CN111720132B - Novel ultra-large section roadway rapid tunneling process - Google Patents

Novel ultra-large section roadway rapid tunneling process Download PDF

Info

Publication number
CN111720132B
CN111720132B CN202010520830.2A CN202010520830A CN111720132B CN 111720132 B CN111720132 B CN 111720132B CN 202010520830 A CN202010520830 A CN 202010520830A CN 111720132 B CN111720132 B CN 111720132B
Authority
CN
China
Prior art keywords
roadway
supporting
tunneling
tunnel
shield machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010520830.2A
Other languages
Chinese (zh)
Other versions
CN111720132A (en
Inventor
董凤宝
杨士超
孙杨
张竞生
田华
陈冬梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinwen Mining Group Design And Research Institute Co ltd
Original Assignee
Xinwen Mining Group Design And Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinwen Mining Group Design And Research Institute Co ltd filed Critical Xinwen Mining Group Design And Research Institute Co ltd
Priority to CN202010520830.2A priority Critical patent/CN111720132B/en
Publication of CN111720132A publication Critical patent/CN111720132A/en
Application granted granted Critical
Publication of CN111720132B publication Critical patent/CN111720132B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/08Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
    • E21D9/087Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a novel ultra-large section roadway rapid tunneling process, and relates to the technical field of roadway tunneling construction. The novel rapid tunneling process for the oversized section roadway comprises the following steps: s1, arranging a shield machine at the excavation position, and cutting the target position into a circular tunnel with a specified diameter by using the shield machine; s2, supporting the upper half part in the formed round roadway; and S3, after the shield machine continuously cuts and supports for a certain distance, retreating the shield machine, carrying out centralized blasting or pneumatic pick removing process on the circular tunnel, and S4, filling the removed waste rock into the middle of the bottom surface of the circular tunnel, keeping the whole bottom plate horizontal, and supporting the formed straight wall part. Compared with the prior art, the invention has the characteristics of high mechanization level, high tunneling speed and capability of forming a roadway quickly, solves the problems of difficult construction and low tunneling speed of an underground oversized section roadway, and has obvious advantages in long-distance oversized section roadway tunneling construction.

