备有限公司 It is a kind of can side bale handle Bridge Erector
CN109750605A (en) * 2019-03-05 2019-05-14 冯丛 A kind of compound main beam of civil engineering bridge construction
CN212688727U (en) * 2020-07-09 2021-03-12 北京市政路桥股份有限公司 Bridge erecting machine

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
管会生: "《土木工程机械》", 31 January 2018, 西南交通大学出版社, pages: 216 - 219 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114635362A (en) * 2022-03-23 2022-06-17 保利长大工程有限公司 Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge
CN116201033A (en) * 2023-03-27 2023-06-02 安徽省公路桥梁工程有限公司 Large cantilever flange steel box girder pre-splicing and hoisting construction method

Similar Documents

Publication Publication Date Title
CN101851898B (en) Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN110130229A (en) It a kind of several juxtaposed double cantilever erections machines and its sets a roof beam in place and passing method
CN106400701B (en) A kind of list girder low level balanced cantilever assembly Bridge Erector
CN109024291A (en) A kind of integration Bridge Erector and its working method
CN204343173U (en) A kind of Segmental assembling bridge-erecting machine
CN106917360A (en) Lift leg formula frame plate machine and its frame plate method
CN101250854A (en) Bridge-building machine for long-span double-track box girder stringing method
CN110258352A (en) Construction method of steel-concrete composite bridge with two spans
CN105970833A (en) Precast segment span-by-span assembling bridge fabrication machine
CN110820602A (en) A single-segment box girder bridge erecting machine and its operation method
CN116043715A (en) Construction method for construction of prefabricated segmental beams under complex working conditions
CN111776950A (en) A cantilever telescopic hoisting frame gantry device
CN106012824A (en) Movable bridge anti-collision guardrail construction operation trolley
CN110468743B (en) A mobile hanger and construction method for the renovation of old bridge pier caps
CN111851301A (en) a bridge erecting machine
CN110656570A (en) A telescopic pedestrian bridge, construction device and construction method
CN212052371U (en) Hanging basket device for variable width concrete box girder suspension casting construction
CN113120771A (en) Double-side synchronous hoisting equipment suitable for rear cantilever arm of composite-section beam bridge and construction method
CN209338005U (en) A kind of mobile height leg gantry crane of erecting beam construction
CN111119072A (en) A method of dislocation construction of high pier bridges in mountainous areas
CN115125856A (en) A multifunctional bridge building machine
CN112030777B (en) A down-type mobile formwork support bracket spanning transfer construction method
CN210341680U (en) Door type corrugated steel web plate installation and overhanging type hanging bracket structure
CN111483925B (en) Asynchronous basket of hanging of wave form steel web bridge
CN205804194U (en) Prefabricated subsection splicing span by span bridge fabrication machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20201030