CN111815498A CN202010684193.2A CN202010684193A CN111815498A CN 111815498 A CN111815498 A CN 111815498A CN 202010684193 A CN202010684193 A CN 202010684193A CN 111815498 A CN111815498 A CN 111815498A
Authority
CN
China
Prior art keywords
embankment
dike
protection
ecological
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010684193.2A
Other languages
Chinese (zh)
Other versions
CN111815498B (en
Inventor
林俊贵
陈少平
蔡鸿昌
吴鼎立
郭丽珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Jindun Construction Engineering Co., Ltd
Original Assignee
Fujian Jindun Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Jindun Construction Engineering Co ltd filed Critical Fujian Jindun Construction Engineering Co ltd
Priority to CN202010684193.2A priority Critical patent/CN111815498B/en
Publication of CN111815498A publication Critical patent/CN111815498A/en
Application granted granted Critical
Publication of CN111815498B publication Critical patent/CN111815498B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/40Controlling or monitoring, e.g. of flood or hurricane; Forecasting, e.g. risk assessment or mapping
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/152Water filtration

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • General Engineering & Computer Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Revetment (AREA)

Abstract

The invention relates to a construction method for protecting dikes in municipal engineering, which comprises a data recording stage, wherein hydrologic information of rivers in a pre-constructed river reach is collected and recorded at first for the construction preparation stage to process data; the construction preparation stage is used for judging whether an artificial dike dam or an ecological dike dam is adopted by using the data collected in the data collection stage, judging the material and the dike dam mode of the dike dam in the artificial dike dam protection process, meeting the water flow impact requirement, judging the type of the plant to be planted in the ecological dike dam and meeting the requirement of purifying a water source; the method collects hydrological parameters of a pre-constructed river reach before construction, judges whether ecological dike protection can be adopted or not, enables the construction of the municipal engineering dike protection to meet the requirements of beauty and greening as much as possible, judges the material of the dike protection through hydrological data detected in advance, prevents an impact mode, enables the dike protection to have higher reliability and meet the requirements of flood control, judges the required purification grade through the detected water quality data, and selects different ecological water purification plants according to the judgment grade to meet the requirements of ecological still water.