Description

Novel ultra-large section roadway rapid tunneling process
Technical Field
The invention relates to the technical field of tunneling construction, in particular to a novel rapid tunneling process for a tunnel with an ultra-large section.
Background
The existing underground roadway tunneling construction process comprises two types: blasting and fully mechanized excavating. In the tunneling of a tunnel with an ultra-large section, the two processes have poor effects, the blasting and tunneling process is difficult to construct and the progress is slow; the cutting size of the fully-mechanized excavating machine equipment in the fully-mechanized excavating process is small, and the roadway forming is difficult.
Limited by the cutting size of the roadheader, the roadway is too high to reach the cutting arm; the roadways are too wide, the roadheader needs to swing left and right for cutting, but is limited by a rear conveying belt, and the left and right swing amplitude of the roadheader is limited. Therefore, the construction difficulty of the fully-mechanized excavating machine for tunneling the oversized cross-section roadway is higher, and the field multi-purpose excavating construction is realized.
The blasting excavation is adopted to construct an oversized section roadway, and because the section of the roadway is large, the drilling and the supporting are difficult, the site is multipurpose, the step is tunneled, and the section construction is carried out. The mechanical degree of blasting excavation is low, the divided surface construction is adopted, the excavation progress is slow, the tunnel forming is poor, the tunnel is generally advanced by 60-70 meters, and for a continuous and tense mine, the large-section tunnel forming is often used as a neck engineering.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a novel rapid tunneling process for a tunnel with an oversized section, and the defects in the prior art are overcome.
In order to achieve the purpose, the invention is realized by the following technical scheme: a novel ultra-large section roadway rapid tunneling process comprises the following steps:
s1, arranging a shield tunneling machine at the excavation position, marking and positioning the cutting target position, dividing the target roadway needing to be cut into a plurality of cutting areas, and cutting the target position into a circular roadway with a specified diameter by using the shield tunneling machine;
s2, supporting the upper half part in the formed round tunnel, keeping the net diameter of the supported round tunnel, and measuring the inner diameter of the round tunnel by using a laser range finder, wherein each meter is taken as a measuring point, and the measuring error is not more than +/-2 cm;
s3, continuously cutting a plurality of areas each time by the shield machine, supporting the cut areas, retreating the shield machine, and performing centralized blasting or pneumatic pick removing process on the circular tunnel;
s4, filling the removed waste rocks into the middle of the bottom surface of the round tunnel, keeping the whole bottom plate horizontal, supporting the formed straight wall part, keeping the clear width of the supported straight wall part, and measuring the clear distance of the straight walls on the two sides of the tunnel by using a laser range finder, wherein each meter is taken as a measuring point, and the measuring error is not more than +/-2 cm.
Preferably, the model of the shield machine includes but is not limited to a TBM shield machine.
Preferably, in the step 2, the upper half part of the circular roadway is supported in the following manner:
1) drilling holes in the upper part of the circular roadway by using drilling equipment, and drilling anchor rod holes at intervals of 1-2 m;
2) after the anchor rod hole is drilled, the resin anchoring agent is fed into the bottom of the anchor rod hole by using the anchor rod, and then the anchor rod hole is filled into the equal-strength anchor rod;
3) stirring with a pneumatic drill for 10-30 s, taking off the pneumatic drill after solidification, pressing a steel belt, and pressing an iron tray on the steel belt;
4) then the steel strips are screwed by nuts, the installation direction of the steel strips is vertical to the direction of the circular roadway, and each row of steel strips must be communicated without interruption.
Preferably, the step 3 includes, but is not limited to, a centralized blasting and pneumatic pick removing mode, and a small-section rapid rock breaking mode.
Preferably, the supporting manner of the straight wall part in the step 4 is as follows:
1) positioning and marking a straight wall surface of the roadway to form positioning holes, and drilling holes by using drilling equipment according to the positioning holes at intervals of 2-3 m;
2) preparing supporting steel bars, mounting centering and positioning brackets on the steel bars, wherein the distance between the brackets and the supporting steel bars is 3-5m, checking whether foreign matters exist in holes or not, and keeping the holes clean;
3) adopting low-pressure or high-pressure grouting, arranging a grout stop plug at the position of a grouting port during pressure grouting, slowly injecting grout into the grouting port, keeping the pressure for 5-10min after the grouting is full, and performing grout filling before the grout is initially set until a hole is full during gravity grouting, wherein the grout filling times are 1-2 times;
4) and (3) finishing the installation of the supporting reinforcing steel bars, then performing spraying surface layer treatment, and performing water spraying maintenance on the surface layer after the sprayed concrete is finally set for 3-5 h.
The invention has the beneficial effects that: compared with the prior art, the method has the characteristics of high mechanization level, high tunneling speed and capability of forming a roadway quickly, solves the problems of difficulty in underground oversized section roadway construction and low tunneling speed, and has obvious advantages in long-distance oversized section roadway tunneling construction.
Drawings
Fig. 1 is a cross-sectional view of a roadway according to the present invention.
Detailed Description
The following will clearly and completely describe the technical solutions in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b):
as shown in fig. 1, an embodiment of the present invention provides a novel rapid tunneling process for a tunnel with an ultra-large cross section, including the following steps:
s1, arranging a shield tunneling machine (taking the diameter of a cutting part of the shield tunneling machine as an example of 6.3 m) at an excavation position, marking and positioning a cutting target position, dividing a target roadway needing to be cut into a plurality of cutting areas, and cutting the target position into a circular roadway (as shown in a position a in figure 1) with the diameter of 6.3 m by using the shield tunneling machine, wherein the type of the shield tunneling machine comprises but is not limited to a TBM (tunnel boring machine);
s2, supporting the upper half part in the formed circular roadway, keeping the net diameter of the supported circular roadway to be 6 meters, measuring the inner diameter of the circular roadway by using a laser range finder, and taking each meter as a measuring point, wherein the measuring error is not more than +/-2 cm;
the supporting mode of the upper half part of the circular roadway is as follows:
1) drilling holes in the upper part of the circular roadway by using drilling equipment, and drilling anchor rod holes at intervals of 1-2 m;
2) after the anchor rod hole is drilled, the resin anchoring agent is fed into the bottom of the anchor rod hole by using the anchor rod, and then the anchor rod hole is filled into the equal-strength anchor rod;
3) stirring with a pneumatic drill for 10-30 s, taking off the pneumatic drill after solidification, pressing a steel belt, and pressing an iron tray on the steel belt;
4) then, the steel strips are screwed by nuts, the installation direction of the steel strips is vertical to the direction of the circular roadway, and each row of steel strips must penetrate through the steel strips without interruption;
s3, after the shield machine continuously cuts and supports a certain distance, the shield machine is retreated, when retreating for the first time, the shield machine should be withdrawn from the interior of the circular tunnel formed for the first time, and then, from the second time, the shield machine should be positioned at the position of the formed straight wall when retreating, the method can be positioned at the nearest straight wall, and the straight wall must be supported, the centralized blasting or pneumatic pick removing process is carried out on the round tunnel, the centralized blasting or pneumatic pick removing process is mainly carried out on the straight wall (shown as the position b in figure 1) of the tunnel and the triangular part (shown as the position c in figure 1) clamped by the dotted line circular ring, the width of two sides of the tunnel is enlarged, the round section formed by the tunneling of the TBM shield machine is changed into the semicircular arch section of the straight wall, the tunnel utilization rate is improved, the using requirement of the underground tunnel is met, the method comprises the following steps of (1) carrying out blasting and pneumatic pick removing on a round roadway, wherein the round roadway comprises a centralized blasting and pneumatic pick removing mode and a small-section rapid rock breaking mode;
s4, filling the removed waste rocks into the middle of the bottom surface of the round tunnel, keeping the whole bottom plate (shown as d in figure 1) horizontal, supporting the formed straight wall part at the same time, keeping the clear width of the supported straight wall part to be 6 meters, measuring the clear distance of the straight walls on the two sides of the tunnel by using a laser range finder, and taking each meter as a measuring point, wherein the measuring error is not more than +/-2 cm;
wherein, the partial supporting mode of straight wall is as follows:
1) positioning and marking a straight wall surface of the roadway to form positioning holes, and drilling holes by using drilling equipment according to the positioning holes at intervals of 2-3 m;
2) preparing supporting steel bars, mounting centering and positioning brackets on the steel bars, wherein the distance between the brackets and the supporting steel bars is 3-5m, checking whether foreign matters exist in holes or not, and keeping the holes clean;
3) adopting low-pressure or high-pressure grouting, arranging a grout stop plug at the position of a grouting port during pressure grouting, slowly injecting grout into the grouting port, keeping the pressure for 5-10min after the grouting is full, and performing grout filling before the grout is initially set until a hole is full during gravity grouting, wherein the grout filling times are 1-2 times;
4) and (3) finishing the installation of the supporting reinforcing steel bars, then performing spraying surface layer treatment, and performing water spraying maintenance on the surface layer after the sprayed concrete is finally set for 3-5 h.
Compared with the prior art, the invention has the characteristics of high mechanization level, high tunneling speed and capability of forming a roadway quickly, solves the problems of difficult construction and low tunneling speed of an underground oversized section roadway, and has obvious advantages in long-distance oversized section roadway tunneling construction.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (2)

1. A novel ultra-large section roadway rapid tunneling process is characterized in that: the process comprises the following steps:
s1, arranging a shield tunneling machine at the excavation position, marking and positioning the cutting target position, dividing the target roadway needing to be cut into a plurality of cutting areas, and cutting the target position into a circular roadway with a specified diameter by using the shield tunneling machine;
s2, supporting the upper half part in the formed round tunnel, keeping the net diameter of the supported round tunnel, and measuring the inner diameter of the round tunnel by using a laser range finder, wherein each meter is taken as a measuring point, and the measuring error is not more than +/-2 cm; the supporting mode of the upper half part of the circular roadway is as follows:
1) drilling holes in the upper part of the circular roadway by using drilling equipment, and drilling anchor rod holes at intervals of 1-2 m;
2) after the anchor rod hole is drilled, the resin anchoring agent is fed into the bottom of the anchor rod hole by using the anchor rod, and then the anchor rod hole is filled into the equal-strength anchor rod;
3) stirring with a pneumatic drill for 10-30 s, taking off the pneumatic drill after solidification, pressing a steel belt, and pressing an iron tray on the steel belt;
4) then, the steel strips are screwed by nuts, the installation direction of the steel strips is vertical to the direction of the circular roadway, and each row of steel strips must penetrate through the steel strips without interruption;
s3, continuously cutting a plurality of areas each time by the shield machine, supporting the cut areas, retreating the shield machine, and performing centralized blasting or pick picking, upper laying and bottom laying on the round tunnel or rapidly breaking rocks with small sections to expand the width of two sides of the tunnel;
s4, filling the removed waste rocks into the middle of the bottom surface of the round tunnel, keeping the whole bottom plate horizontal, supporting the formed straight wall part, keeping the net width of the supported straight wall part, and measuring the net distance of the straight walls on the two sides of the tunnel by using a laser range finder, wherein each meter is taken as a measuring point, and the measuring error is not more than +/-2 cm; the supporting mode of the straight wall part is as follows:
1) positioning and marking a straight wall surface of the roadway to form positioning holes, and drilling holes by using drilling equipment according to the positioning holes at intervals of 2-3 m;
2) preparing supporting steel bars, mounting centering and positioning brackets on the steel bars, wherein the distance between the brackets and the supporting steel bars is 3-5m, checking whether foreign matters exist in holes or not, and keeping the holes clean;
3) adopting low-pressure or high-pressure grouting, arranging a grout stop plug at the position of a grouting port during pressure grouting, slowly injecting grout into the grouting port, keeping the pressure for 5-10min after the grouting is full, and performing grout filling before the grout is initially set until a hole is full during gravity grouting, wherein the grout filling times are 1-2 times;
4) and (3) finishing the installation of the supporting reinforcing steel bars, then performing spraying surface layer treatment, and performing water spraying maintenance on the surface layer after the sprayed concrete is finally set for 3-5 h.
2. The novel ultra-large section roadway rapid tunneling process according to claim 1, characterized in that: the model of the shield machine is a TBM shield machine.
CN202010520830.2A 2020-06-10 2020-06-10 Novel ultra-large section roadway rapid tunneling process Active CN111720132B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010520830.2A CN111720132B (en) 2020-06-10 2020-06-10 Novel ultra-large section roadway rapid tunneling process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010520830.2A CN111720132B (en) 2020-06-10 2020-06-10 Novel ultra-large section roadway rapid tunneling process

Publications (2)

Publication Number Publication Date
CN111720132A CN111720132A (en) 2020-09-29
CN111720132B true CN111720132B (en) 2022-02-25

Family

ID=72566276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010520830.2A Active CN111720132B (en) 2020-06-10 2020-06-10 Novel ultra-large section roadway rapid tunneling process

Country Status (1)

Country Link
CN (1) CN111720132B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116556980B (en) * 2023-05-27 2024-03-19 中煤第三建设(集团)有限责任公司 Quick tunneling construction method for water-rich large-section roadway in mining area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220746A (en) * 2008-02-01 2008-07-16 中铁十三局集团有限公司 TBM pilot tunnel expansion digging method for 20km double-line double-cavity ultra-long tunnel construction
CN105863651A (en) * 2016-05-30 2016-08-17 中铁工程装备集团有限公司 Tunnel construction method with shield methodand new Austrian tunneling method being combined
CN206092025U (en) * 2016-07-21 2017-04-12 淮南矿业(集团)有限责任公司 Quick -witted bolting with wire mesh mechanism is constructed in colliery shield in pit
CN206487483U (en) * 2017-02-23 2017-09-12 淮南矿业(集团)有限责任公司 A kind of mining tunneling boring hard rock mole
CN111022086A (en) * 2019-12-27 2020-04-17 周伟永 Single-layer arch frame for roadway engineering support and rapid support method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220746A (en) * 2008-02-01 2008-07-16 中铁十三局集团有限公司 TBM pilot tunnel expansion digging method for 20km double-line double-cavity ultra-long tunnel construction
CN105863651A (en) * 2016-05-30 2016-08-17 中铁工程装备集团有限公司 Tunnel construction method with shield methodand new Austrian tunneling method being combined
CN206092025U (en) * 2016-07-21 2017-04-12 淮南矿业(集团)有限责任公司 Quick -witted bolting with wire mesh mechanism is constructed in colliery shield in pit
CN206487483U (en) * 2017-02-23 2017-09-12 淮南矿业(集团)有限责任公司 A kind of mining tunneling boring hard rock mole
CN111022086A (en) * 2019-12-27 2020-04-17 周伟永 Single-layer arch frame for roadway engineering support and rapid support method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"TBM 型盾构机在新景公司保安分区8#煤回风巷的应用";程凯等;《山东煤炭科技》;20200531;第123-125页 *
"煤矿岩巷全断面掘进机(TBM) 及智能化关键技术";王杜娟等;《煤炭学报》;20200605;第2.2节,图7 *

Also Published As

Publication number Publication date
CN111720132A (en) 2020-09-29

Similar Documents

Publication Publication Date Title
CN109209392B (en) Full-ring excavation method suitable for IV-V-grade surrounding rock of large-section tunnel
CN110185457B (en) TBM (Tunnel boring machine) horizontal pilot tunnel construction method
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN110195604B (en) Construction method for tunnel main tunnel TBM (tunnel boring machine) tunneling section
CN111997639B (en) Method for getting rid of trouble and reinforcing and improving geology of TBM construction tunnel bad geology section card machine
CN110700843B (en) Tunnel three-step synchronous excavation construction method based on partition blasting
CN110259490B (en) Subway underground excavation station construction method
CN113266372A (en) Construction method for soft rock super-large section tunnel step in karst cave development stratum
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN111472801A (en) Construction method for passing existing line under shallow-buried underground excavation drainage gallery
CN103195454A (en) Method for supporting filling roadway or chamber
CN113803074A (en) Construction method of tunnel structure for artificial and mechanical combined obstacle removal of water-rich sand layer
CN111894591A (en) Collaborative mining method for inclined thick and large ore body panel and panel interval column
CN110700860B (en) Construction method of soil-stone boundary tunnel crossing loess valley
CN110863832B (en) Large-section tunnel stability control construction method for penetrating through earth-rock boundary stratum
CN112943306A (en) Roadway fault zone supporting method and step based on instability deformation research
CN116537794A (en) Combined construction method for undermining existing railway by shallow-buried underground-excavated three-hole large-section tunnel
CN110821500B (en) Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum
CN111720132B (en) Novel ultra-large section roadway rapid tunneling process
CN111577311A (en) Construction process of cantilever type heading machine in soft rock tunnel
CN112302663B (en) Milling and blasting combined construction method for water-rich desertification dolomite formation tunnel
CN110847929A (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN110566236A (en) Pipe shed and steel support combined supporting device and supporting method
CN109707394B (en) Construction method for subway tunnel shield receiving end tunnel portal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant