CN114635362A - Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge - Google Patents

Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge Download PDF

Info

Publication number
CN114635362A
CN114635362A CN202210293341.7A CN202210293341A CN114635362A CN 114635362 A CN114635362 A CN 114635362A CN 202210293341 A CN202210293341 A CN 202210293341A CN 114635362 A CN114635362 A CN 114635362A
Authority
CN
China
Prior art keywords
steel pipe
side steel
bridge
lifting station
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210293341.7A
Other languages
Chinese (zh)
Inventor
乔连波
宋玲敏
严平
张天波
刘宇波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changda Construction Engineering Guangdong Co ltd
Guangdong Changxin Municipal Engineering Co ltd
Poly Changda Engineering Co Ltd
Original Assignee
Changda Construction Engineering Guangdong Co ltd
Guangdong Changxin Municipal Engineering Co ltd
Poly Changda Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changda Construction Engineering Guangdong Co ltd, Guangdong Changxin Municipal Engineering Co ltd, Poly Changda Engineering Co Ltd filed Critical Changda Construction Engineering Guangdong Co ltd
Priority to CN202210293341.7A priority Critical patent/CN114635362A/en
Publication of CN114635362A publication Critical patent/CN114635362A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a cantilever type beam lifting station for erecting a beam slab, which is used for hoisting and erecting the beam slab on a bridge and comprises a supporting component and an overhead traveling crane component, wherein the supporting component comprises a first side steel pipe upright and a second side steel pipe upright, the overhead traveling crane component comprises a self-propelled overhead traveling crane beam and a winch moving along the self-propelled overhead traveling crane beam, and the upper parts of the first side steel pipe upright and the second side steel pipe upright are fixedly connected with the self-propelled overhead traveling crane beam. Adopt supporting component, the cooperation of overhead traveling crane subassembly is hoisted, I-shaped beam bridge limit hoist and mount has been realized, it is more high-efficient to make hoist and mount, it is more swift, it is more convenient, need not to carry out high stand construction outside the bridge limit line, the risk of high altitude construction has been reduced, only need prefabricated decking and below fortune roof beam passageway can install, reduce bridge sideline outside place restriction influence, the construction degree of difficulty has been reduced, be favorable to the equipment multiple spot to put in, improve hanging beam efficiency of construction, the lifting beam station simple structure, the installation and demolish the degree of difficulty and significantly reduce, the turnover efficiency is high.

Description

用于梁板架设的悬臂式提梁站及其吊装上桥方法Cantilever beam lifting station for beam plate erection and method for hoisting on bridge

技术领域technical field

本发明涉及桥梁施工领域,尤其涉及一种用于梁板架设的悬臂式提梁站及其吊装上桥方法。The invention relates to the field of bridge construction, in particular to a cantilever beam-lifting station for beam-slab erection and a method for hoisting and hoisting a bridge.

背景技术Background technique

目前,高架桥的上部结构形式采用预应力混凝土工字梁,桥面连续,主要采用架桥机整体起吊施工。At present, the upper structure of the viaduct adopts the prestressed concrete I-beam, the bridge deck is continuous, and the bridge erection machine is mainly used for the overall lifting construction.

但是,传统的提梁站设计为高低腿门式起重机存在以下缺陷:However, the traditional beam lifting station designed as a high and low leg gantry crane has the following disadvantages:

1、钢管立柱较高,高空作业存在一定的安全隐患、且支架的结构安全性能要求较高,吊装不便;1. The steel pipe column is relatively high, there are certain safety hazards in high-altitude operation, and the structural safety performance requirements of the bracket are relatively high, making it inconvenient to hoist;

2、安装场地要求比较高,提梁站需桥外一平坦开阔的场地浇筑扩大基础,且地基承载力需满足方案需求;2. The installation site requirements are relatively high. The beam-lifting station needs to pour a flat and open site outside the bridge to expand the foundation, and the bearing capacity of the foundation needs to meet the requirements of the scheme;

3、传统高低腿提梁站安装过程还涉及填土夯实、螺旋管桩、扩大基础施工等,安装准备工作多且耗时长;3. The installation process of the traditional high and low leg beam lifting station also involves soil compaction, spiral pipe piles, expansion of foundation construction, etc., and the installation preparation work is much and time-consuming;

4、提梁站的拆除不方便;4. It is inconvenient to dismantle the beam lifting station;

5、不适合当前桥梁施工安全简便的需求。5. It is not suitable for the safety and convenience of the current bridge construction.

发明内容SUMMARY OF THE INVENTION

为了克服现有技术的不足,本发明的目的之一在于提供一种用于梁板架设的悬臂式提梁站及其吊装上桥方法,其能解决吊装不便的问题。In order to overcome the deficiencies of the prior art, one of the objectives of the present invention is to provide a cantilevered beam lifting station for beam plate erection and a method for hoisting the bridge, which can solve the problem of inconvenient hoisting.

本发明的目的之一采用如下技术方案实现:One of the objects of the present invention adopts the following technical scheme to realize:

一种用于梁板架设的悬臂式提梁站,用于在桥上吊装架设梁板,包括支撑组件、天车组件,所述支撑组件包括第一侧钢管立柱、与第一侧钢管立柱相对的第二侧钢管立柱,所述第一侧钢管立柱位于桥中,所述第一侧钢管立柱处设置有侧部辅助支撑,所述侧部辅助支撑包括辅助斜杆、若干根辅助横杆,所述辅助斜杆的两端分别与所述天车组件的下部和所述第一侧钢管立柱的下部铰接,所述辅助横杆的两端分别与所述第一侧钢管立柱和所述辅助斜杆铰接,所述辅助横杆处于水平状态;所述天车组件包括自行式天车梁、沿自行式天车梁移动的卷扬机,所述第一侧钢管立柱、第二侧钢管立柱的上部与所述自行式天车梁固定连接。A cantilever beam-lifting station for beam-slab erection, used for hoisting and erecting beam-slabs on a bridge, includes a support assembly and a crane assembly, the support assembly includes a first side steel pipe column, a steel pipe column opposite to the first side steel column. The second side steel pipe column, the first side steel pipe column is located in the bridge, the first side steel pipe column is provided with a side auxiliary support, and the side auxiliary support includes auxiliary inclined rods and several auxiliary cross rods, so The two ends of the auxiliary inclined rod are respectively hinged with the lower part of the crane assembly and the lower part of the first side steel pipe column, and the two ends of the auxiliary cross rod are respectively connected with the first side steel pipe column and the auxiliary inclined steel column. The rod is hinged, and the auxiliary cross rod is in a horizontal state; the crane assembly includes a self-propelled crane beam and a hoist that moves along the self-propelled crane beam. The self-propelled crane beam is fixedly connected.

进一步地,所述第一侧钢管立柱的延伸方向与所述第二侧钢管立柱的延伸方向平行。Further, the extension direction of the first side steel pipe column is parallel to the extension direction of the second side steel pipe column.

进一步地,所述第一侧钢管立柱的延伸方向与所述自行式天车梁的延伸方向垂直。Further, the extension direction of the first side steel pipe column is perpendicular to the extension direction of the self-propelled crane beam.

进一步地,所述用于梁板架设的悬臂式提梁站包括第一提梁站、第二提梁站,所述第一提梁站、第二提梁站分布于待吊装的梁板的两侧;所述用于梁板架设的悬臂式提梁站还包括设置于桥上的工字梁运输车。Further, the cantilevered beam lifting station for beam plate erection includes a first beam lifting station and a second beam lifting station, and the first beam lifting station and the second beam lifting station are distributed on both sides of the beam plate to be hoisted; the The cantilever beam lifting station used for beam plate erection also includes an I-beam transport vehicle arranged on the bridge.

进一步地,所述辅助斜杆、辅助横杆、第一侧钢管立柱呈直角三角形分布。Further, the auxiliary inclined rods, the auxiliary cross rods, and the first side steel pipe uprights are distributed in a right-angled triangle.

进一步地,所述辅助斜杆与所述第一侧钢管立柱呈15°-20°。Further, the auxiliary inclined rod is at 15°-20° with the first side steel pipe upright.

进一步地,所述辅助斜杆与所述第一侧钢管立柱呈18°。Further, the auxiliary inclined rod and the first side steel pipe column are at 18°.

进一步地,所述辅助斜杆、辅助横杆、自行式天车梁呈直角三角形分布。Further, the auxiliary inclined rods, auxiliary cross rods, and self-propelled crane beams are distributed in a right-angled triangle.

一种用于梁板架设的悬臂式提梁站的吊装上桥方法,包括以下步骤:A method for hoisting a bridge on a cantilevered beam-lifting station for beam-slab erection, comprising the following steps:

准备步骤:运梁车将工字梁运至桥梁边线2-3m处,运梁车停放在外悬臂下方桥面等待装货;Preparation steps: The beam transporter transports the I-beam to the sideline of the bridge 2-3m, and the beam transporter is parked on the bridge deck under the outer cantilever to wait for loading;

检查步骤:试运行提梁站起重天车,检查天车刹车、钢丝绳磨损及锚固锁紧情况、各安全开关情况,确认无异常后方可开始起吊;Inspection steps: Trial operation of the lifting crane, check the brake of the crane, the wear of the wire rope, the anchoring and locking conditions, and the conditions of each safety switch. After confirming that there is no abnormality, the lifting can be started;

下吊步骤:将两台起重天车同时往悬臂外开,当两台卷扬机起吊中心接近工字梁吊点时减速运行,以缓慢的速度靠近,直到与工字梁吊点重合后下方吊钩;Lifting steps: open the two cranes to the cantilever at the same time, when the lifting center of the two hoists is close to the I-beam lifting point, slow down and approach at a slow speed until it overlaps with the I-beam lifting point. hook;

吊装步骤:挂好绳索后,起重机缓慢将工字梁吊上桥面,并沿桥内侧横移将工字梁放置在桥面运梁车上。Hoisting steps: After hanging the rope, the crane slowly hoisted the I-beam to the bridge deck, and moved the I-beam laterally along the inside of the bridge to place the I-beam on the bridge deck girder truck.

进一步地,在所述吊装步骤中,挂好绳索后,先缓慢将工字梁试吊10mm且静止2分钟,观察起重机运行情况,起重机运行无异常方可缓慢将工字梁吊上桥面。Further, in the hoisting step, after hanging the rope, first slowly lift the I-beam for 10mm and stand still for 2 minutes, observe the operation of the crane, and then slowly hoist the I-beam to the bridge deck only if the crane runs abnormally.

相比现有技术,本发明的有益效果在于:Compared with the prior art, the beneficial effects of the present invention are:

所述辅助斜杆的两端分别与所述天车组件的下部和所述第一侧钢管立柱的下部铰接,所述辅助横杆的两端分别与所述第一侧钢管立柱和所述辅助斜杆铰接,所述辅助横杆处于水平状态;所述天车组件包括自行式天车梁、沿自行式天车梁移动的卷扬机,所述第一侧钢管立柱、第二侧钢管立柱的上部与所述自行式天车梁固定连接。采用支撑组件、天车组件的配合进行吊装,实现了工字梁桥边吊装,使吊装更高效、更快捷、更方便,无需在桥梁边线外进行高的立柱施工,减少了高空作业的风险,只需有预制桥面板及下方运梁通道即可安装,减少桥梁边线外侧场地制约影响,降低了施工难度,有利于设备多点投放、提高吊梁施工效率,提梁站结构简单,安装及拆除难度大大减少,周转效率高。Both ends of the auxiliary inclined rod are hinged with the lower part of the crane assembly and the lower part of the first side steel pipe column, respectively, and the two ends of the auxiliary cross rod are respectively connected with the first side steel pipe column and the auxiliary steel pipe column. The inclined rod is hinged, and the auxiliary cross rod is in a horizontal state; the crane assembly includes a self-propelled crane beam, a hoist moving along the self-propelled crane beam, the upper part of the first side steel pipe column and the second side steel pipe column It is fixedly connected with the self-propelled crane beam. The supporting components and the crane components are used for hoisting, which realizes the hoisting of the I-beam bridge side, making the hoisting more efficient, faster and more convenient, without the need for high column construction outside the bridge side line, reducing the risk of high-altitude operations. It can be installed only with a prefabricated bridge deck and a beam transport channel below, which reduces the influence of site constraints on the outside of the bridge side line, reduces the construction difficulty, is conducive to the multi-point placement of equipment, and improves the construction efficiency of the lifting beam. The beam lifting station has a simple structure and is difficult to install and remove. Greatly reduced, high turnover efficiency.

上述说明仅是本发明技术方案的概述,为了能够更清楚了解本发明的技术手段,而可依照说明书的内容予以实施,并且为了让本发明的上述和其他目的、特征和优点能够更明显易懂,以下特举较佳实施例,并配合附图,详细说明如下。The above description is only an overview of the technical solution of the present invention, in order to be able to understand the technical means of the present invention more clearly, it can be implemented according to the content of the description, and in order to make the above and other objects, features and advantages of the present invention more obvious and easy to understand , the following specific preferred embodiments, and in conjunction with the accompanying drawings, are described in detail as follows.

附图说明Description of drawings

图1为本发明用于梁板架设的悬臂式提梁站中一较佳实施例的示意图;1 is a schematic diagram of a preferred embodiment of the cantilever beam lifting station used for beam plate erection according to the present invention;

图2为图1所示用于梁板架设的悬臂式提梁站的侧视图;Fig. 2 is the side view of the cantilevered beam lifting station for beam plate erection shown in Fig. 1;

图3为图1所示用于梁板架设的悬臂式提梁站的俯视图;Fig. 3 is the top view of the cantilevered beam lifting station for beam plate erection shown in Fig. 1;

图4为用于梁板架设的悬臂式提梁站吊装上桥方法的流程图。FIG. 4 is a flow chart of a method for hoisting a bridge on a cantilevered beam-lifting station for beam-slab erection.

图中:100、第一提梁站;200、第二提梁站;10、支撑组件;11、第一侧钢管立柱;12、第二侧钢管立柱;13、侧部辅助支撑;131、辅助斜杆;132、辅助横杆;20、天车组件;21、自行式天车梁;22、卷扬机;30、工字梁运输车;300、梁板。In the figure: 100, the first beam lifting station; 200, the second beam lifting station; 10, the support assembly; 11, the first side steel pipe column; 12, the second side steel pipe column; 13, the side auxiliary support; 131, the auxiliary inclined rod ; 132, auxiliary cross bar; 20, crane assembly; 21, self-propelled crane beam; 22, winch; 30, I-beam transport vehicle; 300, beam plate.

具体实施方式Detailed ways

下面,结合附图以及具体实施方式,对本发明做进一步描述,需要说明的是,在不相冲突的前提下,以下描述的各实施例之间或各技术特征之间可以任意组合形成新的实施例。Hereinafter, the present invention will be further described with reference to the accompanying drawings and specific embodiments. It should be noted that, on the premise of no conflict, the embodiments or technical features described below can be arbitrarily combined to form new embodiments. .

需要说明的是,当组件被称为“固定于”另一个组件,它可以直接在另一个组件上或者也可以存在居中的组件。当一个组件被认为是“连接”另一个组件,它可以是直接连接到另一个组件或者可能同时存在居中组件。当一个组件被认为是“设置于”另一个组件,它可以是直接设置在另一个组件上或者可能同时存在居中组件。本文所使用的术语“垂直的”、“水平的”、“左”、“右”以及类似的表述只是为了说明的目的。It should be noted that when a component is referred to as being "fixed to" another component, it can be directly on the other component or there may also be a centered component. When a component is considered to be "connected" to another component, it may be directly connected to the other component or there may be a co-existence of an intervening component. When a component is considered to be "set on" another component, it may be directly set on the other component or there may be a co-existing centered component. The terms "vertical," "horizontal," "left," "right," and similar expressions are used herein for illustrative purposes only.

除非另有定义,本文所使用的所有的技术和科学术语与属于本发明的技术领域的技术人员通常理解的含义相同。本文中在本发明的说明书中所使用的术语只是为了描述具体的实施例的目的,不是旨在于限制本发明。本文所使用的术语“及/或”包括一个或多个相关的所列项目的任意的和所有的组合。Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terms used herein in the description of the present invention are for the purpose of describing specific embodiments only, and are not intended to limit the present invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.

请参阅图1-4,一种用于梁板架设的悬臂式提梁站,用于在桥上吊装架设梁板300,包括支撑组件10、天车组件20,所述支撑组件10包括第一侧钢管立柱11、与第一侧钢管立柱11相对的第二侧钢管立柱12,所述第一侧钢管立柱11位于桥中,所述第一侧钢管立柱11处设置有侧部辅助支撑13,所述侧部辅助支撑13包括辅助斜杆131、若干根辅助横杆132,所述辅助斜杆131的两端分别与所述天车组件20的下部和所述第一侧钢管立柱11的下部铰接,所述辅助横杆132的两端分别与所述第一侧钢管立柱11和所述辅助斜杆131铰接,所述辅助横杆132处于水平状态;所述天车组件20包括自行式天车梁21、沿自行式天车梁21移动的卷扬机22,所述第一侧钢管立柱11、第二侧钢管立柱12的上部与所述自行式天车梁21固定连接。采用支撑组件10、天车组件20的配合进行吊装,实现了工字梁桥边吊装,使吊装更高效、更快捷、更方便,无需在桥梁边线外进行高的立柱施工,减少了高空作业的风险,只需有预制桥面板及下方运梁通道即可安装,减少桥梁边线外侧场地制约影响,降低了施工难度,有利于设备多点投放、提高吊梁施工效率,提梁站结构简单,安装及拆除难度大大减少,周转效率高。Please refer to FIGS. 1-4 , a cantilever beam lifting station for beam plate erection, used for hoisting and erecting beam plate 300 on a bridge, includes a support assembly 10 and a crane assembly 20, the support assembly 10 includes a first side The steel pipe column 11 and the second side steel pipe column 12 opposite to the first side steel pipe column 11, the first side steel pipe column 11 is located in the bridge, and the first side steel pipe column 11 is provided with a side auxiliary support 13, so The side auxiliary support 13 includes auxiliary inclined rods 131 and several auxiliary cross rods 132. Both ends of the auxiliary inclined rods 131 are hinged with the lower part of the crane assembly 20 and the lower part of the first side steel pipe column 11 respectively. , the two ends of the auxiliary cross bar 132 are hinged with the first side steel pipe column 11 and the auxiliary inclined bar 131 respectively, and the auxiliary cross bar 132 is in a horizontal state; the crane assembly 20 includes a self-propelled crane The beam 21 , the hoist 22 moving along the self-propelled crane beam 21 , the upper parts of the first side steel pipe column 11 and the second side steel pipe column 12 are fixedly connected with the self-propelled crane beam 21 . The supporting assembly 10 and the crane assembly 20 are used for hoisting, realizing the hoisting of the I-beam bridge side, making the hoisting more efficient, faster and more convenient, without the need for high column construction outside the bridge side line, reducing the need for high-altitude operations. Risk, it can be installed only with prefabricated bridge deck and the lower beam transport channel, which reduces the influence of site constraints on the outside of the bridge side line, reduces the construction difficulty, is conducive to the multi-point placement of equipment, and improves the construction efficiency of the lifting beam. The beam lifting station has a simple structure and is easy to install. The difficulty of dismantling is greatly reduced, and the turnover efficiency is high.

具体的,提梁站钢管立柱采用Ф426×10mm钢管桩,全部Ф426×10mm钢管桩坐落于桥面板上,使用型钢基础进行支撑,管桩横桥向间距为10.05m,顺桥向间距为2.35m,提梁站处相邻跨桥面板立管前全部完成,提梁站两侧钢管支撑架纵向每排桩顶面采用双拼I30a工字钢做为垫梁,垫梁上再布置承重桁架,垫梁必须与桁架及管桩顶焊牢。该提梁站为固定形式,为了适应本项目25-40m梁段的吊装,25m、30m、40m梁段吊装时采用专门的吊架配合提梁站进行吊装。起吊天车主要由自行式天车梁和卷扬机组成,桥面吊装净空高度≥7m,单台提梁站设计起重能力为60T。Specifically, Ф426×10mm steel pipe piles are used for the steel pipe columns of the beam-lifting station. All Ф426×10mm steel pipe piles are located on the bridge deck and are supported by steel foundations. m, before the risers of the adjacent bridge decks at the beam-lifting station are completed, the top surface of each row of longitudinal piles of the steel pipe support frame on both sides of the beam-lifting station is made of double-joint I30a I-beam as the cushion beam, and the load-bearing truss is arranged on the cushion beam. The beam must be welded firmly to the truss and the top of the pipe pile. The beam lifting station is in a fixed form. In order to adapt to the hoisting of the 25-40m beam section of this project, the 25m, 30m and 40m beam sections are hoisted with special hangers in conjunction with the beam lifting station. The hoisting crane is mainly composed of self-propelled crane girder and hoist, the bridge deck hoisting clearance height is ≥7m, and the designed lifting capacity of a single girder station is 60T.

优选的,所述第一侧钢管立柱11的延伸方向与所述第二侧钢管立柱12的延伸方向平行。所述第一侧钢管立柱11的延伸方向与所述自行式天车梁21的延伸方向垂直。Preferably, the extending direction of the first side steel pipe column 11 is parallel to the extending direction of the second side steel pipe column 12 . The extension direction of the first side steel pipe column 11 is perpendicular to the extension direction of the self-propelled crane beam 21 .

优选的,所述用于梁板架设的悬臂式提梁站包括第一提梁站100、第二提梁站200,所述第一提梁站100、第二提梁站200分布于待吊装的梁板300的两侧;所述用于梁板架设的悬臂式提梁站还包括设置于桥上的工字梁运输车30。整个装置结构新颖,设计巧妙,适用性强,便于推广。Preferably, the cantilevered beam lifting station for beam plate erection includes a first beam lifting station 100 and a second beam lifting station 200, and the first beam lifting station 100 and the second beam lifting station 200 are distributed on the beam plate 300 to be hoisted. Both sides; the cantilevered beam lifting station for beam plate erection also includes an I-beam transport vehicle 30 arranged on the bridge. The whole device has novel structure, ingenious design, strong applicability and easy promotion.

优选的,所述辅助斜杆131、辅助横杆132、第一侧钢管立柱11呈直角三角形分布。所述辅助斜杆131与所述第一侧钢管立柱11呈15°-20°。具体的,所述辅助斜杆131与所述第一侧钢管立柱11呈18°。所述辅助斜杆131、辅助横杆132、自行式天车梁21呈直角三角形分布。Preferably, the auxiliary inclined rods 131, the auxiliary cross rods 132, and the first side steel pipe uprights 11 are distributed in a right-angled triangle. The auxiliary inclined rod 131 and the first side steel pipe column 11 are at 15°-20°. Specifically, the auxiliary inclined rod 131 and the first side steel pipe column 11 are at 18°. The auxiliary inclined rods 131, the auxiliary cross rods 132, and the self-propelled crane beam 21 are distributed in a right-angled triangle.

一种用于梁板架设的悬臂式提梁站的吊装上桥方法,包括以下步骤:A method for hoisting a bridge on a cantilevered beam-lifting station for beam-slab erection, comprising the following steps:

准备步骤:运梁车将工字梁运至桥梁边线2-3m处,运梁车停放在外悬臂下方桥面等待装货;Preparation steps: The beam transporter transports the I-beam to the sideline of the bridge 2-3m, and the beam transporter is parked on the bridge deck under the outer cantilever to wait for loading;

检查步骤:试运行提梁站起重天车,检查天车刹车、钢丝绳磨损及锚固锁紧情况、各安全开关情况,确认无异常后方可开始起吊;Inspection steps: Trial operation of the lifting crane, check the brake of the crane, the wear of the wire rope, the anchoring and locking conditions, and the conditions of each safety switch. After confirming that there is no abnormality, the lifting can be started;

下吊步骤:将两台起重天车同时往悬臂外开,当两台卷扬机起吊中心接近工字梁吊点时减速运行,以缓慢的速度靠近,直到与工字梁吊点重合后下方吊钩;Lifting steps: open the two cranes to the cantilever at the same time, when the lifting center of the two hoists is close to the I-beam lifting point, slow down and approach at a slow speed until it overlaps with the I-beam lifting point. hook;

吊装步骤:挂好绳索后,起重机缓慢将工字梁吊上桥面,并沿桥内侧横移将工字梁放置在桥面运梁车上。优选的,在所述吊装步骤中,挂好绳索后,先缓慢将工字梁试吊10mm且静止2分钟,观察起重机运行情况,起重机运行无异常方可缓慢将工字梁吊上桥面。Hoisting steps: After hanging the rope, the crane slowly hoisted the I-beam to the bridge deck, and moved the I-beam laterally along the inside of the bridge to place the I-beam on the bridge deck girder truck. Preferably, in the hoisting step, after the ropes are hung up, the I-beam is slowly hoisted for 10 mm and kept for 2 minutes, and the operation of the crane is observed. The I-beam can be slowly hoisted to the bridge deck only when the crane is running normally.

上述实施方式仅为本发明的优选实施方式,不能以此来限定本发明保护的范围,本领域的技术人员在本发明的基础上所做的任何非实质性的变化及替换均属于本发明所要求保护的范围。The above-mentioned embodiments are only preferred embodiments of the present invention, and cannot be used to limit the scope of protection of the present invention. Any insubstantial changes and substitutions made by those skilled in the art on the basis of the present invention belong to the scope of the present invention. Scope of protection claimed.

Claims (10)

1.一种用于梁板架设的悬臂式提梁站,用于在桥上吊装架设梁板,包括支撑组件、天车组件,其特征在于:1. a cantilevered beam-lifting station for beam plate erection, for hoisting and erecting beam plate on a bridge, comprising support assembly, crane assembly, it is characterized in that: 所述支撑组件包括第一侧钢管立柱、与第一侧钢管立柱相对的第二侧钢管立柱,所述第一侧钢管立柱位于桥中,所述第一侧钢管立柱处设置有侧部辅助支撑,所述侧部辅助支撑包括辅助斜杆、若干根辅助横杆,所述辅助斜杆的两端分别与所述天车组件的下部和所述第一侧钢管立柱的下部铰接,所述辅助横杆的两端分别与所述第一侧钢管立柱和所述辅助斜杆铰接,所述辅助横杆处于水平状态;The support assembly includes a first side steel pipe column and a second side steel pipe column opposite to the first side steel pipe column, the first side steel pipe column is located in the bridge, and the first side steel pipe column is provided with a side auxiliary support , the side auxiliary support includes auxiliary inclined rods and several auxiliary transverse rods, two ends of the auxiliary inclined rods are respectively hinged with the lower part of the crane assembly and the lower part of the first side steel pipe column. Both ends of the cross bar are respectively hinged with the first side steel pipe column and the auxiliary inclined bar, and the auxiliary cross bar is in a horizontal state; 所述天车组件包括自行式天车梁、沿自行式天车梁移动的卷扬机,所述第一侧钢管立柱、第二侧钢管立柱的上部与所述自行式天车梁固定连接。The crane assembly includes a self-propelled crane beam and a hoist that moves along the self-propelled crane beam. The upper parts of the first side steel pipe column and the second side steel pipe column are fixedly connected to the self-propelled crane beam. 2.如权利要求1所述的用于梁板架设的悬臂式提梁站,其特征在于:所述第一侧钢管立柱的延伸方向与所述第二侧钢管立柱的延伸方向平行。2 . The cantilever beam lifting station for beam plate erection according to claim 1 , wherein the extension direction of the first side steel pipe column is parallel to the extension direction of the second side steel pipe column. 3 . 3.如权利要求1所述的用于梁板架设的悬臂式提梁站,其特征在于:所述第一侧钢管立柱的延伸方向与所述自行式天车梁的延伸方向垂直。3 . The cantilever beam lifting station for beam plate erection according to claim 1 , wherein the extension direction of the first side steel pipe column is perpendicular to the extension direction of the self-propelled crane beam. 4 . 4.如权利要求1所述的用于梁板架设的悬臂式提梁站,其特征在于:所述用于梁板架设的悬臂式提梁站包括第一提梁站、第二提梁站,所述第一提梁站、第二提梁站分布于待吊装的梁板的两侧;所述用于梁板架设的悬臂式提梁站还包括设置于桥上的工字梁运输车。4. The cantilevered beam-lifting station for beam-slab erection according to claim 1, wherein the cantilevered beam-lifting station for beam-slab erection comprises a first beam-lifting station and a second beam-lifting station, the first beam-lifting station The first beam lifting station and the second beam lifting station are distributed on both sides of the beam plate to be hoisted; the cantilever beam lifting station for beam plate erection also includes an I-beam transport vehicle arranged on the bridge. 5.如权利要求1所述的用于梁板架设的悬臂式提梁站,其特征在于:所述辅助斜杆、辅助横杆、第一侧钢管立柱呈直角三角形分布。5 . The cantilever beam lifting station for beam plate erection according to claim 1 , wherein the auxiliary inclined rods, the auxiliary cross rods and the first side steel pipe uprights are distributed in a right triangle. 6 . 6.如权利要求5所述的用于梁板架设的悬臂式提梁站,其特征在于:所述辅助斜杆与所述第一侧钢管立柱呈15°-20°。6 . The cantilever beam lifting station for beam plate erection according to claim 5 , wherein the auxiliary inclined rod and the first side steel pipe upright are at an angle of 15°-20°. 7 . 7.如权利要求6所述的用于梁板架设的悬臂式提梁站,其特征在于:所述辅助斜杆与所述第一侧钢管立柱呈18°。7 . The cantilever beam lifting station for beam plate erection according to claim 6 , wherein the auxiliary inclined rod and the first side steel pipe column are at 18°. 8 . 8.如权利要求1所述的用于梁板架设的悬臂式提梁站,其特征在于:所述辅助斜杆、辅助横杆、自行式天车梁呈直角三角形分布。8 . The cantilever beam lifting station for beam plate erection according to claim 1 , wherein the auxiliary inclined rods, the auxiliary cross rods, and the self-propelled crane beams are distributed in a right-angled triangle. 9 . 9.一种权利要求1-8任意一项所述的用于梁板架设的悬臂式提梁站的吊装上桥方法,其特征在于,包括以下步骤:9. A method for hoisting and hoisting a bridge for a cantilevered beam-lifting station for beam-slab erection according to any one of claims 1-8, characterized in that, comprising the following steps: 准备步骤:运梁车将工字梁运至桥梁边线2-3m处,运梁车停放在外悬臂下方桥面等待装货;Preparation steps: The beam transporter transports the I-beam to the sideline of the bridge 2-3m, and the beam transporter is parked on the bridge deck under the outer cantilever to wait for loading; 检查步骤:试运行提梁站起重天车,检查天车刹车、钢丝绳磨损及锚固锁紧情况、各安全开关情况,确认无异常后方可开始起吊;Inspection steps: Trial operation of the lifting crane, check the brake of the crane, the wear of the wire rope, the anchoring and locking conditions, and the conditions of each safety switch. After confirming that there is no abnormality, the lifting can be started; 下吊步骤:将两台起重天车同时往悬臂外开,当两台卷扬机起吊中心接近工字梁吊点时减速运行,以缓慢的速度靠近,直到与工字梁吊点重合后下方吊钩;Lifting steps: open the two cranes to the cantilever at the same time, when the lifting center of the two hoists is close to the I-beam lifting point, slow down and approach at a slow speed until it overlaps with the I-beam lifting point. hook; 吊装步骤:挂好绳索后,起重机缓慢将工字梁吊上桥面,并沿桥内侧横移将工字梁放置在桥面运梁车上。Hoisting steps: After hanging the rope, the crane slowly hoisted the I-beam to the bridge deck, and moved the I-beam laterally along the inside of the bridge to place the I-beam on the bridge deck girder truck. 10.如权利要求9所述的吊装上桥方法,其特征在于:在所述吊装步骤中,挂好绳索后,先缓慢将工字梁试吊10mm且静止2分钟,观察起重机运行情况,起重机运行无异常方可缓慢将工字梁吊上桥面。10. The method for hoisting a bridge as claimed in claim 9, characterized in that: in the hoisting step, after hanging the rope, first slowly test the I-beam for 10mm and stand still for 2 minutes, observe the operation of the crane, and the crane Only when there is no abnormality in operation, the I-beam can be slowly lifted to the bridge deck.
CN202210293341.7A 2022-03-23 2022-03-23 Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge Pending CN114635362A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210293341.7A CN114635362A (en) 2022-03-23 2022-03-23 Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210293341.7A CN114635362A (en) 2022-03-23 2022-03-23 Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge

Publications (1)

Publication Number Publication Date
CN114635362A true CN114635362A (en) 2022-06-17

Family

ID=81950691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210293341.7A Pending CN114635362A (en) 2022-03-23 2022-03-23 Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge

Country Status (1)

Country Link
CN (1) CN114635362A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116479765A (en) * 2023-04-09 2023-07-25 中交路桥华东工程有限公司 A construction method for lifting beams on gantry crane beams

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB667948A (en) * 1950-06-23 1952-03-12 Erhard Mettler Improvements in or relating to analytical balances
CN102205929A (en) * 2011-03-31 2011-10-05 四川川交路桥有限责任公司 High and low gantry crane formed by steel tube upright post for hoisting long-span T beam
CN102433844A (en) * 2011-09-26 2012-05-02 中交四航局第一工程有限公司 Cantilever beam lifting system of trestle, and bridge deck precast beam erection construction system and method
CN103628411A (en) * 2013-11-21 2014-03-12 中交第二航务工程局有限公司 Upper-air tower-attaching cantilever type girder-lifting truss-hanging system in mountainous area
CN111851301A (en) * 2020-07-09 2020-10-30 北京市政路桥股份有限公司 a bridge erecting machine
CN211848997U (en) * 2019-12-25 2020-11-03 中交第一航务工程局有限公司 Semi-span pier beam-lifting machine for bridge on high pier column prefabricated T beam in limited space
CN112523087A (en) * 2020-10-16 2021-03-19 保利长大工程有限公司 A beam lifting station for beam slab erects

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB667948A (en) * 1950-06-23 1952-03-12 Erhard Mettler Improvements in or relating to analytical balances
CN102205929A (en) * 2011-03-31 2011-10-05 四川川交路桥有限责任公司 High and low gantry crane formed by steel tube upright post for hoisting long-span T beam
CN102433844A (en) * 2011-09-26 2012-05-02 中交四航局第一工程有限公司 Cantilever beam lifting system of trestle, and bridge deck precast beam erection construction system and method
CN103628411A (en) * 2013-11-21 2014-03-12 中交第二航务工程局有限公司 Upper-air tower-attaching cantilever type girder-lifting truss-hanging system in mountainous area
CN211848997U (en) * 2019-12-25 2020-11-03 中交第一航务工程局有限公司 Semi-span pier beam-lifting machine for bridge on high pier column prefabricated T beam in limited space
CN111851301A (en) * 2020-07-09 2020-10-30 北京市政路桥股份有限公司 a bridge erecting machine
CN112523087A (en) * 2020-10-16 2021-03-19 保利长大工程有限公司 A beam lifting station for beam slab erects

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116479765A (en) * 2023-04-09 2023-07-25 中交路桥华东工程有限公司 A construction method for lifting beams on gantry crane beams

Similar Documents

Publication Publication Date Title
CN108560927B (en) Steel rib column hoisting system and use method thereof
CN109024291A (en) A kind of integration Bridge Erector and its working method
CN110258352A (en) Construction method of steel-concrete composite bridge with two spans
WO2024148715A1 (en) Method for erecting continuous steel truss bridge
CN112160246B (en) Method for installing composite beam
CN116043713A (en) A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN113120771A (en) Double-side synchronous hoisting equipment suitable for rear cantilever arm of composite-section beam bridge and construction method
CN216474531U (en) Water steel box girder lifting, sliding and installing system with existing bridge penetrating downwards
CN105088970A (en) Construction method of corrugated steel web PC box girder cable-stayed bridge
CN205205685U (en) Span wire pier is function portal device at most
CN116853963B (en) A hoisting device and hoisting method for main beam of cable-stayed bridge
WO2024148716A1 (en) Method for erecting curved steel truss cable-stayed bridge
CN114635362A (en) Cantilever type beam lifting station for beam slab erection and method for hoisting beam lifting station to bridge
CN114476962B (en) A steel-concrete composite beam erection system based on bridge crane
CN209338005U (en) A kind of mobile height leg gantry crane of erecting beam construction
CN115182265A (en) Integrated bridge girder erection machine used under working condition of dry splicing segment bent cap and construction method
CN207987749U (en) Ride cable-styled erection crane
CN112030777B (en) A down-type mobile formwork support bracket spanning transfer construction method
CN114572854A (en) Assembled squat silo roof hoisting system and silo roof hoisting method
CN205529915U (en) Ladder type masts type hangs pieces together loop wheel machine
CN219218724U (en) Main girder hanging and paving integrated machine for combined girder cable-stayed bridge
CN217627283U (en) Asynchronous hanging basket with triangular truss type hoisting equipment
CN206438420U (en) The assembled equipment of fixed asymmetric bridge girder cantilever
CN216764103U (en) Hoisting portal frame for roller type combined cable saddle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 510000 No. 942 Guangzhou Avenue Center, Tianhe District, Guangzhou City, Guangdong Province

Applicant after: Poly Changda Engineering Co., Ltd.

Applicant after: Changda Municipal Engineering (Guangdong) Co.,Ltd.

Applicant after: Changda Construction Engineering (Guangdong) Co.,Ltd.

Address before: 510000 No. 942 Guangzhou Avenue Center, Tianhe District, Guangzhou City, Guangdong Province

Applicant before: Poly Changda Engineering Co., Ltd.

Applicant before: Guangdong Changxin Municipal Engineering Co.,Ltd.

Applicant before: Changda Construction Engineering (Guangdong) Co.,Ltd.

SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220617