Description

Construction method for dike protection of municipal engineering
Technical Field
The invention belongs to the field of embankment construction, and particularly relates to a method for constructing embankment in municipal engineering
Background
The dike dam is an important engineering facility for protecting important facilities or areas along the river bank, can reduce the loss of the river bank area caused by the invasion of the flood, has small water flow impact in the dike dam required by municipal engineering, is not required to be closed to the flood invasion during construction, is also required to be closed to greening and beautiful, and can purify the river pollution.
Disclosure of Invention
The invention aims to solve the problems that the building of dike-protecting in municipal engineering needs to meet the requirements of beauty, greening, river pollution treatment and flood control, and provides a method for constructing the dike-protecting in the municipal engineering
In the data recording stage, firstly, hydrologic information of rivers in the pre-construction river reach is collected and recorded for the construction preparation stage to process data; and a construction preparation stage, namely judging whether an artificial dike dam or an ecological dike dam is adopted by using the data collected in the data collection stage, judging the material and dike dam mode of the dike dam in the artificial dike dam protection process, meeting the water flow impact requirement, judging the type of the plant to be planted in the ecological dike dam, and meeting the requirement of purifying a water source.
Further, in the data recording stage, firstly acquiring hydrologic information of a pre-constructed river channel, and storing the hydrologic information into a river channel hydrologic data matrix P (V, H, HP, HM), wherein V represents average water flow of the constructed river bank, the maximum precipitation H within three years, the average water level HP of the river channel within three years and the maximum water level HM of the river channel within three years; and a water quality data matrix W (C, N, T), wherein C represents permanganate index CODMn for reacting polluted organic matters and reductive inorganic matters, N represents an index of ammonia nitrogen content in the water flow and has a standard control value NH 3-N; t represents the total nitrogen content TN in the water stream,
furthermore, in the construction preparation stage, before construction, firstly, a river channel hydrological data matrix P (V, H, HP, HM) and a water quality data matrix W (C, N, T) are measured, the inclination angle a of the pre-constructed river reach is measured, a bank protection construction mode coefficient Y is calculated through the following formula,
Figure BDA0002586903000000021
k1 is a preset coefficient, the other parameters are pre-recorded parameters, and Y is compared with a preset embankment building mode comparison parameter Y0 to judge whether manual embankment protection is needed or not;
when Y is more than Y0, judging that the river reach water impact is large, and recommending artificial dike protection;
when the artificial dike protection is judged to be adopted, firstly, the PH value of the water flow at the pre-built dike section and the content of corrosive carbonate are measured at intervals of a preset distance H0, and a water flow corrosive matrix F (Hi, PH, CO2) is recorded, wherein Hi is the ith measuring section, i represents a serial number, PH represents the PH value in the ith river section, CO2 represents the content of carbonate in the ith river section, and materials required for building the dike protection are selected according to the PH value and the C02 content of the material.
Furthermore, a specific judgment mode is adopted when the material of the bank protection surface is determined,
when the pH is greater than 6.5 or/and CO2 is less than 15, judging that the water flow of the river reach is weak in corrosivity, and building a dam protection surface by adopting normal concrete;
when the pH value is 5< 6.5 or/and the CO2 is 15< 30, judging that the water flow of the river reach is moderate in corrosivity, and adopting concrete added with a corrosion-resistant formula to construct a bank protection surface;
when the pH is 4< 5 or/and the CO2<60, judging that the water flow of the river reach is strong in corrosivity, and carrying out anti-corrosion treatment on the constructed embankment surface.
Then, the bank protection face is judged to be adopted according to the difference between the bank protection building mode coefficient Y and the preset coefficient YO, and judgment constants Y1, Y2 and Y3 are preset.
When Y-Y0< Y1 is judged as the first impact grade, the bank protection surface does not adopt impact relief treatment;
when Y1< Y-Y0< Y2, judging the second impact level, and adopting anti-impact treatment on the embankment surface;
when Y2< Y1< Y3, judging the grade to be a third impact grade, and paving flood control embankment blocks on the embankment surface by adopting severe impact prevention treatment;
when Y is less than Y0, judging that the river reach has less water flow impact, and suggesting to use a form of combining an artificial dike dam and an ecological dike dam for treatment;
further, when the ecological embankment is judged to be allowed to be used, a water quality standard parameter matrix W0(C0, N0 and T0) is preset in the construction preparation stage, wherein C0 represents the maximum value of permanganate index CODMn allowed by normal water quality, N0 represents the maximum value of ammonia nitrogen content in the normal water quality, T0 represents the maximum value of total nitrogen content in the normal water quality, the water quality standard parameter matrix W0(C0, N0 and T0) of the water quality data matrix W (C, N and T) is compared, the water quality pollution index K calculated according to the following formula is compared with a preset standard value K0 to judge the plants planted in the ecological embankment,
Figure BDA0002586903000000031
when K is more than KO, judging to adopt the ecological embankment protection project to purify the water quality,
the processing module is internally provided with ecological embankment plant planting grades H1, H2 and H3 which are preset values.
When H1< K < H2 is judged as the requirement of the first-level water purification plant, the ecological embankment can be planted with wild arrowheads and loosestrife with ordinary water purification capacity;
when H2< K < H3 is judged as the requirement of the secondary water purification plant, the ecological embankment can adopt calamus, reed and silvergrass with better water purification capacity;
when H3< K, the ecological embankment can adopt the giant reed with the strongest water purification capacity;
the method has the technical effects that hydrological parameters of a pre-constructed river reach are collected before construction, whether ecological dike protection can be adopted or not is judged, so that the requirements of urban river channels, attractiveness and greening can be met as much as possible in municipal engineering dike protection construction, the material of the dike protection is judged through hydrological data detected in advance, an impact protection mode is adopted, the dike protection is more reliable, the flood control requirement is met, the required purification grade is judged through the water quality data detected, different ecological water purification plants are selected according to the judgment grade, and the requirement of ecological still water is met.
Particularly, acquiring hydrologic information of a pre-constructed river channel, and storing the hydrologic information into a river channel hydrologic data matrix P (V, H, HP, HM), wherein V represents average water flow of the constructed river bank, the single day in three years, the highest precipitation H, the average water level HP of the river channel in three years and the highest water level HM of the river channel in three years; and a water quality data matrix W (C, N, T), wherein C represents permanganate index CODMn for reacting polluted organic matters and reductive inorganic matters, N represents an index of ammonia nitrogen content in the water flow and has a standard control value NH 3-N; t represents total nitrogen content TN in the water flow, and the detected hydrological data parameters and water quality data parameters are convenient to detect, representative and capable of reflecting hydrological and water quality conditions.
In particular, in the construction preparation stage, before construction, firstly, a river channel hydrological data matrix P (V, H, HP, HM) and a water quality data matrix W (C, N, T) are measured, the inclination angle a of the pre-constructed river reach is measured, a bank protection construction mode coefficient Y is calculated by the following formula,
Figure BDA0002586903000000041
k1 is a preset coefficient, the other parameters are pre-recorded parameters, and Y is compared with a preset embankment building mode comparison parameter Y0 to judge whether manual embankment protection is needed or not;
when Y is greater than Y0, judging that the river reach has larger water flow impact, advising to use an artificial dike, and judging whether an ecological dike can be adopted according to parameters so that the constructed ecological dike can meet engineering requirements.
Particularly, after the artificial dike protection is judged, firstly, the PH value and the content of corrosive carbonate of the water flow at the pre-built dike section are measured at intervals of a preset distance H0, and a water flow corrosivity matrix F (Hi, PH, CO2) is recorded, wherein Hi is the ith measured section, i represents a serial number, PH represents the PH value in the ith section, CO2 represents the content of carbonate in the ith section, and materials required for building the dike protection are selected according to the PH value and the C02 content.
Furthermore, a specific judgment mode is adopted when the material of the bank protection surface is determined,
when the pH is greater than 6.5 or/and CO2 is less than 15, judging that the water flow of the river reach is weak in corrosivity, and building a dam protection surface by adopting normal concrete;
when the pH value is 5< 6.5 or/and the CO2 is 15< 30, judging that the water flow of the river reach is moderate in corrosivity, and adopting concrete added with a corrosion-resistant formula to construct a bank protection surface;
when the pH is 4< 5 or/and the CO2<60, judging that the water flow of the river reach is strong in corrosivity, and carrying out anti-corrosion treatment on the constructed embankment surface.
Then, the bank protection face is judged to be adopted according to the difference between the bank protection building mode coefficient Y and the preset coefficient YO, and judgment constants Y1, Y2 and Y3 are preset.
When Y-Y0< Y1 is judged as the first impact grade, the bank protection surface does not adopt impact relief treatment;
when Y1< Y-Y0< Y2, judging the second impact level, and adopting anti-impact treatment on the embankment surface;
when Y2< Y1< Y3, judging the grade to be a third impact grade, and paving flood control embankment blocks on the embankment surface by adopting severe impact prevention treatment;
when Y is less than Y0, judging that the river reach has less water flow impact, and suggesting to use a form of combining an artificial dike dam and an ecological dike dam for treatment; the material and the anti-impact grade of the embankment are judged according to actual construction, and the reliability of the embankment is improved.
Particularly, when the ecological embankment is judged to be allowed to be used, a water quality standard parameter matrix W0(C0, N0 and T0) is preset in the construction preparation stage, wherein C0 represents the maximum value of permanganate index CODMn allowed by normal water quality, N0 represents the maximum value of ammonia nitrogen content in the normal water quality, T0 represents the maximum value of total nitrogen content in the normal water quality, the water quality standard parameter matrix W0(C0, N0 and T0) of the water quality data matrix W (C, N and T) is compared, the water quality pollution index K is calculated according to the following formula and compared with a preset standard value K0 to judge the plants planted in the ecological embankment,
Figure BDA0002586903000000051
when K is more than KO, judging to adopt the ecological embankment protection project to purify the water quality,
the processing module is internally provided with ecological embankment plant planting grades H1, H2 and H3 which are preset values.
When H1< K < H2 is judged as the requirement of the first-level water purification plant, the ecological embankment can be planted with wild arrowheads and loosestrife with ordinary water purification capacity;
when H2< K < H3 is judged as the requirement of the secondary water purification plant, the ecological embankment can adopt calamus, reed and silvergrass with better water purification capacity;
when H3< K, the ecological embankment can adopt the giant reed with the strongest water purification capacity;
and calculating a pollution index according to the parameters in the water quality, and determining the plants planted in the ecological dike dam according to the pollution index, wherein the ecological dike dam can meet the requirement of purifying the water quality due to the benefit of land placement.
Drawings
Fig. 1 is a flow chart of a municipal engineering embankment construction method provided by the embodiment of the invention.
Detailed Description
The above and further features and advantages of the present invention are described in more detail below with reference to the accompanying drawings.
Preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only for explaining the technical principle of the present invention, and are not intended to limit the scope of the present invention.
It should be noted that in the description of the present invention, the terms of direction or positional relationship indicated by the terms "upper", "lower", "left", "right", "inner", "outer", etc. are based on the directions or positional relationships shown in the drawings, which are only for convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
Furthermore, it should be noted that, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Referring to fig. 1, which is a flowchart illustrating a method for constructing a civil engineering embankment according to an embodiment of the present invention, the embodiment includes,
in the data recording stage, firstly, hydrologic information of rivers in the pre-construction river reach is collected and recorded for the construction preparation stage to process data; and a construction preparation stage, namely judging whether an artificial dike dam or an ecological dike dam is adopted by using the data collected in the data collection stage, judging the material and dike dam mode of the dike dam in the artificial dike dam protection process, meeting the water flow impact requirement, judging the type of the plant to be planted in the ecological dike dam, and meeting the requirement of purifying a water source.
Specifically, in the data recording stage, firstly acquiring hydrologic information of a pre-constructed river channel, and storing the hydrologic information into a river channel hydrologic data matrix P (V, H, HP, HM), wherein V represents average water flow of the constructed river bank, the maximum precipitation H within three years, the average water level HP of the river channel within three years and the maximum water level HM of the river channel within three years; and a water quality data matrix W (C, N, T), wherein C represents permanganate index CODMn for reacting polluted organic matters and reductive inorganic matters, N represents an index of ammonia nitrogen content in the water flow and has a standard control value NH 3-N; t represents the total nitrogen content TN in the water stream,
specifically, in the construction preparation stage, before construction, firstly, the river hydrological data matrix P (V, H, HP, HM) and the water quality data matrix W (C, N, T) are used for measuring the inclination angle a of the pre-built river reach, the embankment building mode coefficient Y is calculated by the following formula,
Figure BDA0002586903000000071
k1 is a preset coefficient, the other parameters are pre-recorded parameters, and Y is compared with a preset embankment construction mode comparison parameter Y0;
when Y is more than Y0, judging that the river reach water impact is large, and recommending artificial dike protection;
specifically, after the artificial dike protection is judged, firstly, the PH value and the content of corrosive carbonate of the water flow at the pre-built dike section are measured at intervals of a preset distance H0, and recorded in a water flow corrosivity matrix F (Hi, PH, CO2), wherein Hi is the ith measured section, i represents a serial number, PH represents the PH value in the ith section, CO2 represents the content of carbonate in the ith section, and materials required for building the dike protection are selected according to the PH value and the C02 content.
Specifically, a specific judgment method is adopted when the material of the bank protection face is determined,
when the pH is greater than 6.5 or/and CO2 is less than 15, judging that the water flow of the river reach is weak in corrosivity, and building a dam protection surface by adopting normal concrete;
when the pH value is 5< 6.5 or/and the CO2 is 15< 30, judging that the water flow of the river reach is moderate in corrosivity, and adopting concrete added with a corrosion-resistant formula to construct a bank protection surface;
when the pH is 4< 5 or/and the CO2<60, judging that the water flow of the river reach is strong in corrosivity, and carrying out anti-corrosion treatment on the constructed embankment surface.
Then, the bank protection face is judged to be adopted according to the difference between the bank protection building mode coefficient Y and the preset coefficient YO, and judgment constants Y1, Y2 and Y3 are preset.
When Y-Y0< Y1 is judged as the first impact grade, the bank protection surface does not adopt impact relief treatment;
when Y1< Y-Y0< Y2, judging the second impact level, and adopting anti-impact treatment on the embankment surface;
when Y2< Y1< Y3, judging the grade to be a third impact grade, and paving flood control embankment blocks on the embankment surface by adopting severe impact prevention treatment;
when Y is less than Y0, judging that the river reach has less water flow impact, and suggesting to use a form of combining an artificial dike dam and an ecological dike dam for treatment;
when the ecological embankment is judged to be allowed to be used, a water quality standard parameter matrix W0(C0, N0 and T0) is preset in the construction preparation stage, wherein C0 represents the maximum value of permanganate index CODMn allowed by normal water quality, N0 represents the maximum value of ammonia nitrogen content in the normal water quality, T0 represents the maximum value of total nitrogen content in the normal water quality, the water quality standard parameter matrix W0(C0, N0 and T0) of the water quality data matrix W (C, N and T) is compared, a water quality pollution index K is calculated according to the following formula and compared with a preset standard value K0 to judge plants planted in the ecological embankment,
Figure BDA0002586903000000081
when K is more than KO, judging to adopt the ecological embankment protection project to purify the water quality,
the processing module is internally provided with ecological embankment plant planting grades H1, H2 and H3 which are preset values.
When H1< K < H2 is judged as the requirement of the first-level water purification plant, the ecological embankment can be planted with wild arrowheads and loosestrife with ordinary water purification capacity;
when H2< K < H3 is judged as the requirement of the secondary water purification plant, the ecological embankment can adopt calamus, reed and silvergrass with better water purification capacity;
when H3< K, the ecological embankment can adopt the giant reed with the strongest water purification capacity;
so far, the technical solutions of the present invention have been described in connection with the preferred embodiments shown in the drawings, but it is easily understood by those skilled in the art that the scope of the present invention is obviously not limited to these specific embodiments. Equivalent changes or substitutions of related technical features can be made by those skilled in the art without departing from the principle of the invention, and the technical scheme after the changes or substitutions can fall into the protection scope of the invention.

Claims (7)

1. A municipal works embankment protection construction method is characterized in that: which comprises the steps of preparing a mixture of a plurality of raw materials,
in the data recording stage, firstly, collecting and recording river hydrological information of a pre-construction river reach for a construction preparation stage to process data, firstly, acquiring hydrological information of the pre-construction river reach, and storing the hydrological information into a river hydrological data matrix P (V, H, HP, HM), wherein V represents average water flow of the construction river reach, the maximum precipitation H within one day of three years, the average water level HP of the river reach within three years, and the maximum water level HM of the river reach within three years; and a water quality data matrix W (C, N, T), wherein C represents permanganate index CODMn for reacting polluted organic matters and reductive inorganic matters, N represents an index of ammonia nitrogen content in the water flow and has a standard control value NH 3-N; t represents the total nitrogen content TN in the water stream;
a construction preparation stage, judging whether an artificial dike protection or an ecological dike protection is adopted by using data collected in the data collection stage, judging the material and the dike protection mode of the dike protection in the artificial dike protection process, meeting the requirement of water flow impact, judging the type of plants required to be planted in the ecological dike protection, meeting the requirement of purifying water quality, before construction, firstly, determining the inclination angle a of the pre-built river reach, calculating the coefficient Y of the dike protection building mode by the following formula,
Figure FDA0002586902990000011
k1 is a preset coefficient, the other parameters are pre-recorded parameters, and Y is compared with a preset embankment building mode comparison parameter Y0 to judge whether manual embankment protection is needed.
2. The municipal engineering embankment construction method according to claim 1, wherein when the construction preparation stage determines whether manual embankment is required,
when Y is more than Y0, judging that the river reach has larger water flow impact, and using an artificial dike dam;
when Y < Y0, the river reach is judged to have small water impact, and the treatment in a form of combining an artificial dike and an ecological dike is recommended.
3. The municipal works embankment protection construction method according to claim 2, wherein after the construction preparation stage judges that manual embankment protection is used, after the manual embankment protection is adopted, the PH value of the water flow at the pre-built embankment river reach and the content of corrosive carbonate are measured at intervals of a preset distance H0, a water flow corrosivity matrix F (Hi, PH, CO2) is recorded, wherein Hi is the ith measured river reach, i represents a serial number, PH represents the PH value in the ith river reach, CO2 represents the content of carbonate in the ith river reach, and materials required for building embankment protection are selected according to the PH value and the C02 content.
4. The municipal works embankment construction method according to claim 3, wherein after the construction preparation stage judges that the artificial embankment is used, a specific judgment method is adopted when the embankment facing material is determined,
when the pH is greater than 6.5 or/and CO2 is less than 15, judging that the water flow of the river reach is weak in corrosivity, and building a dam protection surface by adopting normal concrete;
when the pH value is 5< 6.5 or/and the CO2 is 15< 30, judging that the water flow of the river reach is moderate in corrosivity, and adopting concrete added with a corrosion-resistant formula to construct a bank protection surface;
when the pH is 4< 5 or/and the CO2<60, judging that the water flow of the river reach is strong in corrosivity, and carrying out anti-corrosion treatment on the constructed embankment surface.
5. The municipal works embankment construction method according to claim 3, wherein after the construction preparation stage judges that artificial embankment is used, the mode of adopting an embankment surface is judged according to the difference between an embankment construction mode coefficient Y and a preset coefficient YO, and judgment constants Y1, Y2 and Y3 are preset;
when Y-Y0< Y1 is judged as the first impact grade, the bank protection surface does not adopt impact relief treatment;
when Y1< Y-Y0< Y2, judging the second impact level, and adopting anti-impact treatment on the embankment surface;
when Y2< Y1< Y3, judging the grade to be a third impact grade, and paving flood control embankment blocks on the embankment surface by adopting severe impact prevention treatment;
when Y < Y0, the river reach is judged to have small water impact, and the treatment in a form of combining an artificial dike and an ecological dike is recommended.
6. The municipal engineering embankment construction method according to claim 2, wherein when the ecological embankment is allowed to be used in the construction preparation stage, a water quality standard parameter matrix W0(C0, N0 and T0) is preset in the construction preparation stage, wherein C0 represents the maximum value of permanganate index CODMn allowed by normal water quality, N0 represents the maximum value of ammonia nitrogen content in normal water quality, and T0 represents the maximum value of total nitrogen content in normal water quality, the water quality standard parameter matrix W0(C0, N0 and T0) of the water quality data matrix W (C, N and T) is compared, and the water pollution index K is calculated according to the following formula and compared with a preset standard value K0 to determine plants planted in the ecological embankment.
Figure FDA0002586902990000021
7. The method of claim 6, wherein when the construction preparation phase determines that the use of an ecological embankment is allowed,
when K is more than KO, judging to adopt the ecological embankment protection project to purify the water quality,
ecological embankment plant planting grades H1, H2 and H3 are arranged in the processing module and are preset values;
when H1< K < H2 is judged as the requirement of the first-level water purification plant, the ecological embankment can be planted with wild arrowheads and loosestrife with ordinary water purification capacity;
when H2< K < H3 is judged as the requirement of the secondary water purification plant, the ecological embankment can adopt calamus, reed and silvergrass with better water purification capacity;
when H3< K, the ecological embankment can adopt the giant reed with the strongest water purification capacity;
and calculating a pollution index according to the parameters in the water quality, and determining the plants planted in the ecological dike dam according to the pollution index, wherein the ecological dike dam can meet the requirement of purifying the water quality due to the benefit of land placement.
CN202010684193.2A 2020-07-16 2020-07-16 Construction method for dike protection of municipal engineering Active CN111815498B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010684193.2A CN111815498B (en) 2020-07-16 2020-07-16 Construction method for dike protection of municipal engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010684193.2A CN111815498B (en) 2020-07-16 2020-07-16 Construction method for dike protection of municipal engineering

Publications (2)

Publication Number Publication Date
CN111815498A true CN111815498A (en) 2020-10-23
CN111815498B CN111815498B (en) 2022-02-15

Family

ID=72864841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010684193.2A Active CN111815498B (en) 2020-07-16 2020-07-16 Construction method for dike protection of municipal engineering

Country Status (1)

Country Link
CN (1) CN111815498B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011154714A1 (en) * 2010-06-11 2011-12-15 Hesco Bastion Limited Barrier assembly for shoreline
US20180320356A1 (en) * 2017-05-02 2018-11-08 Thomas Wang River course ecological treatment system
CN110188959A (en) * 2019-06-03 2019-08-30 河海大学 A kind of city inland river water quantity and quality optimization regulating method
CN110306491A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of river channel ecology bank protection construction technique
CN110396979A (en) * 2019-08-01 2019-11-01 福建荣冠环境建设集团有限公司 A kind of ecological restoring method of city river
CN111005345A (en) * 2019-12-03 2020-04-14 福建省水利水电勘测设计研究院 Ecological water system restoration construction method
CN111080060A (en) * 2019-11-11 2020-04-28 天津大学 Method for constructing embankment flood risk evaluation index system
CN210946670U (en) * 2019-07-16 2020-07-07 淮安市水利规划服务中心 River structure suitable for urban river water ecology and water landscape improvement

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2011154714A1 (en) * 2010-06-11 2011-12-15 Hesco Bastion Limited Barrier assembly for shoreline
US20180320356A1 (en) * 2017-05-02 2018-11-08 Thomas Wang River course ecological treatment system
CN110188959A (en) * 2019-06-03 2019-08-30 河海大学 A kind of city inland river water quantity and quality optimization regulating method
CN210946670U (en) * 2019-07-16 2020-07-07 淮安市水利规划服务中心 River structure suitable for urban river water ecology and water landscape improvement
CN110396979A (en) * 2019-08-01 2019-11-01 福建荣冠环境建设集团有限公司 A kind of ecological restoring method of city river
CN110306491A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of river channel ecology bank protection construction technique
CN111080060A (en) * 2019-11-11 2020-04-28 天津大学 Method for constructing embankment flood risk evaluation index system
CN111005345A (en) * 2019-12-03 2020-04-14 福建省水利水电勘测设计研究院 Ecological water system restoration construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
马越: "珠江三角洲地区变水位滨河地区生态修复与景观营造——以佛山市东平河景观工程为例", 《中国园林》 *

Also Published As

Publication number Publication date
CN111815498B (en) 2022-02-15

Similar Documents

Publication Publication Date Title
Wyrwoll et al. The geomorphology and Late Cenozoic geomorphological evolution of the Cape Range–Exmouth Gulf region
CN110184994A (en) A kind of combined type submerged breakwater structure and preparation method thereof
CN111815498B (en) Construction method for dike protection of municipal engineering
Gleick et al. Assessing the costs of adapting to sea-level rise: A case study of San Francisco Bay
Lawrence Natural hazards of shoreline bluff erosion: a case study of Horizon View, Lake Huron
KR101147332B1 (en) Ecological structure with containing water permeability, and system of ubiquitous sensing and controlling for the same
Battalio et al. Predicting closure and breaching frequencies of small tidal inlets–a quantified conceptual model
CN111950885B (en) Environment-friendly civil construction pre-embedding construction method
Doughty et al. The recent evolution of storm-influenced retrograding barriers in southeastern North Carolina, USA
Pethick The taw-torridge estuaries: Geomorphology and management report to taw-torridge estuary officers group
CN216275470U (en) Ecological clean system suitable for rural small-size river course non-point source pollution administers
Carley et al. The practical application of four commercially available numerical beach morphology models on a high energy coastline
Carter Baseline Studies of Port Vila and Erakor Lagoons, Vanuatu
Martin Ground-water monitoring at Santa Barbara, California; Phase 2-effects of pumping on water levels and water quality in the Santa Barbara ground-water basins
Watson Port Stephens Sand Nourishment Projects Evaluation, Monitoring and Sustainability
Dryden PEAK DIFFERENTIAL TIDAL PRESSURES FOR ROCK WALL RECLAMATION AREAS
Park et al. Use of Groundwater-table To Establish a Buffer Zone In a Barrier Island, Nakdong River Estuary, South Korea
Jansson Heavily modified waters in Europe: Case study on the Ume River in northern Sweden
Bellasis Punjab Rivers and Works: A Description of the Shifting Rivers of the Punjab Plains and of Works on Them, Namely: Inundation Canals, Flood Embankments and River Training Works, with the Principles for Designing and Working Them
Gourlay et al. Reef-top currents in vicinity of Heron Island boat harbour, Great Barrier Reef, Australia: 2. Specific influences of tides meteorological events and waves.
Rosati et al. Sea level rise and consequences for navigable coastal inlets
Tickell et al. Stream Baseflows in the Daly Basin
Cleary Variations in inlet behavior and shoreface sand resources: factors controlling management decisions, Figure Eight Island, NC, USA
Elfrink et al. Local morphological evolution of the coast in the Upper Adriatic Sea. Design and management strategies to control coastal erosion
Rosati et al. Field evaluation of Port Everglades, Florida, rehabilitation of south jetty by void sealing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20210830

Address after: 250100 room 705, Jujiang building, No. 389, Huaxin Road, Jinan City, Shandong Province

Applicant after: Jinan Daren Technology Co.,Ltd.

Address before: 351100 No. 501, Jinwan center, Xialin street, Chengxiang District, Putian City, Fujian Province

Applicant before: Fujian Jindun Construction Engineering Co.,Ltd.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20211116

Address after: 351100 501, Jinwan center, Xialin street, Chengxiang District, Putian City, Fujian Province

Applicant after: Fujian Jindun Construction Engineering Co., Ltd

Address before: 250100 room 705, Jujiang building, No. 389, Huaxin Road, Jinan City, Shandong Province

Applicant before: Jinan Daren Technology Co., Ltd

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant